Inside conveyer of working well for artifical push pipe construction Download PDF

Info

Publication number
CN217048677U
CN217048677U CN202122717599.9U CN202122717599U CN217048677U CN 217048677 U CN217048677 U CN 217048677U CN 202122717599 U CN202122717599 U CN 202122717599U CN 217048677 U CN217048677 U CN 217048677U
Authority
CN
China
Prior art keywords
working well
fixedly connected
construction according
baffle
pipe jacking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122717599.9U
Other languages
Chinese (zh)
Inventor
戴卫超
白国岩
张雷
张强
高子力
刘鸿业
张晶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 16th Bureau Group Co Ltd
Electrification Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Original Assignee
China Railway 16th Bureau Group Co Ltd
Electrification Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 16th Bureau Group Co Ltd, Electrification Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd filed Critical China Railway 16th Bureau Group Co Ltd
Priority to CN202122717599.9U priority Critical patent/CN217048677U/en
Application granted granted Critical
Publication of CN217048677U publication Critical patent/CN217048677U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The utility model discloses an inside conveyer of working well for artifical push pipe construction, including the travelling bogie, the terminal surface is close to the equal fixedly connected with electronic jar of four corners department under the travelling bogie, four the terminal surface all is connected with universal pulley under the electronic jar, the terminal surface is close to the equal fixedly connected with stop collar in both sides around the travelling bogie, the equal fixed pull spout of having seted up in travelling bogie both sides, two slide respectively in the pull spout and be provided with a layer board and No. two layer boards, No. one layer board and No. two layer boards carry on the back one side of the body respectively No. one fixedly connected with baffle and No. two baffles, No. two baffle one side is fixed to have seted up and has been accomodate the groove, it is connected with the connecting rod No. one all to rotate on the inner wall of groove to accomodate the front and back end, two connecting rod lower extreme all articulates there is No. two connecting rods. The utility model discloses in, the device possesses simple structure, convenient to use, and flourishing material volume is big, easily lift adjustment, multiple advantages such as security height.

Description

Inside conveyer of working well for artifical push pipe construction
Technical Field
The utility model relates to a push pipe construction field especially relates to inside conveyer of working well for artifical push pipe construction.
Background
The pipe-jacking construction is a non-excavation construction method, and is a pipeline burying construction technology without excavation or with few excavations. The pipe jacking construction is that the friction force between the pipeline and the surrounding soil is overcome by means of the jacking force generated by jacking equipment in a working pit, the pipeline is jacked into the soil according to the designed gradient, and earthwork is transported away. After one section of pipe is pushed into the soil layer, the second section of pipe is pushed into the soil layer continuously. The principle is that by means of the thrust of the main top oil cylinder, the pipeline and the relay, the tool pipe or the development machine is pushed into the receiving pit from the working pit through the soil layer and is lifted. The pipeline is buried between the two pits after following the tool pipe or the heading machine, and soil needs to be transported in the pipe jacking construction process.
At present, the main method is to use a trolley for transportation, but the main method is limited by the material containing amount of the trolley, the trolley can be transported repeatedly, the transportation is very troublesome, and the trolley can move backwards during material containing, so that the transportation is not safe enough.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the defects existing in the prior art and providing an internal transportation device of a working well for manual pipe jacking construction.
In order to realize the purpose, the utility model adopts the following technical scheme: the inner transportation device for the working well for the manual pipe jacking construction comprises a transportation trolley, wherein electric cylinders are fixedly connected to the lower end surface of the transportation trolley close to four corners, universal pulleys are connected to the lower end surfaces of the four electric cylinders, limit sleeves are fixedly connected to the front end surface and the rear end surface of the transportation trolley close to two sides, pull chutes are fixedly formed in two sides of the transportation trolley, a first supporting plate and a second supporting plate are respectively arranged in the two pull chutes in a sliding manner, a first baffle plate and a second baffle plate are respectively and fixedly connected to one opposite sides of the first supporting plate and the second supporting plate, a storage groove is fixedly formed in one side of the second baffle plate, a first connecting rod is rotatably connected to the inner wall of the front end and the rear end of the storage groove, the lower ends of the two first connecting rods are respectively hinged to a second connecting rod, anti-slip plates are hinged to the other ends of the two connecting rods, and fixed plates are fixedly connected to the outer walls of the front end and the rear end of the first baffle plate and the second baffle plate, two that are located same end equal fixedly connected with gag lever post on the relative one side outer wall of fixed plate.
As a further description of the above technical solution:
and the upper end surface of the transport trolley is fixedly provided with a material containing hopper.
As a further description of the above technical solution:
no. one layer board and No. two layer board structures are the same, and the two all rotates on being close to front and back end outer wall and is connected with the gyro wheel.
As a further description of the above technical solution:
the limiting rod is sleeved at the inner end of the limiting sleeve in a sliding manner.
As a further description of the above technical solution:
the antiskid plate is made of rubber materials.
As a further description of the above technical solution:
and a shield blade is arranged on one side of the transport trolley.
As a further description of the above technical solution:
the lower end of the shield blade is provided with a conveying hopper, and a driving motor is fixedly arranged on the conveying hopper.
As a further description of the above technical solution:
the feed opening of the feed delivery hopper is arranged at the position close to the lower end face of one side of the driving motor.
The utility model discloses following beneficial effect has:
1. the utility model provides an inside conveyer of working well for construction of artifical push pipe, the device can effectively increase the holding hopper volume through setting up pull formula layer board, makes it hold more soil, avoids frequent transportation of making a round trip.
2. The utility model provides an inside conveyer of working well for artifical push pipe construction through setting up antiskid ribbed tile auxiliary stay, can effectively prevent that the device from appearing the back and sliding when expecting greatly, causes the security problem.
3. The utility model provides an inside conveyer of working well for construction of artifical push pipe, device possess simple structure, convenient to use, and flourishing material volume is big, easily lift adjustment, multiple advantages such as security height.
Drawings
FIG. 1 is a schematic view of the working structure of the transportation device inside the working well for artificial pipe jacking construction provided by the utility model;
FIG. 2 is a schematic side sectional view of a local structure at a material containing hopper of the conveying device inside a working well for artificial pipe jacking construction provided by the utility model;
FIG. 3 is a schematic front view of a partial structure of a transportation trolley of the transportation device in the working well for artificial pipe jacking construction;
FIG. 4 is a schematic view of a three-dimensional structure at the second support plate of the transportation device inside the working well for artificial pipe jacking construction provided by the utility model;
fig. 5 is the utility model provides an inside conveyer's of working well antiskid ribbed tile expandes structural schematic diagram for artifical push pipe construction.
Illustration of the drawings:
1. transporting the trolley; 2. an electric cylinder; 3. a universal pulley; 4. a limiting sleeve; 5. a material containing hopper; 6. a pull chute; 7. a first support plate; 8. a second supporting plate; 9. a roller; 10. a first baffle plate; 11. a second baffle; 12. a storage groove; 13. a first connecting rod; 14. a second connecting rod; 15. an anti-skid plate; 16. a fixing plate; 17. a limiting rod; 18. a drive motor; 19. a shield blade; 20. a material conveying hopper.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention; the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance, and furthermore, unless otherwise explicitly stated or limited, the terms "mounted," "connected," and "connected" are to be construed broadly and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood as a specific case by those skilled in the art.
Referring to fig. 1-5, the present invention provides an embodiment: the inner transportation device of the working well for the artificial pipe jacking construction comprises a transportation trolley 1, electric cylinders 2 are fixedly connected to the lower end face of the transportation trolley 1 close to the four corners, universal pulleys 3 are connected to the lower end faces of the four electric cylinders 2, stop sleeves 4 are fixedly connected to the front end face and the rear end face of the transportation trolley 1 close to the two sides, pull chutes 6 are fixedly formed in the two sides of the transportation trolley 1, a first supporting plate 7 and a second supporting plate 8 are respectively arranged in the two pull chutes 6 in a sliding manner, a first baffle 10 and a second baffle 11 are respectively and fixedly connected to the opposite sides of the first supporting plate 7 and the second supporting plate 8, an accommodating groove 12 is fixedly formed in one side of the second baffle 11, a first connecting rod 13 is rotatably connected to the inner wall of the front end and the rear end of the accommodating groove 12, a second connecting rod 14 is hinged to the lower ends of the two first connecting rods 13, anti-skid plates 15 are hinged to the other ends of the two connecting rods 14, and fixing plates 16 are fixedly connected to the outer walls of the front end and the rear end of the first baffle 10 and the second baffle 11, and limiting rods 17 are fixedly connected to the outer walls of the two opposite sides of the fixing plates 16 at the same end.
The upper end surface of the transport trolley 1 is fixedly provided with a material containing hopper 5.
No. 7 layer boards and No. two layer boards 8 are the same in structure, and the two all rotates on being close to the front and back end outer wall and is connected with gyro wheel 9 for supplementary a layer board 7 and No. two layer boards 8 slide in pull spout 6.
The limiting rod 17 is sleeved at the inner end of the limiting sleeve 4 in a sliding mode, the limiting rod 17 is limited through the limiting sleeve 4, and the first supporting plate 7 or the second supporting plate 8 is prevented from sliding out of the drawing sliding groove 6 in the transport trolley 1.
The antiskid plate 15 is made of rubber materials, so that friction force is improved.
One side of the transport trolley 1 is provided with a shield blade 19.
The lower end of the shield blade 19 is provided with a material conveying hopper 20, a driving motor 18 is fixedly arranged on the material conveying hopper 20, and the material conveying hopper 20 is of a spiral structure.
The feed opening of the material conveying hopper 20 is arranged at a position close to the lower end surface of one side of the driving motor 18.
The working principle is as follows: the utility model discloses during the device uses, remove conveying hopper 20 below with travelling bogie 1, then electronic jar 2 descends, expandes baffle 10 and No. two baffles 11 simultaneously, improves holding hopper 5's volume to can single transport more soil, then pull out antiskid ribbed tile 15, support on the ground, prevent travelling bogie 1 back.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments or make equivalent substitutions on some technical features, and any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of the present invention.

Claims (8)

1. Inside conveyer of working well for construction of artifical push pipe, including travelling bogie (1), its characterized in that: the lower end face of the transport trolley (1) is close to four corners and is fixedly connected with electric cylinders (2), the lower end faces of the four electric cylinders (2) are connected with universal pulleys (3), the front end face and the rear end face of the transport trolley (1) are close to two sides and are fixedly connected with limit sleeves (4), two sides of the transport trolley (1) are fixedly provided with pull chutes (6), two pull chutes (6) are respectively and slidably provided with a first supporting plate (7) and a second supporting plate (8), the back side of the first supporting plate (7) and the back side of the second supporting plate (8) is respectively and fixedly connected with a first baffle plate (10) and a second baffle plate (11), one side of the second baffle plate (11) is fixedly provided with a storage groove (12), the inner walls of the front end and the rear end of the storage groove (12) are respectively and rotatably connected with a first connecting rod (13), and the lower ends of the first connecting rod (13) are respectively hinged with a second connecting rod (14), two No. two connecting rod (14) other end articulates there is antiskid ribbed tile (15), equal fixedly connected with fixed plate (16) on baffle (10) and No. two baffle (11) front and back end outer wall, be located two of same end equal fixedly connected with gag lever post (17) on the relative one side outer wall of fixed plate (16).
2. The internal transportation device of the working well for artificial pipe jacking construction according to claim 1, wherein: and the upper end surface of the transport trolley (1) is fixedly provided with a material containing hopper (5).
3. The internal transportation device of the working well for artificial pipe jacking construction according to claim 1, wherein: no. one layer board (7) and No. two layer boards (8) structure is the same, and the two is close to all to rotate on the front and back end outer wall and is connected with gyro wheel (9).
4. The inside conveyer of working well for artificial pipe jacking construction according to claim 1, wherein: the limiting rod (17) is sleeved at the inner end of the limiting sleeve (4) in a sliding manner.
5. The inside conveyer of working well for artificial pipe jacking construction according to claim 1, wherein: the antiskid plate (15) is made of rubber materials.
6. The inside conveyer of working well for artificial pipe jacking construction according to claim 1, wherein: and a shield blade (19) is arranged on one side of the transport trolley (1).
7. The internal transportation device of the working well for artificial pipe jacking construction according to claim 6, wherein: the shield structure is characterized in that a material conveying hopper (20) is arranged at the lower end of the shield structure blade (19), and a driving motor (18) is fixedly arranged on the material conveying hopper (20).
8. The internal transportation device of the working well for artificial pipe jacking construction according to claim 7, wherein: the feed opening of the feed conveying hopper (20) is arranged at the position close to the lower end face of one side of the driving motor (18).
CN202122717599.9U 2021-11-08 2021-11-08 Inside conveyer of working well for artifical push pipe construction Active CN217048677U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122717599.9U CN217048677U (en) 2021-11-08 2021-11-08 Inside conveyer of working well for artifical push pipe construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122717599.9U CN217048677U (en) 2021-11-08 2021-11-08 Inside conveyer of working well for artifical push pipe construction

Publications (1)

Publication Number Publication Date
CN217048677U true CN217048677U (en) 2022-07-26

Family

ID=82476329

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122717599.9U Active CN217048677U (en) 2021-11-08 2021-11-08 Inside conveyer of working well for artifical push pipe construction

Country Status (1)

Country Link
CN (1) CN217048677U (en)

Similar Documents

Publication Publication Date Title
CN217048677U (en) Inside conveyer of working well for artifical push pipe construction
CN210315566U (en) Multifunctional deep foundation pit construction device
CN106276056A (en) Multi-segmental combination type earthwork perpendicular lifting apparatus
CN106013162A (en) Construction process for filling underwater concrete by injection method
CN108891902B (en) Wall brick transportation equipment for building indoor wall surface of building construction
CN217760864U (en) Portable hole digging pile soil digging device
CN205467497U (en) Fixed platform formula removes perpendicular rubbish compression station
CN112067101B (en) Truck scale weighing platform with dust removal function
CN210883764U (en) Lifting type butt-joint garbage compression equipment
CN217022303U (en) Sand is bad to be transported and is strickleed off device and have carriage that sand is bad to be transported and is strickleed off function
CN208470839U (en) A kind of jacking construction trolley that is unearthed
CN110127509A (en) A kind of block brick hanging apparatus and application method
CN218754471U (en) Dedicated vertical container spreader and hoist and mount system
CN212766366U (en) Tool transfer trolley for ecological open channel construction
CN213358733U (en) Backfill device for deep foundation pit of vertical buried pipe
CN219751718U (en) Hopper hanging device
CN213797244U (en) Cement pipe mould rack
CN215702912U (en) Concrete mixing tank drier feed arrangement
CN215709490U (en) Civil construction engineering construction material transports platform
CN218618989U (en) Transfer device for building material production
CN215332982U (en) Little headroom working well shield constructs construction and uses dregs car
CN218640828U (en) Electric loader back battery replacement device
CN217482496U (en) Mining portable refuels small handcart
CN219011317U (en) Anti-seepage construction auxiliary device for garbage pool of household garbage power plant
CN215557418U (en) Bagged cement car loader

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant