CN216865922U - Fan basis crab-bolt fast-assembling system - Google Patents
Fan basis crab-bolt fast-assembling system Download PDFInfo
- Publication number
- CN216865922U CN216865922U CN202220217910.5U CN202220217910U CN216865922U CN 216865922 U CN216865922 U CN 216865922U CN 202220217910 U CN202220217910 U CN 202220217910U CN 216865922 U CN216865922 U CN 216865922U
- Authority
- CN
- China
- Prior art keywords
- platform
- plate
- hoisting
- sliding plate
- anchor bolt
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a fan foundation anchor bolt fast-assembling system which is arranged on the inner diameter of an upper anchor plate above a lower anchor plate, when an anchor bolt is hoisted, an operator only needs to provide an auxiliary guide force, the force for hoisting the anchor bolt is provided by a rotary power part, the labor intensity is reduced for installing a plurality of anchor bolts, the operation efficiency is improved, and the problems of large manpower consumption and low efficiency caused by erecting the anchor bolts by manpower are solved; the platform assembly is hollow in the inner diameter of the upper anchor plate to form a platform, so that operation support is provided for workers, the safety problems of falling, swinging, collision and the like are solved, and the safety risks of vertical cross operation are solved under the action of a fence, so that the problems of accidents of falling injury to people, high falling, mechanical striking and the like are easily caused; when hoisting many crab-bolts, can carry out the operation to the crab-bolt of anchor plate all around on last anchor plate, solve and need remove the scaffold frame on ground and reduced the problem of efficiency of construction.
Description
Technical Field
The utility model relates to a fan foundation anchor bolt fast-assembling system, and belongs to the technical field of fan installation construction.
Background
When the anchor bolt of the wind driven generator anchor bolt assembly is installed on land, the existing general method is to use a crane to lift the upper anchor plate, so that the gravity of the upper anchor plate is completely borne by the lifting hook, 1-2 workers go up to the upper anchor plate with the height of about 4m from the ground, the anchor bolt with the length of about 4m is erected by manpower by 2-3 workers on the ground, the anchor bolt penetrates through the anchor bolt hole on the side of the upper anchor plate firstly, then penetrates through the anchor bolt hole on the lower anchor plate, and finally the nuts at the upper anchor plate and the lower anchor plate are locked. Taking a certain project of golden wind 3.0MW wind generating set as an example, the total number of foundation anchor bolts is 176, which means that in the installation of the anchor bolts, the process of more than 176 times needs to be repeated, and the problems of large labor consumption and low efficiency exist. When workers work on the upper anchor plate and the lower anchor plate, the workers on the upper anchor plate can only sit on the upper anchor plate, the inner part of the upper anchor plate is completely empty, the width of the anchor plate is only 0.5m, and although a safety belt can be hung on a crane hook, the distance between a safety belt hanging point and a hook plumb line is more than 2m, once the safety belt is in danger of falling, swinging collision can occur, larger secondary damage is caused, and the problem of large potential safety hazard exists; when workers work, the workers who go up the anchor plates and go down the anchor plates still have the safety risk of vertical crossing operation, and safety accidents such as people injury due to falling objects, falling from high places, mechanical striking and the like are very easy to happen.
In chinese patent publication No. CN209277509U, although the worker can install anchor bolts on the lower anchor plate and the lower anchor plate through the scaffold, the problem of potential safety hazard in the operation of the worker on the upper anchor plate is solved, however, the worker can occupy one working face of the anchor bolt assembly in the installation, and cannot simultaneously operate around the periphery, when the installation of the adjustment and replacement working face is performed, the scaffold needs to be moved by self-locking rollers many times, and the construction efficiency is reduced.
SUMMERY OF THE UTILITY MODEL
In order to solve the technical problem, the utility model provides a fan foundation anchor bolt fast-assembling system.
The utility model is realized by the following technical scheme.
The utility model provides a fan foundation anchor bolt fast-assembling system, which comprises:
hoisting the assembly;
the lifting assembly is arranged on the platform assembly, the platform assembly provides a stress base for the lifting assembly, and a worker can tread on the platform assembly to work;
the platform component is detachably mounted with the upper anchor plate through the sliding plate component.
Also included is a rail mounted on the outer edge of the platform assembly.
The hoisting assembly comprises a controllable telescopic supporting piece, and a fixed pulley is arranged at one end of the supporting piece;
the other end of the supporting piece is rotatably hinged on a base of the rotary power piece;
and one end of the hoisting rope is wound on the rotating end of the rotating power part, and the hoisting rope is provided with a lifting hook for hoisting an anchor bolt by winding the fixed pulley.
The platform assembly comprises a first edge platform and a second edge platform, and the first edge platform and the second edge platform are detachably assembled;
the operation through hole is arranged on the first side platform or the second side platform, and a cover plate is arranged on the operation through hole in a flip manner;
the lifting lug is fixed on the first side platform and the second side platform;
the winch disc can be rotatably arranged on the first side platform and/or the second side platform, and the winch disc can drive the rotating power piece to rotate along the circumferential direction of the upper anchor plate when rotating.
The sliding plate component comprises guide plates fixed on the first side platform and the second side platform, and the sliding plate component and the platform component are fixedly installed;
the sliding plate is hollow and has two through ends, the sliding plate can be sleeved on the guide plate in a sliding manner, and the outer end of the sliding plate is provided with a notch clamped with the inner diameter edge of the upper anchor plate;
limiting through holes are formed in the side edges of the guide plate and the sliding plate, and limiting columns are clamped in the limiting through holes;
the width of the notch at the outer end of the sliding plate is larger than the axial thickness of the inner diameter of the upper anchor plate.
And a handle which is convenient for the sliding plate to slide on the guide plate is fixed on the side edge of the sliding plate.
The utility model has the beneficial effects that: the fan foundation anchor bolt fast-assembling system is arranged on the inner diameter of the upper anchor plate above the lower anchor plate, when the anchor bolts are hoisted, an operator only needs to provide an auxiliary guide force, the force for hoisting the anchor bolts is provided by the rotary power part, the labor intensity is reduced for installing a plurality of anchor bolts, the operation efficiency is improved, and the problems of large labor consumption and low efficiency caused by erecting the anchor bolts by manpower are solved; the platform assembly is hollow in the inner diameter of the upper anchor plate to form a platform, so that operation support is provided for workers, the safety problems of falling, swinging, collision and the like are solved, and the safety risks of vertical cross operation are solved under the action of a fence, so that the problems of accidents of falling injury to people, high falling, mechanical striking and the like are easily caused; when hoisting many crab-bolts, can carry out the operation to the crab-bolt of anchor plate all around on last anchor plate, solve and need remove the scaffold frame on ground and reduced the problem of efficiency of construction.
Drawings
FIG. 1 is a schematic structural diagram of a fan foundation anchor bolt quick-mounting system hoisting device of the utility model;
FIG. 2 is a schematic view of the mounting structure of the platform assembly of the present invention;
FIG. 3 is a schematic view of the structure of the platform assembly, the sliding plate assembly and the enclosure of the present invention;
FIG. 4 is a schematic view of the hoist of the present invention mounted to the platform assembly;
FIG. 5 is a schematic view of the hoist of the present invention at the inner diameter of the upper anchor plate;
FIG. 6 is a schematic view of the hoisting rope hoisting anchor bolt of the utility model installed on the upper anchor plate and the lower anchor plate;
FIG. 7 is a schematic view of the construction of the sliding panel assembly of the present invention;
in the figure: 11-anchor bolts; 12-upper anchor plate; 13-lower anchor plate; 21-a support; 23-a winch; 24-hoisting ropes; 31-a first edge platform; 32-a second edge platform; 33-cover plate; 34-a lifting lug; 35-a hoisting disc; 41-a guide plate; 42-a sliding plate; 43-a limiting column; 44-a handle; and 5-fencing.
Detailed Description
The technical solution of the present invention is further described below, but the scope of the claimed invention is not limited to the described.
As shown in fig. 1-7.
The utility model relates to a fan foundation anchor bolt fast-assembling system, which comprises:
the hoisting component can hoist the anchor bolt 11 to be installed with the upper anchor plate 12 and the lower anchor plate 13;
the hoisting assembly comprises a supporting piece 21, the supporting piece 21 is composed of telescopic rods with controllable telescopic length, for example, telescopic rods formed by controlling at least two sections of rods to be sleeved together in a telescopic manner at intervals through screws;
the fixed pulley is arranged at the end part of the supporting piece 21 extending out of the outer diameter of the upper anchor plate 12;
the rotating power piece 23 is placed on the platform assembly and positioned on the inner diameter of the upper anchor plate 12, the rotating power piece 23 is a winch, and the end part of the supporting piece 21 positioned on the inner diameter of the upper anchor plate 12 is hinged with the base of the rotating power piece 23 in a way of rotating up and down along the axial direction of the anchor bolt 11;
the hoisting rope 24 is composed of steel wire ropes, and the hoisting rope 24 can also adopt a synthetic fiber sling, for example, a single 1t/2m terylene flat sling is selected; hoisting rope 24 one end winding is located rotatory power part 23, and hoisting rope 24 walks around the fixed pulley and installs the lifting hook that is used for hoisting crab-bolt 11, and the lifting hook can adopt to choose for use 1t steel lifting hook.
A platform assembly providing a stress base for the hoisting assembly, and a worker can step on the platform assembly to work;
the platform assembly comprises a first side platform 31 and a second side platform 32 which are formed by welding or installing bolts by rigid materials such as steel plates and/or steel beams, and the like, wherein the first side platform 31 and the second side platform 32 are detachably assembled through bolts;
one or more operation through holes for operators to go up and down are arranged on the platform component, the operation through holes can be arranged on the first side platform 31 or the second side platform 32, and cover plates 33 are arranged on the operation through holes through loose-leaf flip covers;
the hoisting disc 35 is rotatably arranged on the platform assembly through a bearing or a shaft hole in clearance fit, the hoisting disc 35 is arranged on the first side platform 31 or the second side platform 32, the rotary power piece 23 is arranged on the hoisting disc 35 to achieve the purpose that the platform assembly provides a stress base for the hoisting assembly, and the hoisting disc 35 can drive the rotary power piece 23 to rotate along the circumferential direction of the upper anchor plate 12 when rotating; the rotary power member 23 may be directly mounted on the first side platform 31 or the second side platform 32.
A sliding plate component fixedly mounted with the platform component, the sliding plate component being detachably mounted with the upper anchor plate 12;
the sliding plate component comprises guide plates 41 which are welded and fixed on the first side platform 31 and the second side platform 32 at intervals, so that the sliding plate component and the platform component are fixedly installed; the number of the guide plates 41 may be four or more, two guide plates 41 are distributed on the first edge platform 31, and the other two guide plates 41 are distributed on the second edge platform 32; the number of the guide plates 41 may be plural;
a sliding plate 42 which is hollow inside and has two through ends, and the outer end of the sliding plate 42 is provided with a notch clamped with the inner diameter side of the upper anchor plate 12;
limiting through holes are formed in the side edges of the guide plate 41 and the sliding plate 42, and limiting columns 43 are clamped in the limiting through holes;
the width of the notch at the outer end of the sliding plate 42 is larger than the axial thickness of the inner diameter of the upper anchor plate 12, when the sliding plate 42 slides on the guide plate 41 to clamp the notch with the inner diameter of the upper anchor plate 12, the limiting through hole of the guide plate 41 is aligned with the limiting through hole of the sliding plate 42, and the limiting column 43 clamps the limiting through holes on the side edges of the guide plate 41 and the sliding plate 42 for limiting;
when the upper anchor plate 12 is fixed, the guide plate 41 is lifted to the state that the upper edge and the lower edge of the notch are not matched with the inner diameter edge of the upper anchor plate 12 through a crane, so that the sliding plate 42 slides towards the center of the inner diameter of the upper anchor plate 12 on the guide plate 41, and the sliding plate 42 is quickly separated from the upper anchor plate 12; the detachable installation of the sliding plate component and the upper anchor plate 12 is realized.
A handle 44 for sliding the sliding plate 42 on the guide plate 41 is welded and fixed on the side of the sliding plate 42.
A fence 5 mounted on the outer edge of the platform assembly, the fence protecting personnel on the platform assembly.
A method for installing and constructing a fan foundation anchor bolt anchor plate by using a fan foundation anchor bolt fast-assembling system comprises the following steps:
system installation: the fast assembling system of the fan foundation anchor bolt is arranged on the inner diameter of an upper anchor plate 12 above a lower anchor plate 13, a small slow-speed rotating power piece 23 is arranged on a hoisting disc 35 of a platform assembly, a supporting rod 21 is arranged, a fixed pulley is arranged at the top of the supporting rod 21, the rotating power piece 23 emits a hoisting rope 24 along the direction of the supporting rod 21, the hoisting rope 24 penetrates through the fixed pulley at the top of the supporting rod 21, and a lifting hook is arranged at the head of the hoisting rope 24; the length of the telescopic movable section of the support rod 21 is adjusted to ensure that the support rod 21 extends out of the outer edge of the outer diameter of the upper anchor plate 12 by a distance of 100mm, and the movable section is fixed by fastening screws to ensure that the support rod 21 can not be stretched any more;
hoisting preparation: the hoisting rope 24 is lowered by rotating the power part 23, so that the lifting hook at the tail end of the hoisting rope 24 is lowered to the ground; meanwhile, ground workers make the installation preparation of the anchor bolts 11, place all the anchor bolts 11 in a combined place orderly, screw a thin locking nut at the lower end (short thread end) of each anchor bolt 11, and screw a nylon adjusting nut at the upper end of each positioned anchor bolt 11; the ground worker binds the anchor bolt 11 with a synthetic fiber sling, the hanging point is about 1/3 (upper end) of the anchor bolt, and the hook is hooked with the synthetic fiber sling.
Hoisting construction: the rotating power piece 23 is started to lift the anchor bolt 11; when the upper end of the anchor bolt 11 is about 100mm away from the lower part of the upper anchor plate 12, the lifting is stopped; at the moment, ground workers adjust the angle of the anchor bolt 11, the anchor bolt 11 is lifted manually, the upper end of the anchor bolt penetrates into the anchor hole of the upper anchor plate 12, and then the lower end of the anchor bolt penetrates into the corresponding anchor hole of the lower anchor plate 13; after the anchor bolts 11 in the same region are installed, the supporting rod 21 retracts, and the rotating power piece 23 is started to retract the hoisting rope 24 and the lifting hook; the rotating power part 23 rotates the rotating platform on the winding disc 23 to face the next area, the steps are repeated again, and all anchor bolts are hoisted and penetrated in sequence.
The fan foundation anchor bolt fast-assembling system is arranged on the inner diameter of an upper anchor plate 12 above a lower anchor plate 13, when the anchor bolts 11 are hoisted, an operator only needs to provide an auxiliary guide force, the force for hoisting the anchor bolts 11 is provided by a rotary power part 23, the labor intensity is reduced for installing a plurality of anchor bolts 11, the operation efficiency is improved, and the problems of large manpower consumption and low efficiency caused by erecting the anchor bolts by manpower are solved; the platform assembly is hollow in the inner diameter of the upper anchor plate 12 to form a platform, so that operation support is provided for workers, the safety problems of falling, swinging, collision and the like are solved, and under the action of a fence, the safety risks of vertical cross operation are solved, and the problems of accidents of people injury due to falling objects, falling from high places, mechanical striking and the like are easily caused; when hoisting a plurality of anchor bolts 11, can go on the operation to anchor bolt 11 on last anchor plate 12 on anchor plate 13 global all around, solve the problem that needs remove the scaffold frame on ground and reduced the efficiency of construction.
Claims (9)
1. The utility model provides a fan basis crab-bolt fast-assembling system which characterized in that includes:
hoisting the assembly;
the hoisting assembly comprises a controllable telescopic supporting piece (21), and a fixed pulley is mounted at one end of the supporting piece (21);
the other end of the supporting piece (21) is rotatably hinged on a base of the rotary power piece (23);
one end of the hoisting rope (24) is wound on the rotating end of the rotating power part (23), and the hoisting rope (24) is provided with a lifting hook for hoisting the anchor bolt (11) by winding the fixed pulley;
the hoisting assembly is arranged on the platform assembly;
the sliding plate component is detachably mounted with the upper anchor plate (12) through the sliding plate component.
2. The fan foundation anchor bolt quick-assembling system of claim 1, characterized in that: and a fence (5) mounted on the outer edge of the platform assembly.
3. The fan foundation anchor bolt quick-assembling system of claim 1, characterized in that: the platform assembly comprises a first side platform (31) and a second side platform (32), and the first side platform (31) and the second side platform (32) are detachably assembled;
the hoisting disc (35) is rotatably arranged on the first side platform (31) and/or the second side platform (32), and the hoisting disc (35) can drive the rotating power piece (23) to rotate along the circumferential direction of the upper anchor plate (12) when rotating.
4. The wind turbine foundation anchor bolt quick-assembling system of claim 3, characterized in that: the device also comprises an operation through hole arranged on the first side platform (31) or the second side platform (32), and a cover plate (33) is arranged on the operation through hole in a flip-open manner.
5. The wind turbine foundation anchor bolt quick-assembling system of claim 3, characterized in that: the lifting lug (34) is further included, and the lifting lug (34) is fixed on the first side platform (31) and the second side platform (32).
6. The wind turbine foundation anchor bolt quick-assembling system of claim 3, characterized in that: the sliding plate component comprises a guide plate (41) fixed on the first side platform (31) and the second side platform (32), and the sliding plate component and the platform component are fixedly installed;
the sliding plate (42) is hollow and is provided with two through ends, the sliding plate (42) is sleeved on the guide plate (41) in a sliding mode, and the outer end of the sliding plate (42) is provided with a groove opening clamped with the inner diameter side of the upper anchor plate (12).
7. The wind turbine foundation anchor bolt quick-assembling system of claim 6, characterized in that: and limiting through holes are formed in the side edges of the guide plate (41) and the sliding plate (42), and limiting columns (43) are clamped in the limiting through holes.
8. The wind turbine foundation anchor bolt quick-assembling system of claim 6, characterized in that: the width of the notch at the outer end of the sliding plate (42) is larger than the axial thickness of the inner diameter of the upper anchor plate (12).
9. The wind turbine foundation anchor bolt quick-assembling system of claim 6, characterized in that: a handle (44) which is convenient for the sliding plate (42) to slide on the guide plate (41) is fixed on the side edge of the sliding plate (42).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202220217910.5U CN216865922U (en) | 2022-01-26 | 2022-01-26 | Fan basis crab-bolt fast-assembling system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202220217910.5U CN216865922U (en) | 2022-01-26 | 2022-01-26 | Fan basis crab-bolt fast-assembling system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN216865922U true CN216865922U (en) | 2022-07-01 |
Family
ID=82152346
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202220217910.5U Active CN216865922U (en) | 2022-01-26 | 2022-01-26 | Fan basis crab-bolt fast-assembling system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN216865922U (en) |
-
2022
- 2022-01-26 CN CN202220217910.5U patent/CN216865922U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107697818B (en) | Construction method and special construction equipment for wall of prestressed concrete wind power tower | |
US11448197B2 (en) | Modular tool | |
CN216865922U (en) | Fan basis crab-bolt fast-assembling system | |
CN111998182B (en) | Platform for environment management | |
CN114278073A (en) | Fan basis crab-bolt fast-assembling system | |
CN216740623U (en) | Split clamping plate assembly | |
CN114411797A (en) | Installation and construction method of anchor plate of anchor bolt of fan foundation | |
CN112110347A (en) | Hoisting device for operation site | |
CN108928783B (en) | Shear type climbing hoisting machine for existing building additionally installed elevator | |
CN114427288B (en) | Installation construction method of split clamping plate assembly and anchor plate and split clamping plate assembly | |
CN216865945U (en) | Flexible fence structure | |
CN214195482U (en) | High-altitude operation platform for construction of steel structure engineering | |
CN210561720U (en) | Pier stud maintenance repair operation platform | |
CN112499486A (en) | Portable transformer lifter and operation method thereof | |
CN112324161A (en) | Mounting structure of annular rail dismounting device and annular rail dismounting method | |
CN216764072U (en) | Vertical hoisting device | |
JPH10245189A (en) | Omnidirectional moving crane used for high rise building construction | |
CN215711265U (en) | Temporary support hoisting device utilizing existing support under bridge | |
CN214246514U (en) | Civil engineering construction scaffold | |
CN216403640U (en) | Cable shaft power maintenance hoist device | |
JP7213515B2 (en) | Structure for tower movable scaffold, tower movable scaffold and tower work method | |
CN219708920U (en) | Crane travelling mechanism overhauls platform support frame | |
CN212838188U (en) | Novel wind-powered electricity generation blade overhauls double-deck hanging flower basket | |
CN218952752U (en) | Telescopic elevator shaft protection platform device | |
CN220351515U (en) | Small-sized lifting special device based on working face of main transformer |