CN217128946U - Prevent cracked building fluting and fill mould - Google Patents

Prevent cracked building fluting and fill mould Download PDF

Info

Publication number
CN217128946U
CN217128946U CN202220673418.9U CN202220673418U CN217128946U CN 217128946 U CN217128946 U CN 217128946U CN 202220673418 U CN202220673418 U CN 202220673418U CN 217128946 U CN217128946 U CN 217128946U
Authority
CN
China
Prior art keywords
fixed
roof
plate
crack
ejector pin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220673418.9U
Other languages
Chinese (zh)
Inventor
刘锋亮
惠伟
吕聪
李庆威
张帅
崔金隆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN202220673418.9U priority Critical patent/CN217128946U/en
Application granted granted Critical
Publication of CN217128946U publication Critical patent/CN217128946U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides a prevent cracked building fluting and fill mould, relates to building crack control field, including the fixed block, the left side of fixed block is equipped with the ejector pin, and the left side of ejector pin is equipped with even board, and the upper end of fixed block is equipped with the collar, and the upper end of collar is equipped with roof A, installs the screw thread post on the roof A. The utility model discloses an inflation of gasbag is exerted pressure for it at the in-process that grout solidifies, reduces the effect that its volume after solidifying reduces, avoids wall body cell body department to appear the crack, presses roof A, even board and roof B on the wall outside the cell body through second electric telescopic handle supporting pressing plate, exerts pressure through lever principle, can guarantee that grout does not reveal in the cell body, and the efficiency of construction is high, simple structure easily operates.

Description

Prevent cracked building fluting and fill mould
Technical Field
The utility model belongs to the technical field of the building crack control seam and specifically relates to a prevent fissured building fluting and fill mould is related to.
Background
Building need carry out the fluting operation on the wall in order to predetermine water and electricity circuit and pipeline after the building is accomplished, the staff has opened the groove at the use tool after, article such as pre-buried electric wire way and water pipe need, common way is after pre-buried electric wire way, workman's use tool smears grout in the electric wire way and waits for its automatic solidification, but grout can reduce in the solidification process loss of water volume and lead to comparatively weak with the combination department structure of wall, the cement volume reduces to produce stress and leads to wall fluting position to appear the crack, it is very pleasing to the eye and influence the housing quality.
SUMMERY OF THE UTILITY MODEL
In order to overcome not enough among the background art, the utility model discloses a building fluting of crack control seam fills mould, the utility model discloses an inflation of gasbag is exerted pressure for it at the in-process that the grout solidifies, reduces the effect that its volume after solidifying reduces, avoids wall body cell body department to appear the crack, presses roof A, even board and roof B on the wall outside the cell body through second electric telescopic handle supporting pressure plate, exerts pressure through lever principle, can guarantee that the grout does not reveal in the cell body, and the efficiency of construction is high, simple structure easily operates.
In order to realize the utility model aims at, the utility model adopts the following technical scheme:
the utility model provides a prevent cracked building fluting and fill mould, includes the fixed block, and the left side of fixed block is equipped with the ejector pin, and the left side of ejector pin is equipped with the link plate, and the upper end of fixed block is equipped with the collar, and the upper end of collar is equipped with roof A, installs the screw thread post on the roof A.
The right flank middle part of fixed block is fixed with an electric telescopic handle, and the symmetry is fixed with the mounting panel respectively around the upper surface left side of fixed block, is fixed with the installation axle between two mounting panels.
The mounting shaft is connected with the center hole of the mounting ring through a bearing, a second electric telescopic rod is fixed on the side face of the mounting ring, a first clamping ring is fixed at the middle part of the second electric telescopic rod, a pressing plate is hinged to the upper end of the second electric telescopic rod, and a clamping plate is fixed at the middle part of the left side of the pressing plate.
The left side middle part of fixed block is fixed with the ejector pin, and the middle part of ejector pin is fixed with the second snap ring, and the left side that the side of ejector pin is located the second snap ring is equipped with the elastic webbing, and the upper end cover of elastic webbing is located the left side of first snap ring on the second electric telescopic handle, and the left end of ejector pin is fixed with roof B, and roof B's upper surface right half is fixed with first flange.
The left half parts of the upper surface and the lower surface of the connecting plate are respectively fixed with a second convex plate in an up-down symmetrical manner.
The upper end left side of roof A is fixed with the shrouding, and the threaded hole has been seted up at the middle part of shrouding, and the second square hole has been seted up on roof A's middle part right side, lies in the left side in second square hole on roof A and has seted up first square hole, and roof A's lower surface right half part is fixed with the third relief block.
Threaded hole has the screw thread post through threaded connection, the lower surface middle part of screw thread post is fixed with flexible pipe, flexible pipe is nested mutually by being no less than four hollow tubes and is constituteed, can freely extend under the circumstances of low side atress, the low side that guarantees flexible pipe can reach the wall cell body, the lower surface of screw thread post is fixed with the gasbag with flexible pipe position centre of a circle, the gasbag is made by elastic material such as rubber membrane, can exert pressure to the grout in the cell body when aerifing the inflation and make it can not produce the crack when solidifying the shrink, the gasbag links together with the lower extreme of flexible pipe, screw thread post upper end intercommunication has the intake pipe.
The second convex plate and the first convex plate at the lower end of the connecting plate are mutually close to and clamped together when in use, the second convex plate and the third convex plate at the upper end of the connecting plate are mutually close to and clamped together when in use, and the pressing plate and the clamping plate are clamped in the first square hole and the second square hole.
Since the technical scheme is used, the utility model discloses following beneficial effect has:
a building fluting of crack control seam fills mould, the inflation through the gasbag is exerted pressure for it at the in-process that the grout solidifies, reduces the effect that its volume after solidifying reduces, avoids wall body cell body department to appear the crack, supports the clamp plate through second electric telescopic handle with roof/even board and roof pressure on the wall outside the cell body, exert pressure through lever principle, can guarantee that the grout does not reveal in the cell body, the efficiency of construction is high, simple structure easily operates.
Drawings
Fig. 1 is a schematic left-side perspective view of the present invention;
FIG. 2 is a right side perspective view of the present invention;
fig. 3 is a schematic front half-sectional perspective view of fig. 2 according to the present invention;
fig. 4 is an enlarged view of a portion a of fig. 3 according to the present invention;
fig. 5 is a partial enlarged view of fig. 3B according to the present invention;
FIG. 6 is a schematic view of the three-dimensional structure of the threaded post of the present invention;
fig. 7 is a schematic view of the front half-section three-dimensional structure of the threaded column of the present invention.
1. A fixed block; 101. a first electric telescopic rod; 102. mounting a plate; 103. installing a shaft; 2. a mounting ring; 201. a second electric telescopic rod; 202. a first snap ring; 203. pressing a plate; 204. clamping a plate; 3. a top rod; 301. a second snap ring; 302. an elastic band; 303. a top plate B; 304. a first convex plate; 4. connecting plates; 401. a second convex plate; 5. a top plate A; 501. closing the plate; 502. a threaded hole; 503. a first square hole; 504. a second square hole; 505. a third relief printing plate; 6. a threaded post; 601. an air inlet pipe; 602. an air bag; 603. a telescopic tube.
Detailed Description
The invention will be explained in more detail by the following examples, which disclose the invention and are intended to protect all technical improvements within the scope of the invention.
Combine attached figure 1~7, a building fluting of crack control seam fills mould, including fixed block 1, the left side of fixed block 1 is equipped with ejector pin 3, and the left side of ejector pin 3 is equipped with link plate 4, and the upper end of fixed block 1 is equipped with collar 2, and the upper end of collar 2 is equipped with roof A5, installs threaded post 6 on the roof A5.
The middle part of the right side face of the fixed block 1 is fixed with a first electric telescopic rod 101, the left front and back sides of the upper surface of the fixed block 1 are symmetrically fixed with mounting plates 102 respectively, and a mounting shaft 103 is fixed between the two mounting plates 102.
The mounting shaft 103 is connected with the center hole of the mounting ring 2 through a bearing, the side face of the mounting ring 2 is fixed with a second electric telescopic rod 201, the middle part of the second electric telescopic rod 201 is fixed with a first clamping ring 202, the upper end of the second electric telescopic rod 201 is hinged with a pressing plate 203, and the middle part of the left side of the pressing plate 203 is fixed with a clamping plate 204.
The middle of the left side face of the fixing block 1 is fixedly provided with a top rod 3, the middle of the top rod 3 is fixedly provided with a second snap ring 301, the left side of the side face of the top rod 3, which is located on the second snap ring 301, is provided with an elastic band 302, the upper end of the elastic band 302 is sleeved on the second electric telescopic rod 201 and is located on the left side of the first snap ring 202, the left end of the top rod 3 is fixedly provided with a top plate B303, and the right half part of the upper surface of the top plate B303 is fixedly provided with a first convex plate 304.
The left half parts of the upper surface and the lower surface of the connecting plate 4 are respectively fixed with a second convex plate 401 up and down symmetrically.
A sealing plate 501 is fixed on the left side of the upper end of the top plate A5, a threaded hole 502 is formed in the middle of the sealing plate 501, a second square hole 504 is formed in the right side of the middle of the top plate A5, a first square hole 503 is formed in the left side, located in the second square hole 504, of the top plate A5, the first square hole 503 and the second square hole 504 penetrate through the top plate A5, it is guaranteed that cement can be poured into a groove body from the first square hole 503 and the second square hole 504, the size of the first square hole 503 is smaller than that of the second square hole 504 and equal to that of the pressing plate 203, the size of the clamping plate 204 is equal to that of the first square hole 503, the pressing plate 203 and the clamping plate 204 can be clamped in the first square hole 503 and the second square hole 504, and a third relief plate 505 is fixed on the right half of the lower surface of the top plate A5.
The threaded hole 502 is internally connected with a threaded column 6 through threads, the middle part of the lower surface of the threaded column 6 is fixedly provided with a telescopic tube 603, the lower surface of the threaded column 6 is fixedly provided with an air bag 602 by the position of the center of the telescopic tube 603, the air bag 602 is connected with the lower end of the telescopic tube 603, and the upper end of the threaded column 6 is communicated with an air inlet pipe 601.
The second convex plate 401 and the first convex plate 304 at the lower end of the connecting plate 4 are close to each other and clamped together when in use, the second convex plate 401 and the third convex plate 505 at the upper end of the connecting plate 4 are close to each other and clamped together when in use, and the pressing plate 203 and the clamping plate 204 are clamped in the first square hole 503 and the second square hole 504.
A building fluting of crack control seam fills mould, when using, when needing to the cell body on the wall to fill grout, make roof 303 aim at the lowermost end of cell body on the wall through the position of adjustment fixed block 1 earlier, fill grout between cell body and roof 303, first electric telescopic handle 101 starts the extension afterwards and withstands opposite wall body with fixed block 1's rigidity, select even board 4 of suitable length to put second flange 401 in first flange 304 left side and make even board 4 joint in roof B303 top, continue to pack grout to the cell body in even board 4's top, even board 4 and roof B303 can guarantee that grout can not outflow leak, later place third relief board 505 on second flange 401's right side, make roof 5 joint in even board 4's top, continue to add cement to roof A5 inboard through first square hole 503 and second square hole 504, later through rotating collar 2 and flexible second electric telescopic handle 201 on installation axle 103 and make clamp plate 203 second square hole 504 block go into Meanwhile, the clamping plate 204 is clamped in the first square hole 503, the elastic belt 302 is stretched to generate elastic force to press the second electric telescopic rod 201 downwards, the second electric telescopic rod 201 presses the top plate A5 and the connecting plate 4 downwards through the pressing plate 203 to enable the fixing to be firmer, finally, the shortened telescopic pipe 603 and the air bag 602 penetrate into the trough body from the threaded hole 502 from top to bottom, the air bag 602 naturally moves downwards under the action of the gravity of the telescopic pipe 603 to be inserted into the cement mortar filled in the trough body, the air inlet pipe 601 is inserted into an air outlet of an external inflating device, air is input into the air bag 602 to enable the air bag 602 to expand, the expanded air bag 602 occupies more volume to push the cement mortar upwards to gradually fill the trough body, then, the solidification of the cement mortar can be waited, the high-pressure air in the air bag 602 can continuously exert pressure on the cement mortar in the trough body in the solidification process to offset the shrinking effect of the air bag in the solidification process, after the cement paste is primarily solidified, an external inflating device is taken down from the air inlet pipe 601, the air bag 602 is deflated and contracted and is separated from the solidified cement, the air bag 602 can be intermittently inflated and deflated, air circulation is accelerated, after the cement paste is completely solidified, the threaded column 6 is rotated in the threaded hole 502, the air bag 602 is pulled upwards to contract the telescopic pipe 603, so that the telescopic pipe 502 is taken out of the threaded hole 502, and then the ejector rod 3, the connecting plate 4 and the top plate A5 are sequentially taken down according to the reverse operation of the operation, so that pouring of the tank body cement paste can be completed.
The invention is not described in detail in the prior art, and although the invention has been specifically shown and described in connection with the preferred embodiments, the method and the way of implementing the technical solution are numerous, and only the preferred embodiments of the invention have been described above, it should be understood by those skilled in the art that various changes in form and details may be made therein without departing from the spirit and scope of the invention as defined in the appended claims, which are within the scope of the invention.

Claims (8)

1. The utility model provides a prevent cracked building fluting and fill mould, includes fixed block (1), characterized by: the left side of fixed block (1) is equipped with ejector pin (3), and the left side of ejector pin (3) is equipped with even board (4), and the upper end of fixed block (1) is equipped with collar (2), and the upper end of collar (2) is equipped with roof A (5), installs screw thread post (6) on roof A (5).
2. The crack-resistant architectural notching filling mold of claim 1, wherein: the electric telescopic handle is characterized in that a first electric telescopic rod (101) is fixed in the middle of the right side face of the fixing block (1), mounting plates (102) are symmetrically fixed on the left side of the upper surface of the fixing block (1) in the front-back direction, and a mounting shaft (103) is fixed between the two mounting plates (102).
3. The crack-resistant architectural notching filling mold of claim 1, wherein: the mounting shaft (103) is connected with the center hole of the mounting ring (2) through a bearing, the side face of the mounting ring (2) is fixed with a second electric telescopic rod (201), the middle part of the second electric telescopic rod (201) is fixed with a first clamping ring (202), the upper end of the second electric telescopic rod (201) is hinged with a pressing plate (203), and the middle part of the left side of the pressing plate (203) is fixed with a clamping plate (204).
4. A crack resistant architectural notching filling mold as set forth in claim 3, wherein: the left surface middle part of fixed block (1) is fixed with ejector pin (3), the middle part of ejector pin (3) is fixed with second snap ring (301), the left side that the side of ejector pin (3) is located second snap ring (301) is equipped with elastic webbing (302), the upper end cover of elastic webbing (302) is located the left side of first snap ring (202) on second electric telescopic handle (201), the left end of ejector pin (3) is fixed with roof B (303), the half part on the right side of the upper surface of roof B (303) is fixed with first flange (304).
5. The crack-resistant architectural notching filling mold of claim 4, wherein: the left half parts of the upper surface and the lower surface of the connecting plate (4) are respectively and symmetrically fixed with a second convex plate (401) up and down.
6. A crack resistant architectural notching filling mold as set forth in claim 5, further characterized by: the upper end left side of roof A (5) is fixed with shrouding (501), and screw hole (502) have been seted up in the middle part of shrouding (501), and second square hole (504) have been seted up on the middle part right side of roof A (5), and first square hole (503) have been seted up on the left side that lies in second square hole (504) on roof A (5), and the lower surface right half of roof A (5) is fixed with third relief printing plate (505).
7. The crack-resistant architectural notching filling mold of claim 1, wherein: threaded column (6) is connected with the threaded column (6) through threads in the threaded hole (502), the lower surface middle part of threaded column (6) is fixed with telescopic tube (603), telescopic tube (603) is formed by nesting not less than four hollow tubes, the lower end can be freely extended under the condition that the lower end is not stressed, the lower end of telescopic tube (603) can reach the lower end of the wall groove body, the lower surface of threaded column (6) is fixed with air bag (602) with the position center of circle of telescopic tube (603), air bag (602) is made of rubber membrane, pressure can be applied to cement paste in the groove body during inflation and expansion so that the cement paste can not crack when solidification and contraction, the lower ends of air bag (602) and telescopic tube (603) are connected together, and the upper end of threaded column (6) is communicated with air inlet pipe (601).
8. The crack-resistant architectural grooving filling mold according to claim 6, wherein: the second convex plate (401) and the first convex plate (304) at the lower end of the connecting plate (4) are close to each other and clamped together when in use, the second convex plate (401) and the third convex plate (505) at the upper end of the connecting plate (4) are close to each other and clamped together when in use, and the pressing plate (203) and the clamping plate (204) are clamped in the first square hole (503) and the second square hole (504).
CN202220673418.9U 2022-03-27 2022-03-27 Prevent cracked building fluting and fill mould Active CN217128946U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220673418.9U CN217128946U (en) 2022-03-27 2022-03-27 Prevent cracked building fluting and fill mould

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220673418.9U CN217128946U (en) 2022-03-27 2022-03-27 Prevent cracked building fluting and fill mould

Publications (1)

Publication Number Publication Date
CN217128946U true CN217128946U (en) 2022-08-05

Family

ID=82644943

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220673418.9U Active CN217128946U (en) 2022-03-27 2022-03-27 Prevent cracked building fluting and fill mould

Country Status (1)

Country Link
CN (1) CN217128946U (en)

Similar Documents

Publication Publication Date Title
CN217128946U (en) Prevent cracked building fluting and fill mould
CN102433989A (en) Equipment base pre-reservation round anchor bolt hole die
CN213573033U (en) Construction auxiliary device for building floor preformed hole
CN113059660A (en) Laminated plate mold and using method
CN207138628U (en) A kind of T-shaped three water flowing is risen mould
CN110091945B (en) Foaming injection type saddle processing technology
CN213018342U (en) Water conservancy pipeline protection casing
CN109779127B (en) Building combined building block
CN201358580Y (en) Prepared hole die of concrete
CN212562492U (en) Preformed hole construction equipment that building engineering used
CN210475140U (en) W-shaped copper water stop cross joint punch forming device
CN208262724U (en) Pneumatic tire pressing tool
CN209110131U (en) A kind of steel cable lock box device
CN209736370U (en) Straightening device for building metal pipe fitting material
CN208214867U (en) A kind of auxiliary component clamp device of machine tooling
CN203334675U (en) Bolt sleeve and waterproof through-wall bolt device for supporting template of bolt sleeve
CN208380088U (en) A kind of reinforcing support construction for architectural engineering
CN217420249U (en) A quick connecting device for pouring steel-pipe column inner tube concrete
CN216915024U (en) Intelligent film adjusting forming machine
CN219466929U (en) High strength pressure pipe is along with shape cooling injection mold
CN211416012U (en) PE foaming mold utensil convenient to adjust
CN210288456U (en) Assembled steel mould for foundation bearing platform of house building engineering
CN217499940U (en) Device is demolishd to bridge temporary support low temperature
CN220868803U (en) Hanging die structure of cast-in-situ belt of assembled laminated slab
CN219487747U (en) Floating device and unmanned aerial vehicle

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant