CN216476596U - Novel playground is built parking area and is used bearing structure - Google Patents

Novel playground is built parking area and is used bearing structure Download PDF

Info

Publication number
CN216476596U
CN216476596U CN202122890068.XU CN202122890068U CN216476596U CN 216476596 U CN216476596 U CN 216476596U CN 202122890068 U CN202122890068 U CN 202122890068U CN 216476596 U CN216476596 U CN 216476596U
Authority
CN
China
Prior art keywords
fixedly connected
positioning
plate
frame shaft
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122890068.XU
Other languages
Chinese (zh)
Inventor
户广旗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Weihai Zhongcheng Pipe Fitting Co ltd
Original Assignee
Weihai Zhongcheng Pipe Fitting Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Weihai Zhongcheng Pipe Fitting Co ltd filed Critical Weihai Zhongcheng Pipe Fitting Co ltd
Priority to CN202122890068.XU priority Critical patent/CN216476596U/en
Application granted granted Critical
Publication of CN216476596U publication Critical patent/CN216476596U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Toys (AREA)

Abstract

The utility model relates to the technical field of parking lot construction, in particular to a novel supporting structure for constructing a parking lot on an playground, which comprises a bottom plate, wherein the top end of the bottom plate is fixedly connected with a plurality of prefabricated columns, each prefabricated column is arranged in a front-back array mode, a space corresponding to a vehicle is arranged between the front-back adjacent prefabricated columns, a top plate is arranged on the upper side of the bottom plate, the left part of the top end of the bottom plate is fixedly connected with a first connecting plate, the left end of the first connecting plate is fixedly connected with a plurality of positioning shafts, the right part of the top end of the bottom plate is fixedly connected with a second connecting plate, the middle part of the second connecting plate is provided with positioning holes corresponding to the positioning shafts, and a positioning device is arranged between the front-back adjacent two prefabricated columns.

Description

Novel playground is built parking area and is used bearing structure
Technical Field
The utility model relates to the technical field of parking lot construction, in particular to a novel support structure for constructing a parking lot on a playground.
Background
With the rapid increase of the automobile holding amount and the rapid development of the economy in China, automobiles enter common people, the number of automobiles is increased year by year, parking spaces are not enough for parking on roads, so that traffic jam is caused, the number of parking positions in many cities only reaches 20% -30% of the international standard, large parking buildings are overhigh in cost, high in average cost, large in investment and difficult to recover, most cities in China are planned in the last 90 th century, the automobiles are few at the moment, development space is not considered in parking planning and configuration, no space exists in building parking lots in city centers, a large space which can be utilized in cities in China, namely a school playground, is a large space, and as long as the problem of normal order of school teaching is solved in time and space, the playground can be improved by utilizing the playground, the playground is a region where people move, but the playground occupies a large area, wastes a large space and has low economic benefit, the land space at the bottom of the playground occupies a large space and cannot be utilized, the driving situations of people during traveling are increased, the surrounding parking space is small, the parking lot is built by utilizing the space at the lower part of the playground and is a good solution, and the common building support structure adopts multi-point support and has low support strength.
Disclosure of Invention
Aiming at the defects of the prior art, the utility model provides a novel support structure for building a parking lot on a playground, which has the effects of facilitating underground building of the parking lot, having higher support strength and being convenient for assembly and positioning.
In order to achieve the purpose, the utility model provides the following technical scheme: the utility model provides a novel playground builds bearing structure for parking area, comprising a base plate, a plurality of prefabricated posts of top fixedly connected with of bottom plate, each the array is arranged around the prefabricated post is, is provided with the interval corresponding with the vehicle between the adjacent prefabricated post around, the upside of bottom plate is provided with the roof, the first even board of top left part fixedly connected with of bottom plate, the first left end fixedly connected with of even board has a plurality of location axles, the top right part fixedly connected with second of bottom plate links the board, the second links the middle part of board be provided with each the corresponding locating hole of location axle is provided with positioner around to between two adjacent prefabricated posts of arranging.
Furthermore, the positioning device comprises a first frame shaft and a second frame shaft, the left end of the support sleeve is fixedly connected with the right end of the first frame shaft, the left end of the second frame shaft is fixedly connected with a circular plate, a cavity corresponding to the circular plate is arranged in the support sleeve, a limiting hole is arranged at the upper part of each prefabricated column, one end of the first frame shaft and one end of the second frame shaft are inserted into the corresponding limiting holes, and the outer wall of each first frame shaft and the outer wall of each second frame shaft are fixedly connected with the upper part of each corresponding prefabricated column.
Furthermore, a plurality of bent steel bars are arranged on the lower side of the top plate, the bent steel bars are arranged in the left-right direction, the bent steel bars are fixedly connected with the upper portions of the corresponding prefabricated columns, frame plates are fixedly connected to the front ends and the rear ends of the bent steel bars, and the frame plates are fixedly connected with the opposite ends of the corresponding first connecting plates.
Preferably, a waterproof layer is arranged at the top end of the top plate.
In order to further improve the support stability, the prefabricated column support structure further comprises a plurality of positioning parts which are arranged in a front-back array mode, and each positioning part penetrates through the bottom of each corresponding prefabricated column.
Preferably, the positioning part is an iron pipe.
Compared with the prior art, the utility model provides a novel support structure for constructing a parking lot in a playground, which has the following beneficial effects:
the novel playground supporting structure for building the parking lot is characterized in that when the novel playground supporting structure is installed, prefabricated columns can be fixed on the upper portion of a bottom plate, the whole playground is erected below the playground in a hoisting mode, positioning shafts are inserted into positioning holes of adjacent second connecting plates to modularly connect the whole, ground protective layers such as concrete are arranged on the upper portion of the bottom plate, the playground is erected on the upper portion of a top plate, positioning devices are used for supporting the upper portions of a plurality of prefabricated columns, the deflection of the prefabricated columns in the using process is reduced, the stability is improved, the whole playground is mainly hoisted, the number of workers is small, safe construction can be guaranteed, the number of parking spaces is increased in a short time, traffic pressure in a city can be greatly relieved, parking spaces can be increased in playground hoisting engineering, the problem of difficulty in parking in the city can be thoroughly solved, and underground construction of the parking lot is facilitated, the supporting strength is higher, the effect of being convenient for assemble the location.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is an enlarged view of a portion of FIG. 1A;
FIG. 3 is a schematic diagram of the right view structure of the present invention;
FIG. 4 is a schematic cross-sectional view taken along line A-A of FIG. 3 according to the present invention;
FIG. 5 is a schematic cross-sectional view taken along line B-B of FIG. 3 according to the present invention;
fig. 6 is a schematic view of a portion of the enlarged structure at B in fig. 3 according to the present invention.
The symbols in the drawings illustrate that:
1. a base plate; 2. prefabricating a column; 3. a top plate; 4. a waterproof layer; 5. a first connecting plate; 6. positioning the shaft; 7. A second connecting plate; 8. bending the reinforcing steel bar; 9. a frame plate; 10. a first frame shaft; 11. a support sleeve; 12. a second frame shaft; 13. a positioning part; 14. a circular plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example (b):
referring to fig. 1-6, a novel playground building supporting structure for a parking lot includes a bottom plate 1 and a plurality of positioning portions 13, a plurality of prefabricated columns 2 are fixedly connected to the top end of the bottom plate 1, the prefabricated columns 2 are arranged in a front-back array, a space corresponding to a vehicle is arranged between the adjacent prefabricated columns 2, a top plate 3 is arranged on the upper side of the bottom plate 1, a waterproof layer 4 is arranged on the top end of the top plate 3, the waterproof layer 4 can be made of asphalt materials, the upper portion of the playground is supported by the waterproof layer 4, external moisture is reduced to enter the lower portion of the top plate 3, and protection performance is further improved.
The left part of the top end of the bottom plate 1 is fixedly connected with a first connecting plate 5, the left end of the first connecting plate 5 is fixedly connected with a plurality of positioning shafts 6, the right part of the top end of the bottom plate 1 is fixedly connected with a second connecting plate 7, the middle part of the second connecting plate 7 is provided with positioning holes corresponding to the positioning shafts 6, a positioning device is arranged between two adjacent prefabricated columns 2 which are arranged in the front-back direction and comprises a first frame shaft 10 and a second frame shaft 12, the left end of a support sleeve 11 is fixedly connected with the right end of the first frame shaft 10, the left end of the second frame shaft 12 is fixedly connected with a support sleeve 11, a cavity corresponding to the support sleeve 11 is arranged inside a circular plate 14, the upper part of each prefabricated column 2 is provided with a limit hole, one end of each of the first frame shaft 10 and one end of the second frame shaft 12 are inserted into the corresponding limit hole, the outer wall of each first frame shaft 10 and the outer wall of each second frame shaft 12 are fixedly connected with the upper part of each corresponding prefabricated column 2, when the first frame shaft 10 and the second frame shaft 12 are installed, the supporting sleeve 11 slides in the circular plate 14, so that the distance between the axes of the first frame shaft 10 and the second frame shaft 12 is adjusted, and the positioning is adapted to the different directions of the positioning holes between the two adjacent prefabricated columns 2, so as to reduce the situation of difficult installation caused by machining errors, when the prefabricated columns 2 are installed, the whole body can be erected below the playground in a hoisting manner after the prefabricated columns 2 are fixed through the upper part of the bottom plate 1, then the positioning shaft 6 is inserted into the positioning holes of the adjacent second connecting plate 7, so as to modularly connect the whole body, a ground protective layer such as concrete is arranged on the upper part of the bottom plate 1, then the playground is erected on the upper part of the top plate 3, the upper parts of the plurality of prefabricated columns 2 are supported through the positioning device, the situation that the prefabricated columns 2 are inclined in the use process is reduced, and the stability is improved, wholly use hoist and mount as the main, workman's quantity is less, and safe construction can ensure, increases parking stall quantity in the short time, will alleviate the traffic pressure in city by a wide margin, and playground promotes the engineering and can increase the parking stall, can thoroughly solve the difficult problem of city parking, reaches to be favorable to the underground to build the parking area, and support intensity is higher, the effect of the equipment location of being convenient for.
The downside of roof 3 is provided with a plurality of bent steel bars 8, each bent steel bar 8 is to controlling arranging, each bent steel bar 8 all with each upper portion fixed connection who corresponds prefabricated post 2, the equal fixedly connected with frame plate 9 in bent steel bar 8's front end and rear end, each frame plate 9 all with each relative end fixed connection who corresponds first even board 5, strengthen the joint strength on the upper portion of each 20 through a plurality of bent steel bars 8, and through fixed connection between frame plate 9 and the first even board 5, and then improve the stability that supports prefabricated post 2.
The positioning parts 13 are arranged in a front-back array mode, each positioning part 13 penetrates through the bottom of each corresponding prefabricated column 2, the prefabricated columns 2 are connected through the positioning parts 13, the positions of the bottoms of the prefabricated columns 2 are further limited, the connection strength of the prefabricated columns 2 is further improved, the deflection condition of the prefabricated columns 2 is reduced, the positioning parts 13 are iron pipes, the weight of the positioning parts 13 is reduced through the internal hollow form of the iron pipes, and when the positioning parts are installed, the positioning parts can be bent to form partial areas of the positioning parts 13, and the situation that holes in the bottoms of the prefabricated columns 2 are not coaxial is met.
When the prefabricated column 2 is installed, the whole body is erected below the playground in a preset manner after the prefabricated column 2 is fixed on the upper portion of the bottom plate 1, then the positioning shaft 6 is inserted into the positioning hole of the adjacent second connecting plate 7, the whole body is connected in a modularized manner, a ground protection layer such as concrete is arranged on the upper portion of the bottom plate 1, and the playground is erected on the upper portion of the top plate 3.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.
In the description of the present invention, it should be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection, a removable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.

Claims (6)

1. The utility model provides a novel playground builds bearing structure for parking area which characterized in that: the prefabricated column structure comprises a base plate (1), a plurality of prefabricated columns (2) are fixedly connected to the top end of the base plate (1), the prefabricated columns (2) are arranged in a front-back array mode, intervals corresponding to vehicles are arranged between the front-back adjacent prefabricated columns (2), a top plate (3) is arranged on the upper side of the base plate (1), a first connecting plate (5) is fixedly connected to the left portion of the top end of the base plate (1), a plurality of positioning shafts (6) are fixedly connected to the left end of the first connecting plate (5), a second connecting plate (7) is fixedly connected to the right portion of the top end of the base plate (1), positioning holes corresponding to the positioning shafts (6) are formed in the middle of the second connecting plate (7), and positioning devices are arranged between the front-back adjacent two prefabricated columns (2) which are arranged.
2. The novel playground-building parking lot support structure as claimed in claim 1, wherein: the positioning device comprises a first frame shaft (10) and a second frame shaft (12), the left end of a support sleeve (11) is fixedly connected with the right end of the first frame shaft (10), the left end of the second frame shaft (12) is fixedly connected with a circular plate (14), a cavity corresponding to the circular plate (14) is arranged inside the support sleeve (11), a limiting hole is formed in the upper portion of each prefabricated column (2), one end of the first frame shaft (10) and one end of the second frame shaft (12) are inserted into the corresponding limiting holes, and the outer walls of the first frame shaft (10) and the second frame shaft (12) are fixedly connected with the corresponding upper portions of the prefabricated columns (2).
3. The novel playground-building parking lot support structure as claimed in claim 2, wherein: the lower side of the top plate (3) is provided with a plurality of bent steel bars (8), each bent steel bar (8) is arranged in the left-right direction, each bent steel bar (8) is fixedly connected with the upper part of each corresponding prefabricated column (2), the front end and the rear end of each bent steel bar (8) are fixedly connected with frame plates (9), and each frame plate (9) is fixedly connected with the opposite end of each corresponding first connecting plate (5).
4. A novel playground-building parking lot support structure according to claim 3, wherein: and a waterproof layer (4) is arranged at the top end of the top plate (3).
5. The novel playground-building parking lot support structure as claimed in claim 4, wherein: the prefabricated column structure is characterized by further comprising a plurality of positioning parts (13), the positioning parts (13) are arranged in a front-back array mode, and the positioning parts (13) penetrate through the bottoms of the corresponding prefabricated columns (2).
6. The novel playground-building parking lot support structure as claimed in claim 5, wherein: the positioning part (13) is an iron pipe.
CN202122890068.XU 2021-11-24 2021-11-24 Novel playground is built parking area and is used bearing structure Active CN216476596U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122890068.XU CN216476596U (en) 2021-11-24 2021-11-24 Novel playground is built parking area and is used bearing structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122890068.XU CN216476596U (en) 2021-11-24 2021-11-24 Novel playground is built parking area and is used bearing structure

Publications (1)

Publication Number Publication Date
CN216476596U true CN216476596U (en) 2022-05-10

Family

ID=81398780

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122890068.XU Active CN216476596U (en) 2021-11-24 2021-11-24 Novel playground is built parking area and is used bearing structure

Country Status (1)

Country Link
CN (1) CN216476596U (en)

Similar Documents

Publication Publication Date Title
CN104988989B (en) Movable building structure and making method thereof
CN108049666B (en) A kind of echelon installation method of super plane multilayer steel truss electronic workshop steel construction
CN216476596U (en) Novel playground is built parking area and is used bearing structure
CN212582721U (en) Bearing platform of tower crane for vertical tower of top plate of foundation garage
CN111827752A (en) Ultra-deep pit micro stereo garage constructed by plate type layer frames and construction method thereof
CN218712196U (en) Supporting structure for erecting vehicle running channel of construction bridge
CN217001003U (en) Self-assembly falling-proof shed for bridge dismantling
CN202990497U (en) Modular parking lot
CN202152442U (en) Assembling type steel tube-vertical post system
CN210370098U (en) Full-assembly steel structure intelligent parking unit and combined structure thereof
CN214461175U (en) Large-span special-shaped steel structure building
CN109267820B (en) Modular movable enclosure with additional visiting walkways and installation method
CN210369025U (en) Floor-free tower crane foundation construction structure with steel structure
CN113982108A (en) Prefabricated post and precast beam connected node and adopt beam column structure of this node
CN111638116A (en) Vertical reaction frame for prefabricated pier stress test and assembling process thereof
CN220504665U (en) Ectopic assembled H-shaped steel tower
CN220266846U (en) Assembled beam slab column node structure
CN212478095U (en) Steel bar processing shed with detachable field
CN212897158U (en) Assembled multi-ribbed composite horizontal warehouse and horizontal warehouse wall
CN219840529U (en) Door frame and door opening connecting and fixing device
CN210460182U (en) Assembled wind-resistant enclosure
CN214696091U (en) T-shaped column supporting structure for garage and assembled garage
CN219491865U (en) Bearing support of stereo garage
CN219793772U (en) Municipal traffic road greening separation railing
CN221000641U (en) Triangular bracket connecting structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant