CN217270362U - Pipeline design of steam turbine waste heat power generation system - Google Patents

Pipeline design of steam turbine waste heat power generation system Download PDF

Info

Publication number
CN217270362U
CN217270362U CN202123261866.2U CN202123261866U CN217270362U CN 217270362 U CN217270362 U CN 217270362U CN 202123261866 U CN202123261866 U CN 202123261866U CN 217270362 U CN217270362 U CN 217270362U
Authority
CN
China
Prior art keywords
steam
turbine
pipeline
connecting line
surge tank
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202123261866.2U
Other languages
Chinese (zh)
Inventor
费秀国
林钢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Daneng Power Technology Co ltd
Original Assignee
Nanjing Daneng Power Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Daneng Power Technology Co ltd filed Critical Nanjing Daneng Power Technology Co ltd
Priority to CN202123261866.2U priority Critical patent/CN217270362U/en
Application granted granted Critical
Publication of CN217270362U publication Critical patent/CN217270362U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P80/00Climate change mitigation technologies for sector-wide applications
    • Y02P80/10Efficient use of energy, e.g. using compressed air or pressurized fluid as energy carrier
    • Y02P80/15On-site combined power, heat or cool generation or distribution, e.g. combined heat and power [CHP] supply

Landscapes

  • Turbine Rotor Nozzle Sealing (AREA)

Abstract

The utility model discloses a steam turbine waste heat power generation system's pipeline design, including turbine, hydrophobic expansion tank, surge tank and steam conduit, the surge tank provides steam seal for the turbine both sides, steam conduit inserts turbine, hydrophobic expansion tank and surge tank's steam inlet respectively through connecting line one, connecting line two, connecting line three, still the intercommunication has the condensate pipe line on the surge tank, the steam outlet of turbine has the condenser through exhaust pipe connection, the delivery port of condenser passes through water source pipeline intercommunication surge tank. Compared with the prior art, the utility model the advantage lie in: the pipeline system of the steam turbine with a simple structure is utilized, the complexity of the pipeline is avoided, and the investment cost is reduced.

Description

Pipeline design of steam turbine waste heat power generation system
Technical Field
The utility model relates to a steam turbine technical field specifically indicates a steam turbine waste heat power generation system's pipeline design.
Background
At present, some redundant medium-low temperature steam is directly discharged for some industrial enterprises, waste of heat resources is caused, the steam is utilized to drive a steam turbine or a turbine to rotate to generate electric energy, therefore, exhaust steam discharged from a steam outlet of the steam turbine is condensed into water through a condenser, the water is conveyed to a boiler for cyclic utilization, and in the process, much energy exchange is involved, the structure is complex, the number of pipelines is large, and the control is complex and variable.
SUMMERY OF THE UTILITY MODEL
The to-be-solved technical problem of the utility model is to overcome above technical defect, provide a pipeline system who utilizes the steam turbine of simple structure, avoid the pipeline to combine complicatedly to and reduce input cost's a steam turbine waste heat power generation system's pipeline design.
Solve the technical problem, the utility model provides a technical scheme does: the utility model provides a steam turbine waste heat power generation system's pipeline design, includes turbine, hydrophobic expansion tank, surge tank and steam conduit, the surge tank provides steam seal for the turbine both sides, steam conduit inserts the steam inlet of turbine, hydrophobic expansion tank and surge tank respectively through connecting line one, connecting line two, connecting line three, still the intercommunication has condensation water pipeline on the surge tank, the steam outlet of turbine has the condenser through exhaust pipe connection, the delivery port of condenser passes through water source pipeline intercommunication surge tank.
Furthermore, a regulating valve and a quick-closing valve are arranged on the first connecting pipeline, valves are arranged on the second connecting pipeline and the third connecting pipeline, and electromagnetic valves are arranged on the second connecting pipeline and the condensed water pipeline.
Furthermore, two ends of a rotating shaft of the turbine are connected with steam sealing devices for steam sealing, and a steam outlet pipeline of the pressure equalizing box is connected with the steam sealing devices at the two ends.
Compared with the prior art, the utility model the advantage lie in:
1. the pipeline system has simple structure, convenient installation and convenient maintenance and replacement;
2. the device can be suitable for units such as superheated steam, saturated steam and the like;
3. the cost can be reduced.
Drawings
Fig. 1 is a piping layout diagram of a steam turbine cogeneration system.
In the drawings: 1. the steam turbine comprises a turbine, 2, a hydrophobic expansion tank, 3, a pressure equalizing tank, 4, a steam pipeline, 5, a first connecting pipeline, 6, a second connecting pipeline, 7, a third connecting pipeline, 8, a condensed water pipeline, 9, a steam exhaust pipeline, 10, a condenser, 11, a water source pipeline, 12, a regulating valve, 13, a quick closing valve, 14, a valve, 15, an electromagnetic valve, 16, a steam outlet pipeline, 17 and a steam sealing device.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
Referring to fig. 1, a pipeline design of a steam turbine waste heat power generation system comprises a turbine 1, a hydrophobic expansion tank 2, a pressure equalizing tank 3 and a steam pipeline 4, wherein two ends of a rotating shaft of the turbine 1 are connected with steam sealing devices 17 for steam sealing, a steam outlet pipeline 16 of the pressure equalizing tank 3 is connected with the steam sealing devices 17 at two ends, the steam pipeline 4 is respectively connected with steam inlets of the turbine 1, the hydrophobic expansion tank 2 and the pressure equalizing tank 3 through a first connecting pipeline 5, a second connecting pipeline 6 and a third connecting pipeline 7, the pressure equalizing tank 3 is further communicated with a condensed water pipeline 8, a steam outlet of the turbine 1 is connected with a condenser 10 through a steam exhaust pipeline 9, a water outlet of the condenser 10 is communicated with the pressure equalizing tank 3 through a water source pipeline 11, the first connecting pipeline 5 is provided with a regulating valve 12 and a quick closing valve 13, the second connecting pipeline 6 and the third connecting pipeline 7 are provided with valves 14, all be equipped with solenoid valve 15 on connecting line two 6 and the condensate pipe 8, utilize solenoid valve 15 can be according to the temperature and the pressure regulation aperture of local pressure incasement, realize automated control, valve 14 can provide the safety guarantee, and cooperation solenoid valve 15 forms dual guarantee, and the exhaust steam of the play steam port exhaust of turbine 1 afterbody is carried to condenser 10, continues to utilize as the water source after the condensation.
The utility model provides a simple structure, reasonable in design's steam turbine pipe-line system is applicable to waste heat excess pressure electricity generation field, also can adapt to the undulant and change of scope of steam turbine load completely.
The present invention and the embodiments thereof have been described above, but the description is not limited thereto, and the embodiment shown in the drawings is only one of the embodiments of the present invention, and the actual structure is not limited thereto. In summary, those skilled in the art should understand that they can devise similar structural modes and embodiments without departing from the spirit of the present invention, and shall fall within the protection scope of the present invention.

Claims (3)

1. The utility model provides a pipeline of steam turbine waste heat power generation system, includes turbine (1), hydrophobic expansion tank (2), surge tank (3) and steam conduit (4), its characterized in that: the steam seal is provided for turbine (1) both sides in surge tank (3), steam conduit (4) insert the steam inlet of turbine (1), hydrophobic expansion tank (2) and surge tank (3) respectively through connecting line one (5), connecting line two (6), connecting line three (7), still the intercommunication has condensate pipe way (8) on surge tank (3), the steam outlet of turbine (1) is connected with condenser (10) through exhaust pipe way (9), the delivery port of condenser (10) passes through water source pipeline (11) intercommunication surge tank (3).
2. The steam turbine cogeneration system of claim 1, wherein said steam turbine further comprises: be equipped with governing valve (12) and quick-closing valve (13) on connecting line (5), all be equipped with valve (14) on connecting line two (6) and connecting line three (7), all be equipped with solenoid valve (15) on connecting line two (6) and condensate pipe (8).
3. The steam turbine cogeneration system of claim 1, wherein said steam turbine further comprises: two ends of a rotating shaft of the turbine (1) are connected with steam sealing devices (17) used for steam sealing, and a steam outlet pipeline (16) of the pressure equalizing box (3) is connected with the steam sealing devices (17) at two ends simultaneously.
CN202123261866.2U 2021-12-23 2021-12-23 Pipeline design of steam turbine waste heat power generation system Active CN217270362U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202123261866.2U CN217270362U (en) 2021-12-23 2021-12-23 Pipeline design of steam turbine waste heat power generation system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202123261866.2U CN217270362U (en) 2021-12-23 2021-12-23 Pipeline design of steam turbine waste heat power generation system

Publications (1)

Publication Number Publication Date
CN217270362U true CN217270362U (en) 2022-08-23

Family

ID=82888451

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202123261866.2U Active CN217270362U (en) 2021-12-23 2021-12-23 Pipeline design of steam turbine waste heat power generation system

Country Status (1)

Country Link
CN (1) CN217270362U (en)

Similar Documents

Publication Publication Date Title
WO2020181675A1 (en) Flexible coal-fired power generation system, and operation method therefor
CN105697075A (en) Extraction condensing heat supply system additionally provided with non-reheat medium-pressure steam turbine
JPS6193208A (en) Turbine bypass system
JP2021014839A (en) Steam power generation plant, modification method for steam power generation plant, and operation method for steam power generation plant
CN113175362B (en) Bus pipe connection system for realizing zero output of low-pressure cylinder and operation method
CN214275885U (en) Low pressure bypass heat supply of thermal power plant reforms transform structure
CN107178398B (en) Thermoelectric decoupling system for improving energy utilization quality of thermal power plant
CN113175363A (en) Master pipe connection system for adjusting high-pressure cylinder to do work and operation method
CN210509309U (en) Steam complementary energy utilization coupling steam extraction heat supply system for thermoelectric unit electric power peak regulation
CN110793011A (en) Two-stage steam extraction type medium-temperature and medium-pressure waste incineration power generation system and use method thereof
CN217270362U (en) Pipeline design of steam turbine waste heat power generation system
CN113175360A (en) Bus pipe connection system for improving deep peak shaving low-pressure cylinder efficiency and operation method
CN206755145U (en) Turbine high-pressure bypasses desuperheat water lines
CN113175367A (en) Master control system for improving peak regulation capacity and flexibility of unit and operation method
CN109826680B (en) Steam distribution system based on mother pipe control of different parameter grade units and application method
CN111237735A (en) Emergency industrial steam supply system for realizing shutdown and non-shutdown of large coal-fired generator set
CN113494321B (en) High-pressure cylinder zero-output-force-based bus pipe connection system and operation method
CN214275750U (en) Two main pipe segmentation main steam pipe-line system of msw incineration power generation
CN214035809U (en) Steam pipeline system of multi-shaft gas and steam combined cycle unit
CN210485839U (en) Heat supply system
CN113250770A (en) Thermal power generating unit non-external steam source starting system and method
CN203215658U (en) Expansible low-pressure coal economizer system
CN110925730A (en) Emergency industrial heating system based on shutdown and non-shutdown of coal-fired generating set
CN213807769U (en) Waste heat utilization structure of steam turbine shaft seal system
CN215597384U (en) Interconnected mutual-backup heat supply system without shutdown and shutdown