CN108643192A - Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method - Google Patents

Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method Download PDF

Info

Publication number
CN108643192A
CN108643192A CN201810468093.9A CN201810468093A CN108643192A CN 108643192 A CN108643192 A CN 108643192A CN 201810468093 A CN201810468093 A CN 201810468093A CN 108643192 A CN108643192 A CN 108643192A
Authority
CN
China
Prior art keywords
column
steel
steel pipe
reinforcement cage
pipe column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810468093.9A
Other languages
Chinese (zh)
Inventor
王振威
赖锡强
高世泉
雷斌
刘晓宁
申伟伟
白朋朋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Gongkan Geotechnical Group Co Ltd
Original Assignee
Shenzhen Gongkan Geotechnical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Gongkan Geotechnical Group Co Ltd filed Critical Shenzhen Gongkan Geotechnical Group Co Ltd
Priority to CN201810468093.9A priority Critical patent/CN108643192A/en
Publication of CN108643192A publication Critical patent/CN108643192A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/665Mould-pipes or other moulds for making piles

Abstract

The present invention relates to the technical fields of Brace in Deep Footing Groove supporting ultralong steel tube column pile driving construction, disclose Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method, include the following steps:(1) rotary digging forms column stake holes;(2) steel reinforcement cage is put into stake holes, is fixed at aperture at the top of steel reinforcement cage;(3) lower end of steel pipe column is inserted into steel reinforcement cage, steel pipe column is welded and fixed with steel reinforcement cage;(4) in steel reinforcement cage top position only pulpboard is welded with around steel pipe column;(5) steel reinforcement cage and steel pipe column are transferred to stake holes, aperture will be fixed at the top of steel pipe column;(6) steel reinforcement cage and steel pipe column are put into completely in column stake holes, complete lifting, to carrying out filling concrete in steel reinforcement cage, then to carrying out filling concrete in steel pipe column, stand column pile is formd after concrete setting;Provide a kind of green, safe and efficient Brace in Deep Footing Groove supporting tubular steel post pile driving construction field joint, installation, in steel pipe post casting concrete pile construction method.

Description

Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method
Technical field
The present invention relates to the technical fields of Brace in Deep Footing Groove supporting ultralong steel tube column pile driving construction, especially Brace in Deep Footing Groove Supporting ultralong steel tube column pile construction method.
Background technology
When deep basal pit using support support form when, most of stand column pile of support construction be supporting steel pipe column or Reinforced concrete upright column.Concrete filled steel tube staking out compared with reinforced concrete upright column stake, have easy for construction, shock resistance it is strong, The advantages such as overall cost is low, it is convenient and reusable in supporting removal, meet green construction requirement.
In mega project practice of construction, the length of steel pipe column is often very long, is ultralong steel tube column, is required in work progress Steel pipe stanchion heart deviation is small, and verticality is smaller, to meet construction quality requirement.
In order to reach the design requirement of steel pipe post stake, making, the scene of ultralong steel tube column should be solved in practice of construction Splicing, precisely the critical processes operational issue such as lifting, degree control, pouring concrete within steel pipe.
In the prior art, a kind of green of shortage, safe and efficient Brace in Deep Footing Groove supporting tubular steel post pile driving construction scene are right Connect, install, in steel pipe post casting concrete pile construction method.
Invention content
The purpose of the present invention is to provide Brace in Deep Footing Groove supporting ultralong steel tube column pile construction methods, it is intended to solve existing The problem of lacking a kind of efficient Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method in technology.
The invention is realized in this way Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method, the stand column pile packet Include bored concrete pile part and the top positioned at the bored concrete pile part and the steel tube concrete pile that is connect with the bored concrete pile part Part, the construction method include the following steps:
(1), using Spiral digging machine column stake holes is formed in designated position rotary digging;
(2), the reinforcing bar cage hoisting finished will be made to be put into the column stake holes, the top of the steel reinforcement cage is temporarily solid It is scheduled at the aperture of the column stake holes;
(3), the steel pipe column finished will be made to lift to the aperture of the column stake holes, by the lower end of the steel pipe column Be inserted into the steel reinforcement cage, and at this point, the upper-end part of driving of the steel pipe column in the top of the steel reinforcement cage, by the steel pipe column with The steel reinforcement cage is welded and fixed;
(4), the only pulpboard overflowed for stopping concrete grout, the only pulpboard are welded in the steel reinforcement cage top position It is arranged around the periphery of the steel pipe column;
(5), after the completion of the only pulpboard welding, the steel reinforcement cage being integrated will be welded and fixed and continued toward institute with steel pipe column Decentralization in column stake holes is stated, and will be temporarily fixed at the top of the steel pipe column at the aperture of the column stake holes;
(6), the steel reinforcement cage being integrated will be welded and fixed and steel pipe column carries out installation positioning and will be welded after installation positioning It connects the steel reinforcement cage being fixed as one to be put into completely with steel pipe column in the column stake holes, completes lifting;First toward the column Concrete perfusion in steel reinforcement cage in stake holes, then the concrete perfusion in the steel pipe column in the column stake holes, the steel reinforcement cage The bored concrete pile part of the stand column pile is formed after interior concrete setting, after the concrete setting in the steel pipe column described in formation The steel tube concrete pile part of stand column pile.
Further, in step (3), the periphery of the steel pipe column is disposed with multigroup dowel group, multigroup connection For muscle group along the axially-spaced arrangement of the steel pipe column, the dowel group includes the more peripheries for being looped around the steel pipe column Dowel welds the dowel with the steel reinforcement cage with steel pipe column respectively, realizes that the steel pipe column is welded with the steel reinforcement cage Connect fixation.
Further, the only pulpboard be provided with it is multiple for gush by and prevent on mud concrete coarse aggregate by it is logical Hole.
Further, in step (2), the steel reinforcement cage finished is made by the sub- fixed shape of steel reinforcement cage section docking of multistage At docking fixing means is:One section of sub- steel reinforcement cage section is lifted to the column stake holes, by the cross-talk steel reinforcement cage section Top is temporarily fixed at the aperture of the column stake holes, and the next section of sub- steel reinforcement cage section is lifted to the column stake holes At aperture, by two sections of sub- steel reinforcement cage sections, vertically fixed docking, the entirety formed after docking continue in the column stake holes Decentralization, and will be temporarily fixed at the aperture of the column stake holes at the top of the next section of sub- steel reinforcement cage section;Sequentially operate with Upper step, until the sub- steel reinforcement cage section docking of the multistage for completing entire steel reinforcement cage.
Further, it in step (3), makes the steel pipe column finished and is docked by more steel-pipe weldings and formed, more Steel pipe docking on splicing platform forms the steel pipe column;The splicing platform includes the support of the spaced and parallel arrangement of multiple tracks Frame, the steel pipe are placed on perpendicular to the extending direction of support frame as described above on multiple tracks support frame as described above, the both ends of support frame as described above It is provided with the baffle for preventing roller from tumbling.
Further, it is 2 that the welding between the more steel pipes, which uses carbon-dioxide arc welding welding manner, weld seam grade, Grade, the weld seam carry out anticorrosion with painting processing.
Further, in step (1), the down-set shield for being useful for preventing collapse hole at the aperture of the column stake holes Cylinder.
Further, in step (6), the peripheral ring on the steel pipe column top around more bendings spacer bar, it is more A spacer bar is welded with the periphery of the steel pipe column respectively, and the spacer bar is connected to the inner wall of the casing, real The positioning of the steel reinforcement cage and steel pipe column that are now fixed as one.
Further, joint bar is welded at the top of the steel pipe column, the joint bar makes the top and first of the stand column pile Road supporting beam connection.
Further, it is connected with hangs muscle lifting lug at the top of the steel pipe column, the hangs muscle lifting lug includes lifting lug and along institute The hangs muscle that the length direction of lifting lug extends downwardly is stated, the hangs muscle welds the steel pipe column, and the lifting lug is hollow to form rectangular lead to Hole when the rod is placed on the casing, realizes the interim solid of the steel pipe column when the rod insertion square through hole It is fixed.
Compared with prior art, Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method provided by the invention, provides A kind of green, installation, is poured in steel pipe post safe and efficient Brace in Deep Footing Groove supporting tubular steel post pile driving construction field joint The construction method for building concrete pile, solve ultralong steel tube column making, scene splicing, precisely lifting, degree control, The operational issue of the critical processes such as pouring concrete within steel pipe improves the pile quality of stand column pile, meets quality requirement, improves Construction efficiency.
Description of the drawings
Fig. 1 is the construction process of Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method provided in an embodiment of the present invention Schematic diagram;
Fig. 2 is that schematic diagram is fixed in the docking of steel reinforcement cage and steel pipe column provided in an embodiment of the present invention;
Fig. 3 is the schematic diagram of the steel reinforcement cage being welded and fixed and erection of steel pipe column positioning provided in an embodiment of the present invention;
Fig. 4 is the schematic diagram of the steel reinforcement cage being welded and fixed and steel pipe column rigging out provided in an embodiment of the present invention;
Fig. 5 is concrete perfusion schematic diagram in steel reinforcement cage provided in an embodiment of the present invention;
Fig. 6 is concrete perfusion schematic diagram in steel pipe column provided in an embodiment of the present invention.
Specific implementation mode
In order to make the purpose , technical scheme and advantage of the present invention be clearer, with reference to the accompanying drawings and embodiments, right The present invention is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, and It is not used in the restriction present invention.
The same or similar label correspond to the same or similar components in the attached drawing of the present embodiment;In description of the invention In, it is to be understood that if there is the orientation or positional relationship of the instructions such as term "upper", "lower", "left", "right" for based on attached drawing institute The orientation or positional relationship shown, is merely for convenience of description of the present invention and simplification of the description, and does not indicate or imply the indicated dress It sets or element must have a particular orientation, with specific azimuth configuration and operation, therefore the use of position relationship described in attached drawing Language only for illustration, should not be understood as the limitation to this patent, for the ordinary skill in the art, can be with The concrete meaning of above-mentioned term is understood as the case may be.
The realization of the present invention is described in detail below in conjunction with specific embodiment.
Referring to Fig.1 shown in -6, preferred embodiment is provided for the present invention.
Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method provided in this embodiment, for solving in the prior art The problem of lacking a kind of efficient Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method.
200 construction method of Brace in Deep Footing Groove supporting ultralong steel tube stand column pile, stand column pile 200 include bored concrete pile part 210 with And the top positioned at bored concrete pile part 210 and the steel tube concrete pile part 220 that is connect with bored concrete pile part 210, construction method Include the following steps:
(1), using Spiral digging machine 200 hole 100 of stand column pile is formed in designated position rotary digging;
(2), the lifting of steel reinforcement cage 110 finished will be made to be put into 200 hole 100 of stand column pile, the top of steel reinforcement cage 110 is faced When be fixed at the aperture in 200 hole 100 of stand column pile;
(3), it will make at the lifting to the aperture in 200 hole 100 of stand column pile of steel pipe column 120 finished, it will be under steel pipe column 120 End is inserted into steel reinforcement cage 110, and at this point, the upper-end part of driving of steel pipe column 120 in the top of steel reinforcement cage 110, by steel pipe column 120 with Steel reinforcement cage 110 is welded and fixed;
(4), the only pulpboard 130 overflowed for stopping concrete grout is welded in 110 top position of steel reinforcement cage, only pulpboard 130 around the periphery of steel pipe column 120 arrangement;
(5), stop pulpboard 130 weld after the completion of, will be welded and fixed the steel reinforcement cage 110 being integrated continued with steel pipe column 120 it is past Decentralization in 200 hole 100 of stand column pile, and the top of steel pipe column 120 is temporarily fixed at the aperture in 200 hole 100 of stand column pile;
(6), the steel reinforcement cage 110 being integrated will be welded and fixed and steel pipe column 120 carries out installation positioning, it, will after installation positioning It is welded and fixed the steel reinforcement cage 110 being integrated to be put into completely in 200 hole 100 of stand column pile with steel pipe column 120, completes lifting;First toward vertical Concrete perfusion in steel reinforcement cage 110 in 200 hole 100 of stanchion, then the interior perfusion of steel pipe column 120 in 200 hole 100 of stand column pile are mixed It is solidifying native, the bored concrete pile part 210 of stand column pile 200, the coagulation in steel pipe column 120 are formed after the concrete setting in steel reinforcement cage 110 The steel tube concrete pile part 220 of stand column pile 200 is formed after soil solidification.
200 construction method of Brace in Deep Footing Groove supporting ultralong steel tube stand column pile of above-mentioned offer provides a kind of green, peace Entirely, efficient Brace in Deep Footing Groove supporting tubular steel post pile driving construction field joint, installation, casting concrete pile in steel pipe post Construction method, solve the making of ultralong steel tube column, scene splicing, precisely lifting, degree control, coagulation is perfused in steel pipe The operational issue of the critical processes such as soil improves the pile quality of stand column pile 200200, meets quality requirement, improves construction effect Rate.
Specifically, in step (3), the periphery of steel pipe column 120 is disposed with 140 groups of multigroup dowel, multigroup dowel 140 For group along the axially-spaced arrangement of steel pipe column 120,140 groups of dowel includes the connection of the more peripheries for being looped around steel pipe column 120 Muscle 140 welds dowel 140 with steel reinforcement cage 110 with steel pipe column 120 respectively, realizes that steel pipe column 120 is welded with steel reinforcement cage 110 It is fixed.
Furthermore only pulpboard 130 be provided with it is multiple for gushed on mud by and prevent concrete coarse aggregate by through-hole.
In the present embodiment, in step (2), makes the steel reinforcement cage 110 finished and fixed by the 110 sections of docking of the sub- steel reinforcement cage of multistage It is formed, docking fixing means is:One cross-talk steel reinforcement cage is lifted to 200 holes 100 of stand column pile for 110 sections, by the cross-talk steel reinforcement cage 110 sections of top is temporarily fixed at the aperture in 200 hole 100 of stand column pile, by 110 sections of liftings of next cross-talk steel reinforcement cage to stand column pile At the aperture in 200 holes 100, by two cross-talk steel reinforcement cages, 110 sections of vertical fixed docking, the entirety formed after docking continues toward stand column pile Decentralization in 200 holes 100, and the top of 110 sections of next cross-talk steel reinforcement cage is temporarily fixed at the aperture in 200 hole 100 of stand column pile; Above step is sequentially operated, until completing 110 sections of docking of the sub- steel reinforcement cage of multistage of entire steel reinforcement cage 110.
It in step (3), makes the steel pipe column 120 finished and is docked by more steel-pipe weldings and formed, more steel pipes are splicing Docking forms steel pipe column 120 on platform;Splicing platform includes the supporting rack of the spaced and parallel arrangement of multiple tracks, and steel pipe is perpendicular to supporting rack Extending direction be placed on multiple tracks supporting rack, the baffle of supporting rack being provided at both ends with for preventing roller from tumbling.
Specifically, it is 2 grades that the welding between more steel pipes, which uses carbon-dioxide arc welding welding manner, weld seam grade, weldering Seam carries out anticorrosion with painting processing.
It is down-set at the aperture in 200 hole 100 of stand column pile to be useful for preventing collapse hole in step (1) in the present embodiment Casing 150.
In step (6), the peripheral ring on 120 top of steel pipe column is around the spacer bar 160 of more bendings, multiple positioning steel Muscle 160 is welded with the periphery of steel pipe column 120 respectively, and spacer bar 160 is connected to the inner wall of casing 150, and realization is fixed as one Steel reinforcement cage 110 and steel pipe column 120 positioning.
Furthermore the top of steel pipe column 120 is welded with joint bar 170, and joint bar 170 makes the top of stand column pile 200 and first Support beam connection.
The top of steel pipe column 120 is connected with 180 lifting lug 190 of hangs muscle, and 180 lifting lug 190 of hangs muscle includes that lifting lug 190 and edge are hung The hangs muscle 180 that the length direction of ear 190 extends downwardly, 180 welded still pipe column 120 of hangs muscle, lifting lug 190 is hollow to form rectangular lead to Hole when rod is placed on casing 150, realizes being fixed temporarily for steel pipe column 120 when rod insertion square through hole.
In the past for extra large comprehensive transportation hub project:
In preceding extra large comprehensive transportation hub project, the structure design basement number of plies is 6 layers, and excavation of foundation pit depth reaches 31.7m, Foundation Pit Support Design uses+6 road concrete support of diaphram wall, support post that foundation pit bottom or less is used to be perfused for φ 1.6m φ 0.9m steel core concrete columns more than stake, foundation pit bottom to be inserted into bored concrete pile.
This project steel pipe column 120 length about 31.45m, weighs about 20t, is ultralong steel tube column, design requirement column is in per pass Position deviation ± the 20mm of reservation member, 120 heart deviation ± 50mm of steel pipe column, verticality is supported to be not more than 0.5%.
This project construction technology process is as follows:
1,200 spiral-digging pore of stand column pile
200 pore-forming of this project stand column pile uses Spiral digging machine pore-forming.Since the design function of this project stand column pile 200 is resistance to compression And resistance to plucking, 200 hole of stand column pile, 100 depth 70m, enter middle differentiation sial 3m, bottom hole sediment thickness is≤50mm, verticality requirement Height, bottom hole slagging thickness requirement is high, and difficulty of construction is big.
In order to solve the above problem, pore-forming is carried out using precious high BG46 types Spiral digging machine, which reaches 111.2m, power head peak torque are 460KN/M, and precision is high, and construction efficiency is high, ensures its hole quality.
This project place is in reclaimation area, complex geologic conditions, and 3m below earth's surface is 8~10m thick mud layers, under mud For 3~5m thick sand beds, to ensure that 200 hole quality of stand column pile, aperture place the steel pile casting 150 of diameter phi 1.8m, long 18m.At Hole is crept into using rotary digging, is constructed to middle weathered granite face, then using " major diameter rotary digging bored concrete pile hard rock is classified reaming engineering method " (provincial engineering method GDGF091-2014) is improved into 200 hole of stand column pile, 100 efficiency;Secondary pile hole cleaning is using " rotary digging bored concrete pile is without mud Circulation secondary borehole cleaning engineering method " (provincial engineering method GDGF091-2014) enters the next step after qualified.
2,110 aperture of steel reinforcement cage lifts
(1) steel reinforcement cage 110 makes
Since 200 hole 100 of stand column pile is as deep as 70m, 200 foundation pit bottom steel reinforcement cage of stand column pile, 110 length about 40m, design requirement 110 cage main reinforcement of steel reinforcement cage be 36C25, cover to reinforcement thickness 70mm, 110 overall weight of steel reinforcement cage reach 6.5t.
Since the length of steel reinforcement cage 110, weight are big, to prevent steel reinforcement cage 110 from deforming in making, transport, hoisting process, this item Mesh is docked per segment length about 20m in aperture during practice of construction, using sectional making steel reinforcement cage 110.
(2) 110 aperture of steel reinforcement cage lifts
Steel reinforcement cage 110 makes, after the completion of stake holes, is segmented and is lifted by crane to steel reinforcement cage 110 using 80t crawler cranes, in hole Mouth welding spreading, the verticality and pile position deviation for ensuring steel reinforcement cage 110 using protective layer reach design requirement, steel reinforcement cage 110 It is put into stake holes (the long L-3 of stake) m, is fixed on aperture.
3, steel pipe column 120 lifts by crane
(1) 120 processing and fabricating of steel pipe column
200 steel pipe of stand column pile requires precisely with supporting beam connecting joint structure complexity, docking location, including tension steel plate, The built-in fittings such as anti-shear steel plate, steel corbel.
Due to 120 long 31.45m of finished steel tubing string, it is unfavorable for transporting, by special Gang Gou factories according to design requirement point two Section makes.
(2) the interior homogeneous tube splicing of steel pipe column 120
It needs to carry out homogeneous tube splicing after the transport to construction site of steel pipe column 120.To ensure field joint quality, at the construction field (site) Process special column steel pipe splicing platform.
Splicing platform is integrally made of 6 supporting racks, and it is true to regard steel pipe embedded part design requirement for spacing between per pass supporting rack Fixed, supporting rack can be accommodated 2 steel pipe columns 120 and be rolled work on platform by I-steel processing and fabricating, the wide 6m of per pass supporting rack Industry facilitates site welding, avoids welding in the overhead position, and improves working efficiency and welding quality.Every one of supporting rack absolute altitude is consistent, side board It is on same vertical plane and vertical with platform level, it is whole to carry out steel pipe column 120 using the vertical method in two points one lines, section Splicing ensures that two sections of steel pipe central axis are on same line when steel pipe column 120 docks, is integrally hung down with reaching after column steel pipe docks Straight degree meets the standard of design requirement.
The splicing of 120 homogeneous tube of steel pipe column is hung to platform by first segment steel pipe column 120 is flat using crawler crane, is close to side Baffle and fixation recycle crawler crane, and second segment steel pipe column 120 is close to platform side baffle by auxiliary manpower, and makes two Section steel pipe column 120 splices tight-lipped patch, then fixes;After the completion of alignment, to be welded using carbon-dioxide arc welding, weld seam grade is 2 grades, Weld seam is done into anticorrosion with painting processing after qualification to be detected.
(3) steel pipe column 120 lifts by crane
To ensure its lifting safety, using hanging based on 130t crawler cranes, 80t crawler cranes hang for pair, major-minor double-machine lifting crane Method, in the air it is complete it is in 90 ° turn round, after by it is main hang hang vertically it is vertical.
4, steel pipe column 120 is fixed with 110 aperture of steel reinforcement cage
(1) steel pipe column 120 lifts in place
Steel pipe column 120 is hung to orifice position, steel pipe column 120 is inserted into 110 projected depth of steel reinforcement cage by design requirement 3.5m starts the welding of steel pipe column 120 and steel reinforcement cage 110.
(2) steel pipe column 120 is fixed with steel reinforcement cage 110
After steel reinforcement cage 110 is inserted into steel perfusion, it is welded to connect muscle 140 in inserting paragraph, keeps steel pipe column 120 solid with steel reinforcement cage 110 It is fixed.Dowel 140 is arranged twice altogether, spacing 2m, and per pass is by being welded on the connection steel of 120 conplane four direction of steel pipe column Muscle forms, and connection rebar sizes are steel pipe column 120 and 110 spacing of steel reinforcement cage.
(3) stop the installation of pulpboard 130
After the completion of steel pipe column 120 is fixed with steel reinforcement cage 110, in 110 top position of steel reinforcement cage, welding one stops pulpboard 130 (the thick ring-like steel plates of 4mm), only reserves certain amount, it is thick both to have can effectively prevent concrete for the circular hole of a diameter of 25mm on pulpboard 130 Aggregate passes through, but can facilitate mud on gush, cause streaming for concrete when avoiding pouring concrete and generate the waste of concrete.
Reinforcing bar continues to transfer steel pipe column 120 after the completion of stopping the welding of pulpboard 130, and steel pipe column 120 is transferred to hole completely, and is faced When be fixed on aperture.
5, steel pipe column 120 and 110 integral installation of steel reinforcement cage and positioning
The whole positioning of steel pipe column 120 and steel reinforcement cage 110 mainly by 120 top setting spacer bar 160 of steel pipe column, in advance The joint bar 170 of making, improve after hangs muscle 180 solve.
(1) spacer bar 160 is set
According to the repetition measurement to 120 positions of steel pipe column as a result, making spacer bar 160;In the 120 top positions 0.5m of steel pipe column Four direction weld spacer bar 160, come the plan-position that steel pipe column 120 is final in control hole.
(2) joint bar 170 is set
For the elevation location of 120 built-in fitting of precise positioning steel pipe column, and make the top of stand column pile 200 and first of supporting beam essence Quasi- connection, this project are provided with joint bar 170 on the top of steel pipe column 120.
Mark is carried out in a 170 top wherein reinforcing bar of joint bar, tapping top rib portion can measure in steel pipe according to reinforcing bar length Capital absolute altitude after the completion of the decentralization of column 120.After joint bar 170 is provided with, the next step is carried out.
(3) hangs muscle 180 after setting improvement
It due to traditional 180 lifting lug 190 of hangs muscle, is process using round steel, since 120 weight of steel pipe column reaches 20t, is being hung During dress, lifting lug 190 is easily deformed, is stretched, and leads to 120 integral sinking of steel pipe column, and it is bad adopt remedial measures, make At built-in fitting position deviation, so using improved hangs muscle 180, it can ensure 190 integral rigidity of lifting lug, avoid due to lifting lug 190 Deformation causes the deviation of the position vertical direction of built-in fitting.
Hangs muscle 180 calculates length, make after, be welded on the top of steel pipe column 120, crawler crane is hung on lifting lug 190 120 entirety of steel pipe column is put into stake holes by the hole of setting.It is fixed using rod.Absolute altitude repetition measurement is carried out to joint bar 170 again, really It is accurate to protect steel pipe embedded part elevation location.
6, first time foundation pit bottom cast-in-place pile concrete is perfused
After the completion of steel pipe column 120 and 110 integral installation of steel reinforcement cage and positioning, first to foundation pit bottom bored concrete pile part 210 into Row filling concrete;When perfusion, 288 tremies 300 of Φ are selected, it is 30mm~50mm above that expects pipe is stretched into stake holes bottom It sets, using traditional snag filling concrete technology, at filling concrete to the above 1m of stake top absolute altitude.
After the completion of 210 filling concrete of bored concrete pile part, about 1h or so, before waiting for concrete not yet initial set, slump part After loss, 120 inside points concrete casting of steel pipe column can be carried out.
7, pile is perfused in second of 120 inner concrete of steel pipe column
Perfusion conduit bottom is pulled up to more than 120 bottom of steel pipe column, 2m or so below concrete absolute altitude starts to pour steel Concrete in tube column;It is acted on due to stopping pulpboard 130 so that high above, the 120 outside concrete of steel pipe column of bored concrete pile top mark is not It will produce floating.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention All any modification, equivalent and improvement etc., should all be included in the protection scope of the present invention made by within refreshing and principle.

Claims (10)

1. Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method, which is characterized in that the stand column pile includes bored concrete pile portion Point and the top positioned at the bored concrete pile part and the steel tube concrete pile part that is connect with the bored concrete pile part, it is described to apply Work method includes the following steps:
(1), using Spiral digging machine column stake holes is formed in designated position rotary digging;
(2), the reinforcing bar cage hoisting finished will be made to be put into the column stake holes, will be temporarily fixed at the top of the steel reinforcement cage At the aperture of the column stake holes;
(3), the steel pipe column finished will be made to lift to the aperture of the column stake holes, the lower end of the steel pipe column is inserted into In the steel reinforcement cage, and at this point, the upper-end part of driving of the steel pipe column in the top of the steel reinforcement cage, by the steel pipe column with it is described Steel reinforcement cage is welded and fixed;
(4), the only pulpboard overflowed for stopping concrete grout is welded in the steel reinforcement cage top position, the only pulpboard is surround The periphery of the steel pipe column is arranged;
(5), after the completion of the only pulpboard welding, the steel reinforcement cage being integrated will be welded and fixed and continued toward described vertical with steel pipe column It transfers, and will be temporarily fixed at the top of the steel pipe column at the aperture of the column stake holes in stanchion hole;
(6), the steel reinforcement cage being integrated will be welded and fixed and steel pipe column carries out installation positioning, it is after installation positioning, welding is solid It is set to the integrated steel reinforcement cage to be put into completely with steel pipe column in the column stake holes, completes lifting;First toward the column stake holes Concrete perfusion in interior steel reinforcement cage, then the concrete perfusion in the steel pipe column in the column stake holes, in the steel reinforcement cage The bored concrete pile part of the stand column pile is formed after concrete setting, and the column is formed after the concrete setting in the steel pipe column The steel tube concrete pile part of stake.
2. Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method as described in claim 1, which is characterized in that in step (3) in, the periphery of the steel pipe column is disposed with multigroup dowel group, axial phase of multigroup dowel group along the steel pipe column Arranged for interval, the dowel group include the dowel of the more peripheries for being looped around the steel pipe column, and the dowel is distinguished It is welded with steel pipe column with the steel reinforcement cage, realizes that the steel pipe column is welded and fixed with the steel reinforcement cage.
3. Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method as claimed in claim 2, which is characterized in that described to stop Pulpboard be provided with it is multiple for gushed on mud by and prevent concrete coarse aggregate by through-hole.
4. Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method as claimed in claim 3, which is characterized in that in step (2) it in, makes the steel reinforcement cage finished and is formed by the sub- steel reinforcement cage section docking fixation of multistage, docking fixing means is:By one section The sub- steel reinforcement cage section is lifted to the column stake holes, will be temporarily fixed at the stand column pile at the top of the cross-talk steel reinforcement cage section At the aperture in hole, the next section of sub- steel reinforcement cage section is lifted to the aperture of the column stake holes, by two sections of sub- reinforcing bars The vertically fixed docking of cage section, the entirety formed after docking continue to transfer toward in the column stake holes, and by the next section of sub- steel It is temporarily fixed at the top of muscle cage section at the aperture of the column stake holes;Above step is sequentially operated, until completing entire reinforcing bar The sub- steel reinforcement cage section docking of multistage of cage.
5. Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method as claimed in claim 4, which is characterized in that in step (3) it in, makes the steel pipe column finished and is docked by more steel-pipe weldings and formed, the more steel pipes dock on splicing platform Form the steel pipe column;The splicing platform includes the supporting rack of the spaced and parallel arrangement of multiple tracks, and the steel pipe is perpendicular to the branch The extending direction of support is placed on multiple tracks support frame as described above, and support frame as described above is provided at both ends with for preventing roller from tumbling Baffle.
6. Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method as claimed in claim 5, which is characterized in that more institutes It is 2 grades to state the welding between steel pipe and use carbon-dioxide arc welding welding manner, weld seam grade, and the weld seam carries out anticorrosion with painting Processing.
7. Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method as claimed in claim 6, which is characterized in that in step (1) in, the down-set casing for being useful for preventing collapse hole at the aperture of the column stake holes.
8. Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method as claimed in claim 7, which is characterized in that in step (6) in, the peripheral ring on the steel pipe column top around more bendings spacer bar, multiple spacer bars respectively with it is described The periphery of steel pipe column is welded, and the spacer bar is connected to the inner wall of the casing, realizes the steel reinforcement cage being fixed as one And the positioning of steel pipe column.
9. Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method as claimed in claim 8, which is characterized in that the steel Joint bar is welded at the top of tubing string, the joint bar makes the top of the stand column pile be connect with first of supporting beam.
10. Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method as described in any one of claims 1-9, feature It is, hangs muscle lifting lug is connected at the top of the steel pipe column, and the hangs muscle lifting lug includes lifting lug and the length along the lifting lug The hangs muscle that direction extends downwardly, the hangs muscle weld the steel pipe column, the hollow formation square through hole of lifting lug, when rod is inserted into The square through hole when rod is placed on the casing, realizes being fixed temporarily for the steel pipe column.
CN201810468093.9A 2018-05-16 2018-05-16 Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method Pending CN108643192A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810468093.9A CN108643192A (en) 2018-05-16 2018-05-16 Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810468093.9A CN108643192A (en) 2018-05-16 2018-05-16 Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method

Publications (1)

Publication Number Publication Date
CN108643192A true CN108643192A (en) 2018-10-12

Family

ID=63756223

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810468093.9A Pending CN108643192A (en) 2018-05-16 2018-05-16 Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method

Country Status (1)

Country Link
CN (1) CN108643192A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109680978A (en) * 2019-02-15 2019-04-26 深圳市市政工程总公司 Basement increasing layer underpinning construction method
CN109826190A (en) * 2019-02-15 2019-05-31 深圳市市政工程总公司 The construction method of pile integral structure
CN110172977A (en) * 2019-06-12 2019-08-27 深圳市工勘岩土集团有限公司 Foundation pit support steel column grout pile top concrete prevents superfilled construction method and structure
CN110629744A (en) * 2019-09-16 2019-12-31 中铁广州工程局集团深圳工程有限公司 Construction process of steel pipe concrete pile of subway station
CN112575771A (en) * 2020-06-15 2021-03-30 顾炎文 Green construction method of reverse underground engineering steel concrete pile and column vertical supporting system
CN113605377A (en) * 2021-08-05 2021-11-05 中铁二局第四工程有限公司 Rock stratum ultra-deep steel pipe column and uplift pile combined construction process
CN113756289A (en) * 2021-09-02 2021-12-07 中铁二十局集团第三工程有限公司 Steel reinforcement cage and fender pile construction method
CN113802767A (en) * 2021-09-24 2021-12-17 浙江东南网架股份有限公司 Steel pipe column construction method by reverse construction method
CN113863365A (en) * 2021-09-14 2021-12-31 中交二航局第三工程有限公司 Novel rectangular steel pipe internally-added reinforced concrete combined supporting column and construction method thereof
CN114592505A (en) * 2022-02-24 2022-06-07 深圳市工勘岩土集团有限公司 Low-clearance foundation pit reverse construction method steel pipe column first-inserting positioning construction method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102261067A (en) * 2011-05-05 2011-11-30 中交四航局第一工程有限公司 Method for installing reinforcement cage of large-diameter ultra-long pile
CN106245627A (en) * 2016-08-30 2016-12-21 中铁三局集团有限公司 A kind of quick positioning construction method of steel pipe stanchion

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102261067A (en) * 2011-05-05 2011-11-30 中交四航局第一工程有限公司 Method for installing reinforcement cage of large-diameter ultra-long pile
CN106245627A (en) * 2016-08-30 2016-12-21 中铁三局集团有限公司 A kind of quick positioning construction method of steel pipe stanchion

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109826190A (en) * 2019-02-15 2019-05-31 深圳市市政工程总公司 The construction method of pile integral structure
CN109680978A (en) * 2019-02-15 2019-04-26 深圳市市政工程总公司 Basement increasing layer underpinning construction method
CN110172977A (en) * 2019-06-12 2019-08-27 深圳市工勘岩土集团有限公司 Foundation pit support steel column grout pile top concrete prevents superfilled construction method and structure
CN110629744A (en) * 2019-09-16 2019-12-31 中铁广州工程局集团深圳工程有限公司 Construction process of steel pipe concrete pile of subway station
CN110629744B (en) * 2019-09-16 2021-08-13 中铁广州工程局集团深圳工程有限公司 Construction process of steel pipe concrete pile of subway station
CN112575771B (en) * 2020-06-15 2023-08-04 顾炎文 Environment-friendly construction method for vertical support system of reverse-acting underground engineering steel concrete with piles and columns
CN112575771A (en) * 2020-06-15 2021-03-30 顾炎文 Green construction method of reverse underground engineering steel concrete pile and column vertical supporting system
CN113605377A (en) * 2021-08-05 2021-11-05 中铁二局第四工程有限公司 Rock stratum ultra-deep steel pipe column and uplift pile combined construction process
CN113756289B (en) * 2021-09-02 2023-06-02 中铁二十局集团第三工程有限公司 Reinforcing cage and fender pile construction method
CN113756289A (en) * 2021-09-02 2021-12-07 中铁二十局集团第三工程有限公司 Steel reinforcement cage and fender pile construction method
CN113863365A (en) * 2021-09-14 2021-12-31 中交二航局第三工程有限公司 Novel rectangular steel pipe internally-added reinforced concrete combined supporting column and construction method thereof
CN113802767A (en) * 2021-09-24 2021-12-17 浙江东南网架股份有限公司 Steel pipe column construction method by reverse construction method
CN113802767B (en) * 2021-09-24 2022-12-20 浙江东南网架股份有限公司 Steel pipe column construction method by reverse construction method
CN114592505A (en) * 2022-02-24 2022-06-07 深圳市工勘岩土集团有限公司 Low-clearance foundation pit reverse construction method steel pipe column first-inserting positioning construction method

Similar Documents

Publication Publication Date Title
CN108643192A (en) Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method
CN105735319B (en) A kind of large diameter steel pipe stand column pile fast positioning plumbing device and construction method
CN110847177A (en) Fixed verticality adjusting and upward floating preventing device and method with steel pipe supporting column serving as structural column
CN105672314B (en) A kind of semi-inverse method steel pipe post pile construction method
CN112900450A (en) Rotary drilling and full-rotation combined back-inserting method positioning method for steel pipe structure pile by reverse construction method
CN211773659U (en) Fixed verticality-adjusting and upward-floating-preventing device with steel pipe support column serving as structural column
CN109183812B (en) Construction method of combined deep foundation pit supporting structure
CN111945714B (en) Steel sleeve guiding method combined with steel upright column inserting construction method
CN111676993A (en) Special construction method for constructing basement foundation by inserting steel structure
CN114134928B (en) Construction method of steel pipe column tower crane foundation
CN110904956B (en) Cast-in-place pile construction process
CN114150766A (en) Prefabricated reinforced concrete column connecting joint and construction method thereof
CN109024608A (en) The construction method that steel pipe column for contrary sequence method quickly positions
CN208650087U (en) Steel pipe column fast-positioning device for contrary sequence method
CN114737602A (en) Method for positioning concrete filled steel tube center column in cover-excavation top-down construction of subway station
CN110172977A (en) Foundation pit support steel column grout pile top concrete prevents superfilled construction method and structure
CN111021343A (en) Construction method of upright post pile
CN103911989A (en) Underwater pouring root type foundation with retaining wall and construction method thereof
CN203782691U (en) Underwater pouring type pipe column provided with retaining wall and internal mold system thereof
CN214832608U (en) Reverse construction method steel pipe upright pile combination device
CN215105474U (en) Ultra-deep foundation pit tower crane lattice type bearing platform foundation system
CN113089654B (en) Construction process of hole digging pile in complex soil layer and steel casing for construction
CN210827573U (en) A template device for reverse construction method construction heavy-calibre well
CN211499464U (en) Steel pipe concrete composite column for high-rise building and reinforcing system thereof
CN113982017A (en) Method for installing reinforcement cage in pile hole

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181012