Novel glue wire net frame heated board that anchor combines
Technical Field
The utility model relates to an heated board technical field especially relates to a novel glue wire net rack heated board that anchor combines.
Background
The thermal insulation board is a board for building thermal insulation, and the traditional thermal insulation board mostly uses organic polystyrene, polyurethane, rubber powder polyphenyl particles or inorganic mineral wool, foamed ceramics and the like with low thermal conductivity as main materials, has the moisture-proof and waterproof performances, and can reduce the thickness of an outer enclosure structure of a building so as to increase the indoor use area.
Among the correlation technique, when carrying out architectural decoration, for improving indoor heat preservation effect, can install the heated board on the wall usually, traditional heated board heat preservation effect is not good, and weatherability and intensity are relatively poor moreover, and the processing of being not convenient for, and then improved the complexity of follow-up installation.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the problem of the prior art that the good but fire behavior of organic material heat preservation effect is not good, and weatherability and intensity are relatively poor moreover, the shortcoming of the anchor combination that is not convenient for process, and the novel wire net frame heated board that glues that proposes.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
a novel steel wire rack heat insulation plate combined with bonding anchors comprises a base layer, wherein a cement mortar leveling layer is fixedly connected to the side surface of the base layer, a heat insulation assembly is arranged on one side of the cement mortar leveling layer, an expansion bolt is arranged on the heat insulation assembly, the heat insulation assembly comprises a rock wool heat insulation plate, a steel wire inner net piece is fixedly connected to the side surface of the rock wool heat insulation plate, and a steel wire outer net piece is fixedly connected to the side surface of the steel wire inner net piece;
through the setting of heat preservation subassembly, strengthened the intensity of heated board, further improve the life of heated board, satisfied the use of heated board different environment.
The above technical solution further comprises: and the steel wire inner net sheet is provided with obliquely inserted steel wires.
The steel wire inner net piece and the steel wire outer net piece are formed by cross welding of a plurality of steel wires with the diameter of 2-3 mm.
And the heat insulation component is provided with a straight inserted wire.
The heat insulation assembly is fixed on the side face of the cement mortar leveling layer through an expansion bolt, and oblique inserting abdominal wires are arranged inside the heat insulation assembly.
The other side of the heat preservation assembly is provided with a thick plastering mortar layer, and the other side of the thick plastering mortar layer is fixedly connected with a decorative layer.
Compared with the prior art, the beneficial effects of the utility model are that:
the utility model discloses in, through the setting of heat preservation subassembly, strengthened the intensity of heated board, further improve the life of heated board, satisfied the use of the different environment of heated board, have that coefficient of heat conductivity is low, the gas permeability is good, the sound absorption performance is excellent, the hydrophobic moisture resistance is good, characteristics such as fire prevention, weatherability are strong, easily cutting, construction convenience, further improved the result of use of heated board.
Drawings
Fig. 1 is a schematic structural view of a novel adhesive-anchor combined steel wire mesh frame insulation board provided by the utility model;
fig. 2 is a schematic structural diagram of the thermal insulation assembly in fig. 1.
In the figure: 1. a base layer; 2. leveling layer of cement mortar; 3. a heat preservation assembly; 31. rock wool insulation boards; 32. inner net sheets of steel wires; 33. a steel wire outer mesh sheet; 34. obliquely inserting steel wires; 4. an expansion bolt; 5. obliquely inserting abdominal wires; 6. a thick layer of plastering mortar; 7. a decorative layer; 8. and (5) inserting the wire directly.
Detailed Description
The technical solution of the present invention will be further explained with reference to the accompanying drawings and specific embodiments.
Example one
As shown in fig. 1-2, the utility model provides a novel steel wire rack insulation board that bonds anchor, including base layer 1, the side of base layer 1 is fixedly connected with cement mortar screed-coat 2, one side of cement mortar screed-coat 2 is provided with insulation assembly 3, be provided with expansion bolt 4 on the insulation assembly 3, insulation assembly 3 includes rock wool insulation board 31, the side of rock wool insulation board 31 is fixedly connected with steel wire inner net piece 32, the side of steel wire inner net piece 32 is fixedly connected with steel wire outer net piece 33;
through the setting of insulation component 3, strengthened the intensity of heated board, further improved the life of heated board, satisfied the use of the different environment of heated board, have that coefficient of heat conductivity is low, the gas permeability is good, sound absorption performance is excellent, the hydrophobic moisture resistance is good, characteristics such as fire prevention, weatherability are strong, easily cutting, construction convenience, further improved the result of use of heated board.
The above technical solution further comprises: the inner mesh 32 is provided with an inclined steel wire 34.
The steel wire inner mesh 32 and the steel wire outer mesh 33 are formed by interweaving a plurality of steel wires with the diameter of two millimeters, the steel wire inner mesh 32 is 100 x 100, and the steel wire outer mesh 33 is 50 x 50, so that the strength of the heat preservation assembly 3 is improved.
A straight plug wire 8 is arranged on the heat insulation component 3;
through the arrangement of the straight inserting wires 8, the stability of the thick plastering mortar layer 6 adhered to the heat insulation component 3 is improved.
The heat insulation component 3 is fixed on the side surface of the cement mortar leveling layer 2 through an expansion bolt 4, and an inclined web inserting wire 5 is arranged inside the heat insulation component 3;
through the setting of expansion bolts 4, improved insulation component 3 and wall connection's stability, through inserting the setting of binder silk 5 to one side moreover, not only further improved insulation component 3 and wall connection's stability, increased insulation component 3's intensity moreover.
In this embodiment, through the setting of heat preservation subassembly 3, not only improved the heat preservation effect of heated board, strengthened the intensity and holistic durability of heated board moreover. Through rock wool heated board 31's setting, promote heated board fire behavior to A level, when with the same grade of structure fire prevention, the lower coefficient of heat conductivity of heated board has been guaranteed, the coefficient of heat conductivity is less, then the energy through the material transmission is less, and then the heat-proof quality of heated board has been improved, and it passes through the setting of inserting abdominal wire 5 to one side still to have higher acoustic absorption coefficient, the stability of insulating assembly 3 and wall connection has not only further been improved, the intensity of insulating assembly 3 has been increased, and through expansion bolt 4's setting, the stability of insulating assembly 3 and wall connection has been improved, show and strengthened the holistic durability of insulating assembly, can reach with the building with the life-span.
Example two
As shown in fig. 1, based on the first embodiment, a thick mortar layer 6 is disposed on the other side of the heat preservation assembly 3, and a decorative layer 7 is fixedly connected to the other side of the thick mortar layer 6.
In this embodiment, through the setting of thick mortar layer 6 of plastering, not only improved the convenience of decorative layer 7 installation, improved the stability of installation moreover, through the setting of thick mortar layer 6 of plastering, improved the weatherability of heated board moreover.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.