CN216476211U - Quick detach formula scaffold frame is used in building engineering construction - Google Patents
Quick detach formula scaffold frame is used in building engineering construction Download PDFInfo
- Publication number
- CN216476211U CN216476211U CN202123026538.4U CN202123026538U CN216476211U CN 216476211 U CN216476211 U CN 216476211U CN 202123026538 U CN202123026538 U CN 202123026538U CN 216476211 U CN216476211 U CN 216476211U
- Authority
- CN
- China
- Prior art keywords
- scaffold
- plate
- support
- engineering construction
- building engineering
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 15
- 230000009194 climbing Effects 0.000 claims abstract description 19
- 230000007246 mechanism Effects 0.000 claims abstract description 7
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 6
- 239000000872 buffer Substances 0.000 claims description 19
- 238000003466 welding Methods 0.000 claims description 12
- 239000003351 stiffener Substances 0.000 claims description 6
- 230000000149 penetrating effect Effects 0.000 claims description 2
- 239000007853 buffer solution Substances 0.000 claims 2
- 230000000694 effects Effects 0.000 abstract description 8
- 238000009434 installation Methods 0.000 description 7
- 229910000831 Steel Inorganic materials 0.000 description 3
- 230000006835 compression Effects 0.000 description 3
- 238000007906 compression Methods 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 230000003139 buffering effect Effects 0.000 description 2
- 235000017166 Bambusa arundinacea Nutrition 0.000 description 1
- 235000017491 Bambusa tulda Nutrition 0.000 description 1
- 241001330002 Bambuseae Species 0.000 description 1
- 241000282326 Felis catus Species 0.000 description 1
- 235000015334 Phyllostachys viridis Nutrition 0.000 description 1
- 230000004075 alteration Effects 0.000 description 1
- 239000011425 bamboo Substances 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005034 decoration Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 230000035939 shock Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 229920002994 synthetic fiber Polymers 0.000 description 1
- 239000002023 wood Substances 0.000 description 1
Images
Landscapes
- Movable Scaffolding (AREA)
Abstract
The utility model discloses a quick-release scaffold for building engineering construction, which belongs to the technical field of scaffolds, and comprises a scaffold bottom plate, wherein the lower end of the scaffold bottom plate is provided with a plurality of moving wheels, both ends of the scaffold bottom plate are provided with climbing mechanisms, both sides of the upper end of the scaffold bottom plate are provided with two supporting upright posts, and the upper side of the scaffold bottom plate is provided with a scaffold middle plate, the utility model discloses a right-angle plate is arranged between the two supporting upright posts, the scaffold middle plate and the scaffold top plate are placed between the two right-angle plates, fixing bolts are screwed into the scaffold middle plate and the scaffold top plate, so as to achieve the effect of fixing the scaffold middle plate and the scaffold top plate, a plurality of reinforcing rods are arranged between the two right-angle plates to support the scaffold middle plate and the scaffold top plate, and simultaneously support the diagonal plates to support the straight angle plates, so that the stability of the scaffold middle plate and the scaffold top plate after being installed is better, the safety is higher.
Description
Technical Field
The utility model belongs to the technical field of the scaffold frame, concretely relates to quick detach formula scaffold frame is used in building engineering construction.
Background
Scaffolding refers to various supports erected on a construction site for workers to handle and solve vertical and horizontal transportation. The general term of the building industry refers to the places which cannot be directly constructed on the building site and are used for exterior wall, interior decoration or high floor height. Mainly for constructors to live up and down or for peripheral safety net enclosure, overhead installation components and the like, the scaffold is said to be made of bamboo, wood, steel pipes or synthetic materials. Some projects also use scaffolds as templates, and in addition, the scaffold is widely used in advertising, municipal administration, traffic roads and bridges, mines and other departments.
CN210459918U discloses a quick detach formula steel construction engineering scaffold, the steadiness after scaffold middle plate and the scaffold roof installation in former scaffold is relatively poor, the security is lower, need earlier to loosen the climbing mechanism who fixes on the support post when installing or dismantling the scaffold middle plate, just can install or dismantle the work to the scaffold middle plate after rotating suitable angle, the installation and the dismantlement work of inconvenient scaffold middle plate, do not possess the function of carrying out the shock attenuation buffering to the fly leaf in the former scaffold simultaneously, the workman opens the fly leaf when climbing to the scaffold roof through the cat ladder, strike the scaffold roof after the fly leaf rotates, use the fly leaf to damage easily.
SUMMERY OF THE UTILITY MODEL
For solving the problem that proposes among the above-mentioned background art, the utility model provides a quick detach formula scaffold frame is used in building engineering construction has the steadiness good, the high characteristics of security.
In order to achieve the above object, the utility model provides a following technical scheme: a quick-release scaffold for building engineering construction comprises a scaffold bottom plate, a plurality of movable wheels are arranged at the lower end of the scaffold bottom plate, the two ends of the scaffold bottom plate are provided with climbing mechanisms, the two sides of the upper end of the scaffold bottom plate are provided with two supporting upright posts, a scaffold middle plate is arranged on the upper side of the scaffold bottom plate, a scaffold top plate is arranged on the upper side of the scaffold middle plate, a movable plate is arranged in the scaffold top plate, a climbing ladder is arranged at the position of the upper end of the scaffold middle plate corresponding to the movable plate, the scaffold top plate and the scaffold middle plate are provided with right-angle plates at two ends, a plurality of fixing bolts are arranged on the right-angle plates in a penetrating manner, a plurality of reinforcing rods are arranged between the two right-angle plates, and a supporting inclined rod is arranged between the right-angle plate and the supporting upright posts, and positioning plates are arranged at the positions, corresponding to the scaffold top plate and the scaffold middle plate, of the two sides between the supporting upright posts.
Preferably, all through spot welding welded connection between support down tube and the support post and between support down tube and the right-angle plate, stiffener and right-angle plate formula structure as an organic whole of welding.
Preferably, the positioning plate is connected with the supporting upright post through a bolt, and one end of the positioning plate close to the middle plate of the scaffold is flush with one end of the supporting upright post.
Preferably, the movable plate is provided with a buffer seat on one side away from the middle position of the scaffold top plate, connecting plates are arranged at two ends of the buffer seat, a fixing plate is arranged on the lower side of the connecting plate, sliding rods are arranged on two sides between the connecting plate and the fixing plate, and springs are arranged on the surfaces of the sliding rods between the connecting plate and the fixing plate in an embedded mode.
Preferably, the fixing plate is welded and connected with the supporting upright column through pressure welding, and a rubber cushion pad is arranged at the upper end of the cushion seat.
Preferably, sliding connection is respectively arranged between the connecting plate and the supporting upright column and between the sliding rod and the fixing plate, and arc-shaped structures are arranged on two sides of the upper end of the buffer seat.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses a set up the right-angle plate between two support posts, put scaffold medium plate and scaffold roof between two right-angle plates, twist into scaffold medium plate and scaffold roof with fixing bolt, reach the effect of going on fixing to scaffold medium plate and scaffold roof, it supports scaffold medium plate and scaffold roof to set up a plurality of stiffeners between two right-angle plates, support the down tube simultaneously and support the straight angle plate, it is better to make scaffold medium plate and scaffold roof after the installation steadiness, the security is higher.
2. The utility model discloses a set up the cushion socket, the workman opens the fly leaf when climbing to the scaffold frame roof through the climbing ladder, and the fly leaf rotates and the contact of cushion socket, and the cushion socket passes through the connecting plate and drives the slide bar and slide in the fixed plate, and the spring receives the compression simultaneously, utilizes the elasticity of spring to reach and plays the cushioning effect to the fly leaf, avoids the fly leaf to open direct striking scaffold frame roof and causes the damage.
Drawings
FIG. 1 is a perspective view of the present invention;
fig. 2 is a left side perspective view of the present invention;
fig. 3 is a perspective view of the mounting of the middle plate and the top plate of the scaffold of the present invention;
FIG. 4 is an enlarged view of the point A of FIG. 2 according to the present invention;
in the figure: 1. a scaffold floor; 2. a climbing mechanism; 3. a middle plate of the scaffold; 4. supporting the upright post; 5. a right-angle plate; 6. a scaffold top plate; 7. a movable plate; 8. a buffer seat; 9. climbing a ladder; 10. a supporting diagonal rod; 11. a connecting plate; 12. a moving wheel; 13. positioning a plate; 14. a reinforcing bar; 15. fixing the bolt; 16. a slide bar; 17. a fixing plate; 18. a spring.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Example 1
Referring to fig. 1-4, the present invention provides the following technical solutions: the utility model provides a quick detach formula scaffold frame for building engineering construction, including scaffold bottom plate 1, scaffold bottom plate 1's lower extreme is provided with a plurality of removal wheels 12, scaffold bottom plate 1's both ends are provided with climbing mechanism 2, scaffold bottom plate 1's upper end both sides are provided with two support post 4, scaffold bottom plate 1's upside is provided with scaffold middle plate 3, scaffold middle plate 3's upside is provided with scaffold roof 6, be provided with fly leaf 7 in the scaffold roof 6, scaffold middle plate 3 upper end is provided with climbing ladder 9 with the position that fly leaf 7 corresponds, scaffold roof 6 and scaffold middle plate 3's both ends all are provided with right-angle plate 5, it is provided with a plurality of fixing bolt 15 to run through on the right-angle plate 5, be provided with a plurality of stiffeners 14 between two right-angle plates 5, be provided with support down tube 10 between right-angle plate 5 and the support post 4, both sides are provided with locating plate 13 with scaffold roof 6 and the position that scaffold middle plate 3 corresponds between rear end both sides support post 4.
Specifically, support between down tube 10 and the support post 4 and support between down tube 10 and the right-angle plate 5 all through spot welding welded connection, stiffener 14 and right-angle plate 5 formula structure as an organic whole of welding.
Through adopting above-mentioned technical scheme, spot welding makes between support down tube 10 and the support post 4 and support down tube 10 and right-angle plate 5 between more firm, and stiffener 14 is more firm with right-angle plate 5 formula structure as an organic whole of welding, improves device overall stability.
Specifically, through bolted connection between locating plate 13 and the support post 4, locating plate 13 is close to the one end of 3 one ends of scaffold frame medium plate and the one end of support post 4 and flushes.
Through adopting above-mentioned technical scheme, can play the positioning action to scaffold middle plate 3 and the installation of scaffold roof 6 through setting up locating plate 13, make things convenient for the installation work of scaffold middle plate 3 and scaffold roof 6.
When the scaffold middle plate 3 and the scaffold top plate 6 are installed, the scaffold middle plate 3 and the scaffold top plate 6 are placed between the two right-angle plates 5, the rear ends of the scaffold middle plate 3 and the scaffold top plate 6 are pushed to be in contact with the positioning plate 13, the fixing bolts 15 are screwed into the scaffold middle plate 3 and the scaffold top plate 6, the effect of fixing the scaffold middle plate 3 and the scaffold top plate 6 is achieved, the reinforcing rods 14 are arranged between the two right-angle plates 5 to support the scaffold middle plate 3 and the scaffold top plate 6, and the inclined supporting rods 10 support the right-angle plates 5 at the same time, so that the scaffold middle plate 3 and the scaffold top plate 6 are better in stability and higher in safety after installation, the scaffold middle plate 3 and the scaffold top plate 6 are more convenient to install and disassemble, and the practicability of the device is improved;
example 2
The present embodiment is different from embodiment 1 in that: a buffer seat 8 is arranged on one side, away from the middle position of the scaffold top plate 6, of the movable plate 7, connecting plates 11 are arranged at two ends of the buffer seat 8, a fixing plate 17 is arranged on the lower side of the connecting plate 11, sliding rods 16 are arranged on two sides between the connecting plate 11 and the fixing plate 17, and springs 18 are arranged on the surfaces of the sliding rods 16 between the connecting plate 11 and the fixing plate 17 in an embedded mode.
Through adopting above-mentioned technical scheme, utilize the elasticity of spring 18 to reach and play the cushioning effect to fly leaf 7, avoid fly leaf 7 to open and directly strike scaffold roof 6 and cause the damage.
Specifically, the fixed plate 17 is welded to the support column 4 by pressure welding, and a rubber cushion is arranged at the upper end of the cushion seat 8.
Through adopting above-mentioned technical scheme, make between fixed plate 17 and the support post 4 more firm, the upper end of cushion socket 8 sets up rubber buffer pad simultaneously and can improve the buffering effect to fly leaf 7.
Specifically, the connecting plate 11 and the supporting column 4 and the sliding rod 16 and the fixing plate 17 are connected in a sliding manner, and two sides of the upper end of the buffer seat 8 are provided with arc-shaped structures.
By adopting the technical scheme, the connecting plate 11 can be driven to slide on the supporting upright post 4 when the buffer seat 8 moves, meanwhile, the sliding rod 16 slides in the fixed plate 17, and the two sides of the upper end of the buffer seat 8 are arranged to be of an arc-shaped structure, so that the movable plate 7 can be prevented from being scratched by the buffer seat 8.
When this embodiment uses, through setting up buffer seat 8, the workman opens fly leaf 7 when climbing to scaffold frame roof 6 through climbing ladder 9, and fly leaf 7 rotates and buffer seat 8 contact, and buffer seat 8 drives slide bar 16 through connecting plate 11 and slides in fixed plate 17, and spring 18 receives the compression simultaneously, utilizes the elasticity of spring 18 to reach and play the cushioning effect to fly leaf 7, avoids fly leaf 7 to open direct striking scaffold frame roof 6 and causes the damage.
The structure and the working principle of the middle scaffold bottom plate 1, the climbing mechanism 2, the scaffold middle plate 3, the supporting upright post 4, the scaffold top plate 6, the movable plate 7, the climbing ladder 9 and the moving wheel 12 of the utility model are disclosed in a quick-release steel structure engineering scaffold disclosed in the Chinese patent publication No. CN 210459918U.
The utility model discloses a theory of operation and use flow: when the utility model is used, the device is arranged at a proper position, when the scaffold middle plate 3 and the scaffold top plate 6 are arranged, the scaffold middle plate 3 and the scaffold top plate 6 are placed between the two right-angle plates 5, the rear ends of the scaffold middle plate 3 and the scaffold top plate 6 are pushed to contact with the positioning plate 13, the fixing bolts 15 are screwed into the scaffold middle plate 3 and the scaffold top plate 6, the effect of fixing the scaffold middle plate 3 and the scaffold top plate 6 is achieved, a plurality of reinforcing rods 14 are arranged between the two right-angle plates 5 to support the scaffold middle plate 3 and the scaffold top plate 6, and the inclined supporting rods 10 support the straight angle plates 5, so that the scaffold middle plate 3 and the scaffold top plate 6 are more stable and safer after being arranged, and the scaffold middle plate 3 and the scaffold top plate 6 are more convenient to be arranged and disassembled, the practicability of the device is improved, and by arranging the buffer seat 8, the workman opens fly leaf 7 when climbing to scaffold frame roof 6 through climbing ladder 9, and fly leaf 7 rotates and the contact of buffer seat 8, and buffer seat 8 drives slide bar 16 through connecting plate 11 and slides in fixed plate 17, and spring 18 receives the compression simultaneously, utilizes the elasticity of spring 18 to reach and play the cushioning effect to fly leaf 7, avoids fly leaf 7 to open direct striking scaffold frame roof 6 and causes the damage.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (6)
1. The utility model provides a building engineering construction is with quick detach formula scaffold, includes scaffold bottom plate (1), its characterized in that: the lower end of the scaffold bottom plate (1) is provided with a plurality of moving wheels (12), the two ends of the scaffold bottom plate (1) are provided with climbing mechanisms (2), the two sides of the upper end of the scaffold bottom plate (1) are provided with two supporting upright posts (4), the upper side of the scaffold bottom plate (1) is provided with a scaffold middle plate (3), the upper side of the scaffold middle plate (3) is provided with a scaffold top plate (6), a movable plate (7) is arranged in the scaffold top plate (6), a climbing ladder (9) is arranged at the position, corresponding to the movable plate (7), of the upper end of the scaffold middle plate (3), right-angle plates (5) are arranged at the two ends of the scaffold top plate (6) and the scaffold middle plate (3), a plurality of right-angle fixing bolts (15) are arranged on the right-angle plates (5) in a penetrating manner, a plurality of reinforcing rods (14) are arranged between the two right-angle plates (5), support down tube (10) are arranged between the right-angle plates (5) and the support upright posts (4), and positioning plates (13) are arranged at positions between the two sides of the rear ends of the support upright posts (4) and corresponding to the scaffold top plate (6) and the scaffold middle plate (3).
2. The quick-release scaffold for building engineering construction according to claim 1, characterized in that: support between down tube (10) and support post (4) and support between down tube (10) and right angle board (5) all through spot welding welded connection, stiffener (14) and right angle board (5) formula structure as an organic whole of welding.
3. The quick-release scaffold for building engineering construction according to claim 1, characterized in that: the positioning plate (13) is connected with the supporting upright post (4) through a bolt, and one end of the positioning plate (13) close to the middle plate (3) of the scaffold is flush with one end of the supporting upright post (4).
4. The quick-release scaffold for building engineering construction according to claim 1, characterized in that: the scaffold roof board (6) intermediate position one side is kept away from in fly leaf (7) is provided with buffer seat (8), the both ends of buffer seat (8) are provided with connecting plate (11), the downside of connecting plate (11) is provided with fixed plate (17), both sides are provided with slide bar (16) between connecting plate (11) and fixed plate (17), the surface nestification of slide bar (16) is provided with spring (18) between connecting plate (11) and fixed plate (17).
5. The quick-release scaffold for building engineering construction according to claim 4, wherein: the fixing plate (17) is connected with the supporting upright post (4) in a welding mode through pressure welding, and a rubber cushion pad is arranged at the upper end of the cushion seat (8).
6. The quick-release scaffold for building engineering construction according to claim 4, wherein: the buffer base is characterized in that sliding connections are respectively formed between the connecting plate (11) and the supporting upright posts (4) and between the sliding rods (16) and the fixing plate (17), and arc-shaped structures are arranged on two sides of the upper end of the buffer base (8).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202123026538.4U CN216476211U (en) | 2021-12-02 | 2021-12-02 | Quick detach formula scaffold frame is used in building engineering construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202123026538.4U CN216476211U (en) | 2021-12-02 | 2021-12-02 | Quick detach formula scaffold frame is used in building engineering construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN216476211U true CN216476211U (en) | 2022-05-10 |
Family
ID=81419236
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202123026538.4U Expired - Fee Related CN216476211U (en) | 2021-12-02 | 2021-12-02 | Quick detach formula scaffold frame is used in building engineering construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN216476211U (en) |
-
2021
- 2021-12-02 CN CN202123026538.4U patent/CN216476211U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN215212255U (en) | Suspension type frame combined high-altitude operation platform | |
CN216476211U (en) | Quick detach formula scaffold frame is used in building engineering construction | |
CN213296374U (en) | Subway construction foundation ditch excavation supporting construction | |
CN212689735U (en) | Movable protective fence for building construction | |
CN112853991A (en) | Anti-toppling scaffold for bridge road and building construction and construction method | |
CN209837869U (en) | Construction guardrail | |
CN213806482U (en) | Combined scaffold for construction site | |
CN215212187U (en) | Civil engineering construction support frame | |
CN114575584A (en) | Pedal assembly, scaffold ladder and using method thereof | |
CN113202280A (en) | Conversion bracket type steel structure for steel structure high-altitude construction and construction method thereof | |
CN111424945A (en) | Safe good scaffold with many supporting legs | |
CN217352125U (en) | Bailey bridge builds with channel-section steel assembled steel landing stage railing | |
CN219011283U (en) | Bearing platform tower crane foundation structure | |
CN221194376U (en) | Combined type adjustable balcony safety protection plate | |
CN113309339B (en) | Frame beam lower scaffold structure with complex structure | |
CN213802505U (en) | Mounting rack for installation of scaffold-free elevator | |
CN219637769U (en) | Metal guardrail convenient to connect and assemble | |
CN218205600U (en) | Scaffold frame for building site convenient to installation | |
CN220644812U (en) | Door type steel structure roof structure | |
CN110821130A (en) | Steel construction scaffold convenient to remove dismouting | |
CN220377902U (en) | Face limit guard rail convenient to loading and unloading | |
CN214531802U (en) | Floor slab frame with height adjustment function for building | |
CN218541429U (en) | Round closed sound barrier movable mounting platform | |
CN220621364U (en) | Steel pipe protection railing of adjustable height and width | |
CN212836605U (en) | Scaffold for outdoor landscape design |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20220510 |