CN217206491U - Anti-leakage device for construction joint of offshore power tunnel - Google Patents

Anti-leakage device for construction joint of offshore power tunnel Download PDF

Info

Publication number
CN217206491U
CN217206491U CN202123201821.6U CN202123201821U CN217206491U CN 217206491 U CN217206491 U CN 217206491U CN 202123201821 U CN202123201821 U CN 202123201821U CN 217206491 U CN217206491 U CN 217206491U
Authority
CN
China
Prior art keywords
tunnel
tunnel body
waterstop
electric power
side wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202123201821.6U
Other languages
Chinese (zh)
Inventor
吴棕鹏
吕刚勇
谭宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fifth Engineering Bureau Co Ltd
Original Assignee
China Construction Fifth Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fifth Engineering Bureau Co Ltd filed Critical China Construction Fifth Engineering Bureau Co Ltd
Priority to CN202123201821.6U priority Critical patent/CN217206491U/en
Application granted granted Critical
Publication of CN217206491U publication Critical patent/CN217206491U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model belongs to the technical field of the tunnel antiseep technique and specifically relates to a near sea electric power tunnel construction seam crossing antiseep device is related to, including the tunnel body, deformation joint is all left to the roof, side wall and the bottom plate of tunnel body, and deformation joint's surface all is equipped with the waterstop, and the waterstop all is horizontal connection with the deformation joint of roof and side wall, and the waterstop in the bottom plate deformation joint of tunnel body is the slope setting, and the waterstop is used for blockking moisture. Through this body coupling of waterstop to the tunnel, can guarantee that the tunnel body has good water-proof effects.

