CN217201879U - Installation car of taking one's place is transported fast to piping lane interior pipeline - Google Patents

Installation car of taking one's place is transported fast to piping lane interior pipeline Download PDF

Info

Publication number
CN217201879U
CN217201879U CN202221119118.2U CN202221119118U CN217201879U CN 217201879 U CN217201879 U CN 217201879U CN 202221119118 U CN202221119118 U CN 202221119118U CN 217201879 U CN217201879 U CN 217201879U
Authority
CN
China
Prior art keywords
baffle
pipeline
displacement device
movable
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221119118.2U
Other languages
Chinese (zh)
Inventor
欧阳学伍
卜晓明
谢建军
荣熊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fifth Bureau Installation Engineering Co Ltd
Original Assignee
China Construction Fifth Bureau Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fifth Bureau Installation Engineering Co Ltd filed Critical China Construction Fifth Bureau Installation Engineering Co Ltd
Priority to CN202221119118.2U priority Critical patent/CN217201879U/en
Application granted granted Critical
Publication of CN217201879U publication Critical patent/CN217201879U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model provides a rapid pipeline transferring and positioning installation vehicle in a pipeline, which comprises a displacement device, a movable baffle and a fixed baffle, wherein the movable baffle and the fixed baffle are arranged on the displacement device; the displacement device is used for displacing in the pipe gallery; one end of the fixed baffle is connected with the upper end face of the displacement device, and the other end of the fixed baffle extends upwards; one end of the movable baffle is rotatably connected with the upper end face of the displacement device, the other end of the movable baffle extends upwards, and the pipeline is arranged between the movable baffle and the fixed baffle. The utility model provides a piping lane interior pipeline is transported fast and is taken one's place installation car transports the mounting point through adopting once only with the pipeline is direct from discharge to take one's place for pipeline installation technique has been accelerated, reduces the construction process, and the pipeline need not the secondary and raises, and the secondary dismouting is not needed in pipeline bracket one-time erection, has improved pipeline installation efficiency, has realized the quick installation of piping lane overhead pipeline.

Description

Installation car of taking one's place is transported fast to piping lane interior pipeline
Technical Field
The utility model relates to a piping erection technical field especially relates to an installation car of taking one's place is transported fast to piping lane interior pipeline.
Background
Overhead pipeline installation in the flat pipe gallery is because the reason of flat pipe gallery inner space, often can't use engineering machine tool to the pipeline transport to the mounting point, adopt hoist lifting pipeline again, after lay the pipeline on the support adopt the mode of vertical translation pipeline to install the pipeline. When a pipeline with a larger diameter and heavier weight is installed, the pipeline support is usually dismantled first, the pipeline is lifted by the hoisting block and then the support is installed, and the pipeline can be placed on the support after the support is fixed. Therefore, the pipeline lifting point support cannot be installed at one time, the integrity of the support is deteriorated, and the later elevation and gradient of the support cannot be guaranteed; the pipe is labor and time consuming to place on the bracket. The pipeline can not be unloaded to be in place once, secondary transfer is needed, and a pipeline stacking site is needed. Not only the construction period is prolonged, but also the labor cost, the corresponding mechanical cost and the site cost are greatly increased.
SUMMERY OF THE UTILITY MODEL
The utility model provides a rapid pipeline transferring and positioning installation vehicle in a pipeline, which comprises a displacement device, a movable baffle and a fixed baffle, wherein the movable baffle and the fixed baffle are arranged on the displacement device; the displacement device is used for displacing in the pipe gallery; one end of the fixed baffle is connected with the upper end face of the displacement device, and the other end of the fixed baffle extends upwards; the movable baffle and the fixed baffle are arranged at intervals, one end of the movable baffle is rotatably connected with the upper end face of the displacement device, the other end of the movable baffle extends upwards, and the pipeline is arranged between the movable baffle and the fixed baffle.
Optionally, the movable baffle comprises a baffle body, a connecting seat, a rotating shaft, a connecting piece and a locking pin shaft; the connecting seat is used for being connected with the displacement device, and the connecting seat and the baffle plate main body are rotatably connected through a rotating shaft; the connecting piece sets up in the baffle main part, and runs through on the connecting piece and install the locking round pin axle, links to each other with the round pin shaft hole that sets up on frame construction through the locking round pin axle to realize the relative locking between baffle main part and the frame construction and fix.
Optionally, the connecting seat, the connecting piece and the locking pin shaft are provided with two pieces which are arranged in a one-to-one correspondence manner and are respectively arranged on two sides of the baffle main body.
Optionally, two mutually perpendicular side faces of one of the cross beams of the frame structure for supporting the pipeline are provided with pin shaft holes, the connecting piece comprises a fixed section and a movable section, one end of the fixed section is fixedly connected with the baffle main body, the other end of the fixed section is rotatably connected with one end of the movable section, and the locking pin shaft is arranged on the movable section in a penetrating mode, so that the locking pin shaft and the pin shaft holes on different faces of the cross beams are connected with each other through rotation of the movable section.
Optionally, the locking pin shaft comprises a locking section and a limiting section, the locking section and the limiting section are connected with each other to form a T-shaped structure, and the locking section is used for connecting with the pin shaft hole; still the cover is equipped with the elastic component on the locking pin axle, and the elastic component sets up between spacing section and connecting piece.
Optionally, the movable baffle is arranged in a triangular structure, and one side of the movable baffle is perpendicular to the upper end surface of the displacement device.
Optionally, the displacement device comprises a plurality of beams, longitudinal beams, upright columns and universal wheels, the beams, the longitudinal beams and the upright columns are connected with each other to form a frame structure, and the universal wheels are respectively connected with the lower end face of the frame structure.
Optionally, the upright is provided as a telescopic structure.
Compared with the prior art, the utility model discloses following beneficial effect has:
the utility model provides a piping lane interior pipeline fast transferring takes one's place installation car transports the mounting point through adopting once only with the pipeline is direct from discharge to take one's place, accelerated the piping erection technique, reduce the construction process, the pipeline need not the secondary and raises, and the secondary dismouting is not needed in the installation of conduit bracket one time, has improved piping erection efficiency, has realized the quick installation of piping lane overhead pipeline.
In addition to the above-described objects, features and advantages, the present invention has other objects, features and advantages. The present invention will be described in further detail with reference to the drawings.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this application, are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification. In the drawings:
fig. 1 is an axial view of an installation vehicle for rapid pipe transfer and in-place in a pipe rack in an embodiment of the present invention, when the pipe is clamped;
FIG. 2 is an isometric view of the displacement apparatus of FIG. 1;
FIG. 3 is an axial schematic view of the flapper of FIG. 1;
fig. 4 is an axial view of an installation vehicle for rapid pipe transfer and in-place in a pipe rack in an embodiment of the present invention;
fig. 5 is a schematic diagram of an installation vehicle for rapid pipe transfer in place in a pipe rack according to an embodiment of the present invention, when the pipe is in place (the dashed line in the figure represents a second state schematic of the movable baffle).
Wherein:
1. the device comprises a displacement device 1.1, a cross beam 1.2, a longitudinal beam 1.3, an upright post 1.4 and universal wheels;
2. the movable baffle 2.1, the baffle body 2.2, the connecting seat 2.3, the rotating shaft 2.4, the connecting piece 2.5, the locking pin shaft 2.6 and the elastic piece;
3. fixing a baffle plate;
10. pipeline, 20, installation site.
Detailed Description
In order to make the above objects, features, advantages, and the like of the present invention more clearly understandable, embodiments of the present invention will be described in detail below with reference to the accompanying drawings. It should be noted that the drawings of the utility model all adopt simplified forms and all use non-precise proportions, and are only used for conveniently and clearly assisting in explaining the implementation of the utility model; the number mentioned in the present invention is not limited to the specific number in the examples of the drawings; the directions or positional relationships indicated in the "front" middle "rear" left "right" upper "lower" top "bottom" middle "etc. in the present invention are all based on the directions or positional relationships shown in the drawings of the present invention, and do not indicate or suggest that the indicated device or component must have a specific direction, and cannot be understood as a limitation of the present invention.
In this embodiment:
referring to fig. 1, the rapid pipeline transferring and in-place mounting vehicle for the pipe gallery comprises a displacement device 1, and a movable baffle 2 and a fixed baffle 3 which are arranged on the displacement device 1; the displacement device 1 is used for displacement in a pipe gallery; one end of the fixed baffle 3 is fixedly connected with the upper end face of the displacement device 1, and the other end of the fixed baffle extends upwards; the movable baffle 2 and the fixed baffle 3 are arranged at intervals, one end of the movable baffle 2 is rotatably connected with the upper end face of the displacement device 1, the other end of the movable baffle extends upwards, and the pipeline 10 is arranged between the movable baffle 2 and the fixed baffle 3.
Referring to fig. 2, the displacement device 1 comprises a plurality of beams 1.1, longitudinal beams 1.2, vertical columns 1.3 and universal wheels 1.4, wherein the beams 1.1, the longitudinal beams 1.2 and the vertical columns 1.3 are connected with each other to form a frame structure, and the universal wheels 1.4 are respectively connected with the lower end surface of the frame structure, so that the frame structure can be flexibly displaced.
Optionally, in order to facilitate the height adjustment of the displacement device 1, the column 1.3 is configured to be a telescopic structure, so that the application range of the rapid transferring and in-place mounting vehicle for the pipe gallery internal pipe 10 is wider. Preference is given here to: the stand 1.3 is including the first extensible member and the second extensible member of establishing each other cover, and all is equipped with the spacing hole that is used for installing the gag lever post on first extensible member and the second extensible member, and first extensible member and second extensible member pass through gag lever post interconnect and realize spacing fixed relatively.
Referring to fig. 3, the movable baffle 2 includes a baffle body 2.1, a connecting seat 2.2, a rotating shaft 2.3, a connecting piece 2.4 and a locking pin shaft 2.5; the connecting seat 2.2 is used for being connected with the frame structure, and the connecting seat 2.2 and the baffle plate main body 2.1 are rotatably connected through a rotating shaft 2.3; the connecting piece 2.4 is arranged on the baffle main body 2.1, the locking pin shaft 2.5 is installed on the connecting piece 2.4 in a penetrating mode, and the connecting piece is connected with a pin shaft hole formed in the frame structure through the locking pin shaft 2.5, so that the baffle main body 2.1 and the frame structure are locked and fixed relatively.
Optionally, in order to effectively fix the baffle main body 2.1, the connecting seat 2.2, the connecting piece 2.4 and the locking pin shaft 2.5 are provided with two pieces which are arranged in a one-to-one correspondence manner and are respectively arranged on two sides of the baffle main body 2.1.
Optionally, for realizing being connected of two fitting pin axle 2.5 and frame construction, be used for supporting two sides of one of them crossbeam 1.1 mutually perpendicular of pipeline 10 all to be equipped with the round pin shaft hole at frame construction, and connecting piece 2.4 includes canned paragraph and movable section, the one end of canned paragraph links firmly with baffle main part 2.1, the other end of canned paragraph and the one end rotatable coupling of movable section, fitting pin axle 2.5 runs through and installs on the movable section, thereby realize fitting pin axle 2.5 and the round pin shaft hole interconnect on the crossbeam 1.1 difference face through the rotation of movable section.
Optionally, in order to increase the locking force between the locking pin shaft 2.5 and the pin shaft hole, the locking pin shaft 2.5 includes a locking section and a limiting section, the locking section and the limiting section are connected with each other to form a T-shaped structure, and the locking section is used for connecting with the pin shaft hole; the locking pin shaft 2.5 is also sleeved with an elastic piece 2.6, and the elastic piece 2.6 is arranged between the limiting section and the connecting piece 2.4; the locking force between the locking pin shaft 2.5 and the pin shaft hole is increased by the elastic force of the elastic piece 2.6, so that the baffle main body 2.1 is prevented from deviating under the action of the self gravity of the pipeline 10. Preference is given here to: the elastic element 2.6 is preferably designed as a spring or compression spring.
Optionally, in order to enable the pipeline 10 to be quickly and flexibly transferred from the displacement device 1 to the installation location 20, the baffle main body 2.1 is preferably configured to be a triangular structure, and one side of the baffle main body is parallel to the displacement device 1, so that the pipeline 10 is in a manner of being displaced obliquely downwards during the process of being transferred from the displacement device 1 to the installation location 20, so as to reduce the resistance during the displacement process.
The process of transferring the pipeline from the storage position to the installation position by applying the rapid pipeline transferring and in-place installation vehicle in the pipe gallery is as follows:
1) installing the pipeline in the pipeline gallery for rapid transferring, in-place and installing vehicle, and adjusting the upright posts 1.3 according to the height of the pipeline installing position so as to ensure that the upper end surface of the displacement device is aligned with the pipeline installing position;
2) placing a pipeline to be transported on the upper end face of a displacement device, simultaneously ensuring that one side of the outer surface of the pipeline is connected with a fixed baffle and the other side of the outer surface of the pipeline is limited by a movable baffle (as shown in figure 4) so as to clamp the pipeline, and controlling the displacement device to displace in a pipeline gallery so as to drive the pipeline to be transported to a position corresponding to a pipeline installation position;
3) the flapper is flipped over so that the flapper is in alignment with the upper end surface of the displacement device (as shown in fig. 5), and the pipe is rolled to displace the pipe to the installation position.
The process of transferring the pipeline from the installation position to the storage position by applying the rapid pipeline transferring and in-place installing vehicle in the pipeline tunnel is as follows:
1) installing the pipeline in the pipeline gallery for rapid transferring and in-place installation vehicle, and adjusting the upright posts 1.3 according to the height of the pipeline installation position so as to ensure that the movable baffle is aligned with the pipeline installation position after being overturned;
2) quickly transferring the pipeline in the pipe gallery in place, placing the pipeline in a mounting vehicle, moving the pipeline to a specified position, and turning over the movable baffle plate so that the movable baffle plate is aligned with the upper end surface of the displacement device;
3) rolling the pipe to position the pipe onto the displacement device;
4) and moving the displacement device to transfer the pipeline to a storage place or a designated position.
The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (8)

