CN217350388U - Lifting appliance and auxiliary assembly for assembling and hoisting iron tower - Google Patents
Lifting appliance and auxiliary assembly for assembling and hoisting iron tower Download PDFInfo
- Publication number
- CN217350388U CN217350388U CN202221205754.7U CN202221205754U CN217350388U CN 217350388 U CN217350388 U CN 217350388U CN 202221205754 U CN202221205754 U CN 202221205754U CN 217350388 U CN217350388 U CN 217350388U
- Authority
- CN
- China
- Prior art keywords
- iron tower
- hoisting
- clamping groove
- guide rail
- hoist
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/728—Onshore wind turbines
Landscapes
- Load-Engaging Elements For Cranes (AREA)
Abstract
The utility model relates to an iron tower assemblage hoist and mount, auxiliary assembly, this iron tower assemblage hoist and mount hoist, include: the first locking block is used for being connected with a lifting point rope, the first locking block is provided with a first clamping groove which is used for being matched with the side edge of the angle steel, the end part of one side wall of the first clamping groove is provided with an extension section which extends in the direction away from the bottom of the first clamping groove, and the extension section is provided with a first connecting through hole; the second clamping groove is used for being matched with the other side edge of the angle steel, a second connecting through hole is formed in the side wall of the second clamping groove, and the axis of the second connecting through hole is parallel to the depth direction of the second clamping groove; the screw rod structure, the screw rod structure with first connecting hole and the cooperation can be dismantled to the second connecting hole, realizes the hoist through structural design and treats the high-speed joint of hoist and mount work piece, reaches the purpose that reduces hoisting time.
Description
Technical Field
The utility model relates to a technical field of transmission line group tower particularly, relates to an iron tower assemblage hoist and mount, auxiliary assembly.
Background
The suspension holding pole hoisting tower assembling technology has the advantages of mature process, simple construction equipment, low equipment purchasing and using cost, convenient transportation, wide application range, less terrain constraint conditions and the like, and is widely applied.
When using suspension armful pole hoist and mount group tower technique to carry out iron tower equipment, need use the lifting rope to realize treating the promotion of hoist and mount work piece usually, at present, common hoist and mount mode includes:
1. winding a steel wire sleeve on a workpiece to be hoisted, combining two rope ends of the steel wire sleeve, connecting a shackle and then connecting a hoisting point rope;
2. and winding the workpiece to be hoisted by adopting a flexible hanging strip.
By adopting the two modes, the workpiece to be hoisted is hoisted, the hidden danger that hoisting time is prolonged because hoisting points need to be additionally formed exists, and by adopting the first mode, the steel wire sleeve is easy to deform and distort and is inconvenient to use next time, the steel wire sleeve and the iron tower are easy to damage if the steel wire sleeve does not have a liner at a winding point, a zinc coating of the iron tower is damaged, and the potential safety hazard exists if the steel wire sleeve is damaged; by adopting the second mode, the tower material can not be damaged, but the hidden danger that the sling is easy to damage still exists.
In view of this, the present application is specifically made.
SUMMERY OF THE UTILITY MODEL
Aiming at the problem that the conventional hoisting mode in the prior art needs to establish a connection point, so that the hoisting time is too long, the utility model relates to a hoisting tool for assembling iron towers through a structural design, on one hand, the utility model realizes the quick connection between the hoisting tool and a workpiece to be hoisted through the structural design aiming at hoisting, thereby achieving the purpose of reducing the hoisting time; on the one hand, the utility model discloses still relate to an iron tower assemblage hoist and mount auxiliary assembly, based on above-mentioned hoist, the effectual promotion that realizes iron tower assemblage efficiency.
The utility model discloses a following technical scheme realizes:
the utility model relates to an iron tower assemblage hoist and mount, include: the first locking block is used for being connected with a lifting point rope, the first locking block is provided with a first clamping groove which is used for being matched with the side edge of the angle steel, the end part of one side wall of the first clamping groove is provided with an extension section which extends in the direction far away from the bottom of the first clamping groove, and the extension section is provided with a first connecting through hole; the second clamping groove is used for being matched with the other side edge of the angle steel, a second connecting through hole is formed in the side wall of the second clamping groove, and the axis of the second connecting through hole is parallel to the depth direction of the second clamping groove; the screw structure is detachably matched with the first connecting through hole and the second connecting through hole.
In the scheme, the iron tower assembly hoisting tool comprises a first locking block and a second locking block which are detachably connected through a screw rod structure, the first locking block and the second locking block are respectively provided with a first clamping groove and a second clamping groove which are matched with two side edges of an angle steel, when the iron tower assembly hoisting tool is used for hoisting, the connection of the iron tower assembly hoisting tool and the angle steel of a workpiece to be hoisted is realized through the first locking block and the second locking block respectively, so that a hoisting point is provided, the establishment of the connection relation between the workpiece to be hoisted and a hoisting point rope is convenient, the establishment of the connection relation between the first locking block and the second locking block can be realized directly through the screw rod structure through the use of the iron tower assembly hoisting tool, the hoisting of the workpiece to be hoisted is realized, and compared with the winding mode of a steel wire sleeve or a flexible sling in the prior art, the establishment of the connection relation can be quickly realized, the quick connection between the lifting appliance and the workpiece to be lifted is realized, and the purpose of reducing the lifting time is achieved.
Furthermore, the side walls of the first clamping groove and the second clamping groove are provided with anti-abrasion layers.
Further, the first connecting through hole is formed in the end portion, far away from the first clamping groove, of the extension section.
Furthermore, the first connecting through holes are multiple and are arranged at intervals along the extending direction of the extension section.
Furthermore, the first locking block is also provided with a lifting point structure used for being connected with a lifting point rope, the lifting point structure comprises a lifting ring and a rotating base, the rotating base is rotatably connected with the first locking block through a screw rod, and a rotating shaft of the rotating base is collinear with the axis of the screw rod; the lifting ring is rotatably connected with the rotating base, and the rotating shaft of the lifting ring is perpendicular to the axis of the screw rod.
Second aspect of the invention
The utility model discloses still relate to an iron tower assemblage hoist and mount auxiliary assembly, including foretell iron tower assemblage hoist and mount hoist, still include the fixing base, the fixing base is used for and treats that the hoist and mount work piece is mutually supported, and the motion of hoist and mount work piece on assemblage iron tower surface has been realized to supplementary realization, iron tower assemblage hoist and mount hoist is used for and treats that the hoist and mount work piece is connected, provides the tie point of being connected with the hoisting point rope.
In this scheme, when utilizing above-mentioned iron tower assemblage hoist and mount auxiliary assembly to transport, with the fixing base with treat being connected of hoist and mount work piece, through the supplementary work piece of waiting to hoist and mount of fixing base at the surface motion of assemblage iron tower, and through the setting of above-mentioned tower assemblage hoist and mount hoist, with iron tower assemblage hoist and mount hoist with treat that hoist and mount work piece is connected, form corresponding hoist and mount point to conveniently hoist, through this auxiliary assembly's use, the effectual promotion that realizes iron tower assemblage efficiency.
Further, the fixing base includes the guide rail, the guide rail includes long guide rail and short guide rail, long guide rail with short guide rail collineation sets up, long guide rail pass through rotary device with short guide rail is connected, still including being used for realizing long guide rail with the electric putter of the change of contained angle between the short guide rail, electric putter's both ends are in with the setting respectively long guide rail's first engaging lug, setting are in short guide rail's second engaging lug rotatable coupling.
Furthermore, the guide rail is two, two the guide rail interval sets up, two the guide rail all is provided with electric putter, two electric putter all is provided with the controller, the controller with electric putter one-to-one.
Furthermore, still include supplementary horizontal pole, the both ends of supplementary horizontal pole all are provided with connecting portion, connecting portion are used for dismantling with the iron tower of having assembled and are connected.
Furthermore, the auxiliary cross rod is of a telescopic rod structure.
Compared with the prior art, the utility model, following advantage and beneficial effect have:
the utility model relates to an iron tower assemblage hoist that can realize the establishment of the connection relation of a first locking block and a second locking block directly through a screw structure by using the iron tower assemblage hoist, thereby realizing the hoisting of the workpiece to be hoisted, and compared with the winding way of a steel wire sleeve or a flexible sling in the prior art, the connection relation can be quickly established, the quick connection between the hoist and the workpiece to be hoisted is realized, and the purpose of reducing the hoisting time is achieved;
the utility model relates to an iron tower assemblage hoist and mount auxiliary assembly, based on above-mentioned hoist, through this auxiliary assembly's use, the effectual promotion that realizes iron tower assemblage efficiency.
Drawings
The accompanying drawings, which are included to provide a further understanding of the embodiments of the invention and are incorporated in and constitute a part of this application, illustrate embodiment(s) of the invention and together with the description serve to explain the principle of the invention. In the drawings:
fig. 1 is a schematic structural view of an iron tower erection hoisting tool provided by an embodiment of the present invention;
fig. 2 is a schematic view of the fixing seat, the iron tower erection hoisting tool and the workpiece to be hoisted provided by the embodiment of the present invention;
FIG. 3 is a partial enlarged view of area A in FIG. 2;
FIG. 4 is a partial enlarged view of the area B in FIG. 2;
fig. 5 is a schematic view of an iron tower erection process provided by an embodiment of the present invention;
fig. 6 is a schematic structural view of an auxiliary cross bar according to an embodiment of the present invention;
fig. 7 is a schematic view of the iron tower, the auxiliary cross bar and the fixing base provided by the embodiment of the present invention.
Reference numbers and corresponding part names in the drawings:
110-a first locking block, 111-a first clamping groove, 112-an extension section, 113-a first connecting through hole, 120-a second locking block, 121-a second clamping groove, 122-a second connecting through hole, 131-a hanging ring, 132-a rotating base, 133-a screw, 200-a fixed base, 210-a long guide rail, 211-a first connecting lug, 220-a short guide rail, 221-a second connecting lug, 230-a rotating device, 240-an electric push rod, 300-an auxiliary cross rod, 310-a connecting part, 320-a first rod body, 330-a second rod body, 340-a third rod body, 400-a workpiece to be hoisted and 500-a hoisting point rope.
Detailed Description
To make the objects, technical solutions and advantages of the present invention more apparent, the present invention is further described in detail below with reference to the following examples and drawings, and the exemplary embodiments and descriptions thereof of the present invention are only used for explaining the present invention, and are not intended as limitations of the present invention.
In the following description, numerous specific details are set forth in order to provide a thorough understanding of the present invention. However, it will be apparent to those of ordinary skill in the art that: it is not necessary to employ these specific details to practice the invention. In other instances, well-known structures, circuits, materials, or methods have not been described in detail so as not to obscure the invention.
Throughout the specification, reference to "one embodiment," "an embodiment," "one example," or "an example" means: the particular features, structures, or characteristics described in connection with the embodiment or example are included in at least one embodiment of the present invention. Thus, the appearances of the phrases "one embodiment," "an embodiment," "one example" or "an example" in various places throughout this specification are not necessarily all referring to the same embodiment or example. Furthermore, the particular features, structures, or characteristics may be combined in any suitable combination and/or sub-combination in one or more embodiments or examples. Further, those of ordinary skill in the art will appreciate that the illustrations provided herein are for illustrative purposes and are not necessarily drawn to scale. As used herein, the term "and/or" includes any and all combinations of one or more of the associated listed items.
In the description of the present invention, it should be understood that the terms "front", "back", "left", "right", "upper", "lower", "vertical", "horizontal", "high", "low", "inner", "outer", and the like indicate orientations or positional relationships based on those shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the scope of the present invention.
Examples
As shown in fig. 1, the utility model relates to an iron tower assemblage hoist and mount, include: the first locking block 110 is used for being connected with a hoisting point rope 500, the first locking block 110 is provided with a first clamping groove 111 which is used for being matched with the side edge of an angle steel, the end part of one side wall of the first clamping groove 111 is provided with an extension section 112 which extends in the direction away from the bottom of the first clamping groove 111, and the extension section 112 is provided with a first connecting through hole 113; the second locking block 120 is provided with a second clamping groove 121 used for being matched with the other side edge of the angle steel, the side wall of the second clamping groove 121 is provided with a second connecting through hole 122, and the axis of the second connecting through hole 122 is parallel to the depth direction of the second clamping groove 121; a screw 133 structure, wherein the screw 133 structure is detachably engaged with the first connecting through hole 113 and the second connecting through hole 122.
It should be noted that, as a person skilled in the art knows, in the process of assembling the iron tower, a section of iron tower units are overlapped to realize the assembly of the iron tower, and the corresponding iron tower unit is the workpiece 400 to be hoisted, and the iron tower unit is composed of a plurality of angle steels.
The end of one of the side walls of the first clamping groove 111 is provided with an extension section 112 extending away from the bottom of the first clamping groove 111, that is, for two side walls of the first clamping groove 111, there is a height difference, and the length of one side wall is greater than that of the other side wall.
Wherein, the first locking block 110 and the second locking block 120 are respectively matched with two side edges of the angle iron, specifically, the corresponding matching positions are a first clamping groove 111 and a second clamping groove 121, when the iron tower assembly hoisting sling is matched with the workpiece 400 to be hoisted, the first holding groove 111 and the second holding groove 121 are respectively connected with two side edges, the two side walls are clamped in the first holding groove 111 and the second holding groove 121, the extension segment 112 correspondingly supports the angle iron, and since the first locking block 110 and the second locking block 120 are detachably connected by the screw 133, as a person skilled in the art should know, the first connecting through hole 113 should be spaced apart from the bottom of the first clamping groove 111, and the direct distance between the first connecting through hole and the bottom of the first clamping groove satisfies the width of the side edge of the angle iron, so as to achieve clamping.
In the scheme, the lifting tool for the assembling and hoisting of the iron tower comprises a first locking block 110 and a second locking block 120 which are detachably connected through a screw 133 structure, the first locking block 110 and the second locking block 120 are respectively provided with a first clamping groove 111 and a second clamping groove 121 which are matched with two side edges of an angle steel, when the lifting tool for the assembling and hoisting of the iron tower is used for lifting, the connection between the lifting tool for the assembling and hoisting of the iron tower and the angle steel of a workpiece 400 to be lifted is realized through the first locking block 110 and the second locking block 120 respectively, so that a lifting point is provided, the connection relation between the workpiece 400 to be lifted and a lifting point rope 500 is convenient to establish, through the use of the lifting tool for the assembling and hoisting of the iron tower, the connection relation between the first locking block 110 and the second locking block 120 can be directly realized through the screw 133 structure, the lifting of the workpiece 400 to be lifted is realized, and compared with the winding manner of a steel wire sleeve or a flexible sling in the prior art, the connection relation can be quickly established, the quick connection between the lifting appliance and the workpiece 400 to be lifted is realized, and the purpose of reducing the lifting time is achieved.
In some embodiments, the side walls of the first clamping groove 111 and the second clamping groove 121 are provided with a wear layer.
Wherein, through the structural design of wearing layer, can effectually reduce the influence of treating hoist and mount work piece 400 surface galvanizing coat.
In some embodiments, the first connection through hole 113 is disposed at an end of the extension segment 112 away from the first clamping groove 111.
Further, the first connecting through holes 113 are multiple, and the first connecting through holes 113 are arranged at intervals along the extending direction of the extension section 112.
Wherein, a plurality of the first connecting through holes 113 are arranged at intervals, and as the skilled person should know, the distance between the first connecting through holes 113 and the bottom of the first clamping groove 111 can be changed by matching with different first connecting through holes 113, so that the clamping with different side widths and higher side widths can be realized, and the applicability is improved.
In some embodiments, the first lock block 110 is further provided with a hoisting point structure for connecting with a hoisting point rope 500, the hoisting point structure comprises a hoisting ring 131 and a rotating base 132, the rotating base 132 is rotatably connected with the first lock block 110 through a screw 133, and the rotating shaft of the rotating base 132 is collinear with the axis of the screw 133; the hanging ring 131 is rotatably connected with the rotating base 132, and the rotating shaft of the hanging ring 131 is perpendicular to the axis of the screw 133.
Wherein the rotating base 132 includes, but is not limited to, bearings.
Wherein, as a person skilled in the art should know, the first locking block 110 has a first clamping groove 111, one side wall of the first clamping groove 111 is provided with an extension section 112, and in order to ensure the stability of the hoisting structure, the hoisting structure is preferably arranged at the position of the structure forming the bottom of the first clamping groove 111.
Specifically, first locking piece 110 is provided with the through-hole, rotating base 132 with the through-hole passes through screw 133 and is connected, thereby realizes rotating base 132's rotation, can realize 360 rotation ranges, and to rings 131, its with rotating base 132 rotatable coupling, specifically, rings 131 are U type structure, its open end with rotating base 132's lateral wall rotatable coupling, thereby realizes rings 131 rotates along this hookup location, and because rotating base 132 can rotate, thereby realizes the change of rings 131 place planar direction, thereby better convenient hoist and mount.
As shown in fig. 2-5, the utility model discloses still relate to an iron tower assemblage hoist and mount auxiliary assembly, including foretell iron tower assemblage hoist and mount hoist, still include fixing base 200, fixing base 200 is used for and treats hoist and mount work piece 400 mutually supporting, and the motion of hoisting work piece 400 on the assemblage iron tower surface has been treated in the supplementary realization, iron tower assemblage hoist and mount hoist is used for being connected with treating hoist and mount work piece 400, provides the tie point of being connected with hoisting point rope 500.
Wherein, as should know to skilled person in the art, need hoist when carrying out iron tower assemblage process, the mode of direct hoist and mount work piece 400 of waiting to hoist, there is the risk that work piece 400 of waiting to hoist and mount collides with the assembled iron tower surface to influence the quality of waiting to hoist work piece 400, in prior art, a fixing base 200 is provided and is used for fixing work piece 400 of waiting to hoist, it fixes to wait to hoist work piece 400 one side of fixing base 200, the opposite side of fixing base 200 mutually supports with the assembled iron tower surface, thereby realizes waiting to hoist work piece 400 and follows the surface motion of assembled iron tower, and can avoid direct contact between them, thereby influences the quality of waiting to hoist work piece 400.
Specifically, a connecting piece connected with the workpiece 400 to be hoisted is arranged on a connecting surface between the fixing seat 200 and the workpiece 400 to be hoisted, wherein the connecting piece includes, but is not limited to, a hoop, a buckle and other fixing devices, and the main purpose of the connecting piece is to fix the fixing seat 200 and the workpiece 400 to be hoisted, so as to ensure that the workpiece 400 to be hoisted moves along with the movement of the fixing seat 200.
In order to reduce the friction coefficient between the fixing base 200 and the surface of the assembled iron tower, a teflon layer may be disposed on the corresponding mating surface.
In this scheme, when utilizing above-mentioned iron tower assemblage hoist and mount auxiliary assembly to hoist, with fixing base 200 with treat being connected of hoist and mount work piece 400, through the supplementary work piece 400 of waiting to hoist of fixing base 200 at the surface motion of the iron tower that has been assembled, and through the setting of above-mentioned tower assemblage hoist and mount hoist, with iron tower assemblage hoist and mount hoist and be connected with treat hoist and mount work piece 400, form corresponding hoist and mount point to conveniently hoist, through this auxiliary assembly's use, effectual realization iron tower assemblage efficiency's promotion.
In some embodiments, the fixing base 200 includes a guide rail, the guide rail includes a long guide rail 210 and a short guide rail 220, the long guide rail 210 and the short guide rail 220 are arranged in a collinear manner, the long guide rail 210 is connected with the short guide rail 220 through a rotating device 230, the fixing base further includes an electric push rod 240 for realizing the change of an included angle between the long guide rail 210 and the short guide rail 220, and two ends of the electric push rod 240 are rotatably connected with a first connecting lug 211 arranged on the long guide rail 210 and a second connecting lug 221 arranged on the short guide rail 220, respectively.
Specifically, through the setting of electric putter 240, can directly realize through the extension and the shortening of control electric putter 240 the change of long guide rail 210 and short guide rail 220 contained angle to convenient the regulation.
Specifically, the rotating device 230 includes, but is not limited to, a hinge, and the like.
In some embodiments, the number of the guide rails is two, the two guide rails are arranged at intervals, the two guide rails are both provided with an electric push rod 240, the two electric push rods 240 are both provided with controllers, and the controllers correspond to the electric push rods 240 one to one.
The controller corresponds to the electric push rod 240 one by one, so that the controller and the electric push rod 240 can be adjusted one by one in a targeted manner, and a driving mode with balanced stress, direct stress transmission, smooth rotation and simple structural style is provided through the arrangement of the electric push rod 240.
As shown in fig. 6-7, in some embodiments, the assembled iron tower further includes an auxiliary cross bar 300, and both ends of the auxiliary cross bar 300 are provided with connecting portions 310, and the connecting portions 310 are used for being detachably connected to the assembled iron tower.
As a skilled person in the art will know, for the iron tower structure, not every section has a horizontal material, when there is no horizontal material on the assembled section, the fixing base 200 can be matched with the cross material of the iron tower, and because the cross material is overlapped, there is a certain height difference, so that the left and right of the fixing base 200 are not flat, the left and right positions are difficult to be in place in a point state to be consistent, and the operation in place is inconvenient, and through the arrangement of the auxiliary cross rod 300, for the iron tower end without the horizontal material, the stability of the fixing base 200 can be ensured by the way of autonomously connecting the auxiliary cross rod 300, so as to facilitate the placing of the hoisting workpiece 400.
In some embodiments, the auxiliary cross bar 300 is a telescoping bar structure.
Specifically, aiming at the structural design of the telescopic rod structure, the length adjustment of the auxiliary cross rod 300 can be realized, so that the applicability is improved aiming at different transverse widths corresponding to different heights of the iron tower.
Specifically, supplementary horizontal pole 300 includes first body of rod 320, the second body of rod 330 and the third body of rod 340, the both ends of the second body of rod 330 all are provided with rectangular shape hole, first body of rod 320 and the third body of rod 340 set up respectively the both ends of the second body of rod 330, and the tip that just corresponds is provided with the aperture, and the limited of flexible length is realized to the mode of accessible locating pin, connecting portion 310 sets up the other end of being connected at first body of rod 320 and the third body of rod 340 and second body of rod 330 respectively.
The above-mentioned embodiments, further detailed description of the objects, technical solutions and advantages of the present invention, it should be understood that the above description is only the embodiments of the present invention, and is not intended to limit the scope of the present invention, and any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the scope of the present invention.
Claims (10)
1. The utility model provides an iron tower assemblage hoist and mount which characterized in that includes:
the first locking block (110) is used for being connected with a hoisting point rope, a first clamping groove (111) used for being matched with the side edge of an angle steel is formed in the first locking block (110), an extension section (112) extending in the direction away from the bottom of the first clamping groove (111) is arranged at the end of one side wall of the first clamping groove (111), and a first connecting through hole (113) is formed in the extension section (112);
the second locking block (120) is provided with a second clamping groove (121) which is used for being matched with the other side edge of the angle steel, the side wall of the second clamping groove (121) is provided with a second connecting through hole (122), and the axis of the second connecting through hole (122) is parallel to the depth direction of the second clamping groove (121);
the screw structure is detachably matched with the first connecting through hole (113) and the second connecting through hole (122).
2. The iron tower erection hoisting sling according to claim 1, wherein the side walls of the first clamping groove (111) and the second clamping groove (121) are provided with an anti-wear layer.
3. The iron tower erection hoisting hanger of claim 1, wherein the first connecting through hole (113) is provided at an end of the extension section (112) remote from the first clamping groove (111).
4. The iron tower erection hoisting tool of claim 3, wherein the number of the first connecting through holes (113) is plural, and the plural first connecting through holes (113) are arranged at intervals along the extending direction of the extension section (112).
5. The iron tower erection hoisting tool of any one of claims 1 to 4, wherein the first locking block (110) is further provided with a hoisting point structure for connecting with a hoisting point rope, the hoisting point structure comprises a hoisting ring (131) and a rotating base (132), the rotating base (132) is rotatably connected with the first locking block (110) through a screw (133), and the rotating shaft of the rotating base (132) is collinear with the axis of the screw (133); the hanging ring (131) is rotatably connected with the rotating base (132), and a rotating shaft of the hanging ring (131) is perpendicular to an axis of the screw rod (133).
6. An iron tower assemblage hoisting auxiliary assembly, characterized in that, includes an iron tower assemblage hoisting sling of any one of claims 1-5, further includes a fixing base (200), the fixing base (200) is used for cooperating with the workpiece to be hoisted, the movement of the workpiece to be hoisted on the surface of the assembled iron tower is realized in an auxiliary manner, the iron tower assemblage hoisting sling is used for being connected with the workpiece to be hoisted, and a connection point connected with a hoisting point rope is provided.
7. The iron tower assemblage hoist auxiliary assembly of claim 6, characterized in that fixing base (200) includes a guide rail, the guide rail includes long guide rail (210) and short guide rail (220), long guide rail (210) with short guide rail (220) collineation setting, long guide rail (210) pass through rotary device (230) with short guide rail (220) are connected, still include be used for realizing long guide rail (210) with the change of contained angle between short guide rail (220) electric putter (240), the both ends of electric putter (240) respectively with set up in first engaging lug (211) of long guide rail (210), set up in second engaging lug (221) rotatable coupling of short guide rail (220).
8. The auxiliary assembly for assembling and hoisting iron tower according to claim 7, wherein the number of the guide rails is two, the two guide rails are arranged at intervals, the two guide rails are provided with electric push rods (240), the two electric push rods (240) are provided with controllers, and the controllers correspond to the electric push rods one to one.
9. The assembly for assisting in assembling and hoisting of the iron tower according to any one of claims 6 to 8, further comprising an auxiliary cross bar (300), wherein two ends of the auxiliary cross bar (300) are each provided with a connecting portion (310), and the connecting portions (310) are used for being detachably connected with the assembled iron tower.
10. The auxiliary assembly for assembling and hoisting iron tower as claimed in claim 9, wherein the auxiliary cross bar (300) is a telescopic rod structure.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221205754.7U CN217350388U (en) | 2022-05-19 | 2022-05-19 | Lifting appliance and auxiliary assembly for assembling and hoisting iron tower |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221205754.7U CN217350388U (en) | 2022-05-19 | 2022-05-19 | Lifting appliance and auxiliary assembly for assembling and hoisting iron tower |
Publications (1)
Publication Number | Publication Date |
---|---|
CN217350388U true CN217350388U (en) | 2022-09-02 |
Family
ID=83013719
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202221205754.7U Active CN217350388U (en) | 2022-05-19 | 2022-05-19 | Lifting appliance and auxiliary assembly for assembling and hoisting iron tower |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN217350388U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116715137A (en) * | 2023-08-09 | 2023-09-08 | 国网山西省电力公司晋中供电公司 | Transmission line pole tower traction fixture and crane |
-
2022
- 2022-05-19 CN CN202221205754.7U patent/CN217350388U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116715137A (en) * | 2023-08-09 | 2023-09-08 | 国网山西省电力公司晋中供电公司 | Transmission line pole tower traction fixture and crane |
CN116715137B (en) * | 2023-08-09 | 2023-11-21 | 国网山西省电力公司晋中供电公司 | Transmission line pole tower traction fixture and crane |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN217350388U (en) | Lifting appliance and auxiliary assembly for assembling and hoisting iron tower | |
CN108394809A (en) | Crucible hoisting tooling | |
CN105565146B (en) | Suspension hook holding structure, crane and suspension hook fixing means | |
JP7081150B2 (en) | Guy line holding bracket | |
CN204527220U (en) | Transport trolley | |
CN211226069U (en) | Hoisting machinery for pipeline construction | |
CN108557655A (en) | A kind of pipeline hanging device without spin | |
CN207484304U (en) | Can double width synchronous construction Segmental assembling bridge-erecting machine | |
CN208516840U (en) | A kind of pole and Lift-on/Lift-off System | |
CN216687158U (en) | Track device for cantilever hoisting | |
CN207960496U (en) | Be easily installed drilling tool from hoisting type horizontal boring machine | |
US9862578B2 (en) | Tiltable and rotatable lifting pole assembly | |
CN204917646U (en) | Hoist and mount compensating beam | |
US20220033234A1 (en) | Truss lifter | |
CN207608190U (en) | A kind of major diameter surge shaft brill filling cantilever trolley | |
JP2017154838A (en) | crane | |
CN221644347U (en) | Multi-hanging-point balance crane | |
CN206970002U (en) | A kind of extension type reinforcing bar transportation lifting appliance | |
CN211895795U (en) | Steel pipe hoisting and lifting equipment | |
CN218860148U (en) | Special holding pole and lifting system for hoisting shaft of Yangtze river large-span tower | |
CN218810007U (en) | Auxiliary transfer equipment for high-altitude installation | |
CN113668936B (en) | Auxiliary assembly for erecting and hoisting iron tower | |
CN212198267U (en) | Indoor crane | |
CN215946493U (en) | Lifting appliance for lifting pipe of crown block | |
CN216426495U (en) | Hoist and mount compensating beam |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |