CN216663995U CN202122303533.5U CN202122303533U CN216663995U CN 216663995 U CN216663995 U CN 216663995U CN 202122303533 U CN202122303533 U CN 202122303533U CN 216663995 U CN216663995 U CN 216663995U
Authority
CN
China
Prior art keywords
flood control
control wall
base
flood
upright post
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202122303533.5U
Other languages
Chinese (zh)
Inventor
曾理霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Shize Construction Engineering Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202122303533.5U priority Critical patent/CN216663995U/en
Application granted granted Critical
Publication of CN216663995U publication Critical patent/CN216663995U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The utility model provides a temporary flood control wall for an urban building, which relates to the technical field of flood control engineering and comprises a flood control wall and a base; the flood prevention wall is arranged on the outer side of the building main body in a surrounding manner and comprises stand columns and flood prevention plates used between the adjacent stand columns; the bottom surface of the upright post is provided with a base which is embedded below the ground surface, and the lower part of the base is provided with a concrete foundation; the upright columns comprise straight connecting upright columns for straight line connection and angle connecting upright columns for corner connection; the utility model effectively separates the building main body from the flood and reduces the property loss caused by the flood and the influence on the life of people.

Description

Be used for interim flood control wall of city building
Technical Field
The utility model relates to the technical field of flood prevention engineering, in particular to a temporary flood prevention wall for urban buildings.
Background
With the rapid development of urban construction, some historical problems are gradually exposed, and when rainstorm or flood occurs, the basement and the first floor of the urban construction often cannot block the flood in time, so that vehicles and equipment of the basement, shops and entrances and exits on the first floor and the like are damaged by the flood, and huge property loss and difficulty in life are caused.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a temporary flood control wall for urban buildings, which is used for effectively separating a building main body from flood and reducing property loss caused by the flood and influence on life of people, aiming at overcoming the defects and shortcomings of the prior art.
In order to achieve the purpose, the utility model adopts the technical scheme that: a temporary flood control wall for urban buildings comprises a flood control wall and a base; the flood prevention wall is arranged on the outer side of the building main body in a surrounding manner and comprises stand columns and flood prevention plates used between the adjacent stand columns; the bottom surface of the upright post is provided with a base which is embedded below the ground surface, and the lower part of the base is provided with a concrete foundation; the stand includes that straight line connection used directly links the stand and is connected used angle with the corner and link the stand.
Preferably, the directly-connected upright column comprises a first circular bottom plate, and two first mounting grooves formed in two opposite positions of the first upright column and the first upright column; the first circular bottom plate is arranged on the bottom surface of the first upright post; a first screw rod is welded on the first circular bottom plate in the middle of the first mounting groove.
Preferably, the corner connecting upright column comprises a second circular bottom plate, a second upright column and two second mounting grooves formed in the corner positions of the second upright column; the second round bottom plate is arranged on the bottom surface of the second upright post; and a second screw is welded on the second circular bottom plate in the middle of the second mounting groove.
Preferably, mounting holes are formed in the two ends of the flood prevention plate; when the flood prevention plate is inserted into the first mounting groove of the direct-connected upright post, the first screw penetrates through the mounting hole, and the top surface of the flood prevention plate is provided with a nut for fastening; when the flood prevention plate is inserted into the second mounting groove of the angle connection upright post, the second screw penetrates through the mounting hole and is provided with a nut on the top surface of the flood prevention plate for fastening.
Preferably, the first circular bottom plate and the second circular bottom plate are both provided with three fixing holes which are uniformly distributed; the fixing hole of the first round bottom plate and the first mounting groove are arranged in a staggered manner; the fixing holes of the second round bottom plate and the second mounting grooves are arranged in a staggered mode.
Preferably, the top of the base is provided with a screw hole; the upright post and the base are fixed through screws penetrating through the fixing holes to the screw holes.
Preferably, the bottom end of the flood prevention plate is provided with an elastic rubber strip which is of a hollow structure, and two ends of the elastic rubber strip are provided with through holes; when the elastic rubber strip is arranged in the first mounting groove, the first screw penetrates through the through hole; when the elastic rubber strip is arranged in the second mounting groove, the second screw penetrates through the through hole.
Preferably, the center of the bottom of the base is provided with a triangular groove, and the periphery of the bottom of the base is also provided with four rib plates; and the position of the screw hole at the lower part of the base is matched with the position of the fixing hole of the upright post when the concrete foundation is poured.
Preferably, when the flood prevention wall is not used, the screw hole in the top of the base is sealed by a screw.
The utility model has the beneficial effects that:
1. set up interim flood prevention wall in the building subject outside to effectively separate building subject and flood, effectively avoid the flood to get into building basement and first floor, and then reduce the loss of property that the flood caused and the influence to people's life.
2. First screw rod and second screw rod cooperation nut make flood prevention board paste ground closely, in addition the setting of elastic rubber strip, have greatly avoided flood to permeate to the building main part inside from flood prevention board bottom.
3. The base sets up triangle-shaped recess and floor, has strengthened the installation intensity of base by a wide margin, and effectively avoids the base to take place the skew to the phenomenon that can't correspond appears in the screw of greatly reducing the base and the fixed orifices later stage of stand takes place.
4. The flood control wall can be installed before flood control and detached after flood control, is convenient to use, and can not cause travel obstacles when flood does not occur.
Drawings
Fig. 1 is a schematic plan view of a temporary flood control wall for an urban building.
Fig. 2 is a schematic view of the installation plane of the flood prevention plate and the directly connected upright post.
Fig. 3 is a three-dimensional schematic view of the installation of the flood prevention plates and the directly connected columns.
Fig. 4 is a three-dimensional schematic view of a directly connected column.
Fig. 5 is a schematic view of the installation plane of the flood prevention plate and the corner connecting column.
Fig. 6 is a three-dimensional schematic view of the installation of the flood prevention plates and the corner connecting columns.
Fig. 7 is a three-dimensional schematic view of a corner connecting column.
Fig. 8 is a schematic view of a flood prevention plate.
Fig. 9 is a schematic view of the installation of the upright and the base.
Fig. 10 is a three-dimensional schematic view of a base.
Fig. 11 is a bottom view of the base.
Fig. 12 is a three-dimensional schematic view of an elastic rubber strip.
Fig. 13 is a schematic plan view of the flood control wall when not in use.
Fig. 14 is a schematic sectional view of the installation of the base when the flood prevention wall is not in use.
Description of reference numerals: 1. flood prevention wall, 11, stand, 111, directly link the stand, 1111, first circular bottom plate, 1112, first stand, 1113, first mounting groove, 1114, first screw rod, 112, angle link stand, 1121, second circular bottom plate, 1122, second stand, 1123, second mounting groove, 1124, second screw rod, 12, flood prevention board, 121, mounting hole, 01, fixed orifices, 2, base, 21, screw hole, 22, triangle-shaped recess, 23, floor, 3, nut, 4, screw, 5, elastic rubber strip, 51, perforation, 100, building main body, 200, ground, 300, concrete foundation.
Detailed Description
The present invention will be described in further detail with reference to the accompanying fig. 1-14.
The embodiment of the application discloses a temporary flood prevention wall for urban buildings, which comprises a flood prevention wall 1 and a base 2, and is shown in the figures 1 and 9; flood prevention wall 1 encloses to close the setting in the building main part 100 outside, and flood prevention wall 1 includes used flood prevention board 12 between stand 11 and the adjacent stand 11, and the stand 11 bottom surface is equipped with base 2, and base 2 is pre-buried in ground 200 surperficial below and base 2 lower part is equipped with concrete foundation 300, and stand 11 includes that straight line connects used straight-connecting stand 111 and corner and is connected used angle even stand 112.
Compared with the prior art, the flood control wall 1 is used for installing the temporary flood control wall of the urban building on the outer side of the building main body 100, so that the building main body 100 is effectively separated from flood before flood control, the flood is effectively prevented from entering a building basement and a first floor, and property loss caused by the flood and influence on life of people are reduced.
Referring to fig. 4, the direct-connected upright post 111 includes a first circular bottom plate 1111, two first mounting grooves 1113 formed at two opposite positions of the first upright post 1112 and the first upright post 1112, the first circular bottom plate 1111 is disposed on the bottom surface of the first upright post 1112, and a first screw 1114 is welded on the first circular bottom plate 1111 in the middle of the first mounting groove 1113.
Referring to fig. 7, the corner connecting pillar 112 includes a second circular bottom plate 1121, a second pillar 1122, and two second mounting grooves 1123 formed at the corner positions of the second pillar 1122, the second circular bottom plate 1121 is disposed on the bottom surface of the second pillar 1122, and a second screw 1124 is welded to the second circular bottom plate 1121 at the middle of the second mounting groove 1123.
Referring to fig. 2-3, 5-6 and 8, mounting holes 121 are formed in two ends of the flood prevention plate 12, when the flood prevention plate 12 is inserted into the first mounting groove 1113 of the direct-connected upright 111, the first screw 1114 penetrates through the mounting holes 121, the nut 3 is arranged on the top surface of the flood prevention plate 12 for fastening, and when the flood prevention plate 12 is inserted into the second mounting groove 1123 of the corner connecting upright 112, the second screw 1124 penetrates through the mounting holes 121 and the nut 3 is arranged on the top surface of the flood prevention plate 12 for fastening.
The flood prevention plates 12 are connected together through the direct-connected upright columns 111 and the angle-connected upright columns 112, so that the flood prevention wall 1 is formed, the installation is stable and fast, the flood prevention plates 12 are tightly attached to the ground 200, and a large gap is prevented between the flood prevention plates 12 and the ground 200.
Referring to fig. 2-7 and 9-10, three fixing holes 01 are uniformly distributed on the first circular bottom plate 1111 and the second circular bottom plate 1121, the fixing hole 01 of the first circular bottom plate 1111 and the first mounting groove 1113 are arranged in a staggered manner, the fixing hole 01 of the second circular bottom plate 1121 and the second mounting groove 1123 are arranged in a staggered manner, a screw hole 21 is formed in the top of the base 2, and the upright post 11 and the base 2 are fixed by a screw 4 penetrating through the fixing hole 01 to the screw hole 21, so that the upright post 11 and the base 11 are convenient to disassemble and assemble, and later-stage adjustment is facilitated.
Referring to fig. 3, 6 and 12, the bottom end of the flood prevention plate 12 is provided with an elastic rubber strip 5, the elastic rubber strip 5 is of a hollow structure, and both ends of the elastic rubber strip are provided with through holes 51, the first screw 1114 penetrates through the through holes 51 when the elastic rubber strip 5 is arranged in the first mounting groove 1113, and the second screw 1124 penetrates through the through holes 51 when the elastic rubber strip 5 is arranged in the second mounting groove 1123, so that the flood is greatly prevented from penetrating into the interior of the building main body 100 from the bottom of the flood prevention plate 12.
Referring to fig. 10-11, a triangular groove 22 is formed in the center of the bottom of the base 2, four rib plates 23 are further arranged on the periphery of the bottom of the base 2, the position of the screw hole 21 is matched with the position of the fixing hole 01 of the upright post 11 when the concrete foundation 300 is poured on the lower portion of the base 2, the installation strength of the base 2 is greatly enhanced, the phenomenon that the base 2 deviates is effectively avoided, and the phenomenon that the screw hole 21 of the base 2 cannot correspond to the fixing hole 01 of the upright post 1 in the later installation process is greatly reduced.
Referring to fig. 13-14, when the flood prevention wall is not used, the screw hole 21 at the top of the base 2 is provided with the screw 4 for sealing, so that inconvenience caused by blockage of the screw hole 21 by sundries in later use is avoided.
The above description is only a preferred embodiment of the present invention, and it should be noted that, for those skilled in the art, many modifications and substitutions can be made without departing from the technical principle of the present invention, and these modifications and substitutions should also be regarded as the protection scope of the present invention.

Claims (9)

1. The utility model provides a be used for interim flood prevention wall of city building which characterized in that: comprises a flood control wall (1) and a base (2); the flood control wall (1) is arranged on the outer side of the building main body (100) in a surrounding mode, and the flood control wall (1) comprises flood control plates (12) used between the stand columns (11) and the adjacent stand columns (11); the bottom surface of the upright post (11) is provided with a base (2), the base (2) is pre-embedded below the surface of the ground (200), and the lower part of the base (2) is provided with a concrete foundation (300); the upright columns (11) comprise straight connecting upright columns (111) for straight line connection and corner connecting upright columns (112) for corner connection.
2. The temporary flood control wall for the urban building according to claim 1, wherein the temporary flood control wall comprises: the straight-connected upright post (111) comprises a first circular bottom plate (1111), a first upright post (1112) and two first mounting grooves (1113) formed at two opposite positions of the first upright post (1112); the first circular bottom plate (1111) is arranged on the bottom surface of the first upright post (1112); a first screw (1114) is welded on the first circular bottom plate (1111) in the middle of the first mounting groove (1113).
3. The temporary flood control wall for the urban building according to claim 1, wherein the temporary flood control wall comprises: the corner connecting upright post (112) comprises a second circular bottom plate (1121), a second upright post (1122) and two second mounting grooves (1123) formed in the corner positions of the second upright post (1122); the second circular bottom plate (1121) is arranged on the bottom surface of the second upright post (1122); and a second screw (1124) is welded on the second circular bottom plate (1121) in the middle of the second mounting groove (1123).
4. The temporary flood control wall for the urban building according to claim 1, 2 or 3, wherein: mounting holes (121) are formed in the two ends of the flood control plate (12); when the flood prevention plate (12) is inserted into the first mounting groove (1113) of the direct-connected upright post (111), the first screw (1114) penetrates through the mounting hole (121), and the top surface of the flood prevention plate (12) is provided with a nut (3) for fastening; when the flood prevention plate (12) is inserted into the second mounting groove (1123) of the angle connection column (112), the second screw (1124) penetrates through the mounting hole (121) and the top surface of the flood prevention plate (12) is provided with a nut (3) for fastening.
5. The temporary flood control wall for the urban building according to claim 2, wherein the temporary flood control wall comprises: the first circular bottom plate (1111) and the second circular bottom plate (1121) are respectively provided with three fixing holes (01) which are uniformly distributed; the fixing hole (01) of the first circular bottom plate (1111) and the first mounting groove (1113) are arranged in a staggered mode; the fixing hole (01) of the second circular bottom plate (1121) and the second mounting groove (1123) are arranged in a staggered mode.
6. The temporary flood control wall for the urban building according to claim 1 or 5, wherein: the top of the base (2) is provided with a screw hole (21); the upright post (11) and the base (2) are fixed through a screw (4) penetrating through the fixing hole (01) to the screw hole (21).
7. The temporary flood control wall for the urban building according to claim 1 or 4, wherein: the bottom end of the flood prevention plate (12) is provided with an elastic rubber strip (5), the elastic rubber strip (5) is of a hollow structure, and two ends of the elastic rubber strip are provided with through holes (51); when the elastic rubber strip (5) is arranged in the first mounting groove (1113), the first screw (1114) penetrates through the through hole (51); when the elastic rubber strip (5) is arranged in the second mounting groove (1123), the second screw rod (1124) penetrates through the through hole (51).
8. The temporary flood control wall for the urban building according to claim 1, wherein the temporary flood control wall comprises: a triangular groove (22) is formed in the center of the bottom of the base (2), and four rib plates (23) are further arranged on the periphery of the bottom of the base (2); the position of the screw hole (21) is matched with the position of the fixing hole (01) of the upright post (11) when the concrete foundation (300) is poured at the lower part of the base (2).
9. The temporary flood control wall for the urban building according to claim 1 or 6, characterized in that: when the flood control wall (1) is not used, the screw hole (21) at the top of the base (2) is sealed by a screw (4).
CN202122303533.5U 2021-09-23 2021-09-23 Be used for interim flood control wall of city building Expired - Fee Related CN216663995U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122303533.5U CN216663995U (en) 2021-09-23 2021-09-23 Be used for interim flood control wall of city building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122303533.5U CN216663995U (en) 2021-09-23 2021-09-23 Be used for interim flood control wall of city building

Publications (1)

Publication Number Publication Date
CN216663995U true CN216663995U (en) 2022-06-03

Family

ID=81765388

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122303533.5U Expired - Fee Related CN216663995U (en) 2021-09-23 2021-09-23 Be used for interim flood control wall of city building

Country Status (1)

Country Link
CN (1) CN216663995U (en)

Similar Documents

Publication Publication Date Title
CN211714015U (en) House building structure built in underground space
CN216663995U (en) Be used for interim flood control wall of city building
CN210685158U (en) Improve prefabricated side fascia of stability
CN106760084B (en) Cable type semi-hidden frame glass curtain wall structure and glass curtain wall
CN206220649U (en) Construction guard fender
CN211735289U (en) Prefabricated formula culvert gate of irrigation and water conservancy
CN210342722U (en) Adjustable supporting device for assembly type building
CN210530504U (en) Multifunctional protective railing for construction site
CN210067011U (en) Assembled building convenient to installation
CN214996608U (en) Safety protection net is used in highway construction
CN217680479U (en) Building template convenient to installation
CN206015685U (en) A kind of Collapsible Loess District deep basal pit diaphram wall inner support system
CN204782128U (en) Sound arrester of transformer substation and overall structure of fire wall
CN219196289U (en) Wall post foot connection structure
CN218598126U (en) Novel ventilation window flood prevention baffle device
CN212053705U (en) Corner external corner connecting piece of horizontal truss
CN219316008U (en) Steel construction factory building
CN203284889U (en) Framework assembly of fast-mounted and dismountable house
CN213741586U (en) Novel steel structure building system
CN219773305U (en) Waterproof structure of curtain wall
CN204781366U (en) Basis post connection structure
CN219060516U (en) Gridding fixing structure for large-specification curtain wall aluminum plate
CN211690294U (en) Assembled underground continuous wall
CN216811061U (en) Concatenation formula construction material protector for municipal works
CN220266846U (en) Assembled beam slab column node structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220819

Address after: Intersection of Huayang Road and Changning Road, Northeast Xincheng, Susong County, Anqing City, Anhui Province, China (3rd Floor, Building 14, District D, Xincheng Garden)

Patentee after: Anhui Shize Construction Engineering Co.,Ltd.

Address before: 525141 Chetoupo Village No. 33, Dapeng, Hejiang Town, Maoming City, Guangdong Province

Patentee before: Zeng Lixia