CN217129448U - Supporting device for geothermal drilling - Google Patents
Supporting device for geothermal drilling Download PDFInfo
- Publication number
- CN217129448U CN217129448U CN202123169544.5U CN202123169544U CN217129448U CN 217129448 U CN217129448 U CN 217129448U CN 202123169544 U CN202123169544 U CN 202123169544U CN 217129448 U CN217129448 U CN 217129448U
- Authority
- CN
- China
- Prior art keywords
- bottom plate
- operation platform
- electric hoist
- support
- operating
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Earth Drilling (AREA)
Abstract
The utility model discloses a support device for geothermal drilling, which comprises a bottom plate, wherein a support structure is arranged at the upper end of the bottom plate; the support structure includes: the electric hoist comprises four adjusting assemblies, four guide assemblies, a first operating hole, an operating platform, a hoisting frame body, an electric hoist body, a second operating hole and two adjusting baffles; the utility model relates to a geothermal drilling technical field, the bearing structure that the present case adopted, whole height through four built-in adjusting part change operation platform, it is spacing to lead to operation platform through four direction subassemblies between operation platform and the bottom plate, prevent that operation platform from taking place to rock, increase operation platform's stability, the effectual traditional geothermal drilling strutting arrangement who has solved exists, bearing structure stability is relatively poor, make drilling equipment take place to rock in the use easily, make operating personnel's operating efficiency reduce, and then influence the technical problem of well drilling effect.
Description
Technical Field
The utility model relates to a geothermal drilling technical field specifically is a strutting arrangement for geothermal drilling.
Background
In view of the above, a deep research aiming at the above problems is carried out, and a tunneling scheme is generated.
SUMMERY OF THE UTILITY MODEL
Not enough to prior art, the utility model provides a strutting arrangement for geothermal drilling has solved current partial background technical problem.
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: the supporting device for the geothermal drilling comprises a bottom plate, wherein a supporting structure is arranged at the upper end of the bottom plate;
the support structure includes: the electric hoist comprises four adjusting assemblies, four guide assemblies, a first operating hole, an operating platform, a hoisting frame body, an electric hoist body, a second operating hole and two adjusting baffles;
four adjusting part install respectively in bottom plate upper end four corners department, four the direction subassembly install respectively in the bottom plate upper end, first handle hole set up in bottom plate center department, operation platform install in four adjusting part and four direction subassembly upper end, the hoisting frame body install in the operation platform upper end, the electric hoist body install in wall department under the hoisting frame body, the second handle hole set up in operation platform center department, two adjusting baffle install respectively in second handle hole both sides.
Preferably, the adjustment assembly comprises: the hydraulic cylinder is arranged on the first hinged support;
the first hinged support is installed on one side of the upper end of the bottom plate, the bottom end of the hydraulic cylinder is hinged to the first hinged support, the second hinged support is installed at the lower end of the operating platform, and the telescopic end of the hydraulic cylinder is hinged to the inside of the second hinged support.
Preferably, the lower end of the bottom plate is provided with four supporting feet for supporting the bottom plate.
Preferably, the guide assembly comprises: the device comprises a first guide sleeve, a second guide sleeve and a guide rod;
the first guide sleeve is arranged on one side of the upper end of the bottom plate, the second guide sleeve is embedded in the first guide sleeve, the guide rod is embedded in the second guide sleeve, and the upper end of the guide rod is connected with the lower end of the operating platform.
Preferably, the connection part of the electric hoist body and the hoisting frame body is provided with a fixing frame for fixing the electric hoist body.
Preferably, the adjusting baffle is fixed at the upper end of the operating platform through bolts.
The utility model provides a geothermal drilling is with strutting arrangement. The method has the following beneficial effects: the bearing structure that the present case adopted, through four built-in adjusting part change operation platform's overall height, it is spacing to lead to operation platform through four direction subassemblies between operation platform and the bottom plate, prevent that operation platform from taking place to rock, increase operation platform's stability, the effectual traditional geothermol power drilling strutting arrangement that has solved exists, bearing structure stability is relatively poor, make drilling equipment take place to rock in the use easily, make operating personnel's operating efficiency reduce, and then influence the technical problem of drilling effect.
Drawings
Fig. 1 is the utility model discloses a geothermal drilling is with strutting arrangement's main view structure schematic diagram.
Fig. 2 is the utility model discloses a supporting device for geothermal drilling overlooks the structure sketch map.
Fig. 3 is an enlarged schematic structural view of the position "a" of the present invention.
In the figure: 1. the electric hoist comprises a base plate, 2, a first operation hole, 3, an operation platform, 4, a hoisting frame body, 5, an electric hoist body, 6, a second operation hole, 7, an adjusting baffle, 8, a first hinged support, 9, a hydraulic cylinder, 10, a second hinged support, 11, a supporting footing, 12, a first guide sleeve, 13, a second guide sleeve, 14, a guide rod, 15 and a fixing frame.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Example 1
As shown in fig. 1-3, a support device for geothermal drilling comprises a bottom plate 1, wherein a support structure is arranged at the upper end of the bottom plate 1;
when the geothermal drilling device needs to be supported, the purpose of supporting the geothermal drilling device is achieved by driving the supporting structure arranged at the upper end of the bottom plate 1 to work.
In a specific implementation, the support structure comprises: the electric hoist comprises four adjusting assemblies, four guide assemblies, a first operating hole 2, an operating platform 3, a hoisting frame body 4, an electric hoist body 5, a second operating hole 6 and two adjusting baffles 7;
four adjusting part install respectively in 1 upper end four corners department of bottom plate, four direction subassemblies are installed respectively in 1 upper end of bottom plate, 1 central department in bottom plate is seted up in first handle hole 2, operation platform 3 installs in four adjusting part and four direction subassembly upper ends, lifting frame body 4 installs in 3 upper ends of operation platform, wall department under lifting frame body 4 is installed to electric hoist body 5, 3 central departments in operation platform are seted up in second handle hole 6, two adjusting barriers 7 are installed respectively in 6 both sides in second handle hole.
It should be noted that, when needs support geothermal drilling device, through the work of driving four adjusting part, promote operation platform 3 rebound, it is spacing to lead to operation platform 3 through four direction subassemblies, prevent operation platform 3 from taking place to rock, through binding drilling equipment on electric hoist body 5, through the work of driving electric hoist body 5, drive drilling equipment and get into in the drilling through first handle hole 2 and second handle hole 6, can be according to the drilling demand of reality, change the position of two adjusting baffle 7, block second handle hole 6 to the upper end of operation platform 3, prevent that the foreign matter from dropping.
Example 2
As shown in the figures 1-3 of the drawings,
in a specific implementation, the adjustment assembly comprises: a first hinged support 8, a hydraulic cylinder 9 and a second hinged support 10;
first free bearing 8 is installed in 1 upper end one side of bottom plate, and 9 bottoms of pneumatic cylinder are articulated with first free bearing 8, and second free bearing 10 is installed in 3 lower extremes of operation platform, and the flexible end of pneumatic cylinder 9 articulates in second free bearing 10.
When the operation platform 3 needs to be supported, the hydraulic cylinder 9 is driven by an operator to operate, and the hydraulic cylinder 9 extends and retracts between the first hinged support 8 and the second hinged support 10 to push the operation platform 3 to move upwards, so that the operation platform 3 is lifted to a specified position.
Example 3
As shown in fig. 1 to 3, further preferably, the guide assembly includes: a first guide sleeve 12, a second guide sleeve 13 and a guide rod 14;
the first guide sleeve 12 is arranged on one side of the upper end of the bottom plate 1, the second guide sleeve 13 is embedded in the first guide sleeve 12, the guide rod 14 is embedded in the second guide sleeve 13, and the upper end of the guide rod 14 is connected with the lower end of the operating platform 3.
When the height of the operation platform 3 is adjusted, the operation platform 3 is guided and limited by the linear motion of the first guide sleeve 12, the second guide sleeve 13, and the guide rod 14, and the operation platform 3 is prevented from shaking.
Preferably, the bottom plate 1 is further provided with four supporting feet 11 at the lower end thereof for supporting the bottom plate 1. As a preferred solution, further, the optimization benefits are.
Preferably, a fixing frame 15 for fixing the electric hoist body 5 is further arranged at the joint of the electric hoist body 5 and the hoisting frame body 4.
Preferably, the adjusting baffle 7 is fixed on the upper end of the operating platform 3 through bolts.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation. The use of the phrase "comprising one of the elements does not exclude the presence of other like elements in the process, method, article, or apparatus that comprises the element.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (6)
1. The supporting device for the geothermal drilling comprises a bottom plate, and is characterized in that a supporting structure is arranged at the upper end of the bottom plate;
the support structure includes: the electric hoist comprises four adjusting assemblies, four guide assemblies, a first operating hole, an operating platform, a hoisting frame body, an electric hoist body, a second operating hole and two adjusting baffles;
four adjusting part install respectively in bottom plate upper end four corners department, four the direction subassembly install respectively in the bottom plate upper end, first handle hole set up in bottom plate center department, operation platform install in four adjusting part and four direction subassembly upper end, the hoisting frame body install in the operation platform upper end, the electric hoist body install in wall department under the hoisting frame body, the second handle hole set up in operation platform center department, two adjusting baffle install respectively in second handle hole both sides.
2. The support device of claim 1, wherein the adjustment assembly comprises: the hydraulic cylinder is arranged on the first hinged support;
the first hinged support is installed on one side of the upper end of the bottom plate, the bottom end of the hydraulic cylinder is hinged to the first hinged support, the second hinged support is installed at the lower end of the operating platform, and the telescopic end of the hydraulic cylinder is hinged to the inside of the second hinged support.
3. The support device for geothermal drilling according to claim 1, wherein the lower end of the bottom plate is provided with four support feet for supporting the bottom plate.
4. The support device of claim 1, wherein the guide assembly comprises: the device comprises a first guide sleeve, a second guide sleeve and a guide rod;
the first guide sleeve is arranged on one side of the upper end of the bottom plate, the second guide sleeve is embedded in the first guide sleeve, the guide rod is embedded in the second guide sleeve, and the upper end of the guide rod is connected with the lower end of the operating platform.
5. The supporting device for the geothermal drilling well according to claim 1, wherein a fixing frame for fixing the electric hoist body is arranged at the joint of the electric hoist body and the hoisting frame body.
6. The support device for geothermal drilling according to claim 1, wherein the adjustment baffle is fixed to the upper end of the operation platform by bolts.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202123169544.5U CN217129448U (en) | 2021-12-15 | 2021-12-15 | Supporting device for geothermal drilling |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202123169544.5U CN217129448U (en) | 2021-12-15 | 2021-12-15 | Supporting device for geothermal drilling |
Publications (1)
Publication Number | Publication Date |
---|---|
CN217129448U true CN217129448U (en) | 2022-08-05 |
Family
ID=82618637
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202123169544.5U Active CN217129448U (en) | 2021-12-15 | 2021-12-15 | Supporting device for geothermal drilling |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN217129448U (en) |
-
2021
- 2021-12-15 CN CN202123169544.5U patent/CN217129448U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN217129448U (en) | Supporting device for geothermal drilling | |
CN206014314U (en) | A kind of small-sized lowering or hoisting gear | |
CN206088957U (en) | Shear fork type lifting device | |
CN206144559U (en) | Portable mining lifting support that fixes | |
CN201577351U (en) | Greenhouse truss crawler-type lifting erecting equipment | |
CN216190935U (en) | Well lid is hoisting device for maintenance | |
CN216303095U (en) | Material overhead hoist is used in room construction | |
CN216005091U (en) | Drilling machine crawler lifting device | |
CN214498319U (en) | House building construction platform | |
CN212839809U (en) | Prefabricated pipeline lifting device | |
CN214365902U (en) | Oil derrick auxiliary fixture | |
CN213358615U (en) | Municipal works are with pile device | |
CN208135763U (en) | Assembled architecture equipment boom hoisting | |
CN213141333U (en) | Lifting platform for installing variable-frequency series resonance device | |
CN201128648Y (en) | Mobile elevator | |
CN213505616U (en) | Portal frame is used in building engineering construction | |
CN220201227U (en) | Hoisting device for electromechanical installation of coal mine | |
CN213326525U (en) | Jacking device that civil engineering used | |
CN213625239U (en) | Bridge engineering construction platform | |
CN211899858U (en) | Movable working room for ground construction | |
CN217268674U (en) | Assembled heavy load construction platform | |
CN111302201A (en) | Self-walking mechanical equipment lifting frame | |
CN216239661U (en) | Simple and easy portable hanging flower basket | |
CN220976319U (en) | Auxiliary device | |
CN217264455U (en) | Portal frame for electromechanical device installation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |