CN216558965U - Install at job site fixed survey observation device - Google Patents
Install at job site fixed survey observation device Download PDFInfo
- Publication number
- CN216558965U CN216558965U CN202122367610.3U CN202122367610U CN216558965U CN 216558965 U CN216558965 U CN 216558965U CN 202122367610 U CN202122367610 U CN 202122367610U CN 216558965 U CN216558965 U CN 216558965U
- Authority
- CN
- China
- Prior art keywords
- ring
- reinforcing
- rod
- fixedly connected
- observation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 55
- 238000010276 construction Methods 0.000 claims abstract description 17
- 238000005259 measurement Methods 0.000 claims abstract description 11
- 239000003351 stiffener Substances 0.000 claims description 20
- 238000000034 method Methods 0.000 abstract description 5
- 230000001932 seasonal effect Effects 0.000 abstract description 3
- 239000007787 solid Substances 0.000 abstract description 3
- 239000003550 marker Substances 0.000 abstract description 2
- 238000012544 monitoring process Methods 0.000 description 7
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000007711 solidification Methods 0.000 description 1
- 230000008023 solidification Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Images
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The utility model discloses a fixed measurement observation device installed on a construction site, which comprises a device shell, wherein concrete is poured inside the device shell, a baffle ring is fixedly connected to the upper side of an inner cavity of the device shell, a limiting ring is inserted at the upper end of the baffle ring through threads, the inner side wall of the limiting ring is fixedly connected with a fixing ring through a connecting rod, an observation marking rod is fixedly inserted in the middle of the fixing ring, a first reinforcing rod is fixedly connected to the middle of the lower end of the observation marking rod, and a reinforcing ring, a second reinforcing rod and a third reinforcing rod are arranged on the inner side of the device shell. Through the overall structure of equipment for the observation device position is not influenced by weather variation and seasonal variation, simultaneously, also is difficult for being influenced by the site operation process, can acquire comparatively accurate observation data. Through the structure that is equipped with spacing ring, connecting rod and solid fixed ring, the increase that can reach observes the stability that the marker pole is connected to and guarantee its vertical characteristic.
Description
Technical Field
The utility model relates to the technical field of construction, in particular to a fixed measurement observation device arranged on a construction site.
Background
The engineering monitoring means that in the construction process of a building structure, a monitoring instrument is adopted to monitor various control indexes of key parts, so that the safety and the reasonability of engineering construction can be checked and ensured; when the engineering monitoring is carried out at the monitoring value close to the control value, necessary control measures are taken to prevent safety accidents or engineering quality accidents in advance, so that the safety of a large number of workers and people is ensured, and the rationality of the construction engineering is ensured.
In the engineering monitoring process, due to the fact that monitoring point positions are unreasonable in arrangement, monitoring errors of different degrees exist due to factors such as position selection of an observation device, and the like, the fixed measurement observation device installed on a construction site is provided.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a fixed measurement observation device arranged on a construction site, so that the observation device is not influenced by weather change and seasonal change, is not easily influenced by the site construction process, and can acquire more accurate observation data.
The technical scheme includes that the fixed measurement observation device arranged on the construction site comprises a device shell, concrete is poured into the device shell, a baffle ring is fixedly connected to the upper side of an inner cavity of the device shell, a limiting ring is inserted into the upper end of the baffle ring through threads, a fixing ring is fixedly connected to the inner side wall of the limiting ring through a connecting rod, an observation mark rod is fixedly inserted into the middle of the fixing ring, a first reinforcing rod is fixedly connected to the middle of the lower end of the observation mark rod, and a reinforcing ring, a second reinforcing rod and a third reinforcing rod are arranged on the inner side of the device shell.
Preferably, the reinforcing ring is provided with a plurality of reinforcing rods, the inner side of the reinforcing ring is fixedly connected with six second reinforcing rods in an annular array mode, and a third reinforcing rod is fixedly connected between each second reinforcing rod and the corresponding first reinforcing rod.
Preferably, the third reinforcing bars are provided in plurality, and the third reinforcing bars are arranged at equal intervals between the respective second reinforcing bars and the first reinforcing bars.
Preferably, the reinforcing ring, the second reinforcing rod, the third reinforcing rod and the first reinforcing rod are all poured in the concrete, so that the strength of the poured concrete is increased.
Preferably, the lower parts of the limiting ring, the connecting rod and the fixing ring are poured in concrete.
Preferably, the device shell is a PVC pipe.
The utility model discloses a fixed measurement observation device installed on a construction site, which has the beneficial effects that:
through the overall structure of equipment for the observation device position is not influenced by weather variation and seasonal variation, simultaneously, also is difficult for being influenced by the site operation process, can acquire comparatively accurate observation data.
Through the structure that is equipped with spacing ring, connecting rod and solid fixed ring, the increase that can reach observes the stability that the marker pole is connected to and guarantee its vertical characteristic.
Through the structure that is equipped with beaded finish, second stiffener, third stiffener and first stiffener, can be so that the concrete intensity of the inside concreting of casing of device is higher, and increase equipment's life and intensity.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a cross-sectional view of the present invention;
FIG. 3 is an enlarged view of the utility model at A.
In the figure: 1 device casing, 2 spacing rings, 3 connecting rods, 4 solid fixed ring, 5 observation mark pole, 6 beaded finish, 7 second stiffener, 8 third stiffeners, 9 first stiffeners, 10 fender ring.
Detailed Description
The utility model will be further elucidated and described with reference to the embodiments and drawings of the specification:
referring to fig. 1-3, the present invention: a fixed measurement observation device installed on a construction site comprises a device shell 1, wherein the device shell 1 can enable poured concrete to be formed more conveniently, concrete is poured in the device shell 1, a baffle ring 10 is fixedly connected to the upper side of an inner cavity of the device shell 1, the baffle ring 10 can limit the depth of a limiting ring 2 inserted in the device shell 1, the upper end of the baffle ring 10 is inserted with the limiting ring 2 through threads, the limiting ring 2 and a connecting rod 3 are fixedly connected with a fixing ring 4, the fixing ring 4 is fixedly connected with an observation marking rod 5, the inner side wall of the limiting ring 2 is fixedly connected with a fixing ring 4 through the connecting rod 3, the fixing ring 4 can enable the observation marking rod 5 to be vertically arranged, the middle part of the fixing ring 4 is fixedly inserted with the observation marking rod 5, the observation marking rod 5 is vertically arranged, and is an observation device position of equipment, the lower extreme middle part fixedly connected with first stiffener 9 of observation mark pole 5, the inboard of device casing 1 is equipped with beaded finish 6, second stiffener 7 and third stiffener 8 beaded finish 6, second stiffener 7, third stiffener 8 and first stiffener 9 are all pour inside the concrete, and increase the concrete intensity of pouring.
As shown in fig. 2:
the beaded finish 6 is equipped with a plurality ofly, the inboard of beaded finish 6 is six second stiffeners 7 of annular array fixedly connected with, fixedly connected with third stiffener 8 between second stiffener 7 and the first stiffener 9. The first reinforcing bar 9 can increase the strength of the observation marking bar 5 when concrete is poured.
As shown in fig. 2:
the third reinforcing rods 8 are provided in plurality, and the third reinforcing rods 8 are arranged at equal intervals between the respective second reinforcing rods 7 and the first reinforcing rods 9. The connection of the reinforcing ring 6, the second reinforcing rod 7, the third reinforcing rod 8 and the first reinforcing rod 9 can increase the overall strength of the connected reinforcing steel bars, so that the strength of the cast concrete is increased.
As shown in fig. 2:
the reinforcing ring 6, the second reinforcing rod 7, the third reinforcing rod 8 and the first reinforcing rod 9 are all poured inside concrete, so that the strength of the poured concrete is increased.
As shown in fig. 1 and 2:
and the lower parts of the limiting ring 2, the connecting rod 3 and the fixing ring 4 are poured in concrete. The connection strength of the limiting ring 2, the connecting rod 3 and the fixing ring 4 can be increased by pouring the concrete.
As shown in fig. 1 and 2:
the device housing 1 is a PVC pipe. The PVC pipe adopts the existing pipeline on the market.
The principle is as follows: when the device is used, the observation device position is directly arranged on a foundation pit supporting crown beam to be monitored, the specific method is to intercept a PVC pipe with the normal service of 1500mm and the diameter of 200 mm, arrange 6C10@100 steel bars in the pipe in a circular shape and anchor the steel bars into the crown beam for 100mm, pour C30 concrete into the PVC pipe and embed the metal observation device position at the top, perform the protection work of the observation device position on site, and use the observation device after solidification.
The connection of the post-pouring reinforcing ring 6, the second reinforcing rod 7, the third reinforcing rod 8 and the first reinforcing rod 9 can increase the overall strength of the connected reinforcing steel bars, so that the strength of the poured concrete is increased, and the strength of the observation marking rod 5 can be increased when the concrete is poured by the first reinforcing rod 9.
Finally, it should be noted that the above embodiments are only used for illustrating the technical solutions of the present invention, and not for limiting the protection scope of the present invention, although the present invention is described in detail with reference to the preferred embodiments, it should be understood by those skilled in the art that modifications or equivalent substitutions can be made on the technical solutions of the present invention without departing from the spirit and scope of the technical solutions of the present invention.
Claims (6)
1. The utility model provides an install at job site fixed survey observation device, includes device casing (1), the inside pouring of device casing (1) has concrete, its characterized in that: the device is characterized in that a baffle ring (10) is fixedly connected to the upper side of an inner cavity of a shell (1), a limiting ring (2) is inserted into the upper end of the baffle ring (10) through threads, the inner side wall of the limiting ring (2) is fixedly connected with a fixing ring (4) through a connecting rod (3), an observation marking rod (5) is fixedly inserted into the middle of the fixing ring (4), a first reinforcing rod (9) is fixedly connected to the middle of the lower end of the observation marking rod (5), and a reinforcing ring (6), a second reinforcing rod (7) and a third reinforcing rod (8) are arranged on the inner side of the shell (1).
2. The fixed measurement observation device installed on a construction site according to claim 1, wherein: the reinforcing ring (6) is equipped with a plurality ofly, the inboard of reinforcing ring (6) is six second stiffeners (7) of annular array fixedly connected with, fixedly connected with third stiffener (8) between second stiffener (7) and first stiffener (9).
3. The fixed measurement observation device installed on a construction site according to claim 2, wherein: the third reinforcing rods (8) are arranged in plurality, and the third reinforcing rods (8) are arranged between the second reinforcing rods (7) and the first reinforcing rods (9) at equal intervals.
4. A fixed survey observation device installed at a construction site according to claim 1, 2 or 3, wherein: the reinforcing ring (6), the second reinforcing rod (7), the third reinforcing rod (8) and the first reinforcing rod (9) are all poured inside concrete, and the strength of the poured concrete is increased.
5. The fixed measurement observation device installed on a construction site according to claim 1, wherein: and the lower parts of the limiting ring (2), the connecting rod (3) and the fixing ring (4) are poured in the concrete.
6. The fixed measurement observation device installed at a construction site according to claim 5, wherein: the device shell (1) is a PVC pipe.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202122367610.3U CN216558965U (en) | 2021-09-28 | 2021-09-28 | Install at job site fixed survey observation device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202122367610.3U CN216558965U (en) | 2021-09-28 | 2021-09-28 | Install at job site fixed survey observation device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN216558965U true CN216558965U (en) | 2022-05-17 |
Family
ID=81567000
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202122367610.3U Expired - Fee Related CN216558965U (en) | 2021-09-28 | 2021-09-28 | Install at job site fixed survey observation device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN216558965U (en) |
-
2021
- 2021-09-28 CN CN202122367610.3U patent/CN216558965U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102493471B (en) | Suspending installation construction process method of structural foot margin anchor bolt | |
CN110629744B (en) | Construction process of steel pipe concrete pile of subway station | |
CN108643192A (en) | Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method | |
CN106245654A (en) | Deposited reinforced concrete pile exempts from inter-pile soil excavation construction method | |
CN209877824U (en) | Measuring device for vertical displacement of beam bridge superstructure | |
CN114809062A (en) | Integral bottom plate-integral vertical ring combined concrete bearing platform foundation and construction process thereof | |
CN216558965U (en) | Install at job site fixed survey observation device | |
CN114737602A (en) | Method for positioning concrete filled steel tube center column in cover-excavation top-down construction of subway station | |
CN109095351B (en) | Recoverable steel reinforcement cage hanging rib hoisting method | |
CN114215048A (en) | Large-diameter pile foundation reinforcement cage centering device | |
CN106193776A (en) | Chimney and the combinative structure of water tower and construction method thereof | |
CN112431193B (en) | Pile foundation steel reinforcement cage top centering location frock | |
CN109056808A (en) | Stake and steel pipe column construction method in a kind of subway station | |
CN112284362A (en) | Measuring device and method for verticality of steel casing in deep water area | |
CN217303964U (en) | A levelling point device that is used for linear measurement during cantilever to pour bridge construction | |
CN210263929U (en) | A preformed hole template for building civil engineering | |
CN108396734B (en) | Device for controlling pile top concrete pouring elevation of punched bored pile | |
CN109211464B (en) | Osmometer embedding device and method | |
CN217811023U (en) | Guide frame for positioning construction of foundation pit support structure upright post pile and lattice post | |
CN210827573U (en) | A template device for reverse construction method construction heavy-calibre well | |
CN108179749B (en) | Lattice column positioner and positioning method thereof | |
CN215857713U (en) | Long auger drilling fills steel reinforcement cage control auxiliary device | |
CN209399990U (en) | A kind of field surface observation pier structure | |
CN209799529U (en) | communication tower prefabricated base convenient for wiring | |
CN108411794B (en) | Precise positioning device and positioning method for positioning framework of spherical hinge under swivel bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20220517 |