CN217205832U CN202220941606.5U CN202220941606U CN217205832U CN 217205832 U CN217205832 U CN 217205832U CN 202220941606 U CN202220941606 U CN 202220941606U CN 217205832 U CN217205832 U CN 217205832U
Authority
CN
China
Prior art keywords
base
spray
frame
front side
rear side
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202220941606.5U
Other languages
Chinese (zh)
Inventor
金崧博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN202220941606.5U priority Critical patent/CN217205832U/en
Application granted granted Critical
Publication of CN217205832U publication Critical patent/CN217205832U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

A noise reduction fence for a construction site comprises a stand column, a mounting frame, a noise reduction inner core and a water spraying mechanism; the mounting rack is arranged between the adjacent upright posts; the mounting frame is provided with mounting lattices at intervals; the front side and the rear side of the installation sash are provided with panels; the panel is provided with a rectangular hole; the silencing inner core is arranged between the front and the rear corresponding panels; a dust-proof plate is arranged between the silencing inner core and the panel; the water spraying mechanism comprises a water pipe, a base and a spray head; a cavity is arranged in the base, and a connecting plate is fixed at the bottom of the base; the connecting plate is fixedly connected with the top end of the upright post; spray pipes are respectively arranged on the upper part of the base and positioned at the front side and the rear side of the base in an inclined manner; the pipeline of the spray pipe is communicated with the cavity of the base, and the pipe wall of the spray pipe is provided with water spray holes at intervals; the spray head is screwed and installed at the water spray hole; the water pipes are connected in series and communicated between the adjacent bases. The utility model provides a traditional rail do not have the ability of making an uproar, installation effectiveness that fall give sound insulation poor, the dismouting inconvenient and do not possess the technical problem of the ability of clean dust fall.

Description

Fence of making an uproar falls in job site
Technical Field
The utility model belongs to the technical field of the building engineering construction, in particular to rail of making an uproar falls in job site.
Background
The construction site refers to a construction site where construction activities such as house construction, civil engineering, equipment installation, and pipeline laying are performed in industrial and civil projects, and the construction site is approved to be occupied, and a site where safety production, civilized work, and construction are performed by human beings, including all regions where construction work can be performed on land, sea, and in the air.
Present job site rail adopts the plastic steel board to enclose more, does not have the ability of making an uproar that falls that gives sound insulation, leads to the construction to cause the noise to disturb residents, and simultaneously, the installation effectiveness of plastic steel board is poor, and the dismouting is inconvenient, needs the whole change when the part damages, and use cost is high, when enclosing the fender, does not possess the ability of clean dust fall, and functional not enough.
Accordingly, one skilled in the art provides a noise reduction fence for a construction site to solve the above problems of the background art.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a rail of making an uproar falls in job site, solve traditional rail and do not have the ability of making an uproar, installation effectiveness are poor, the dismouting is inconvenient and do not possess the technical problem of the ability of clean dust fall of making an uproar.
In order to achieve the above purpose, the utility model adopts the following technical scheme.
A noise reduction fence for a construction site comprises a stand column, a mounting frame, a noise reduction inner core and a water spraying mechanism; the upright columns are arranged in a group and are arranged in parallel at intervals; the mounting frames are provided with one group and correspondingly mounted between the adjacent upright posts; mounting sashes are arranged in the mounting rack at intervals along the vertical direction; panels are respectively arranged in each installation sash and positioned on the front side surface and the rear side surface of the installation sash; rectangular holes are arranged on the panel at equal intervals; the silencing inner core is arranged between the front and rear corresponding panels; dust insulation plates are arranged between the front side and the rear side of the silencing inner core and the panel on the corresponding side; the water spraying mechanism comprises a water passing pipe, a base and a spray head; a cavity is arranged in the base, and a connecting plate is fixedly arranged at the bottom of the base; the connecting plate is fixedly connected with the top end of the upright post; spray pipes are obliquely arranged on the upper part of the base and positioned on the front side and the rear side of the base respectively; the pipeline of the spray pipe is communicated with the cavity of the base, and the pipe wall of the spray pipe is provided with water spray holes at intervals; the spray head is screwed and installed at the water spray hole; the water pipes are connected in series and communicated between the adjacent bases.
Preferably, the front side surface and the rear side surface of the upright post are respectively provided with pressing sheets at intervals along the vertical direction; the pressing sheet is fixed on the stand column through bolts, and the left side edge and the right side edge of the pressing sheet are respectively pressed on the mounting frames on the left side and the right side of the stand column.
Preferably, two threaded holes are formed in the top of the base at intervals along the longitudinal direction; threads are arranged on the side wall of the lower part of the spray pipe; the spray pipe is connected with the base through threads.
Preferably, the mounting frame comprises an upper end frame, a lower end frame and a middle spacing frame; the upper end frame is connected between the adjacent upright columns, and the top of the upper end frame is flush with the top of the upright columns; the upper end frame comprises an upper end plate; the vertical section of the upper end plate is in an inverted U shape, and the front side edge and the rear side edge of the upper end plate are respectively bent inwards by 90 degrees to form lower folded edges; the lower end frame is connected between the adjacent upright posts, and the bottom of the lower end frame is flush with the bottom of the upright posts; the lower end frame comprises a lower end plate; the vertical section of the lower end plate is U-shaped, and the front side edge and the rear side edge of the lower end plate are respectively bent inwards by 90 degrees to form an upper folded edge; the middle spacing frames are arranged in a group and are vertically arranged between the upper end frame and the lower end frame at intervals; the middle partition frame is H-shaped, and baffles are arranged on the front side and the rear side of the middle partition frame respectively along the edges; the baffle is pressed on the panel on the corresponding side in a pressing mode.
Preferably, the silencing inner core comprises an inner shell, a mesh enclosure and a silencing plate; an opening is formed in one side, facing the inside of the enclosure, of the inner shell; the sound-absorbing plate is arranged in the cavity of the inner shell, and one side of the sound-absorbing plate, which faces the opening of the inner shell, is provided with a wave bulge; the mesh enclosure is covered and installed at the opening position of the inner shell, and the separation blades which are symmetrically arranged are embedded and installed between the mesh enclosure and the inner shell.
Preferably, the bottom end of the upright post is fixedly provided with a balancing weight.
Compared with the prior art, the utility model has the following characteristics and beneficial effect.
1. The utility model discloses a rail of making an uproar falls in job site structurally reasonable in design, collocation amortization sound-proof structure can play the effect of offsetting the separation to the noise, avoids disturbing the people, and can carry out swift dismouting change and inside cleanness, uses convenient and fast to have the convenient dust suppression device of maintaining, functional strong, the practicality is very high.
2. The utility model discloses a rail of making an uproar falls in job site when using, falls the rail of making an uproar and fixes around the construction site on job site, rises the stand through balancing weight collocation concrete, assembles the amortization inner core crimping through the fastener, and assembles around the mounting bracket, plays the guard action.
3. The utility model discloses a when the rail of making an uproar falls in job site damages, can pull down alone to change and maintain conveniently, and collocation dust-separation board can play the guard action to the amortization inner core, and can assist the amortization inner core to play the effect of syllable-dividing amortization, the noise passes through the rectangular hole and gets into the dust-separation board, it offsets to reflect at getting into the amortization inner core, the acoustical panel is provided with the wave arch towards the inner shell opening part, can play fine noise cancelling effect, the back is pulled down to well intermediate bay, the limit can be dismantled the washing to the amortization inner core, it is convenient to maintain, have the water spray mechanism of combination formula simultaneously, the shower nozzle blocks up and to change alone, device quantity can select in a flexible way, high durability and convenient use.
Drawings
The present invention will be described in further detail with reference to the accompanying drawings.
Fig. 1 is the overall structure schematic diagram of the noise reduction fence of the present invention.
Fig. 2 is a schematic side view of the middle water spraying mechanism of the present invention.
Fig. 3 is a schematic view of a connection structure between the mounting frame and the upright post.
Fig. 4 is a horizontal section schematic view of the connection structure of the sound-deadening plate and the dust-proof plate of the utility model.
Fig. 5 is a schematic structural view of the upper end frame of the present invention.
Fig. 6 is a schematic structural view of the middle spacer of the present invention.
Fig. 7 is a schematic structural view of the middle lower frame of the present invention.
Reference numerals: 1-upright column, 2-mounting frame, 2.1-upper end frame, 2.1.1-upper end plate, 2.1.2-lower folded edge, 2.2-lower end frame, 2.2.1-lower end plate, 2.2.2-upper folded edge, 2.3-middle spacing frame, 2.3.1-baffle, 3-mounting frame, 4-panel, 5-rectangular hole, 6-dust-isolating plate, 7-water pipe, 8-base, 9-nozzle, 10-connecting plate, 11-nozzle, 12-water spray hole, 13-pressing sheet, 14-bolt, 15-inner shell, 16-blocking sheet, 17-mesh enclosure, 18-silencing board and 19-balancing weight.
Detailed Description
As shown in fig. 1-7, the noise reduction fence for construction sites comprises a stand column 1, a mounting frame 2, a noise reduction inner core and a water spraying mechanism; the upright posts 1 are in a group and are arranged in parallel at intervals; the mounting frames 2 are provided with a group and correspondingly mounted between the adjacent upright posts 1; the mounting frames 3 are arranged in the mounting rack 2 at intervals along the vertical direction; panels 4 are respectively installed in each installation sash 3 at the front side and the rear side of the installation sash 3; rectangular holes 5 which are arranged at equal intervals are arranged on the panel 4; the silencing inner core is arranged between the front and the rear corresponding panels 4; dust separation plates 6 are arranged between the front side and the rear side of the silencing inner core and the corresponding side of the panel 4; the water spraying mechanism comprises a water pipe 7, a base 8 and a spray head 9; a cavity is arranged in the base 8, and a connecting plate 10 is fixedly arranged at the bottom of the base 8; the connecting plate 10 is fixedly connected with the top end of the upright post 1; spray pipes 11 are obliquely arranged on the upper part of the base 8 and positioned at the front side and the rear side of the base 8 respectively; the pipeline of the spray pipe 11 is communicated with the cavity of the base 8, and the pipe wall of the spray pipe 11 is provided with water spray holes 12 at intervals; the spray head 9 is screwed and installed at the position of the water spraying hole 12; the water pipes 7 are communicated in series between the adjacent bases 8.
In the embodiment, the front side surface and the rear side surface of the upright post 1 are respectively provided with pressing sheets 13 at intervals along the vertical direction; the pressing sheet 13 is fixed on the upright post 1 through a bolt 14, and the left side and the right side of the pressing sheet 13 are respectively pressed on the mounting frames 2 at the left side and the right side of the upright post 1.
In this embodiment, two threaded holes are formed in the top of the base 8 at intervals along the longitudinal direction; threads are arranged on the side wall of the lower part of the spray pipe 11; the spray pipe 11 is connected with the base 8 through threads.
In this embodiment, the mounting frame 2 includes an upper end frame 2.1, a lower end frame 2.2 and a middle spacing frame 2.3; the upper end frame 2.1 is connected between the adjacent upright posts 1, and the top of the upper end frame 2.1 is flush with the top of the upright posts 1; the upper end frame 2.1 comprises an upper end plate 2.1.1; the vertical section of the upper end plate 2.1.1 is in an inverted U shape, and the front side edge and the rear side edge of the upper end plate 2.1.1 are respectively bent inwards by 90 degrees to form a lower folded edge 2.1.2; the lower end frame 2.2 is connected between the adjacent upright posts 1, and the bottom of the lower end frame 2.2 is flush with the bottom of the upright post 1; the lower end frame 2.2 comprises a lower end plate 2.2.1; the vertical section of the lower end plate 2.2.1 is U-shaped, and the front side edge and the rear side edge of the lower end plate 2.2.1 are respectively bent inwards by 90 degrees to form an upper folded edge 2.2.2; the middle spacing frames 2.3 are provided with a group and are arranged between the upper end frame 2.1 and the lower end frame 2.2 at intervals along the vertical direction; the middle partition frame 2.3 is H-shaped, and baffles 2.3.1 are respectively arranged on the front side and the rear side of the middle partition frame 2.3 along the edges; the baffle 2.3.1 is pressed against the corresponding side panel 4.
In this embodiment, the silencing inner core comprises an inner shell 15, a mesh enclosure 17 and a silencing plate 18; an opening is formed in one side, facing the inside of the enclosure, of the inner shell 15; the sound-absorbing plate 18 is arranged in the cavity of the inner shell 15, and one side of the sound-absorbing plate 18, which faces the opening of the inner shell 15, is provided with a wavy bulge; the opening position of the inner shell 15 is covered with a mesh enclosure 17, and a baffle 16 which is symmetrically arranged is embedded and fixedly arranged between the mesh enclosure 17 and the inner shell 15.
In this embodiment, a counterweight 19 is fixedly installed at the bottom end of the upright post 1.
In this embodiment, the end of the water pipe 7 is connected with an external water supply device.
The utility model discloses a this kind of job site noise reduction rail, when working, fix this device around the construction site, erect stand 1 through balancing weight 19 collocation concrete, through the fastener with the amortization inner core crimping assemble, and the mounting bracket 2 assembly around, play the guard action, when damaging, can pull down alone and change the maintenance convenience, and collocation dust barrier 6 can play the guard action to the amortization inner core, and can assist the amortization inner core to play the effect of sound insulation amortization, the noise gets into dust barrier 6 through rectangular hole 5, get into the amortization inner core and reflect and offset, the amortization board 18 is provided with the wave arch towards the opening part of inner shell 15, can play fine amortization effect, after middle spacer 2.3 is pulled down, the while can be dismantled and washd the amortization inner core, it is convenient to maintain, have the water spray mechanism of combination formula simultaneously, the shower nozzle 9 blocks up and can change alone, the number of the devices can be flexibly selected, and the use is convenient.

Claims (6)

1. The utility model provides a rail of making an uproar falls in job site which characterized in that: comprises a column (1), a mounting rack (2), a silencing inner core and a water spraying mechanism; the upright posts (1) are arranged in a group and are arranged in parallel at intervals; the mounting racks (2) are provided with a group and correspondingly mounted between the adjacent upright columns (1); the mounting frames (3) are arranged in the mounting rack (2) at intervals along the vertical direction; panels (4) are respectively arranged in each installation sash (3) and positioned on the front side surface and the rear side surface of the installation sash (3); rectangular holes (5) which are arranged at equal intervals are arranged on the panel (4); the silencing inner core is arranged between the front and the rear corresponding panels (4); dust separation plates (6) are arranged between the front side and the rear side of the silencing inner core and the corresponding side of the panel (4); the water spraying mechanism comprises a water passing pipe (7), a base (8) and a spray head (9); a cavity is arranged in the base (8), and a connecting plate (10) is fixedly arranged at the bottom of the base (8); the connecting plate (10) is fixedly connected with the top end of the upright post (1); spray pipes (11) are obliquely arranged on the upper part of the base (8) and positioned at the front side and the rear side of the base (8) respectively; the pipeline of the spray pipe (11) is communicated with the cavity of the base (8), and water spray holes (12) are arranged on the pipe wall of the spray pipe (11) at intervals; the spray head (9) is rotatably connected and arranged at the position of the water spray hole (12); the water passing pipes (7) are connected in series and communicated between the adjacent bases (8).
2. The construction site noise reduction fence according to claim 1, wherein: pressing sheets (13) are respectively arranged on the front side surface and the rear side surface of the upright post (1) at intervals along the vertical direction; the pressing sheet (13) is fixed on the upright post (1) through a bolt (14), and the left side and the right side of the pressing sheet (13) are respectively pressed on the mounting frames (2) on the left side and the right side of the upright post (1).
3. The construction site noise reduction fence according to claim 1, wherein: two threaded holes are formed in the top of the base (8) at intervals along the longitudinal direction; threads are arranged on the side wall of the lower part of the spray pipe (11); the spray pipe (11) is connected with the base (8) through threads.
4. The construction site noise reduction fence according to claim 1, wherein: the mounting frame (2) comprises an upper end frame (2.1), a lower end frame (2.2) and a middle spacing frame (2.3); the upper end frame (2.1) is connected between the adjacent upright posts (1), and the top of the upper end frame (2.1) is flush with the top of the upright posts (1); the upper end frame (2.1) comprises an upper end plate (2.1.1); the vertical section of the upper end plate (2.1.1) is in an inverted U shape, and the front side edge and the rear side edge of the upper end plate (2.1.1) are respectively bent inwards by 90 degrees to form a lower folded edge (2.1.2); the lower end frames (2.2) are connected between the adjacent upright posts (1), and the bottoms of the lower end frames (2.2) are flush with the bottoms of the upright posts (1); the lower end frame (2.2) comprises a lower end plate (2.2.1); the vertical section of the lower end plate (2.2.1) is U-shaped, and the front side edge and the rear side edge of the lower end plate (2.2.1) are respectively bent inwards by 90 degrees to form an upper folded edge (2.2.2); the middle spacing frames (2.3) are provided with a group and are arranged between the upper end frame (2.1) and the lower end frame (2.2) at intervals along the vertical direction; the middle partition frame (2.3) is H-shaped, and baffles (2.3.1) are respectively arranged on the front side and the rear side of the middle partition frame (2.3) along the edges; the baffle (2.3.1) is pressed on the panel (4) on the corresponding side.
5. The noise reduction fence for a construction site according to claim 1, wherein: the silencing inner core comprises an inner shell (15), a mesh enclosure (17) and a silencing plate (18); an opening is formed in one side, facing the inside of the enclosure, of the inner shell (15); the sound-absorbing plate (18) is arranged in a cavity of the inner shell (15), and one side, facing the opening of the inner shell (15), of the sound-absorbing plate (18) is provided with a wave bulge; the mesh enclosure (17) is arranged at the opening position of the inner shell (15) in a covering mode, and the blocking pieces (16) which are symmetrically arranged are fixedly arranged between the mesh enclosure (17) and the inner shell (15) in an embedded mode.
6. The noise reduction fence for a construction site according to claim 1, wherein: and a balancing weight (19) is fixedly installed at the bottom end of the upright post (1).
CN202220941606.5U 2022-04-22 2022-04-22 Fence of making an uproar falls in job site Expired - Fee Related CN217205832U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220941606.5U CN217205832U (en) 2022-04-22 2022-04-22 Fence of making an uproar falls in job site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220941606.5U CN217205832U (en) 2022-04-22 2022-04-22 Fence of making an uproar falls in job site

Publications (1)

Publication Number Publication Date
CN217205832U true CN217205832U (en) 2022-08-16

Family

ID=82773531

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220941606.5U Expired - Fee Related CN217205832U (en) 2022-04-22 2022-04-22 Fence of making an uproar falls in job site

Country Status (1)

Country Link
CN (1) CN217205832U (en)

Similar Documents

Publication Publication Date Title
CN211851062U (en) Noise reduction mechanical shed
CN217205832U (en) Fence of making an uproar falls in job site
CN212671381U (en) Construction is with enclosing fender
CN213062476U (en) Sound insulation building board for building
CN212224264U (en) Sound insulation protection plate for constructional engineering
CN213330377U (en) Make an uproar and enclose fender device falls in construction convenient to dismouting
RU202149U1 (en) Noise shield
RU108458U1 (en) NOISE PROTECTIVE SCREEN
CN212223653U (en) Modular afforestation sound insulation protective screen
CN209837878U (en) Sound insulation retaining wall
CN210857742U (en) Cross-shaped steel structure column
CN209653351U (en) Noise-reduction type construction platform
RU91079U1 (en) NOISE PROTECTIVE SCREEN
CN215210638U (en) Foldable sound insulation curtain
CN214169575U (en) Hollow aluminum material containing buckle
CN218862291U (en) Movable noise reduction enclosure
CN211646057U (en) Aluminum profile combined type sound barrier
KR200227450Y1 (en) a dust proof and sound proof panel for the fence to construct around a construction spot
CN212613472U (en) Building energy-saving anti-seismic external wall panel
CN215056772U (en) Sound-absorbing explosion-venting assembled wall body door
CN219754263U (en) Building construction safety guard rail
RU104943U1 (en) NOISE PROTECTION DEVICE
CN215330620U (en) Cinema sound insulation ceiling structure
CN210622479U (en) High-safety enclosure guardrail for blasting near airport
CN217810590U (en) Sound insulation device for municipal building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20220816