1. A rapid transferring and positioning installation vehicle for pipelines in a pipeline is characterized by comprising a displacement device (1), and a movable baffle (2) and a fixed baffle (3) which are arranged on the displacement device (1);
the displacement device (1) is used for displacement in the pipe gallery;
one end of the fixed baffle (3) is connected with the upper end face of the displacement device (1), and the other end of the fixed baffle extends upwards;
the movable baffle (2) and the fixed baffle (3) are arranged at intervals, one end of the movable baffle (2) is rotatably connected with the upper end face of the displacement device (1), the other end of the movable baffle extends upwards, and the pipeline (10) is arranged between the movable baffle (2) and the fixed baffle (3).
2. The rapid pipe transfer in-place installation vehicle in a pipe rack according to claim 1, characterized in that the movable baffle (2) comprises a baffle body (2.1), a connecting seat (2.2), a rotating shaft (2.3), a connecting piece (2.4) and a locking pin shaft (2.5); the connecting seat (2.2) is used for being connected with the displacement device (1), and the connecting seat (2.2) is rotatably connected with the baffle plate main body (2.1) through a rotating shaft (2.3); connecting piece (2.4) set up on baffle main part (2.1), and run through on connecting piece (2.4) and install locking pin axle (2.5), link to each other with the round pin shaft hole that sets up on frame construction through locking pin axle (2.5) to realize that the relative locking between baffle main part (2.1) and the frame construction is fixed.
3. The rapid pipe transfer in-place installation vehicle for pipe galleries according to claim 2, characterized in that the connecting seats (2.2), the connecting pieces (2.4) and the locking pin shafts (2.5) are provided with two pieces arranged in a one-to-one correspondence and arranged on both sides of the baffle body (2.1) respectively.
4. The rapid pipe transfer in-place installation vehicle in a pipe gallery according to claim 3, wherein pin shaft holes are formed in two mutually perpendicular side surfaces of one cross beam (1.1) of the frame structure for supporting the pipe (10), the connecting piece (2.4) comprises a fixed section and a movable section, one end of the fixed section is fixedly connected with the baffle main body (2.1), the other end of the fixed section is rotatably connected with one end of the movable section, and a locking pin shaft (2.5) penetrates through the movable section, so that the locking pin shaft (2.5) is connected with the pin shaft holes in different surfaces of the cross beam (1.1) through rotation of the movable section.
5. The rapid pipe transfer in-place installation vehicle for pipe galleries according to claim 3, characterized in that the locking pin (2.5) comprises a locking section and a limiting section which are connected with each other, and the locking section is used for connecting with a pin shaft hole;
an elastic part (2.6) is further sleeved on the locking pin shaft (2.5), and the elastic part (2.6) is arranged between the limiting section and the connecting part (2.4).
6. The rapid pipe transfer in place installation vehicle according to any one of claims 1 to 5, characterized in that the movable baffle (2) is arranged in a triangular configuration, one of the sides being arranged perpendicular to the upper end face of the displacement device (1).
7. A rapid pipe transfer in-place installation vehicle in a pipe rack according to claim 6, characterized in that the displacement device (1) comprises a plurality of beams (1.1), longitudinal beams (1.2), vertical columns (1.3) and universal wheels (1.4), all provided with a plurality of pieces, the plurality of beams (1.1), longitudinal beams (1.2) and vertical columns (1.3) being interconnected to form a frame structure, and the plurality of universal wheels (1.4) being connected with the lower end surface of the frame structure respectively.
8. A rapid transit in-place installation vehicle for pipes in pipe galleries according to claim 7 characterised in that the uprights (1.3) are provided as telescopic structures.
CN202221119118.2U 2022-05-10 2022-05-10 Installation car of taking one's place is transported fast to piping lane interior pipeline Active CN217201879U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221119118.2U CN217201879U (en) 2022-05-10 2022-05-10 Installation car of taking one's place is transported fast to piping lane interior pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221119118.2U CN217201879U (en) 2022-05-10 2022-05-10 Installation car of taking one's place is transported fast to piping lane interior pipeline

Publications (1)

Publication Number Publication Date
CN217201879U true CN217201879U (en) 2022-08-16

Family

ID=82777172

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221119118.2U Active CN217201879U (en) 2022-05-10 2022-05-10 Installation car of taking one's place is transported fast to piping lane interior pipeline

Country Status (1)

Country Link
CN (1) CN217201879U (en)

Similar Documents

Publication Publication Date Title
US9969525B2 (en) Stand for machine components
CN103072893B (en) Tool and method for overturning vertical equipment in nuclear power plant
CN111137204B (en) T-shaped long-beam short-distance transport tool and using method thereof
KR100796628B1 (en) Scaffolding for constructing insulation system in cargo tank of lng carrier and setting-up method of the same
CN217201879U (en) Installation car of taking one's place is transported fast to piping lane interior pipeline
JP3026184B2 (en) Bridge erection equipment
CN111157352A (en) Novel self-balancing vertical loading test device
CN112937417A (en) Pipeline unloading device, system and method
JP5469524B2 (en) Installation method and moving method of scaffold device
CN107857205B (en) Storage tank installation lifting equipment and method
KR102049892B1 (en) Moudles for utilities in mechanical room and ditch of fab and method thereof
CN111332964A (en) Steel reinforced column wall-attached device and construction method thereof
CN212162607U (en) Cable lowering device
CN115637874B (en) Construction method for accurately installing heavy-duty member at bottom of floor slab
CN211451847U (en) Sintering machine trolley turnover machine
JP3035231B2 (en) Vertical pipe lifting jig
CN113932068B (en) Method for assembling overhead vibration isolation hanging bracket of spring in annular pipe gallery
CN216306925U (en) Anchoring device of pipe pushing machine
CN215160502U (en) Work piece hoist and mount transfer device
CN219156349U (en) Steel rail hoisting equipment capable of being assembled, disassembled and heightened rapidly in operation line
CN217415806U (en) Reinforcing bar allocation and transportation equipment for building and building
CN114233201B (en) Pull type base device
JP2543487B2 (en) Axle carrier
JP7313945B2 (en) Hanging hardware, suspension structure, and suspension method
CN217731554U (en) Transportation, installation and dismounting device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: 9th Floor, New Zhoubang Science and Technology Building, No. 9 Changye Road, Liulian Community, Pingshan Street, Pingshan District, Shenzhen, Guangdong, 518118

Patentee after: CHINA CONSTRUCTION FIFTH ENGINEERING INSTALLATION Co.,Ltd.

Address before: 410004 No. 158 Zhongyi Road, Yuhua District, Changsha, Hunan

Patentee before: CHINA CONSTRUCTION FIFTH ENGINEERING INSTALLATION Co.,Ltd.