Description

Anti-leakage device for construction joint of offshore power tunnel
Technical Field
The utility model relates to an electric power tunnel technical field, specifically speaking relates to a be close to sea electric power tunnel construction seam crossing antiseep device.
Background
With the development of society, the use of electric power is indispensable for our lives, and an electric power tunnel is closely inseparable connected with the electricity, namely a tunnel for laying cables; to the electric power tunnel that faces the sea, when the sea water flows backward and the circumstances such as foundation ditch precipitation appear, movement joint in the electric power tunnel can receive the pressure of sea water and corrode, lead to the movement joint can produce and leak, in sea water or rainwater can all get into electric power tunnel along the movement joint, influence the normal operating of the cable in the electric power tunnel, when the cable received the influence, the network condition can appear blocking up or fracture etc. has produced very big influence to people's life.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a be close to sea electric power tunnel construction seam crossing antiseep device to solve the problem that proposes in the above-mentioned background art.
In order to realize the above-mentioned purpose, the utility model provides a near sea electric power tunnel construction seam crossing antiseep device, including the tunnel body, deformation joint has all been left to roof, side wall and the bottom plate of tunnel body, deformation joint's surface all is equipped with the waterstop, the waterstop all is horizontal connection with the deformation joint of roof and side wall, the waterstop in the bottom plate deformation joint of tunnel body is the slope setting, the waterstop is used for blockking of moisture.
As a further improvement of the technical scheme, the ground of the tunnel body is provided with a gravel pile, and the gravel pile is embedded in the ground surface.
As a further improvement of the technical scheme, the tunnel body is composed of concrete and a plurality of steel bars, and epoxy asphalt paint is arranged on the surfaces of the steel bars.
As a further improvement of the technical scheme, a pre-embedded plate is preset on the inner side wall of the tunnel body.
As a further improvement of the technical scheme, a fireproof layer is arranged on the side surface of the tunnel body.
Compared with the prior art, the beneficial effects of the utility model are that:
in the anti-leakage device for the joint of the coastal electric power tunnel construction, the water stop is used for horizontally connecting the deformation joints of the top plate and the side wall, so that the top plate and the side wall of the tunnel body have good waterproof effect, the deformation joints on the bottom plate are inclined, the bottom plate of the tunnel body can also have good waterproof effect, and the seawater is reversely poured and the foundation pit precipitation is reasonably improved and optimized.
Drawings
Fig. 1 is a schematic structural view of the tunnel body of the present invention;
FIG. 2 is a waterproof structure diagram of deformation joints of the top plate and the side wall of the utility model;
FIG. 3 is a waterproof structure diagram of the deformation joint of the bottom plate of the present invention;
FIG. 4 is a schematic view of the corner waterproof structure of the top plate and the side wall of the present invention;
FIG. 5 is a schematic view of the corner waterproof structure of the bottom plate and the side wall of the present invention;
fig. 6 is a schematic view of the overall structure of the present invention;
FIG. 7 is a schematic structural view of the pre-buried plate of the present invention;
fig. 8 is a schematic structural view of the fire-retardant layer of the present invention.
The various reference numbers in the figures mean:
1. a tunnel body; 11. deformation joints; 2. a water stop; 3. gravel piles; 4. and (6) pre-burying a plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and to simplify the description, but do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore should not be construed as limiting the present invention.
Referring to fig. 1-8, the embodiment provides an anti-seepage device for a joint of a coastal power tunnel construction, which includes a tunnel body 1, deformation joints 11 are reserved on a top plate, a side wall and a bottom plate of the tunnel body 1, the deformation joints 11 are formed by disconnecting structures at deformation sensitive positions in advance, and certain gaps are reserved to ensure that buildings at all parts have enough deformation widths in the gaps without causing damage to the buildings, water stops 2 are arranged on the surfaces of the deformation joints 11, the water stops 2 are horizontally connected with the deformation joints 11 of the top plate and the side wall, the water stops 2 of the deformation joints 11 in the bottom plate of the tunnel body 1 are obliquely arranged, and the water stops 2 are used for blocking moisture.
In the embodiment, the deformation joints 11 of the top plate and the side wall are horizontally connected through the water stop belts 2, so that the top plate and the side wall of the tunnel body 1 can have good waterproof effects, the water stop belts 2 of the deformation joints 11 on the bottom plate are obliquely arranged, the bottom plate of the tunnel body 1 can also have good waterproof effects, and the reasonable improvement and optimization are made on seawater backflow and foundation pit precipitation; further, the water stops 2 at the corners of the top plate, the bottom plate and the side walls are installed as shown in fig. 4 and 5, so that a good sealing and flow blocking effect can be guaranteed when the water stops 2 are installed at the corners of the tunnel body 1, and misoperation caused by installation of the water stops 2 in the tunnel body 1 by personnel is avoided; the water stop 2 is made of natural rubber or various synthetic rubbers as main raw materials, and is mixed with various additives and fillers, and the mixture is subjected to plasticizing, mixing, calendering, vulcanizing and other processes.
In order to improve the perfection of whole structure, tunnel body 1's ground is equipped with gravel pile 3, and gravel pile 3 comprises outside grit and inside for many pile bodies, and gravel pile 3 inlays to be established in the earth's surface, and gravel pile 3 is used for supporting tunnel body 1, can further improve the stability after tunnel body 1 constructs, reduces the influence of sinking that geological conditions caused tunnel body 1.
Furthermore, the tunnel body 1 is composed of concrete and a plurality of steel bars, epoxy asphalt paint is arranged on the surfaces of the steel bars, the foundation bearing effect on the tunnel body 1 is guaranteed through the composition of the concrete and the steel bars, meanwhile, the epoxy asphalt paint filled on the surfaces of the steel bars increases the corrosion resistance of the steel bars in the using process, reduces the cracking rate of the steel bars, and further prolongs the service life of the steel bars, so that the service life of the whole tunnel body 1 can be prolonged, and the frequency of subsequent maintenance is reduced; secondly, multiple groups of bearing are carried out through the steel bars and the concrete, the service life is durable, and the influence of geological settlement under the stratum condition on the tunnel body 1 is synchronously improved.
Considering that the cable can be corroded when rivers exist in the tunnel body 1, the pre-buried plate 4 is preset on the inner side wall of the tunnel body 1, the cable is located on the pre-buried plate 4, the cable can be prevented from directly contacting the interior of the tunnel body 1, and normal use of the cable is prevented from being influenced when rivers exist in the interior of the tunnel body 1.
Consider when tunnel body 1 meets the condition of catching fire suddenly, can influence the cable, tunnel body 1's side is equipped with the flame retardant coating, and the flame retardant coating adopts steel sheet frame fire protection coating to constitute, can resist external fire source heat, improves tunnel body 1's safe practicality.
The foregoing shows and describes the basic principles, essential features, and advantages of the invention. It should be understood by those skilled in the art that the present invention is not limited by the above embodiments, and the description in the above embodiments and the description is only preferred examples of the present invention, and is not intended to limit the present invention, and that the present invention can have various changes and modifications without departing from the spirit and scope of the present invention, and these changes and modifications all fall into the scope of the claimed invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (5)

1. The utility model provides a near sea electric power tunnel construction seam crossing antiseep device, includes tunnel body (1), its characterized in that: deformation joint (11) are all left to roof, side wall and the bottom plate of tunnel body (1), the surface of deformation joint (11) all is equipped with waterstop (2), waterstop (2) all are the horizontal connection with deformation joint (11) of roof and side wall, waterstop (2) in bottom plate deformation joint (11) of tunnel body (1) are the slope setting, waterstop (2) are used for blockking to moisture.
2. The anti-leakage device for the construction joint of the coastal electric power tunnel according to claim 1, which is characterized in that: the ground of tunnel body (1) is equipped with gravel pile (3), gravel pile (3) are inlayed and are established in the earth's surface.
3. The anti-leakage device for the construction joint of the coastal electric power tunnel according to claim 1, which is characterized in that: the tunnel body (1) is composed of concrete and a plurality of steel bars, and epoxy asphalt paint is arranged on the surfaces of the steel bars.
4. The anti-leakage device for the construction joint of the coastal electric power tunnel according to claim 1, which is characterized in that: the inner side wall of the tunnel body (1) is preset with a pre-embedded plate (4).
5. The anti-leakage device for the construction joint of the coastal electric power tunnel according to claim 1, which is characterized in that: and a fireproof layer is arranged on the side surface of the tunnel body (1).
CN202123201821.6U 2021-12-20 2021-12-20 Anti-leakage device for construction joint of offshore power tunnel Active CN217206491U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202123201821.6U CN217206491U (en) 2021-12-20 2021-12-20 Anti-leakage device for construction joint of offshore power tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202123201821.6U CN217206491U (en) 2021-12-20 2021-12-20 Anti-leakage device for construction joint of offshore power tunnel

Publications (1)

Publication Number Publication Date
CN217206491U true CN217206491U (en) 2022-08-16

Family

ID=82785747

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202123201821.6U Active CN217206491U (en) 2021-12-20 2021-12-20 Anti-leakage device for construction joint of offshore power tunnel

Country Status (1)

Country Link
CN (1) CN217206491U (en)

Similar Documents

Publication Publication Date Title
CN101298782A (en) Method and system for basement engineering water proof and water drain
CN114855846A (en) Underground seepage-proofing pressure-reducing anti-floating blind pipe structure and construction method thereof
CN217206491U (en) Anti-leakage device for construction joint of offshore power tunnel
CN204753848U (en) Construct outdoor floor movement joint department leak protection water structure
CN218175929U (en) Underground anti-seepage pressure-reducing anti-floating blind pipe structure
CN206721925U (en) A kind of anti-settling cable shaft suitable for cable duct bank
CN211006775U (en) Water stop structure for post-cast strip of underground chamber bottom plate
CN206035051U (en) Prefabricated caulking strips's in area circular underground granary of double -layer steel plate assembled
CN206545284U (en) A kind of subsided rest room
CN114263219A (en) Advanced water stop structure of bottom plate post-cast strip for underground engineering and construction method
CN110863502A (en) Construction method and plugging structure for dynamically adjusting foundation pit dewatering and plugging dewatering well
CN220644342U (en) Waterproof structure for bottom of basement outer wall
CN206034482U (en) Circular prefabricated assembled underground granary of interior steel plated
CN205857373U (en) Post-cast strip advanced water-stopping structure
CN206035042U (en) Prefabricated caulking strips's in area circular underground granary of interior steel plated assembled
CN211773899U (en) Anticorrosive prevention of seepage underground hydrant well
CN206189971U (en) Circular underground granary of prefabricated assembled of outer steel plated
CN114991222B (en) Shock absorption disposal method for subway station structure
CN214995359U (en) Waterproof structure for parapet wall eaves
CN216183367U (en) Waterproof structure of foamed concrete
CN219386189U (en) Flood control water conservancy bank protection
CN219343326U (en) Underground expansion joint device for basement roof
CN208618849U (en) A kind of flooring channeling water leakage repairerment system
CN209873894U (en) Basement waterproof structure
CN216839944U (en) Anti-waterlogging backward-flowing structure of medium and small-section cable trench

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant