CN217071232U CN202220374911.0U CN202220374911U CN217071232U CN 217071232 U CN217071232 U CN 217071232U CN 202220374911 U CN202220374911 U CN 202220374911U CN 217071232 U CN217071232 U CN 217071232U
Authority
CN
China
Prior art keywords
steel
platform
flue gas
steel column
envelope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220374911.0U
Other languages
Chinese (zh)
Inventor
张洪兴
李爱鑫
倪思伟
王思博
李贵江
秦翰星
王伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Uni Construction Group Co Ltd
Original Assignee
Beijing Uni Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Uni Construction Group Co Ltd filed Critical Beijing Uni Construction Group Co Ltd
Priority to CN202220374911.0U priority Critical patent/CN217071232U/en
Application granted granted Critical
Publication of CN217071232U publication Critical patent/CN217071232U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Building Environments (AREA)

Abstract

The utility model discloses a steel construction welded platform belongs to steel construction technical field, this steel construction welded platform sets up the top at the girder steel of treating welded girder steel column connection node, including supporting platform, envelope, flue gas purification device, flue gas recovery funnel and prevent wind fire prevention ceiling, this steel construction welded platform sets up envelope through the top at supporting platform, and install flue gas purification device on envelope, purify the flue gas to the utmost, adopt at the envelope top to prevent wind the fire prevention ceiling and effectively seal, prevent that the flue gas is excessive, and install the flue gas recovery funnel on the steel column of envelope top, will probably retrieve from the excessive flue gas of the node of being connected of preventing wind fire prevention ceiling and steel column, this steel construction welded platform is easy to assemble and dismantles.

Description

Steel structure welding platform
Technical Field
The utility model belongs to the technical field of the steel construction, specifically be a steel construction welded platform.
Background
The preferential steel structure building adopted by newly built public buildings such as schools, hospitals, gymnasiums and the like is the common development direction of the building industry at present.
The welding of traditional steel construction building vertical structure post generally adopts the operation platform of job site preparation, and conventional welded platform generally adopts the interim tripod of welding and lower floor steel construction post to carry out the temporary connection. In this way, once a week, the temporary tripod needs to be welded and the temporary support frame needs to be cut after construction is finished. This kind of mode often attaches attention to inadequately because of interim welding construction operation personnel and has very big potential safety hazard, very easily cuts steel construction base metal when interim tripod is demolishd moreover, has the quality hidden danger.
In addition, the conventional platform is free of any shielding, welding operation cannot be carried out when the environment wind power reaches five levels, and the welding construction operation platform is not provided with a smoke dust collecting device according to the regulations, so that dust and smoke dust generated in the process are directly discharged into the atmosphere, and the surrounding environment is polluted.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a steel construction welded platform to solve above-mentioned technical problem.
For this reason, the utility model provides a steel construction welded platform, this steel construction welded platform set up at the top of treating the girder steel of welded girder steel column connected node department, include:
the supporting platform is sleeved outside a steel column at a steel column connection node of a steel beam to be welded, and is supported on the top of the steel beam;
the enclosure structure is connected to the top of the supporting platform and encloses the steel column inside the enclosure structure;
the smoke purifying device is arranged on the outer wall of the enclosure structure;
the smoke recovery funnel is sleeved outside the steel column above the enclosure structure;
the windproof and fireproof ceiling is connected between the top of the enclosure structure and the flue gas recovery funnel.
Preferably, the steel column is sleeved with a clamp, the enclosure structure is connected with the clamp through a connecting rod, and the flue gas recovery funnel is hung on the clamp.
Preferably, the supporting platform is a steel plate with a through hole in the middle.
Preferably, the support platform has a dimension of 2 m.
Preferably, the enclosure structure is a composite heat-insulating plate.
Preferably, the windproof and fireproof ceiling is made of fireproof cloth.
Compared with the prior art, the invention has the characteristics and beneficial effects that: the utility model discloses a steel construction welded platform sets up envelope through the top at supporting platform to install flue gas purification device on envelope, purify the flue gas furthest, adopt at the envelope top to prevent wind the fire prevention ceiling and effectively seal, prevent that the flue gas is excessive, and install flue gas recovery funnel on the steel column of envelope top, will probably retrieve from the excessive flue gas of the junction department of preventing wind fire prevention ceiling and steel column, this steel construction welded platform is easy to assemble and dismantles.
Drawings
FIG. 1 is a schematic view of a steel structure welding platform.
The attached drawings are marked as follows: the device comprises a steel beam 1, a supporting platform 2, a building enclosure 3, a flue gas purification device 4, a flue gas recovery funnel 5, a windproof fireproof ceiling 6, a steel column 7, a hoop 8 and a connecting rod 9.
Detailed Description
In order to make the technical means, innovative features, objectives and functions realized by the present invention easy to understand, the present invention will be further described below.
The embodiments described herein are specific embodiments of the present invention, and are intended to be illustrative of the concepts of the present invention, which are intended to be illustrative and exemplary, and should not be construed as limiting the scope of the embodiments of the present invention. In addition to the embodiments described herein, those skilled in the art will be able to employ other technical solutions which are obvious based on the disclosure of the claims and the specification of the present application, and these technical solutions include technical solutions which make any obvious replacement or modification for the embodiments described herein.
In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "both ends", "one end", "the other end" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element to which the reference is made must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "disposed," "connected," and the like are to be construed broadly, and for example, "connected" may be either fixedly connected or detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
As shown in fig. 1, a steel structure welding platform is provided on the top of a steel beam 1 at a steel beam-steel column connection node to be welded,
the steel structure welding platform comprises a supporting platform 2, a building enclosure 3, a flue gas purification device 4, a flue gas recovery funnel 5 and a windproof fireproof ceiling 6. The supporting platform 2 is a steel plate with a through hole in the middle. The support platform 2 has a dimension of 2 m. A through hole is formed in the middle of the supporting platform 2, the supporting platform 2 is sleeved outside a steel column 7 at a joint of a steel beam steel column to be welded, and the supporting platform 2 is supported on the top of the steel beam 1. The envelope 3 is connected at the top of supporting platform 2 and closes inside steel column 7 encloses, specifically, steel column 7 has cup jointed clamp 8 outward, is connected through connecting rod 9 between envelope 3 and the clamp 8. The envelope 3 is a composite heat-insulating board. The flue gas purification device 4 is arranged on the outer wall of the enclosure structure 3. The flue gas recovery funnel 5 is sleeved outside a steel column 7 above the enclosure structure 3, and specifically, the flue gas recovery funnel 5 is hung on a hoop 8. The windproof fireproof ceiling 6 is connected between the top of the enclosure structure 3 and the flue gas recovery funnel 5. The windproof fireproof ceiling 6 is made of fireproof cloth.
The above embodiments are merely illustrative of the preferred embodiments of the present invention, and are not intended to limit the scope of the present invention, and various modifications and improvements made by those skilled in the art without departing from the spirit of the present invention should fall within the protection scope defined by the claims.

Claims (6)

1. The utility model provides a steel construction welded platform, its characterized in that, this steel construction welded platform sets up at the top of waiting girder steel (1) of welded girder steel column connected node, includes:
the supporting platform (2) is provided with a through hole in the middle, the supporting platform (2) is sleeved outside a steel column (7) at a steel column connection node of a steel beam to be welded, and the supporting platform (2) is supported on the top of the steel beam (1);
the enclosing structure (3) is connected to the top of the supporting platform (2) and encloses the steel column (7) inside the enclosing structure;
the flue gas purification device (4) is arranged on the outer wall of the enclosure structure (3);
the smoke recovery funnel (5) is sleeved outside the steel column (7) above the enclosure structure (3);
and the windproof and fireproof ceiling (6) is connected between the top of the enclosure structure (3) and the flue gas recovery funnel (5).
2. The steel structure welding platform of claim 1, wherein: the steel column (7) has cup jointed clamp (8) outward, be connected through connecting rod (9) between envelope (3) and clamp (8), flue gas recovery funnel (5) are hung and are established on clamp (8).
3. The steel structure welding platform of claim 1, wherein: the supporting platform (2) is a steel plate with a through hole in the middle.
4. The steel structure welding platform of claim 3, wherein: the support platform (2) has a dimension of 2 m.
5. The steel structure welding platform of claim 1, wherein: the enclosure structure (3) is a composite heat-insulation plate.
6. The steel structure welding platform of claim 1, wherein: the windproof fireproof ceiling (6) is made of fireproof cloth.
CN202220374911.0U 2022-02-24 2022-02-24 Steel structure welding platform Active CN217071232U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220374911.0U CN217071232U (en) 2022-02-24 2022-02-24 Steel structure welding platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220374911.0U CN217071232U (en) 2022-02-24 2022-02-24 Steel structure welding platform

Publications (1)

Publication Number Publication Date
CN217071232U true CN217071232U (en) 2022-07-29

Family

ID=82544231

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220374911.0U Active CN217071232U (en) 2022-02-24 2022-02-24 Steel structure welding platform

Country Status (1)

Country Link
CN (1) CN217071232U (en)

Similar Documents

Publication Publication Date Title
CN212032317U (en) Alarm device for forest fire prevention
CN217071232U (en) Steel structure welding platform
CN211666435U (en) Fireproof, dustproof and soundproof building safety net
CN216949411U (en) Be used for inserted lift scaffold to hang and establish protection pocket net device
CN212388907U (en) Prevent tuber pipe of discharging fume suitable for electronic information factory building
CN215631330U (en) Air duct system with fire-resistant and fireproof functions
CN219034108U (en) Fire-catching device and operation platform
CN216042576U (en) Scaffold frame pole setting and horizontal pole connecting and fixing device for building engineering construction
CN211294111U (en) Multifunctional equipment for forest monitoring
CN212377456U (en) Anti-seismic support
CN212671385U (en) Noise absorption board for building site
CN210767685U (en) Fireproof residential exhaust passage convenient for assembling multiple layers
CN210239293U (en) Torch tower with guide rail
CN214368307U (en) Smoke exhaust air pipe connecting piece and smoke exhaust air pipe
CN216406106U (en) Butt scaffold convenient to fix at boiler heating surface bank of tubes
CN216195420U (en) High-stability deformation-resistant house bearing steel pillar
CN217067490U (en) Multifunctional fire-fighting unit
CN214658710U (en) Safety protection net for construction
CN217949978U (en) Construction protective guard is used in building engineering construction
CN210857978U (en) Scaffold connecting and fixing device
CN217151537U (en) Construction is with bordering on building and enclosing fender
CN214423962U (en) Overhead working protective frame
CN218512266U (en) Monitoring device for smoke concentration in tunnel
CN210740630U (en) Ventilation structure for building
CN218406409U (en) Slope roofing large-span eaves gutter hanging flower basket installation device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant