CN217264208U - Tool type tool for hoisting prefabricated well - Google Patents
Tool type tool for hoisting prefabricated well Download PDFInfo
- Publication number
- CN217264208U CN217264208U CN202220799809.5U CN202220799809U CN217264208U CN 217264208 U CN217264208 U CN 217264208U CN 202220799809 U CN202220799809 U CN 202220799809U CN 217264208 U CN217264208 U CN 217264208U
- Authority
- CN
- China
- Prior art keywords
- well body
- prefabricated well
- rod
- prefabricated
- padlock
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Abstract
The utility model provides a prefabricated well is instrument formula frock for hoist and mount, including the bracing piece of a plurality of lower extremes removable being fixed in prefabricated well body upper end, the bracing piece upper end is removable to be linked firmly the padlock subassembly, and the cable tip of being connected with the lifting hook of lifting equipment lower extreme passes through padlock subassembly detachable connections in bracing piece upper end, and lifting equipment targets in place prefabricated well body handling and makes bracing piece and prefabricated well body split, realizes breaking away from fast of prefabricated well body and frock. The utility model discloses a frock of constituteing after the padlock subassembly that the upper end is connected through cable and hoisting equipment and detachable installation in the bracing piece of prefabricated well body upper end, realize the quick installation and the turnover of frock and the prefabricated well body, the lifting hook of hoisting equipment lower extreme passes through cable and padlock subassembly detachable connection, make the prefabricated well body have 360 rotatory advantages at the hoist and mount in-process, solve the well body and hang the needs of taking one's place back prefabricated well body reservation hole different angles, avoid hoist and mount process damage well body structure, improve the efficiency of taking one's place of outdoor pipe network prefabricated well body hoist and mount.
Description
Technical Field
The utility model belongs to the technical field of outdoor pipe network construction, concretely relates to instrument formula frock is used in prefabricated well hoist and mount.
Background
At present, in the construction process of an outdoor pipe network prefabricated well body, the well body hoisting installation must meet the precision requirement; traditional steel cable hoist and mount need stabilize the settlement to the object, and send the special messenger to supervise, when the steel cable hoist and mount target in place, need carry out the steel cable in the hawser below and remove, personnel's safety is difficult to guarantee, can't make lifting rope and well body break away from fast and carry out all the other well body hoists, hoist and mount inefficiency, and can't guarantee removing the precision of in-process hoist and mount, prefabricated well preformed hole is circular in addition, consider the connection of follow-up well body and both arms bellows in the installation, the hole will satisfy not equidirectional demand, therefore, in order to solve above-mentioned problem, it is necessary to propose the improvement.
SUMMERY OF THE UTILITY MODEL
The utility model provides a technical problem: the utility model provides a prefabricated well is hoist and mount and is used instrument formula frock, adopt the upper end to pass through cable and the padlock subassembly that lifts by crane the equipment connection and the frock of removable back constitution of installing in prefabricated well body upper end bracing piece connection, realize quick installation and the turnover of frock and prefabricated well body, hoisting efficiency improves greatly, the lifting hook of lifting by crane the equipment lower extreme passes through cable and padlock subassembly removable connection, make prefabricated well body have 360 rotatory advantages at the hoist and mount in-process, solve the well body and hang the needs of putting the different angles of prefabricated well body preformed hole in the in-process of taking one's place, avoid hoist and mount process damage well body structure, improve outdoor pipe network prefabricated well body hoist efficiency of taking one's place.
The utility model adopts the technical proposal that: prefabricated well is instrument formula frock for hoist and mount, including the bracing piece of a plurality of lower extremes removable be fixed in prefabricated well body upper end, the removable padlock subassembly that links firmly in upper end of the support bar, and the cable tip of being connected with the lifting hook of lifting by crane the equipment lower extreme passes through padlock subassembly detachable connection in upper end of the support bar, it targets in place prefabricated well body handling and makes bracing piece and prefabricated well body split back to lift by crane the equipment, realizes breaking away from fast of prefabricated well body and frock.
The suspension lock assembly comprises a U-shaped suspension lock and a fastening bolt, the supporting rod is of an L-shaped rod-shaped structure, a through hole for the fastening bolt to pass through is formed in the side wall of the upper end of the supporting rod, the opening of the U-shaped suspension lock is arranged downwards, connecting holes corresponding to the positions are formed in the outer side walls of the two lower ends of the U-shaped suspension lock, the fastening bolt sequentially penetrates through the connecting holes and the through holes in the upper end of the supporting rod to be connected with a locking nut in an adaptive mode, and the lower lifting ring fixed at the lower end is sleeved on the cable on the U-shaped suspension lock and detachably fixedly connected with the upper end of the supporting rod into a whole.
Furthermore, a vertical hole is formed in the horizontal rod at the lower end of the supporting rod in the L-shaped rod-shaped structure, the horizontal rod at the lower end of the supporting rod penetrates through a preformed hole in the side wall of the upper end of the prefabricated well body, and the supporting rod is detachably installed on the prefabricated well body through a T-shaped bolt inserted into the vertical hole of the horizontal rod of the supporting rod through the vertical rod at the lower end.
Furthermore, at least four support rods are distributed on the outer wall of the upper end of the prefabricated well body in a balanced mode, at least two cables are connected with a lifting hook at the lower end of the lifting device through an upper lifting ring, and a lower lifting ring fixed to the two lower ends of each cable is connected with a corresponding lifting lock assembly.
The utility model has the advantages compared with the prior art:
1. according to the technical scheme, the tool is formed by connecting the lifting lock assembly with the lifting equipment at the upper end through the cable and the support rod detachably arranged at the upper end of the prefabricated well body, so that the tool and the prefabricated well body are quickly installed and circulated, and the lifting efficiency is greatly improved;
2. according to the technical scheme, round steel is manufactured into an L-shaped rod to serve as a bearing rod, one end with a vertical hole penetrates through a preformed hole of a prefabricated well body, a T-shaped bolt inserted into the vertical hole is used for fixing the bearing rod to the prefabricated well, a lower hanging ring at the end part of a hoisting cable penetrates through a U-shaped hanging lock, and finally the U-shaped hanging lock and the bearing rod are connected through a fastening bolt, so that the prefabricated well body has the advantage of 360-degree rotation in the hoisting process, the requirement of different angles of the preformed hole of the prefabricated well body in the hoisting and placing process of the prefabricated well body is met, and the well body structure is prevented from being damaged in the hoisting process;
3. this technical scheme structure is succinct, the security is high, and the angle modulation is convenient after the prefabricated well body hoists, for the prefabricated well body hoist precision of taking one's place provides the angle modulation condition, improves the prefabricated well body hoist efficiency of taking one's place of outdoor pipe network, and easy dismounting can hoist the prefabricated well body of not unidimensional.
Drawings
FIG. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic view of the usage state of the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to fig. 1-2 in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
It should be noted that, in this document, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation. The use of the phrase "comprising one of the elements" does not exclude the presence of other like elements in the process, method, article, or apparatus that comprises the element.
The tool type tool for hoisting the prefabricated well comprises a plurality of support rods 1 with the lower ends detachably fixed at the upper ends of prefabricated well bodies 5, wherein the upper ends of the support rods 1 are detachably and fixedly connected with hoisting lock assemblies 2, the end parts of cables 4 connected with lifting hooks at the lower ends of hoisting equipment are detachably connected to the upper ends of the support rods 1 through the hoisting lock assemblies 2, and the hoisting equipment hoists the prefabricated well bodies 5 in place and enables the support rods 1 and the prefabricated well bodies 5 to be detached, so that the prefabricated well bodies 5 are quickly separated from the tool; in the structure, the tool is formed by connecting the lifting lock assembly 2 with the lifting equipment at the upper end through the cable 4 and the support rod 1 detachably arranged at the upper end of the prefabricated well body 5, so that the tool and the prefabricated well body 5 are quickly installed and rotated, and the lifting efficiency is greatly improved;
the specific structure of the padlock assembly 2 is as follows: the padlock component 2 comprises a U-shaped padlock 2-1 and fastening bolts 2-2, the supporting rod 1 is of an L-shaped rod-shaped structure, through holes for the fastening bolts 2-2 to pass through are formed in the side wall of the upper end of the supporting rod 1, the U-shaped padlock 2-1 is arranged with an opening facing downwards, connecting holes corresponding in position are formed in the outer side walls of the two lower ends of the U-shaped padlock 2-1, and after the fastening bolts 2-2 sequentially pass through the connecting holes and the through holes in the upper end of the supporting rod 1 to be in adaptive connection with the locking nuts, the cable 4 with the lower end fixed and sleeved on the U-shaped padlock 2-1 is detachably and fixedly connected with the upper end of the supporting rod 1 into a whole.
The detachable connection structure of the lower end of the support rod 1 and the prefabricated well body 5 is as follows: a horizontal rod at the lower end of a support rod 1 in an L-shaped rod-shaped structure is provided with a vertical hole, the horizontal rod at the lower end of the support rod 1 penetrates through a preformed hole on the side wall of the upper end of the prefabricated well body 5, and the support rod 1 is detachably arranged on the prefabricated well body 5 through a T-shaped bolt 3 of which the vertical rod at the lower end is inserted into the vertical hole of the horizontal rod of the support rod 1; as shown in fig. 2, at least four support rods 1 are distributed on the outer wall of the upper end of the prefabricated well body 5 in a balanced manner, at least two cables 4 are connected with a lifting hook at the lower end of a lifting device through an upper lifting ring, and a lower lifting ring fixed at the two lower ends of each cable 4 is connected with a corresponding lifting lock component 2, wherein the plurality of support rods 1 are distributed in a balanced manner, and can be uniformly distributed at the upper ends of two parallel wall surfaces of the prefabricated well body 5, or are arranged at the upper ends of four planes of the prefabricated well body 5, as long as the prefabricated well body 5 can be lifted in a balanced manner due to the distributed positions of the support rods 1; the distribution position of the supporting rods 1 depends on the position of a prepared hole on the prefabricated well body 5.
In the structure, round steel is made into an L-shaped rod to serve as a bearing rod 1, one end with a vertical hole penetrates through a preformed hole of a prefabricated well body 5, the bearing rod 1 is fixed on the prefabricated well 5 by adopting a T-shaped bolt 3 inserted into the vertical hole, a lower hanging ring at the end part of a hoisting cable 4 penetrates through a U-shaped hoisting lock 2-1, and finally the U-shaped hoisting lock 2-1 and the bearing rod 1 are connected through a fastening bolt 2-2, so that the prefabricated well body 5 has the advantage of 360-degree rotation in the hoisting process, the requirements of different angles on the preformed hole of the prefabricated well body 5 in the hoisting and positioning process of the prefabricated well body 5 are met, and the damage to the well body structure in the hoisting process is avoided;
this technical scheme structure is succinct, the security is high, and the angle modulation is convenient after the prefabricated well body 5 hoists, for the prefabricated well body 5 hoists the precision of taking one's place provides the angle modulation condition, improves the outdoor pipe network prefabricated well body hoists the efficiency of taking one's place.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.
Claims (4)
1. Tool type frock is used in prefabricated well hoist and mount, its characterized in that: including bracing piece (1) of a plurality of lower extremes removable being fixed in prefabricated well body (5) upper end, bracing piece (1) upper end is removable to have linked firmly padlock subassembly (2), and passes through padlock subassembly (2) detachable connection in bracing piece (1) upper end with cable rope (4) tip that the lifting hook of lifting by crane the equipment lower extreme is connected, lift by crane the equipment with prefabricated well body (5) handling target in place and make bracing piece (1) and prefabricated well body (5) split back, realize breaking away from fast of prefabricated well body (5) and frock.
2. The tool for hoisting the precast well according to claim 1, characterized in that: the padlock component (2) comprises a U-shaped padlock (2-1) and fastening bolts (2-2), the supporting rod (1) is of an L-shaped rod-shaped structure, through holes for the fastening bolts (2-2) to pass through are formed in the side wall of the upper end of the supporting rod (1), the opening of the U-shaped padlock (2-1) is arranged downwards, connecting holes corresponding to the positions are formed in the outer side walls of the two lower ends of the U-shaped padlock (2-1), and after the fastening bolts (2-2) sequentially pass through the connecting holes and the through holes in the upper end of the supporting rod (1) and are in adaptive connection with locking nuts, the cable (4) with the lower fixed rings sleeved on the U-shaped padlock (2-1) is detachably and fixedly connected with the upper end of the supporting rod (1) into a whole.
3. The tool for hoisting the precast well according to claim 1, characterized in that: the horizontal rod at the lower end of the support rod (1) with the L-shaped rod-shaped structure is provided with a vertical hole, the horizontal rod at the lower end of the support rod (1) penetrates through a preformed hole in the side wall of the upper end of the prefabricated well body (5), and the support rod (1) is detachably installed on the prefabricated well body (5) through a T-shaped bolt (3) inserted into the vertical hole of the horizontal rod of the support rod (1) through the vertical rod at the lower end.
4. The tool for hoisting the precast well according to any one of claims 1 to 3, wherein: at least four support rods (1) are distributed on the outer wall of the upper end of the prefabricated well body (5) in a balanced mode, at least two cables (4) are connected with a lifting hook at the lower end of a lifting device through upper lifting rings, and lower lifting rings fixed to the two lower ends of each cable (4) are connected with corresponding lifting lock assemblies (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202220799809.5U CN217264208U (en) | 2022-04-07 | 2022-04-07 | Tool type tool for hoisting prefabricated well |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202220799809.5U CN217264208U (en) | 2022-04-07 | 2022-04-07 | Tool type tool for hoisting prefabricated well |
Publications (1)
Publication Number | Publication Date |
---|---|
CN217264208U true CN217264208U (en) | 2022-08-23 |
Family
ID=82873910
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202220799809.5U Active CN217264208U (en) | 2022-04-07 | 2022-04-07 | Tool type tool for hoisting prefabricated well |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN217264208U (en) |
-
2022
- 2022-04-07 CN CN202220799809.5U patent/CN217264208U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109680616B (en) | Construction method for hoisting main beam by using cable crane and reverse lifting equipment | |
CN201334306Y (en) | Hoisting machine for upright post member | |
CN217264208U (en) | Tool type tool for hoisting prefabricated well | |
CN115258909A (en) | Horizontal-lifting tail sliding system and method for offshore wind turbine tower | |
CN210884903U (en) | Fixing frame for hoisting curtain wall | |
CN220745084U (en) | Single-row steel bar combined lifting appliance for lifting main steel bars of steel bar framework of bridge tower | |
CN215479268U (en) | Bridge crane fixed pulley wire rope goes out groove fault handling device | |
CN216764029U (en) | Large plate girder stop log installation device | |
CN210260837U (en) | Device for synchronously hoisting multiple purlines on steel structure wall surface | |
CN212953822U (en) | Concrete pipe pile hoisting device | |
CN104291225A (en) | Non-dragging independent mast device for hoisting rigid steel pile | |
CN218754496U (en) | Annular multi-lifting-point lifting appliance structure | |
CN217148245U (en) | Connecting structure for hoisting large-tonnage reinforcement cage | |
CN213575073U (en) | Hoisting device of blast furnace gas-tight box | |
CN219362962U (en) | Yaw reducer hoisting tool | |
CN214989659U (en) | Hoisting point conversion device for prefabricated part and prefabricated part | |
CN216129186U (en) | Steam turbine bearing overhauls equipment of lifting by crane | |
CN217867700U (en) | Hoisting structure | |
CN211283414U (en) | Combined hanger for steel rail | |
CN215854595U (en) | Adjustable hoisting device of U type assembled clear water concrete prefabricated component | |
CN215666580U (en) | Transfer device is used in construction of compound incubation exterior sheathing | |
CN212893454U (en) | Lifting device for improving lifting efficiency of C-shaped steel purlines | |
CN117735384A (en) | Combined lifting appliance for precast pile lifting and precast pile lifting method | |
CN216038140U (en) | Assembly type house PC hoisting stair structure | |
CN217894868U (en) | Horizontal-lifting tail sliding system for offshore wind turbine tower |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CB03 | Change of inventor or designer information | ||
CB03 | Change of inventor or designer information |
Inventor after: Gao Ke Inventor after: Guo Zelin Inventor after: Zuo Xueyan Inventor after: Shang Enguang Inventor after: Wang Deqing Inventor before: Gao Ke Inventor before: Guo Zelin Inventor before: Zuo Xueyan Inventor before: Shang Enguang Inventor before: Wang Deqing |