CN216920428U - Underwater steel pipe parallel connection welding-free fixing device - Google Patents

Underwater steel pipe parallel connection welding-free fixing device Download PDF

Info

Publication number
CN216920428U
CN216920428U CN202220139995.XU CN202220139995U CN216920428U CN 216920428 U CN216920428 U CN 216920428U CN 202220139995 U CN202220139995 U CN 202220139995U CN 216920428 U CN216920428 U CN 216920428U
Authority
CN
China
Prior art keywords
steel pipe
sleeve
parallel connection
groove
wedge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220139995.XU
Other languages
Chinese (zh)
Inventor
许涛
费志高
吴金水
赖炳增
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Xiamen Engineering Co Ltd
Original Assignee
CCCC First Highway Xiamen Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Xiamen Engineering Co Ltd filed Critical CCCC First Highway Xiamen Engineering Co Ltd
Priority to CN202220139995.XU priority Critical patent/CN216920428U/en
Application granted granted Critical
Publication of CN216920428U publication Critical patent/CN216920428U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Earth Drilling (AREA)

Abstract

A welding-free fixing device for underwater steel pipe parallel connection comprises a sleeve sleeved on a steel pipe and a connecting rod fixedly connected with adjacent sleeves, wherein the sleeve is borne and positioned by a bottom support, the bottom support is sleeved at a preset position of the steel pipe parallel connection through a positioning mechanism, a plurality of track grooves extending along the radial direction of the steel pipe are formed in the upper end face of the bottom support, wedge blocks perpendicular to the track grooves and parallel to the steel pipe are arranged in the track grooves in a sliding mode, and the wedge blocks gradually become thick from high to low along the height direction; the top end of the wedge-shaped block is gradually inserted into a gap between the sleeve and the steel pipe in the lowering process of the sleeve, and along with the descending of the sleeve, the bottom end of the wedge-shaped block gradually approaches the steel pipe from the outer side along the track groove, and finally the sleeve is fixed on the steel pipe.

Description

Underwater steel pipe parallel connection welding-free fixing device
Technical Field
The utility model relates to the technical field of bridge engineering, in particular to an underwater steel pipe parallel connection welding-free fixing device.
Background
The bridge mostly is striden river bridge, and strides river bridge construction and often utilizes steel trestle, steel translation as operation platform on water, and this type of platform mostly adopts the steel pipe parallel connection as the basis to support, and the steel pipe pile is fixed earlier in general bridge construction meeting, then hoists the channel-section steel of parallel connection to two steel pipe piles and directly carries out welded connection.
This approach can have the following problems: the steel pipe parallel connection is usually only constructed on the upper part of the water surface, for the area with larger water depth, the parallel connection between the steel pipes is difficult to carry out underwater, if the parallel connection construction is not carried out, the bearing capacity and the stability of the operation platform are greatly reduced, and the safety guarantee coefficient is low. Generally, special operators are arranged to carry out horizontal connection installation and welding, and although the bearing capacity and stability of the operation platform are guaranteed, the problems of difficulty in hoisting construction, large installation risk, low installation efficiency and the like exist. Especially, when the underwater robot is in a seawater environment, a water area with large flow velocity or a high-turbidity water area, the operation environment of special operators is severe, and underwater operation is difficult to carry out.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the technical problems and provides a welding-free fixing device for underwater steel pipe parallel connection, which enhances the stability and improves the construction efficiency of the steel pipe parallel connection.
In order to solve the technical problems, the utility model provides the following technical scheme: a welding-free fixing device for underwater steel pipe parallel connection comprises a sleeve sleeved on a steel pipe and a connecting rod fixedly connected with adjacent sleeves, wherein the sleeve is borne and positioned by a bottom support, the bottom support is sleeved at a preset position of the steel pipe parallel connection through a positioning mechanism, a plurality of track grooves extending along the radial direction of the steel pipe are formed in the upper end face of the bottom support, wedge blocks perpendicular to the track grooves and parallel to the steel pipe are arranged in the track grooves in a sliding mode, and the wedge blocks gradually become thick from high to low along the height direction; the top end of the wedge-shaped block is gradually inserted into a gap between the sleeve and the steel pipe in the lowering process of the sleeve, and along with the descending of the sleeve, the bottom end of the wedge-shaped block gradually approaches the steel pipe from the outer side along the track groove, and finally the sleeve is fixed on the steel pipe.
The underwater steel pipe parallel connection welding-free fixing device is further optimized as follows: the track groove is a groove formed between the two limiting plates, the groove is distributed along the circumferential direction of the steel pipe, and the bottom end of the wedge-shaped block is located in the groove and slides inwards along the groove when the sleeve descends.
The underwater steel pipe parallel connection welding-free fixing device is further optimized as follows: the track groove is a groove formed in the upper end face of the bottom support, the groove is distributed along the circumferential direction of the steel pipe, and the bottom end of the wedge-shaped block is located in the groove and slides inwards along the groove when the sleeve descends.
The underwater steel pipe parallel connection welding-free fixing device is further optimized as follows: the positioning mechanism comprises a limiting rope, hooks are arranged at two ends of the limiting rope, one end of the limiting rope is hooked on the bottom support, and the other end of the limiting rope is hooked at the top of the steel pipe.
The underwater steel pipe parallel connection welding-free fixing device is further optimized as follows: a plurality of hanging holes matched with the hooks are uniformly formed in the bottom support.
The underwater steel pipe parallel connection welding-free fixing device is further optimized as follows: the outer end face of the bottom support is provided with a baffle along the circumferential direction, and the baffle seals the outer end of the track groove.
The underwater steel pipe parallel connection welding-free fixing device is further optimized as follows: the track groove is in interference fit with the wedge-shaped block.
The underwater steel pipe parallel connection welding-free fixing device is further optimized as follows: the groove bottom of the track groove is gradually reduced from the outer end to the inner end.
The underwater steel pipe parallel connection welding-free fixing device is further optimized as follows: the bottom support is of a circular ring structure.
Advantageous effects
According to the underwater steel pipe parallel connection welding-free fixing device, the positioning bottom support is placed at the preset position of the steel pipe parallel connection, so that the position determination of the sleeve is completed, the wedge-shaped block slides inwards along the radial direction of the steel pipe through the track groove, the sleeve and the wedge-shaped block are fixed on the steel pipe under the action of mutual friction force in the sliding process, the parallel connection fixing between the steel pipes is completed, the bearing capacity and the stability of a bridge construction operation platform are guaranteed, and the construction efficiency of the steel pipe parallel connection is improved. The whole steel pipe parallel connection process does not need operators to launch, the water area environment where the bridge is located does not need to be considered, the construction risk is reduced, and the construction safety of the operators is enhanced.
Drawings
FIG. 1 is a schematic structural view of an underwater steel pipe parallel connection welding-free fixing device;
FIG. 2 is a schematic view of the shoe and wedge;
FIG. 3 is a top view of the underwater steel pipe parallel connection welding-free fixing device;
FIG. 4 is a cross-sectional view of a parallel welding-free underwater steel pipe fixing device;
the labels in the figure are: 1. the steel pipe, 2, collet, 3, track groove, 4, wedge, 5, sleeve, 6, connecting rod, 7, positioning mechanism.
Detailed Description
The following detailed description of the preferred embodiments of the utility model refers to the accompanying drawings.
As shown in fig. 1-4: the utility model provides a welded fastening device is exempted from in steel pipe tie under water, establishes sleeve 5 and the adjacent sleeve 5's of fixed connection connecting rod 6 on steel pipe 1 including the cover, and adjacent sleeve 5 sets up relatively, and the both ends of connecting rod 6 weld with the section of thick bamboo wall of two adjacent sleeves 5 respectively to realize the tie between steel pipe 1, also can two connecting rods 6 cross-fixation can be more firm.
Sleeve 5 bears the location by a collet 2, collet 2 establishes the preset position of 1 flat antithetical couplet of steel pipe through 7 covers of positioning mechanism, collet 2 can be the ring shape, be provided with on collet 2 and cooperate sleeve 5 to fix wedge 4 on steel pipe 1 when 1 flat antithetical couplet of steel pipe, sleeve 5 moves down under the effect of gravity, transfer the in-process, the gap of sleeve 5 and steel pipe 1 is inserted gradually on 4 tops of wedge, and along with sleeve 5's decline, the bottom of wedge 4 is close to steel pipe 1 from the outside gradually along track groove 3. Then the wedge-shaped blocks 4 move inwards along the track grooves 3 under the interaction of the wall of the sleeve 5, and finally the wedge-shaped blocks 4 fix the sleeve 5 on the steel pipe 1 under the action of mutual friction force, so that the steel pipe 1 is connected in parallel.
Consequently, the internal diameter of collet 2 is slightly bigger than the external diameter of steel pipe 1 and some, can 1cm big, and collet 2's external diameter is compared not too big than the internal diameter, and too big 4 can be installed apart from steel pipe 1 far away, when sleeve 5 and 4 locks of wedge, push away from steel pipe 1 with wedge 4 on the contrary, can't play fixed effect, and consequently collet 2's inside and outside diameter difference can not be too big, can about 15cm big.
The upper end face of the bottom support 2 is provided with a plurality of track grooves 3 extending along the radial direction of the steel pipe 1, and the plurality of track grooves 3 are distributed around the circumferential direction of the steel pipe 1. The track groove 3 can be a groove formed between two limiting plates, the groove is uniformly distributed around the circumference of the steel pipe 1, and the bottom end of the wedge-shaped block 4 is positioned in the groove and slides inwards along the groove when the sleeve 5 descends. The track groove 3 can also be a groove formed in the upper end surface of the bottom support 2, the groove is distributed around the circumference of the steel pipe 1, and the bottom end of the wedge-shaped block 4 is positioned in the groove and slides inwards along the groove when the sleeve 5 descends.
The track groove 3 is internally provided with a wedge block 4 in a sliding way, the wedge block 4 is perpendicular to the track groove 3 and is parallel to the steel pipe 1, and the wedge block 4 becomes thicker from high to low along the height direction. Wherein, single wedge 4 can be the iron plate, and the section of wedge 4 is right triangle, and short right-angle side is located track groove 3, and long right-angle side is parallel with steel pipe 1, and the specific size changes according to the quantity change of track groove 3's setting. For example, 12 track grooves 3 are arranged on the base plate 2, and the height of the track groove 3 is 2cm, so that the long side of the wedge block 3 is 20cm, the short side of the wedge block 3 is 1cm, and the thickness of the wedge block is 1/12 of the diameter of the steel pipe 1. According to the actual demand, the number of the track grooves 3 is at least 3, the more the track grooves 3 are, the more the wedge blocks 4 are, which means that the sleeve 5 is locked with the wedge blocks 4, so that the sleeve 5 is more firmly fixed on the steel pipe 1. When the wedge blocks 4 are too few, the sleeves 5 may be deviated or inclined, so that the sleeves 5 are not firmly fixed, and the steel pipes 1 are not firmly connected in a parallel manner, thereby deteriorating the bearing capacity and stability of the bridge construction work platform.
In addition, the outer end face of the bottom support 2 is provided with a baffle along the circumferential direction, the baffle seals the outer end of the track groove 3, and the wedge-shaped block 4 is prevented from falling off. In addition, can take interference fit between track groove 3 and the wedge 4, wedge 4 can not drop from track groove 3 outer end, when sleeve 5 transfers in addition, receives the effort wedge 4 of 5 section of thick bamboo walls of sleeve and inwards slides. The wedge-shaped block 4 can be restrained by the height change of the bottom of the track groove 3, and the bottom of the track groove 3 is gradually reduced from the outer end to the inner end, so that the wedge-shaped block 4 can only move in a single direction.
According to the bridge work progress, at first with 1 back of piling of steel pipe, carry out the tie between the steel pipe 1 and ally oneself with, concrete tie position needs the location, and collet 2 establishes the preset position of 1 tie of steel pipe through 7 covers of positioning mechanism, and a plurality of positioning mechanism 7 around collet 2's circumference evenly distributed, and collet 2 can be located the position of tie between the steel pipe 1 steadily unchangeably under the cooperation of positioning mechanism 7. After the sleeve 5 and the wedge block 4 are locked and fixed, the positioning mechanism 7 can be removed. The positioning mechanism 7 comprises a limiting rope, hooks are arranged at two ends of the limiting rope, one end of the limiting rope is hooked on the bottom support 2, and the other end of the limiting rope is hooked at the top of the steel pipe 1. Before construction, the steel pipe subjected to parallel connection is subjected to water depth measurement, the mounting height of the underwater steel pipe parallel connection welding-free fixing device is determined according to measurement data, the length of a limiting rope in a positioning mechanism 7 is determined, the position of a bottom support 2 is limited according to the length of the limiting rope, and therefore the final mounting position is determined.
For hanging on collet 2 in order to make things convenient for the couple in the positioning mechanism 7, evenly seted up a plurality of on collet 2 and get in touch complex hanging hole, a plurality of hanging holes distribute along collet 2's circumference, for the collet 2 of holding up firmly, the hanging hole sets up three at least.
The use method of the underwater steel pipe parallel connection welding-free fixing device comprises the following steps: firstly, measuring the water depth, and determining the installation position of the underwater steel pipe parallel connection welding-free fixing device. Secondly, under the cooperation of positioning mechanism 7, transfer collet 2 to the preset position of 1 parallel connection of steel pipe along 1 concentric axis of steel pipe. And finally, placing the sleeve 5, gradually enabling the bottom end of the wedge block 4 to approach the steel pipe 1 from the outer side along the track groove 3 along with the descending of the sleeve 5, and finally fixing the sleeve 5 on the steel pipe 1 to finish the parallel connection and fixation of the underwater steel pipe 1.
Although the present invention has been described with reference to a preferred embodiment, it should be understood that various changes, substitutions and alterations can be made herein without departing from the spirit and scope of the utility model as defined by the appended claims.

Claims (9)

1. The utility model provides a steel pipe parallel connection exempts from to weld fixture apparatu under water, establishes sleeve (5) and connecting rod (6) of adjacent sleeve of fixed connection (5) on steel pipe (1) including the cover, its characterized in that: the sleeve (5) is supported and positioned by a bottom support (2), the bottom support (2) is sleeved at the preset position of the parallel connection of the steel pipe (1) through a positioning mechanism (7), the upper end face of the bottom support (2) is provided with a plurality of track grooves (3) extending along the radial direction of the steel pipe (1), wedge blocks (4) perpendicular to the track grooves (3) and parallel to the steel pipe (1) are arranged in the track grooves (3) in a sliding mode, and the wedge blocks (4) gradually become thick from high to low along the height direction; the top end of the wedge-shaped block (4) is gradually inserted into a gap between the sleeve (5) and the steel pipe (1) in the lowering process of the sleeve (5), the bottom end of the wedge-shaped block (4) gradually approaches the steel pipe (1) from the outer side along the track groove (3) along with the lowering of the sleeve (5), and finally the sleeve (5) is fixed on the steel pipe (1).
2. The underwater steel pipe parallel connection welding-free fixing device of claim 1, characterized in that: the track groove (3) is a groove formed between the two limiting plates, the groove is distributed around the steel pipe (1) in the circumferential direction, and the bottom end of the wedge-shaped block (4) is located in the groove and slides inwards along the groove when the sleeve (5) descends.
3. The underwater steel pipe parallel connection welding-free fixing device of claim 1, which is characterized in that: the track groove (3) is a groove formed in the bottom support (2), the groove is distributed around the steel pipe (1) in the circumferential direction, and the bottom end of the wedge-shaped block (4) is located in the groove and slides inwards along the groove when the sleeve (5) descends.
4. The underwater steel pipe parallel connection welding-free fixing device of claim 1, which is characterized in that: the positioning mechanism (7) comprises a limiting rope, hooks are arranged at two ends of the limiting rope, one end of the limiting rope is hooked on the bottom support (2), and the other end of the limiting rope is hooked on the top of the steel pipe (1).
5. The underwater steel pipe parallel connection welding-free fixing device of claim 4, wherein: the bottom support (2) is evenly provided with a plurality of hanging holes matched with the hooks.
6. The underwater steel pipe parallel connection welding-free fixing device of claim 1, which is characterized in that: the outer end face of the bottom support (2) is provided with a baffle along the circumferential direction, and the baffle seals the outer end of the track groove (3).
7. The underwater steel pipe parallel connection welding-free fixing device of claim 1, which is characterized in that: the track groove (3) is in interference fit with the wedge block (4).
8. The underwater steel pipe parallel connection welding-free fixing device of claim 1, which is characterized in that: the groove bottom of the track groove (3) is gradually reduced from the outer end to the inner end.
9. The underwater steel pipe parallel connection welding-free fixing device of claim 1, which is characterized in that: the bottom support (2) is of a circular ring structure.
CN202220139995.XU 2022-01-19 2022-01-19 Underwater steel pipe parallel connection welding-free fixing device Active CN216920428U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220139995.XU CN216920428U (en) 2022-01-19 2022-01-19 Underwater steel pipe parallel connection welding-free fixing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220139995.XU CN216920428U (en) 2022-01-19 2022-01-19 Underwater steel pipe parallel connection welding-free fixing device

Publications (1)

Publication Number Publication Date
CN216920428U true CN216920428U (en) 2022-07-08

Family

ID=82262130

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220139995.XU Active CN216920428U (en) 2022-01-19 2022-01-19 Underwater steel pipe parallel connection welding-free fixing device

Country Status (1)

Country Link
CN (1) CN216920428U (en)

Similar Documents

Publication Publication Date Title
CN211813021U (en) High-precision crane hoisting mechanism
CN216920428U (en) Underwater steel pipe parallel connection welding-free fixing device
CN112570968A (en) Pile leg shell ring butt joint method
CN108396754A (en) A kind of floating construction method for spelling steel cofferdam and its lower water of suspention
CN108149704B (en) Offshore wind turbine prefabricated assembly type high-pile bearing platform foundation structure and installation method
CN216194915U (en) Quick installation mechanism of piping lane prefab
CN210239088U (en) A outer wall cantilever frame for utility tunnel construction
CN213297204U (en) Steel upright post positioning plate structure
CN219341461U (en) Municipal pipeline hoist device
CN217107009U (en) Transmission device for mounting reaction frame
CN217151876U (en) Sleeve centering assembly and sleeve supporting and centering device
CN212294631U (en) Hoisting and positioning fixture for large-diameter steel reinforcement cage
CN213731491U (en) Installation frame for marine pipe maintenance equipment
CN218263872U (en) Multifunctional foundation pit cover piece
CN213296356U (en) Steel stand column structure with accurate positioning
CN212609060U (en) Auxiliary lifting appliance for installation of building water supply engineering
CN113235609B (en) Combined supporting structure of large-diameter steel pipe pile and small-diameter steel pipe pile
CN213202066U (en) Hoist is used to precast concrete section of thick bamboo
CN220131682U (en) Circular pipe-jacking pipe joint lifting appliance
CN220166886U (en) Positioning device for bridge pile foundation reinforcement cage
CN207498937U (en) One kind is prefabricated to block assembled diaphram wall
CN213173755U (en) Beam column type support steel-pipe pile pothook
CN218346229U (en) Offshore pile foundation construction device
CN112282649B (en) Device and method for simultaneously setting multiple drilling casings
CN112627731B (en) Deep water torrent light-weight standing type intelligent circulating drilling machine and using method thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant