CN217301900U - High-stability pipeline installation device for hydroelectric pipeline engineering - Google Patents

High-stability pipeline installation device for hydroelectric pipeline engineering Download PDF

Info

Publication number
CN217301900U
CN217301900U CN202220108787.3U CN202220108787U CN217301900U CN 217301900 U CN217301900 U CN 217301900U CN 202220108787 U CN202220108787 U CN 202220108787U CN 217301900 U CN217301900 U CN 217301900U
Authority
CN
China
Prior art keywords
pipeline
installation device
wall
base
backup pad
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202220108787.3U
Other languages
Chinese (zh)
Inventor
陈爱兰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Yifang Construction Co Ltd
Original Assignee
Zhejiang Yifang Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Yifang Construction Co Ltd filed Critical Zhejiang Yifang Construction Co Ltd
Priority to CN202220108787.3U priority Critical patent/CN217301900U/en
Application granted granted Critical
Publication of CN217301900U publication Critical patent/CN217301900U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Abstract

The utility model discloses a high-stability pipeline installation device for water and electricity pipeline engineering, which comprises a base, wherein the top of the base is provided with a supporting plate, the top end of the supporting plate is provided with a chute, the inner wall of the chute is connected with the outer walls of two sliding blocks in a sliding way, the top of the supporting plate is provided with two clamping blocks, and the top of the base is provided with two four connecting plates, the two clamping blocks can slide at the top end of the supporting plate, the threaded connection of the bolt and the nut is utilized, the nut is rotated, the two clamping blocks are conveniently fixed and limited by workers, and then the rotating handle is rotated, thereby adjusting the position of the clamping plate, facilitating the workers to clamp and fix the pipelines with different pipe diameters by using the clamping plate, thereby increasing the stability of the device and the clamping of the pipeline and simultaneously increasing the application range of the device.

Description

High-stability pipeline installation device for hydroelectric pipeline engineering
Technical Field
The utility model relates to a water and electricity pipeline engineering technical field specifically is a high water and electricity pipeline engineering pipeline installation device of stability.
Background
The pipeline is a device which is formed by connecting pipes, pipe connectors, valves and the like and used for conveying gas, liquid or fluid with solid particles, the pipeline is required to be installed in most of current hydroelectric engineering, the pipeline is very commonly and widely used in the construction process of the hydroelectric engineering, the installation of the pipeline refers to clamping or positioning the pipeline in the process of installing the pipeline, but the currently used pipeline installation device still has some defects:
1. traditional pipe installation device lacks the regulation structure when fixing the centre gripping to the water and electricity pipeline, leads to the pipeline centre gripping to different pipe diameters stable inadequately, and the phenomenon that rocks can appear in the pipeline when installing the pipeline, and inconvenient staff installs.
2. Meanwhile, the traditional installation device lacks of a height adjusting structure when in use, so that the height of the traditional installation device cannot be adjusted according to actual pipeline installation, the traditional installation device is very limited in use, and the traditional installation device is inconvenient for workers to use.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a water and electricity piping engineering for pipe-line installation device that stability is high to what put forward leads to the pipe centre gripping to different pipe diameters among the solution above-mentioned background art stable inadequately and can't be according to the problem of highly adjusting of actual piping erection.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a water and electricity pipeline installation device for engineering that stability is high, the on-line screen storage device comprises a base, the top of base is equipped with the backup pad, the spout has been seted up on the top of backup pad, the inner wall of spout and the outer wall sliding connection of two sliders, the top of backup pad is equipped with two clamp splices, the top of base is equipped with two four connecting plates, the top of backup pad is equipped with two splint, the top of backup pad is equipped with two and changes the handle, the bottom of backup pad is equipped with two electric telescopic handle.
Preferably, the top ends of the two sliding blocks are respectively and highly connected with the bottom ends of the clamping blocks, and arc-shaped grooves are respectively formed in one sides of the two clamping blocks.
Preferably, through grooves are formed in two sides of the supporting plate respectively, the inner walls of the through grooves are connected with the outer walls of the two connecting plates in a sliding mode respectively, and one ends of the four connecting plates are fixedly connected with one sides of the two sliding blocks respectively.
Preferably, the other ends of the four connecting plates are respectively provided with a first threaded hole, the inner walls of the two first threaded holes are respectively in threaded connection with the outer wall of the bolt, and the outer walls of the two bolts are respectively in threaded connection with the inner wall of the nut.
Preferably, the inside of two clamp splice has seted up the cavity respectively, and two the opposite side of clamp splice has seted up second screw hole respectively, two the inner wall of second screw hole respectively with the outer wall threaded connection of bull stick, two the one end of bull stick respectively with one side fixed connection of splint, two the outer wall of splint respectively with the inner wall swing joint of cavity, two the other end of bull stick respectively with the one end fixed connection of commentaries on classics handle.
Preferably, two empty slots are formed in the top end of the base, the bottom ends of the inner walls of the two empty slots are fixedly connected with the bottom ends of the electric telescopic rods respectively, the top ends of the two electric telescopic rods are fixedly connected with the bottom end of the supporting plate, and the bottom end of the base is fixedly connected with the top end of the non-slip mat.
Preferably, the one end fixed mounting of base has the switch, two electric telescopic handle all passes through switch and external power electric connection.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses a be provided with backup pad, spout, slider, clamp splice, connecting plate, bolt and splint, utilize the sliding structure that spout and slider constitute, make two clamp splices can slide at the top of backup pad, utilize the threaded connection of bolt and nut, rotate the nut, make things convenient for the staff to fix spacing to two clamp splices, subsequently through rotating the twist grip, thereby adjust the position of splint, make things convenient for the staff to utilize the splint to carry out the centre gripping fixedly to the pipeline of different pipe diameters, thereby increased the application range of the device when having increased the stability of the device and pipeline centre gripping;
2. the utility model discloses a be provided with backup pad, electric telescopic handle and slipmat, utilize electric telescopic handle's scalability, through adjusting electric telescopic handle to make things convenient for the staff to highly adjust the backup pad according to actual need, thereby make things convenient for the high position of work adjusting pipe way, through the slipmat that sets up, increased the device and the frictional force on ground, increased the device's stability, made things convenient for staff's use.
Drawings
Fig. 1 is a schematic overall structure diagram of the present invention;
FIG. 2 is a partial schematic structural view of the present invention;
FIG. 3 is a schematic sectional view of the whole structure of the present invention;
fig. 4 is an enlarged view of a point a in fig. 1.
In the figure: 1. a base; 2. a support plate; 3. a chute; 4. a slider; 5. a clamping block; 6. an arc-shaped slot; 7. a through groove; 8. a connecting plate; 9. a first threaded hole; 10. a bolt; 11. a nut; 12. a cavity; 13. a second threaded hole; 14. a rotating rod; 15. a splint; 16. turning a handle; 17. an empty groove; 18. an electric telescopic rod; 19. a non-slip mat; 20. and (4) switching.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
The first embodiment is as follows:
referring to fig. 1-4, the utility model provides a high-stability pipeline installation device for water and electricity pipeline engineering technical scheme: a high-stability pipeline installation device for water and electricity pipeline engineering comprises a base 1, wherein a supporting plate 2 is arranged at the top of the base 1, a sliding groove 3 is formed in the top end of the supporting plate 2, the inner wall of the sliding groove 3 is in sliding connection with the outer walls of two sliding blocks 4, two clamping blocks 5 are arranged at the top of the supporting plate 2, two four connecting plates 8 are arranged at the top of the base 1, two clamping plates 15 are arranged at the top of the supporting plate 2, two rotating handles 16 are arranged at the top of the supporting plate 2, two electric telescopic rods 18 are arranged at the bottom end of the supporting plate 2, the top ends of the two sliding blocks 4 are respectively and highly connected with the bottom ends of the clamping blocks 5, an arc-shaped groove 6 is respectively formed in one side of each clamping block 5, through grooves 7 are respectively formed in two sides of the supporting plate 2, the inner walls of the two through grooves 7 are respectively and slidably connected with the outer walls of the two connecting plates 8, one ends of the four connecting plates 8 are respectively and fixedly connected with one side of the two sliding blocks 4, the other ends of the four connecting plates 8 are respectively provided with first threaded holes 9, the inner walls of the two first threaded holes 9 are respectively in threaded connection with the outer walls of bolts 10, the outer walls of the two bolts 10 are respectively in threaded connection with the inner wall of a nut 11, the interiors of the two clamping blocks 5 are respectively provided with a cavity 12, the other sides of the two clamping blocks 5 are respectively provided with a second threaded hole 13, the inner walls of the two second threaded holes 13 are respectively in threaded connection with the outer wall of a rotating rod 14, one ends of the two rotating rods 14 are respectively fixedly connected with one side of a clamping plate 15, the outer walls of the two clamping plates 15 are respectively movably connected with the inner wall of the cavity 12, and the other ends of the two rotating rods 14 are respectively fixedly connected with one end of a rotating handle 16;
example two:
on the basis of the first embodiment, as shown in fig. 1 to 4, two empty slots 17 are formed in the top end of the base 1, the bottom ends of the inner walls of the two empty slots 17 are respectively and fixedly connected with the bottom ends of the electric telescopic rods 18, the top ends of the two electric telescopic rods 18 are both and fixedly connected with the bottom end of the supporting plate 2, the bottom end of the base 1 is fixedly connected with the top end of the anti-skid pad 19, a switch 20 is fixedly mounted at one end of the base 1, and the two electric telescopic rods 18 are both electrically connected with an external power supply through the switch 20.
The working principle is as follows: when the device is used, the device is externally connected with a power supply, a worker places one end of a pipeline between two clamping blocks 5, then utilizes a sliding structure consisting of a sliding groove 3 and a sliding block 4, utilizes the fixed connection between the sliding block 4 and the clamping blocks 5, so that the two clamping blocks 5 can slide at the top end of a supporting plate 2, then utilizes an arc-shaped groove 6 formed in the two clamping blocks 5 to clamp and fix the outer wall of the pipeline, then passes two bolts 10 through four first threaded holes 9, then utilizes the threaded connection between a nut 11 and the bolt 10, rotates the nut 11, so that the two bolts 10 fix a connecting plate 8, so that the clamping blocks 5 are convenient for the worker to fix the clamping blocks 5, and then when the worker needs to accurately arrange pipelines with different pipe diameters, the worker rotates a rotating handle 16 through the threaded connection between a rotating rod 14 and a second threaded hole 13, so as to drive the rotating rod 14 to rotate inside the clamping blocks 5, thereby drive splint 15 and remove in the inside of clamp splice 5 to make things convenient for the staff to utilize splint 15 to carry out spacing fixed to the pipeline of different pipe diameters, open switch 20 afterwards, start electric telescopic handle 18, utilize electric telescopic handle 18's scalability, make things convenient for the staff to adjust the height of backup pad 2 according to actual need, thereby make things convenient for the work to adjust the height of pipeline as required, increased the device's application range, made things convenient for staff's use.
In the description of the present invention, it should be understood that the indicated orientation or positional relationship is based on the orientation or positional relationship shown in the drawings, and is only for convenience of description and simplification of description, and does not indicate or imply that the indicated device or element must have a particular orientation, be constructed and operated in a particular orientation, and thus should not be construed as limiting the present invention.
In the present invention, unless otherwise explicitly specified or limited, for example, it may be fixedly connected, detachably connected, or integrated; can be mechanically or electrically connected; they may be directly connected or indirectly connected through an intermediate medium, and may be connected through the inside of two elements or in an interaction relationship between two elements, unless otherwise specifically defined, and the specific meaning of the above terms in the present invention will be understood by those skilled in the art according to specific situations.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. The utility model provides a water and electricity pipeline installation device for engineering that stability is high, includes base (1), its characterized in that: the top of base (1) is equipped with backup pad (2), spout (3) have been seted up on the top of backup pad (2), the inner wall of spout (3) and the outer wall sliding connection of two slider (4), the top of backup pad (2) is equipped with two clamp splice (5), the top of base (1) is equipped with two four connecting plates (8), the top of backup pad (2) is equipped with two splint (15), the top of backup pad (2) is equipped with two and changes handle (16), the bottom of backup pad (2) is equipped with two electric telescopic handle (18).
2. A high stability pipeline installation device for hydroelectric pipeline engineering according to claim 1, wherein: the top ends of the two sliding blocks (4) are respectively and highly connected with the bottom ends of the clamping blocks (5), and arc-shaped grooves (6) are respectively formed in one sides of the two clamping blocks (5).
3. A high stability pipeline installation device for hydroelectric pipeline engineering according to claim 1, wherein: the two sides of the supporting plate (2) are respectively provided with a through groove (7), the inner walls of the through grooves (7) are respectively connected with the outer walls of the two connecting plates (8) in a sliding mode, and one end of each connecting plate (8) is fixedly connected with one side of each sliding block (4).
4. A high stability pipeline installation device for hydroelectric pipeline engineering according to claim 1, wherein: first threaded holes (9) are formed in the other ends of the four connecting plates (8), the inner walls of the two first threaded holes (9) are in threaded connection with the outer wall of a bolt (10), and the outer walls of the two bolts (10) are in threaded connection with the inner wall of a nut (11).
5. A high stability pipeline installation device for hydroelectric pipeline engineering according to claim 1, wherein: two cavity (12) have been seted up respectively to the inside of clamp splice (5), two second screw hole (13) have been seted up respectively to the opposite side of clamp splice (5), two the inner wall of second screw hole (13) respectively with the outer wall threaded connection of bull stick (14), two the one end of bull stick (14) respectively with one side fixed connection of splint (15), two the outer wall of splint (15) respectively with the inner wall swing joint of cavity (12), two the other end of bull stick (14) respectively with the one end fixed connection who changes handle (16).
6. A high stability pipeline installation device for hydroelectric pipeline engineering according to claim 1, wherein: two empty slots (17) are formed in the top end of the base (1), the bottom ends of the inner walls of the two empty slots (17) are fixedly connected with the bottom ends of the electric telescopic rods (18) respectively, the top ends of the electric telescopic rods (18) are fixedly connected with the bottom end of the supporting plate (2), and the top end of the bottom end fixing anti-skid pad (19) of the base (1) is fixedly connected with the top end.
7. A high stability pipeline installation device for hydroelectric pipeline engineering according to claim 1, wherein: the one end fixed mounting of base (1) has switch (20), two electric telescopic handle (18) all are through switch (20) and external power supply electric connection.
CN202220108787.3U 2022-01-17 2022-01-17 High-stability pipeline installation device for hydroelectric pipeline engineering Expired - Fee Related CN217301900U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220108787.3U CN217301900U (en) 2022-01-17 2022-01-17 High-stability pipeline installation device for hydroelectric pipeline engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220108787.3U CN217301900U (en) 2022-01-17 2022-01-17 High-stability pipeline installation device for hydroelectric pipeline engineering

Publications (1)

Publication Number Publication Date
CN217301900U true CN217301900U (en) 2022-08-26

Family

ID=82925736

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220108787.3U Expired - Fee Related CN217301900U (en) 2022-01-17 2022-01-17 High-stability pipeline installation device for hydroelectric pipeline engineering

Country Status (1)

Country Link
CN (1) CN217301900U (en)

Similar Documents

Publication Publication Date Title
CN211117991U (en) Cities and towns natural gas line lays protector
CN217301900U (en) High-stability pipeline installation device for hydroelectric pipeline engineering
CN211220487U (en) Gas pipeline butt joint fixing device
CN213827281U (en) Waste pipeline cutting equipment with segmented cutting function
CN211621677U (en) Underground pipe gallery formwork construction structure
CN218719339U (en) Pipeline support frame
CN219649117U (en) Flange welding equipment for pipeline connection
CN218573227U (en) Packed tower fan with multiple mounting modes
CN218378038U (en) Municipal administration water supply and drainage construction pipeline butt-joint equipment
CN203316780U (en) Anchor rod drilling fixture of screw anchor
CN212584421U (en) Combined pipe gallery support with high shock strength
CN211449886U (en) Pipeline fixing device for water supply engineering
CN213452118U (en) Anti-seismic support with balanced tension
CN108953771B (en) Pipeline installation device for water and electricity pipeline engineering
CN217234631U (en) Pipeline positioning support for water supply and drainage engineering
CN214870083U (en) Temporary pipeline supporting device during butt joint of gas pipelines
CN220613687U (en) Auxiliary clamping mechanism for double-wall pipe machining
CN213177076U (en) Hydraulic and hydroelectric engineering that conveniently operates is with pipe laying fixing device
CN217519365U (en) Pipeline suspension structure for municipal engineering piping lane construction
CN220882115U (en) Water supply and drainage pipeline fixed bolster
CN220668612U (en) High-stability gas equipment mounting bracket
CN217519371U (en) Heat distribution pipeline anti-settling device for urban heating
CN218118860U (en) Pipeline connection supporting mechanism for water conservancy construction
CN213452210U (en) Tube head locking device for mounting outdoor pipe network
CN216158607U (en) Delivery pump support convenient to quick travel is fixed

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20220826

CF01 Termination of patent right due to non-payment of annual fee