CN216988272U - Waste gas and waste paint collecting device for spraying process in steel structure manufacturing - Google Patents

Waste gas and waste paint collecting device for spraying process in steel structure manufacturing Download PDF

Info

Publication number
CN216988272U
CN216988272U CN202220682088.XU CN202220682088U CN216988272U CN 216988272 U CN216988272 U CN 216988272U CN 202220682088 U CN202220682088 U CN 202220682088U CN 216988272 U CN216988272 U CN 216988272U
Authority
CN
China
Prior art keywords
wall
fixedly connected
main box
groove
waste gas
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220682088.XU
Other languages
Chinese (zh)
Inventor
王晓君
吴振东
张学宁
刘红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN202220682088.XU priority Critical patent/CN216988272U/en
Application granted granted Critical
Publication of CN216988272U publication Critical patent/CN216988272U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Details Or Accessories Of Spraying Plant Or Apparatus (AREA)

Abstract

The utility model discloses a waste gas and waste paint collecting device in a spraying process in steel structure manufacturing, which comprises a main box, a transverse pipe, a support and a material collecting plate, wherein a top groove is formed in the outer wall of the top of the main box, a top net is fixedly connected between the peripheral inner walls of the top groove, material guide grooves are fixedly connected between the inner walls at two ends of the main box, a plurality of through holes are formed between the top and the outer wall of the bottom of the material guide grooves and are distributed equidistantly, a partition plate is fixedly connected between the peripheral inner walls at the bottom of the main box, the material collecting plate is placed on the outer wall of the top of the partition plate, the material collecting groove is formed in the outer wall of the top of the material collecting plate, supporting rods are fixedly connected to the outer walls at two ends of the top of the main box, and the transverse pipe is fixedly connected between the top outer walls of the supporting rods. After the paint is infiltrated into the guide chute, the paint can fall into the material collecting plate through the through holes, so that the paint collecting effect is realized, the material collecting plate can be directly drawn out of the main box through the drawing plate, and the material collecting plate can be cleaned.

Description

Waste gas and waste paint collecting device for spraying process in steel structure manufacturing
Technical Field
The utility model relates to the technical field of steel structure spraying, in particular to a waste gas and waste paint collecting device in a spraying process in steel structure manufacturing.
Background
The steel structure is a structure formed by steel materials, is one of main building structure types, mainly comprises steel beams, steel columns, steel trusses and other members made of section steel, steel plates and the like, adopts rust removing and preventing processes such as silanization, pure manganese phosphating, washing drying, galvanization and the like, is generally connected by welding lines, bolts or rivets, and most of the members or parts need to be subjected to corrosion prevention spraying before use.
At the in-process that carries out the spraying to the steel construction, can produce more waste gas and waste paint, do not handle and can cause certain harm to staff's health, and current waste gas and waste paint collecting device are at the in-process that uses, and functional single can only carry out simple collection to waste gas or waste paint, consequently, need urgently to design spraying process waste gas waste paint collection device in the steel construction preparation and solve above-mentioned problem.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the defects in the prior art and provides a waste gas and waste paint collecting device in a spraying process in steel structure manufacturing.
In order to achieve the purpose, the utility model adopts the following technical scheme:
a waste gas and waste paint collecting device in a spraying process in steel structure manufacturing comprises a main box, a transverse pipe, a support and a material collecting plate, wherein a top groove is formed in the outer wall of the top of the main box, a top net is fixedly connected between the inner walls of the periphery of the top groove, a material guide groove is fixedly connected between the inner walls of two ends of the main box, a plurality of through holes distributed at equal intervals are formed between the top outer wall and the bottom outer wall of the material guide groove, a partition plate is fixedly connected between the inner walls of the periphery of the bottom of the main box, the material collecting plate is placed on the outer wall of the top of the partition plate, a material collecting groove is formed in the outer wall of the top of the material collecting plate, supporting rods are fixedly connected to the outer walls of two ends of the top of the main box, the transverse pipe is fixedly connected between the outer walls of the top of the supporting rods, a plurality of air suction pipes are distributed at equal intervals on the outer wall of one side of the transverse pipe, air inlet holes are fixedly connected between the outer wall of the bottom of the transverse pipe and the outer walls of two sides of the main box, and an air suction pipe is fixedly connected to the inner wall of the bottom of the main box, the air suction pipes are respectively and fixedly connected to the outer walls of the two sides of the air suction pump, and an air outlet structure is arranged on the outer wall of one end of the main box.
Preferably, the top both ends outer wall of top net is the equal fixedly connected with support, and the other end outer wall of main tank opens there is the cross slot, and the spliced pole of the cross slot is gone into in the other end outer wall fixedly connected with grafting of collection flitch, and the board is taken out to the other end outer wall fixedly connected with of spliced pole, takes out the board and contacts with the main tank.
Preferably, the baffle is fixedly connected to the outer wall of the other end of the horizontal pipe, the sleeve joint barrel is sleeved on the outer wall of the circumference of the horizontal pipe, the bottom grooves are formed between the outer walls of the two ends of the bottom of the sleeve joint barrel, and the handle is fixedly connected to the outer wall of the top of the sleeve joint barrel.
Preferably, the air inlet groove is formed in the outer wall of one side of the sleeving barrel, the air inlet filter screen is fixedly connected between the inner walls of the periphery of the air inlet groove, the adsorption plate is fixedly connected between the inner wall of the bottom of one end of the main box and the outer wall of the bottom of the partition plate, and the cushion blocks are fixedly connected to the outer walls of the two ends of the bottom of the main box.
Preferably, the air outlet structure comprises a first air outlet groove, and the first air outlet groove is formed in the outer wall of the bottom of one end of the main box.
Preferably, the air outlet structure comprises a second air outlet groove, and the second air outlet groove is formed in the outer wall of one end of the bottom of the main box.
Preferably, the outer wall of the top of the second air outlet groove is fixedly connected with a pressurizing cylinder, and the pressurizing cylinder is funnel-shaped.
The beneficial effects of the utility model are as follows:
1. the steel structure to be sprayed is placed at the top of the support through the arranged main box, the support can support the steel structure, paint vehicle attached to the outer wall of the steel structure can drop on the top net in the process of spraying the steel structure, the paint vehicle can drop in the material collecting plate through the through holes after permeating into the guide chute, the effect of collecting the paint vehicle is achieved, the material collecting plate can be directly drawn out of the main box through the drawing plate and can be cleaned, the simple cleaning effect of the device is achieved, the structure is simple, the operation is convenient, in the spraying process, generated waste gas can be sucked into the bottom of the main box through the transverse pipe and the air suction pipe in the starting state of the air suction pump, the waste gas can be filtered when passing through the air inlet filter screen, the protection effect on internal components of the device is achieved, and when the waste gas passes through the first air outlet chute, the adsorption plate can further purify the waste gas, realized the processing to waste gas, the removable cup joint section of thick bamboo of demolising can realize dismantling the clearance effect to violently managing and air intake filter, and is easy and simple to handle.
2. Through the second of setting out the gas groove, when the waste gas of main tank bottoms portion is giving vent to anger through the second and is giving vent to anger the time slot and exhausting, because the second is given vent to anger the bottom that the groove was established at the main tank, consequently gives vent to anger the gas realization through the second and directly blows to ground to realized the ground deashing effect to the device position, the dust of blowing up can be absorbed by the aspiration pump, has realized the simple dust removal effect to ground.
3. Through the pressure cylinder that sets up, when the aspiration pump is discharging waste gas through the second air outlet groove, the waste gas that enters into in the pressure cylinder can be by the pressure cylinder pressure boost that the internal diameter reduces gradually to strengthen the kinetic energy of the waste gas through the second air outlet groove, strengthened the dust removal effect to ground.
Drawings
FIG. 1 is a schematic view of the overall structure of a waste gas and paint collecting device in the spraying process in the manufacture of a steel structure according to embodiment 1;
FIG. 2 is a schematic sectional front view of a device for collecting waste gas and waste paint from a spraying process in the manufacture of a steel structure according to embodiment 1;
FIG. 3 is a schematic structural view of a second air outlet groove of the waste gas and waste paint collecting device in the spraying process in the manufacture of the steel structure according to embodiment 2;
fig. 4 is a schematic structural view of a pressure cylinder of the waste gas and waste paint collecting device in the spraying process in the manufacturing of the steel structure in embodiment 3.
In the figure: the air suction device comprises a main box 1, an air suction pipe 2, a horizontal pipe 3, a baffle 4, a suction plate 5, a top net 6, a support 7, a top groove 8, an air inlet hole 9, an air inlet filter screen 10, an air inlet groove 11, a handle 12, a sleeve joint barrel 13, a support rod 14, a guide groove 15, a material collecting plate 16, a partition plate 17, a first air outlet groove 18, an adsorption plate 19, an air suction pump 20, a through hole 21, a connecting column 22, a second air outlet groove 23 and a pressurization barrel 24.
Detailed Description
The technical solution of the present patent will be described in further detail with reference to the following embodiments.
In the description of this patent, it is to be understood that the terms "center," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," and the like are used in the orientations and positional relationships indicated in the drawings for the convenience of describing the patent and for the simplicity of description, and are not intended to indicate or imply that the referenced devices or elements must have a particular orientation, be constructed and operated in a particular orientation, and are not to be considered limiting of the patent.
Example 1
Referring to fig. 1-2, a waste gas and waste paint collecting device in a spraying process in steel structure manufacturing comprises a main box 1, a transverse pipe 3, a support 7 and a material collecting plate 16, wherein the outer wall of the top of the main box 1 is provided with a top groove 8, the inner walls of the periphery of the top groove 8 are connected with a top net 6 through bolts, the inner walls of two ends of the main box 1 are connected with a material guide groove 15 through bolts, a plurality of through holes 21 are arranged between the top and the outer wall of the bottom of the material guide groove 15 at equal intervals, a partition plate 17 is connected between the inner walls of the periphery of the bottom of the main box 1 through bolts, the material collecting plate 16 is arranged on the outer wall of the top of the partition plate 17, the material collecting groove is arranged on the outer wall of the top of the material collecting plate 16, supporting rods 14 are welded on the outer walls of two sides of the top of the main box 1, the transverse pipe 3 is connected between the outer walls of the top of the supporting rods 14 through bolts, a plurality of air inlets 9 are arranged on the outer wall of one side of the transverse pipe 3 at equal intervals, all welded between the bottom outer wall of violently pipe 3 and the both sides outer wall of main tank 1 has breathing pipe 2, and there is aspiration pump 20 bottom inner wall of main tank 1 through bolted connection, and breathing pipe 2 welds respectively in the both sides outer wall of aspiration pump 20, and the one end outer wall of main tank 1 is provided with the structure of giving vent to anger.
Wherein, the top both ends outer wall of top net 6 all welds and has had support 7, and the other end outer wall of main tank 1 opens there is the transverse groove, and the other end outer wall welding of album flitch 16 has spliced pole 22 of pegging graft into the transverse groove, and the other end outer wall of spliced pole 22 has through bolted connection takes out board 5, takes out board 5 and contacts with main tank 1.
Wherein, violently manage 3 other end outer wall all welding and have had baffle 4, and violently manage 3 circumference outer wall and cup jointed a section of thick bamboo 13, all opened the kerve between the bottom both ends outer wall of a section of thick bamboo 13, and the top outer wall of a section of thick bamboo 13 of cup jointing all welds and has handle 12.
Wherein, an air inlet groove 11 is formed in the outer wall of one side of the sleeve joint barrel 13, an air inlet filter screen 10 is connected between the inner walls of the periphery of the air inlet groove 11 through bolts, an adsorption plate 19 is connected between the inner wall of the bottom of one end of the main box 1 and the outer wall of the bottom of the partition plate 17 through bolts, and cushion blocks are welded on the outer walls of the two ends of the bottom of the main box 1.
Wherein, the structure of giving vent to anger includes first gas outlet groove 18, and first gas outlet groove 18 sets up in the one end bottom outer wall of main tank 1.
The working principle is as follows: when the device is used, a steel structure to be sprayed is placed at the top of the support 7, the support 7 can support the steel structure, paint attached to the outer wall of the steel structure can drop on the top net 6 in the process of spraying the steel structure, and the paint can drop in the material collecting plate 16 through the through holes 21 after permeating into the guide chute 15, so that the paint collecting effect is achieved, the material collecting plate 16 can be directly drawn out of the main box 1 through the drawing plate 5, the material collecting plate 16 can be cleaned, the simple cleaning effect of the device is achieved, the structure is simple, the operation is convenient, in the spraying process, generated waste gas can be sucked into the bottom of the main box 1 through the transverse pipe 3 and the air suction pipe 2 by the air suction pump 20 in the starting state, the waste gas can be filtered when passing through the air inlet filter screen 10, the protection effect on internal components of the device is achieved, and when the waste gas is discharged through the first air outlet chute 18, the adsorption plate 19 can further purify waste gas, so that the waste gas is treated, the sleeve joint barrel 13 which can be movably disassembled can realize the disassembling and cleaning effects on the transverse pipe 3 and the air inlet filter screen 10, and the operation is simple and convenient.
Example 2
Referring to fig. 3, this embodiment compares in embodiment 1, and the structure of giving vent to anger includes second air outlet groove 23, and second air outlet groove 23 sets up in the bottom one end outer wall of main tank 1 for a spraying process waste gas lacquer collection device in the steel construction preparation.
The working principle is as follows: during the use, when the waste gas of main tank 1 bottom is being discharged through second air outlet groove 23, because second air outlet groove 23 establishes in main tank 1's bottom, consequently go out the gas of air outlet groove 23 through the second and can directly blow to ground to realized the ground deashing effect to the device position, the dust of blowing up can be absorbed by aspiration pump 20, has realized the simple dust removal effect to ground.
Example 3
Referring to fig. 4, in the present embodiment, compared to embodiment 2, the waste gas and waste paint collecting device in the spraying process in the manufacturing of the steel structure, a pressurizing cylinder 24 is connected to the outer wall of the top of the second air outlet groove 23 through a bolt, and the pressurizing cylinder 24 is in a funnel shape.
The working principle is as follows: during the use, when aspiration pump 20 when exhausting waste gas through second gas outlet groove 23, the waste gas that enters into pressure cylinder 24 can be by the pressure cylinder 24 pressure boost that the internal diameter reduces gradually to strengthen the kinetic energy of the waste gas through second gas outlet groove 23, strengthened the dust removal effect to ground.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and equivalent alternatives or modifications according to the technical solution of the present invention and the inventive concept thereof should be covered by the scope of the present invention.

Claims (7)

1. A waste gas and waste paint collecting device in a spraying process in steel structure manufacturing comprises a main box (1), a transverse pipe (3), a support (7) and a material collecting plate (16), and is characterized in that a top groove (8) is formed in the outer wall of the top of the main box (1), a top net (6) is fixedly connected between the inner walls of the periphery of the top groove (8), material guide grooves (15) are fixedly connected between the inner walls of two ends of the main box (1), a plurality of through holes (21) are formed between the outer walls of the top and the bottom of the material guide grooves (15) and are distributed equidistantly, a partition plate (17) is fixedly connected between the inner walls of the periphery of the bottom of the main box (1), the material collecting plate (16) is placed on the outer wall of the top of the partition plate (17), the material collecting groove is formed in the outer wall of the top of the material collecting plate (16), support rods (14) are fixedly connected to the outer walls of two ends of the top of two sides of the top of the main box (1), and the transverse pipe (3) is fixedly connected between the outer walls of the top of the support rods (14), the air inlet structure is characterized in that a plurality of air inlet holes (9) distributed equidistantly are formed in the outer wall of one side of the transverse pipe (3), air suction pipes (2) are fixedly connected between the outer wall of the bottom of the transverse pipe (3) and the outer walls of the two sides of the main box (1), air suction pumps (20) are fixedly connected to the inner wall of the bottom of the main box (1), the air suction pipes (2) are fixedly connected to the outer walls of the two sides of the air suction pumps (20) respectively, and an air outlet structure is arranged on the outer wall of one end of the main box (1).
2. The waste gas and paint collecting device in the spraying process in the manufacturing of the steel structure as claimed in claim 1, wherein the outer walls of two ends of the top net (6) are both fixedly connected with the support (7), the outer wall of the other end of the main box (1) is provided with a transverse groove, the outer wall of the other end of the material collecting plate (16) is fixedly connected with a connecting column (22) inserted into the transverse groove, the outer wall of the other end of the connecting column (22) is fixedly connected with a pulling plate (5), and the pulling plate (5) is in contact with the main box (1).
3. The waste gas and paint collecting device in the spraying process of the steel structure manufacturing according to claim 2 is characterized in that the outer wall of the other end of the horizontal pipe (3) is fixedly connected with a baffle (4), the outer wall of the circumference of the horizontal pipe (3) is sleeved with a sleeve (13), a bottom groove is formed between the outer walls of the two ends of the bottom of the sleeve (13), and the outer wall of the top of the sleeve (13) is fixedly connected with a handle (12).
4. The waste gas and paint collecting device in the spraying process in the manufacturing of the steel structure as claimed in claim 3, wherein the outer wall of one side of the sleeve (13) is provided with an air inlet groove (11), air inlet filter screens (10) are fixedly connected between the peripheral inner walls of the air inlet grooves (11), an adsorption plate (19) is fixedly connected between the inner wall of the bottom of one end of the main box (1) and the outer wall of the bottom of the partition plate (17), and the outer walls of the two ends of the bottom of the main box (1) are fixedly connected with cushion blocks.
5. The waste gas and waste paint collecting device in the spraying process of the steel structure manufacturing according to any one of claims 1 to 4, wherein the air outlet structure comprises a first air outlet groove (18), and the first air outlet groove (18) is formed in the outer wall of the bottom of one end of the main box (1).
6. The waste gas and waste paint collecting device in the spraying process of the steel structure manufacturing according to claim 1, wherein the air outlet structure comprises a second air outlet groove (23), and the second air outlet groove (23) is formed in the outer wall of one end of the bottom of the main box (1).
7. The waste gas and paint collecting device in the spraying process of the steel structure manufacturing according to claim 6, wherein the outer wall of the top of the second air outlet groove (23) is fixedly connected with a pressurizing cylinder (24), and the pressurizing cylinder (24) is funnel-shaped.
CN202220682088.XU 2022-03-28 2022-03-28 Waste gas and waste paint collecting device for spraying process in steel structure manufacturing Active CN216988272U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220682088.XU CN216988272U (en) 2022-03-28 2022-03-28 Waste gas and waste paint collecting device for spraying process in steel structure manufacturing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220682088.XU CN216988272U (en) 2022-03-28 2022-03-28 Waste gas and waste paint collecting device for spraying process in steel structure manufacturing

Publications (1)

Publication Number Publication Date
CN216988272U true CN216988272U (en) 2022-07-19

Family

ID=82372591

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220682088.XU Active CN216988272U (en) 2022-03-28 2022-03-28 Waste gas and waste paint collecting device for spraying process in steel structure manufacturing

Country Status (1)

Country Link
CN (1) CN216988272U (en)

Similar Documents

Publication Publication Date Title
CN101125319A (en) Multi-layer type water curtain spraying chamber
CN108722849A (en) A kind of poultry farming feed exclusion device
CN216988272U (en) Waste gas and waste paint collecting device for spraying process in steel structure manufacturing
CN201102006Y (en) Multi-layer water screen spray house
CN210046519U (en) Shot blasting machine
CN218794896U (en) Hierarchical dust collector
CN215539570U (en) Tail gas treatment system of production large granule fertilizer device
CN215196125U (en) Dust collector is used in production of fire-resistant prefabricated section
CN220371670U (en) Photovoltaic support stand auxiliary processing equipment
CN210964467U (en) Waste gas purification treatment system suitable for die casting machine
CN210373512U (en) Flue gas treatment equipment for electric welding processing
CN211189538U (en) Dust-containing waste gas treatment box
CN210544081U (en) Dust remover for grinding inner wall of steel pipe
CN216727911U (en) Handle powder spraying device with powder recovery structure
CN207787241U (en) Dust treatment device in a kind of timber floor production process
CN219766321U (en) Sand material processing site dust removal equipment
CN215035826U (en) Automatic production line for hydraulic integrated blocks
CN215742353U (en) Quick cleaning device of reclaimed water station filter material
CN213805146U (en) Cleaning device for tightener workshop
CN219784266U (en) Dust collecting equipment is used in on-the-spot construction of building engineering
CN217247598U (en) Powder filtering device
CN212442487U (en) Portable dust collector for feed processing
CN221859384U (en) Smooth blasting hole cleaning device suitable for cutting slope
CN216462553U (en) Version roller double-end automatic welder
CN218452700U (en) Automobile parts welding set

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant