CN216586387U - Liftable formula dykes and dams burst quick plugging device - Google Patents

Liftable formula dykes and dams burst quick plugging device Download PDF

Info

Publication number
CN216586387U
CN216586387U CN202122968612.8U CN202122968612U CN216586387U CN 216586387 U CN216586387 U CN 216586387U CN 202122968612 U CN202122968612 U CN 202122968612U CN 216586387 U CN216586387 U CN 216586387U
Authority
CN
China
Prior art keywords
breach
box body
rubber bag
liftable
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122968612.8U
Other languages
Chinese (zh)
Inventor
白建康
郝江平
房贤
党淑云
白玉虎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202122968612.8U priority Critical patent/CN216586387U/en
Application granted granted Critical
Publication of CN216586387U publication Critical patent/CN216586387U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/30Flood prevention; Flood or storm water management, e.g. using flood barriers

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a liftable rapid dam breach blocking device, the length of which is greater than the width of a dam breach, the device comprises a base, a box body and a rubber bag which are fixedly connected into a whole from bottom to top, and the box body is communicated with the inner cavity of the rubber bag; wherein, the box body is provided with at least one bottom through hole for filling or discharging flood. The utility model realizes automatic water filling of the rubber bag through the internal and external water pressure difference formed by flood impact, can quickly form a blocking structure at the breach of the dam, and can realize the purpose of temporarily intercepting the flood flow during the rescue of the breach of the dam without filling other materials. The utility model has the advantages of high installation speed, repeated use and good short-term plugging effect, can greatly reduce the harm of flood to the life safety and property safety of surrounding people on one hand, can avoid the influence of flood impact on the dike breach construction work on the other hand, and reduces the construction difficulty of dike breach plugging.

Description

Liftable formula dykes and dams burst quick plugging device
Technical Field
The utility model belongs to the technical field of emergency rescue, and particularly relates to a liftable type dam breach rapid plugging device.
Background
At present, for the breach of a dam, a flat plugging method, a vertical plugging method or a mixed plugging method is generally adopted for plugging emergency construction, and specific plugging modes such as sunken ship closure, sunken willow silt falling and the like are adopted in combination with specific situations. The flat plugging method comprises the steps of throwing and filling materials layer by layer upwards along the axis of a selected dam to meet the plugging requirement; the vertical blocking rule is that the construction is carried out gradually by starting from different sides of the port door and advancing towards the water along the axis of the dam so as to achieve the purpose of gradually reducing the port door; the mixed plugging method is a comprehensive mode of the two plugging modes.
However, the above methods consume too much manpower and material resources, and the entire breach must be robustly built to play a role, so that the building time is long (3-4 days at a high speed and 7-8 days at a low speed), and the efficiency is low. During the breach period, the life safety and property safety of people around the breach can be seriously affected by flood disasters.
SUMMERY OF THE UTILITY MODEL
In order to solve the defects in the prior art, the utility model aims to provide a lifting type dam breach rapid plugging device so as to achieve the purpose of timely relieving flood dangerous cases.
In order to achieve the purpose, the technical scheme adopted by the utility model is as follows: a lifting type dam breach rapid plugging device is longer than the width of a dam breach and comprises a base, a box body and a rubber bag which are fixedly connected into a whole from bottom to top, wherein the box body is communicated with the inner cavity of the rubber bag; wherein, the box body is provided with at least one bottom through hole for filling or discharging flood.
As the limitation of the utility model, a gate for controlling the opening and closing of the bottom through hole is fixedly arranged at the bottom through hole of the box body.
As a further limitation of the utility model, the gate comprises a gate body fixedly arranged at the through hole at the bottom of the box body, a hydraulic component for controlling the opening and closing of the gate body and a remote control component electrically connected with the hydraulic component.
As another limitation of the utility model, at least one top through hole is arranged at the top end of the rubber bag, and a hose with a valve is fixedly connected at the top through hole.
As a further limitation of the utility model, the rubber bladder is formed by a plurality of layers of rubber membranes with a circumferential structure and forms an integral sealing structure with the box body.
As a still further limitation of the utility model, a reinforcing plate frame is fixedly arranged on the outer side wall between every two adjacent rubber films.
As a further limitation of the utility model, both sides of the reinforcement panel frame are provided with loops for attachment of the cords.
As other limitations of the utility model, the base comprises a steel shell fixedly connected with the box body, and concrete filler poured in the steel shell; and the bottom end of the base is of a corrugated wedge structure.
Due to the adoption of the technical scheme, compared with the prior art, the utility model has the following beneficial effects:
(1) the utility model utilizes the rubber bag with the telescopic characteristic and forms the internal and external water pressure difference through the impact of flood to realize automatic water filling, can quickly form a blocking structure at the breach of the dam, and can realize the purpose of temporarily cutting off flood flow during the rescue of the breach of the dam without filling other materials. The utility model has fast installation speed and good short-term plugging effect, can greatly reduce the harm of flood to the life safety and property safety of people around, can avoid the influence of flood impact on the dike breach construction work, and reduces the construction difficulty of dike breach plugging.
(2) The base of the concrete filling structure can enable the device to sink into the bottom of a river channel quickly, and a foundation structure capable of resisting flood impact is constructed for the rubber bag. Wherein, the wavy wedge structure in base bottom can inlay in the riverbed silt, can further promote the steadiness of the foundation structure that forms.
(3) According to the utility model, the reinforcing plate frame is arranged between every two adjacent rubber membranes of the rubber bag, so that the integral rigidity of the rubber bag can be enhanced, the rubber bag can further resist the impact of flood, and the formed plugging structure is more stable and reliable.
(4) The rubber bag is composed of a rubber film with a flexible structure, and the two sides of the reinforcing plate frame can be connected with ropes through lantern rings. When the shape of the dike breach is irregular, the flexible membrane type rubber bag can still be tightly attached to the shape of the dike breach, so that the leakage point is reduced; in addition, in the process of lifting the rubber bag, workers can connect the rope by means of the lantern ring to adjust the deformation degree of the rubber bag at the bank edge, and further the rubber bag can be attached to a dike breach to be filled with water and lifted.
(5) The utility model can remotely control the opening and closing of the gate, and realize the control of the flood filling speed in the rubber bag by controlling the opening degree of the gate, thereby ensuring that the rubber bag can stably rise at a constant speed.
Drawings
The utility model is described in further detail below with reference to the figures and the embodiments.
FIG. 1 is a front view of an embodiment of the present invention in structural relationship;
FIG. 2 is a side view of the structural relationship of an embodiment of the present invention;
FIG. 3 is a front view showing the structural relationship between two sides of the rubber bladder after the rope is connected thereto in the embodiment of the present invention;
FIG. 4 is a front view of the structure of the embodiment of the present invention in a folded state;
in the figure: 1. a base; 2. a box body; 3. a rubber bladder; 4. a top via; 5. a hose; 6. a rope.
Detailed Description
Preferred embodiments of the present invention will be described below with reference to the accompanying drawings. It should be understood that the description of the preferred embodiment is only for purposes of illustration and understanding, and is not intended to limit the utility model.
Embodiment lifting type dam breach rapid plugging device
The embodiment is used as a prefabricated structural member, after a breach occurs in a dam dike, the embodiment can be installed at the breach position by means of equipment such as a helicopter, a crane and the like, and a temporary plugging structure is quickly formed at the breach, so that the development of flood disasters is effectively controlled.
The length of the embodiment is larger than the width of the dike breach, and the embodiment provides three prefabricated lengths of 8m, 10m and 20m according to the statistics of data of the dike breach width in the past year. As shown in fig. 1 to 2, the present embodiment includes a base 1, a box body 2 and a rubber bag 3 which are fixedly connected to a whole from bottom to top, and the box body 2 is communicated with an inner cavity of the rubber bag 3.
The base 1 is used for ensuring that the whole body of the embodiment can be quickly sunk to the bottom of a river channel, and comprises a steel shell and a concrete filler poured into the steel shell. Wherein, in order to make base 1 can stabilize on the riverbed, this embodiment sets up base 1 bottom as the wave wedge structure, specifically as shown in fig. 2, base 1 bottom surface is provided with a plurality of archs that the cross-section is inverted triangle-shaped to every bellied extending length all is located the length direction of base 1.
The box 2 is used for ensuring that flood can smoothly rush into the inner cavity of the rubber bag 3, as shown in figure 1 or figure 2, the box 2 is fixedly connected with the steel shell in the base 1 into a whole, the inside of the box is hollow and is communicated with the inner cavity of the rubber bag 3 above, and the side wall of the box is provided with at least one bottom through hole for filling or discharging flood. Wherein, the bottom through hole can be arranged on the long side wall of the box body 2 and also can be arranged on the short side walls at two sides of the box body 2.
In this embodiment, only one bottom through hole is formed in the box body 2 and located on the long side wall of the box body 2, and a gate for controlling the opening and closing of the bottom through hole is further fixedly arranged at the bottom through hole. More specifically, the gate includes a gate body, a hydraulic assembly, and a remote control assembly. The gate body is arranged on the side wall of the box body 2 in a fixing groove mode and can ascend or descend along the height direction of the box body 2; the hydraulic component is fixedly arranged on the box body 2, the stroke direction is positioned in the height direction of the box body 2, and the power output end is fixedly connected with the gate; the remote control assembly includes a mating receiver and remote control, and the receiver is electrically connected to the hydraulic assembly.
It should be noted that the hydraulic assembly in this embodiment adopts a hydraulic cylinder with an existing structure, and two sides and a middle portion of the gate body are respectively provided with one hydraulic cylinder.
Rubber bag 3 is the core structure that is used for realizing the shutoff of choking, as shown in fig. 1 or fig. 2, rubber bag 3 is formed by the flexible rubber membrane hot pressing of multilayer hoop structure, and at least one top through-hole 4 has been seted up on the top, and the bottom mounting sets up on box 2, forms overall seal structure with box 2. For the rigidity that promotes rubber bag 3 to a certain extent, the reinforcing plate frame that has all fixedly set up the metal material on the lateral wall between every adjacent two-layer rubber membrane in rubber bag 3 of this embodiment to, the both sides of reinforcing plate frame all are equipped with the lantern ring that is used for connecting rope 6.
In this embodiment, a top through hole 4 is formed at the top end of the rubber bag 3, and a hose 5 with a valve is fixedly connected to the top through hole 4.
As shown in fig. 4, in the natural state of non-use, the rubber bladder 3 in this embodiment is in a folded and contracted state. When the embodiment is used, firstly, a helicopter or a crane is used for hoisting the embodiment to the dike breach, and the two ends of the embodiment can be ensured to be abutted against the dikes at the two sides of the breach; when the embodiment is ensured to sink to the bottom of the river channel, and the end, with the valve, of the hose 5 at the through hole 4 in the top of the rubber bag 3 is kept and fixed on the bank, the gate is controlled to be opened through the remote control assembly, at the moment, flood can flow into the rubber bag 3 along the gate, and the rubber bag 3 slowly rises along with the filling of the flood, so that the breach of the dam is blocked. When the rubber bag 3 is filled with water until the height difference of flood inside and outside is not large, and the buoyancy force borne by the rubber bag 3 is not enough to support the top of the rubber bag 3 to extend out of the water surface, the hose 5 on the embankment can be communicated with an air source, and the rubber bag 3 is inflated through the hose 5, so that the top of the rubber bag 3 can extend out of the water surface by a certain height, and the breach can be plugged.
When the rubber bag 3 blocks the dike breach, the dike breach construction can be implemented. When the breach construction is finished and the embodiment is recycled, the embodiment is only required to be slowly hoisted by a helicopter or a crane, and water in the rubber bag 3 can be automatically discharged from the through hole at the bottom. After the embodiment is completely lifted out of the water surface, the water in the rubber bag 3 is drained, and the folding and shrinking state is recovered.
When the breach of the dam is irregular, the rubber bag 3 needs to be adjusted to deform and tightly fit with the dam in the lifting process of the rubber bag 3: before sinking the embodiment into the river course bottom, just connect a flexible rope 6 in the both sides of reinforcing sheet frame at every certain height to ensure that the embodiment sinks into the river course bottom after, the free end of flexible rope 6 can reserve on the bank, specifically as shown in fig. 3. Furthermore, during the process of filling water and lifting the rubber bag 3, the worker can adjust the rubber bag 3 to deform and tightly fit the breach of the dam by pulling the flexible ropes 6 on both sides.
Although the present invention has been described in detail with reference to the above embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described above, or equivalents may be substituted for elements thereof. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (8)

1. A liftable formula dykes and dams burst quick plugging device which characterized in that: the length of the device is larger than the width of a dike breach, the device comprises a base, a box body and a rubber bag which are fixedly connected into a whole from bottom to top, and the box body is communicated with the inner cavity of the rubber bag; wherein, the box body is provided with at least one bottom through hole for filling or discharging flood.
2. A liftable dike breach rapid plugging device according to claim 1, characterized in that: and a gate for controlling the opening and closing of the bottom through hole is fixedly arranged at the bottom through hole of the box body.
3. A liftable dike breach rapid plugging device according to claim 2, characterized in that: the gate comprises a gate body fixedly arranged at the through hole at the bottom of the box body, a hydraulic assembly used for controlling the opening and closing of the gate body and a remote control assembly electrically connected with the hydraulic assembly.
4. A liftable dike breach rapid plugging device according to any one of claims 1-3, wherein: at least one top through hole is formed in the top end of the rubber bag, and a hose with a valve is fixedly connected to the top through hole.
5. The liftable rapid dam breach blocking device according to claim 4, wherein: the rubber bag is composed of a plurality of layers of rubber films with annular structures and forms an integral sealing structure with the box body.
6. The liftable rapid dam breach blocking device according to claim 5, wherein: all set firmly the reinforcement sheet frame on the lateral wall between every adjacent two-layer rubber membrane.
7. The liftable rapid dam breach blocking device according to claim 6, wherein: both sides of the reinforcing plate frame are provided with lantern rings for connecting ropes.
8. A liftable dike breach rapid plugging device according to any one of claims 1-3 and 5-7, wherein: the base comprises a steel shell fixedly connected with the box body into a whole and concrete filler poured in the steel shell; and the bottom end of the base is of a corrugated wedge structure.
CN202122968612.8U 2021-11-30 2021-11-30 Liftable formula dykes and dams burst quick plugging device Active CN216586387U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122968612.8U CN216586387U (en) 2021-11-30 2021-11-30 Liftable formula dykes and dams burst quick plugging device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122968612.8U CN216586387U (en) 2021-11-30 2021-11-30 Liftable formula dykes and dams burst quick plugging device

Publications (1)

Publication Number Publication Date
CN216586387U true CN216586387U (en) 2022-05-24

Family

ID=81650635

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122968612.8U Active CN216586387U (en) 2021-11-30 2021-11-30 Liftable formula dykes and dams burst quick plugging device

Country Status (1)

Country Link
CN (1) CN216586387U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114000463A (en) * 2021-11-30 2022-02-01 白建康 Liftable formula dykes and dams burst quick plugging device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114000463A (en) * 2021-11-30 2022-02-01 白建康 Liftable formula dykes and dams burst quick plugging device

Similar Documents

Publication Publication Date Title
CN114000463A (en) Liftable formula dykes and dams burst quick plugging device
CN216586387U (en) Liftable formula dykes and dams burst quick plugging device
CN110565585B (en) Folding portable water filling surrounding well for piping rescue
CN110172990A (en) A kind of installation of offshore wind farm bucket foundation and recycling construction method
CN214613890U (en) Integral flexible water-filling surrounding well for piping emergency
CN111535246B (en) Construction method of wave-gathering breakwater facing structure poured by pouring mold
CN212248074U (en) Hydraulic self-lifting flood control wall
CN217480089U (en) Intelligent stagnant water is equipped suitable for dry basement cabin restoration equipment
CN111691447A (en) Slow sinking type caisson construction method for reducing load of immersed tube tunnel tube top
CN215210841U (en) Water conservancy dyke heightening structure
US7214003B1 (en) Segmental floating bulkhead assembly
CN213328918U (en) Plugging caisson and honeycomb type caisson combination comprising same
CN105714740B (en) Dyke fast blockage equipment
CN201172809Y (en) Flood-combating intelligent combination water proof wall
CN113136889B (en) Construction method of offshore box type prefabricated bearing platform
CN208121699U (en) A kind of lift shuts off caisson
CN110863502A (en) Construction method and plugging structure for dynamically adjusting foundation pit dewatering and plugging dewatering well
JP5669189B2 (en) Construction method of transmission type sea area control structure
CN212533972U (en) Dam deep hole underwater dynamic water flap valve closing device
KR100798630B1 (en) Water-proofing device of rotation type floodgate
CN108193645A (en) A kind of lift shuts off caisson
CN209836948U (en) A manger plate dam for hydraulic and hydroelectric engineering
CN221034648U (en) Hydraulic engineering pipeline protection casing
CN112458933B (en) Double-hole water diversion box culvert joining construction method
CN215211108U (en) Excavation-free steel drum cofferdam installation device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant