CN216999358U - Prefabricated bridge installation translation device - Google Patents
Prefabricated bridge installation translation device Download PDFInfo
- Publication number
- CN216999358U CN216999358U CN202220643095.9U CN202220643095U CN216999358U CN 216999358 U CN216999358 U CN 216999358U CN 202220643095 U CN202220643095 U CN 202220643095U CN 216999358 U CN216999358 U CN 216999358U
- Authority
- CN
- China
- Prior art keywords
- translation device
- base
- prefabricated
- jack
- bridge installation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model relates to the technical field of bridge engineering, in particular to a prefabricated bridge installation translation device which comprises a base, a moving seat and a bearing body, wherein the moving seat is arranged in the base, the bearing body is arranged above the moving seat, two sides of the moving seat are connected with guide rods, a jack is vertically embedded in the moving seat, the top end of the jack is fixedly connected with the bearing body, a rotary cylinder is embedded in the bearing body, the top end of the rotary cylinder is connected with a conveying plate, and a prefabricated plate is placed on the conveying plate; the prefabricated plate that the bridge was used is placed on the transport plate, fixes through the location cylinder, avoids the translation in-process to drop, can promote through multistage jack to remove the seat and carry out lateral shifting to drive the prefabricated plate and carry out the translation.
Description
Technical Field
The utility model relates to the technical field of bridge engineering, in particular to a prefabricated bridge installation translation device.
Background
In the prior art, the prefabricated bridge is generally hoisted on the transport vehicle through the hoisting equipment, and then the prefabricated bridge is transported through the transport vehicle, but in the process of arranging the prefabricated bridge, the size and the mass of the prefabricated bridge are large, so that the transport vehicle shakes when the prefabricated bridge is arranged, the stability of the transport vehicle is poor, and the arrangement quality of the prefabricated bridge is influenced.
In order to solve the problems, a prefabricated bridge installation translation device is provided.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the defects in the prior art and provides a prefabricated bridge installation translation device.
In order to achieve the purpose, the utility model adopts the following technical scheme:
the utility model provides a precast bridge installation translation device, includes the base, removes seat and supporting body, the base is inside to be equipped with remove the seat, the top of removing the seat is equipped with the supporting body, the both sides of removing the seat are connected with the guide bar, the inside of removing the seat is vertical to be buried underground has the jack, the top of jack with supporting body fixed connection, revolving cylinder has been buried underground to the supporting body is inside, revolving cylinder's top is connected with the transport plate, the prefabricated plate has been placed on the transport plate.
As a preferred embodiment of the present invention: and two ends of the guide rod are fixedly connected with the inner wall of the base.
As a preferred embodiment of the present invention: the cross section of the conveying plate is of a U-shaped structure, and positioning cylinders are arranged on the inner walls of two sides of the conveying plate.
As a preferred embodiment of the present invention: the positioning cylinders are provided with four groups and are uniformly distributed on two sides of the precast slab.
As a preferred embodiment of the present invention: all install multistage jack on the inner wall of base both sides, the one end that multistage jack is close to each other all with remove seat fixed connection.
As a preferred embodiment of the present invention: and the lower surface of the base is provided with a crawler belt in parallel.
The utility model has the beneficial effects that:
1. according to the utility model, the precast slab for the bridge is placed on the transport plate and fixed through the positioning cylinder, so that the precast slab is prevented from falling off in the translation process, and the moving seat can be pushed to move transversely through the multi-stage jack, so that the precast slab is driven to translate;
2. according to the utility model, the jack is embedded in the moving seat, so that the supporting body can be jacked in the vertical direction, the rotary air cylinder is arranged on the supporting body, the angle of the conveying plate can be adjusted, the angle of the precast slab is changed, the crawler belt is arranged at the bottom of the device, the bearing capacity is strong, and the reliability is high.
Drawings
FIG. 1 is a schematic top view of a prefabricated bridge installation translation device base according to the present invention;
fig. 2 is a schematic top view of a transport plate of a prefabricated bridge installation translation device according to the present invention.
In the figure: 1. a base; 2. a crawler belt; 3. a multi-stage jack; 4. a movable seat; 5. a jack; 6. a carrier; 7. a rotating cylinder; 8. a transport plate; 9. positioning the air cylinder; 10. prefabricating a slab; 11. a guide rod.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments.
Referring to fig. 1-2, in the embodiment of the present invention, a prefabricated bridge installation translation device includes a base 1, a moving seat 4 and a supporting body 6, the moving seat 4 is disposed inside the base 1, the supporting body 6 is disposed above the moving seat 4, two sides of the moving seat 4 are connected with guide rods 11, a jack 5 is vertically embedded inside the moving seat 4, a top end of the jack 5 is fixedly connected with the supporting body 6, a rotary cylinder 7 is embedded inside the supporting body 6, a top end of the rotary cylinder 7 is connected with a transport plate 8, and a prefabricated plate 10 is disposed on the transport plate 8.
Furthermore, two ends of the guide rod 11 are fixedly connected with the inner wall of the base 1.
Further, the cross section of the conveying plate 8 is in a U-shaped structure, and positioning cylinders 9 are mounted on the inner walls of two sides of the conveying plate.
Further, four sets of positioning cylinders 9 are provided and uniformly distributed on both sides of the prefabricated panel 10.
Further, all install multistage jack 3 on the inner wall of base 1 both sides, the one end that multistage jack 3 is close to each other all with remove 4 fixed connection of seat.
Further, a crawler belt 2 is installed in parallel to the lower surface of the base 1.
The specific implementation mode is as follows: precast slab 10 that the bridge was used is placed on transport plate 8, fix through location cylinder 9, avoid the translation in-process to drop, can promote through multistage jack 3 and remove seat 4 and carry out lateral shifting, thereby drive precast slab 10 and carry out the translation, through burying jack 5 underground in removing seat 4, can carry out the jacking of vertical direction with supporting body 6, install revolving cylinder 7 on the supporting body 6, can adjust transport plate 8's angle, thereby change precast slab 10's angle, the device bottom sets up track 2, strong bearing capacity, high reliability.
It should be noted that the components of the present invention are all standard components or components known to those skilled in the art, and the structure and principle thereof can be known to those skilled in the art through technical manuals or through routine experiments.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and equivalent alternatives or modifications according to the technical solution of the present invention and the inventive concept thereof should be covered by the scope of the present invention.
Claims (6)
1. The utility model provides a precast bridge installation translation device, includes base (1), removes seat (4) and supporting body (6), its characterized in that, base (1) inside is equipped with remove seat (4), the top of removing seat (4) is equipped with supporting body (6), the both sides of removing seat (4) are connected with guide bar (11), the inside of removing seat (4) is vertical to have buried jack (5) underground, the top of jack (5) with supporting body (6) fixed connection, revolving cylinder (7) have been buried underground to supporting body (6) inside, the top of revolving cylinder (7) is connected with transport plate (8), prefabricated plate (10) have been placed on transport plate (8).
2. The prefabricated bridge installation and translation device according to claim 1, wherein two ends of the guide rod (11) are fixedly connected with the inner wall of the base (1).
3. The prefabricated bridge installation and translation device according to claim 1, wherein the cross section of the transportation plate (8) is in a U-shaped structure, and positioning cylinders (9) are installed on the inner walls of two sides of the transportation plate.
4. A prefabricated bridge installation translation device according to claim 3, wherein said positioning cylinders (9) are provided in four groups and are uniformly distributed on both sides of said prefabricated slab (10).
5. The prefabricated bridge installation and translation device according to claim 1, wherein the inner walls of the two sides of the base (1) are respectively provided with a multi-stage jack (3), and the ends of the multi-stage jacks (3) close to each other are fixedly connected with the movable base (4).
6. A prefabricated bridge installation translation device according to claim 1, characterized in that the lower surface of said base (1) is equipped with parallel tracks (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202220643095.9U CN216999358U (en) | 2022-03-23 | 2022-03-23 | Prefabricated bridge installation translation device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202220643095.9U CN216999358U (en) | 2022-03-23 | 2022-03-23 | Prefabricated bridge installation translation device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN216999358U true CN216999358U (en) | 2022-07-19 |
Family
ID=82372143
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202220643095.9U Active CN216999358U (en) | 2022-03-23 | 2022-03-23 | Prefabricated bridge installation translation device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN216999358U (en) |
-
2022
- 2022-03-23 CN CN202220643095.9U patent/CN216999358U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106194216A (en) | A kind of Rectangular Box Culvert and constructing tunnel chassis | |
CN210510510U (en) | Fine adjustment aligning device for axes of pipeline thermal pipeline | |
CN216999358U (en) | Prefabricated bridge installation translation device | |
CN212000663U (en) | Assembly self-supporting horizontal pushing device | |
CN111115461B (en) | Reinforcing steel bar and mould transportation and automatic assembling equipment | |
CN202185966U (en) | Novel hydraulic internal mold for U-shaped beam | |
CN215666725U (en) | A transportation hoisting device for downhole equipment | |
CN1603224A (en) | Integrally turning method of tower crane | |
CN215754765U (en) | Non-driving pipe passing rail device | |
CN212504186U (en) | Bioreactor sliding device | |
CN201309817Y (en) | Hydraulic lifting mounting carrier vehicle | |
CN115162070A (en) | Method for installing and constructing track beam frame in DM80 inverted portal warehouse | |
CN111364300B (en) | Multifunctional construction vehicle for subway rail | |
CN209177934U (en) | Box beam tunnel face narrow and small place has bad luck relay construction transporting device | |
CN112023496A (en) | Hoisting method of rotary drum filter in alumina engineering | |
CN221523314U (en) | Assembly type slidable support structure for construction of ultra-large span steel box bent cap | |
CN217808422U (en) | Be used for subway platform top tuber pipe prefab erection equipment | |
CN221442614U (en) | Side wall A-frame template mobile device under apron | |
CN220449614U (en) | Side box culvert lifting equipment | |
CN217997685U (en) | Rail mounting device for ground module of electric suspension electromagnetic propulsion system | |
CN213923239U (en) | Conveying device for transporting muddy water | |
CN217196051U (en) | Prefabricated highway case roof beam sideslip system | |
CN218409212U (en) | Pressure tank convenient to remove | |
CN212803274U (en) | Vehicle special for mounting, dismounting and transporting full-steel formwork of top plate of underground comprehensive pipe gallery | |
CN220620115U (en) | Deep foundation pit concrete transportation shuttle groove |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |