CN216269401U - Handling device is used in hydraulic engineering pile foundation construction - Google Patents

Handling device is used in hydraulic engineering pile foundation construction Download PDF

Info

Publication number
CN216269401U
CN216269401U CN202121885046.8U CN202121885046U CN216269401U CN 216269401 U CN216269401 U CN 216269401U CN 202121885046 U CN202121885046 U CN 202121885046U CN 216269401 U CN216269401 U CN 216269401U
Authority
CN
China
Prior art keywords
pile foundation
plate
hydraulic engineering
block
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN202121885046.8U
Other languages
Chinese (zh)
Inventor
刘强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Shentong Municipal Engineering Technology Co ltd
Original Assignee
Anhui Shentong Municipal Engineering Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Shentong Municipal Engineering Technology Co ltd filed Critical Anhui Shentong Municipal Engineering Technology Co ltd
Priority to CN202121885046.8U priority Critical patent/CN216269401U/en
Application granted granted Critical
Publication of CN216269401U publication Critical patent/CN216269401U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Handcart (AREA)

Abstract

The utility model belongs to the technical field of water conservancy engineering, and discloses a conveying device for construction of a pile foundation of water conservancy engineering, which comprises a conveying seat, universal wheels are arranged at the bottom of the conveying seat, telescopic rods are arranged inside the upper part of the conveying seat, a bearing plate is arranged at the top of the telescopic rods, a dredging block is arranged at one side of the top of the conveying seat, which is adjacent to the telescopic rods, a slide rail is arranged at one side of the top of the conveying seat, and a conveying plate is arranged above the slide rail. The carrying efficiency is increased.

Description

Handling device is used in hydraulic engineering pile foundation construction
Technical Field
The utility model belongs to the technical field of hydraulic engineering, and particularly relates to a carrying device for hydraulic engineering pile foundation construction.
Background
The deep foundation that comprises the pile and the pile cap of connecting the pile top or the single pile basis of being connected by post and pile foundation, the building shock resistance who adopts the pile foundation is strong for short, and in hydraulic engineering, the use of pile foundation plays crucial effect, just needs to use a large amount of pile foundations to need carry the pile foundation.
And in prior art, handling device can not be safe lift the pile foundation off from the transfer cart to can not transport a plurality of pile foundations simultaneously, lead to the problem that handling efficiency is low, simultaneously, staff when carrying the pile foundation, the pile foundation takes place to slide easily, leads to the pile foundation to drop, pounces staff in.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a conveying device for hydraulic engineering pile foundation construction, which aims to solve the problems that the existing conveying device cannot be installed, the pile foundation can not be dismounted, a plurality of pile foundations can not be conveyed at the same time, and the pile foundations are easy to slide.
In order to achieve the purpose, the utility model provides the following technical scheme: the utility model provides a handling device is used in hydraulic engineering pile foundation construction, includes the transportation seat, the universal wheel is installed to the bottom of transportation seat, the inside telescopic link that is provided with in top of transportation seat, the loading board is installed at the top of telescopic link, one side of the adjacent telescopic link in top of transportation seat is installed and is dredged the guide block, the slide rail is installed to the adjacent one side of leading the block of dredging in top of transportation seat, the top of slide rail is provided with the fortune support plate, the one end of slide rail is provided with the stopper.
Preferably, the installation spiral shell piece is all installed at the both ends of fortune support plate, installation spiral shell piece surface is provided with changes the piece, change top one side of piece and install the second limiting plate.
Preferably, one side of the bearing plate close to the dredging block is provided with a first limiting plate, a screw hole is formed in one side of the bearing plate, a bolt is arranged in the bottom of the first limiting plate, and the screw hole is matched with the bolt.
Preferably, the bottom parts of the two ends of the carrying plate are respectively provided with a sliding block, and the sliding blocks are matched with the sliding rails.
Preferably, the two ends of the carrying plate are provided with four lifting blocks on one side of the screw block, and the screw blocks are arranged on the two ends of the carrying plate adjacently.
Preferably, the rotating block is internally provided with a positioning pin at the bottom and matched with the mounting screw block through the positioning pin.
Compared with the prior art, the utility model has the following beneficial effects:
(1) the utility model is provided with the bearing plate, the dredging block and the carrying plate, the pile foundation is moved into the bearing plate, the pile foundation is transferred into the carrying plate by the dredging block, the carrying plate is moved to one side by the slide rail, the process is repeated, after unloading is finished, the carrying plate is moved to a proper position, and the pile foundation is unloaded, so that the pile foundation can be conveniently unloaded by workers, a plurality of pile foundations can be simultaneously carried, and the carrying efficiency is increased.
(2) According to the utility model, the installation screw block and the rotating block are arranged, the rotating block is installed on the installation screw block, the second limiting plate on the rotating block is rotated to the surface of the pile foundation, and the rotating block is fixed on the installation screw block through the positioning pin, so that the pile foundation can not slide when a worker carries a carrying plate, and the safety of the worker during carrying is improved.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a side view of a shipping seat of the present invention;
FIG. 3 is a schematic structural diagram of a carrier plate according to the present invention;
FIG. 4 is a front view of the carrier plate of the present invention;
in the figure: 1. a transport base; 2. a universal wheel; 3. a telescopic rod; 4. a carrier plate; 5. a screw hole; 6. a first limit plate; 7. a bolt; 8. a guide block is dredged; 9. a slide rail; 10. a limiting block; 11. carrying a plate; 12. a hanging block; 13. installing a screw block; 14. a slider; 15. positioning pins; 16. rotating the block; 17. and a second limiting plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides the following technical solutions: a carrying device for hydraulic engineering pile foundation construction comprises a conveying seat 1, universal wheels 2 are mounted at the bottom of the conveying seat 1, four universal wheels 2 are arranged at the bottom of the conveying seat 1 and are arranged in a rectangular shape, the pile foundation can be stably carried by the conveying seat 1, a telescopic rod 3 is arranged inside the upper portion of the conveying seat 1, a bearing plate 4 is mounted at the top of the telescopic rod 3, the pile foundation can be effectively and stably carried, a dredging block 8 is mounted at one side, adjacent to the telescopic rod 3, of the top of the conveying seat 1, the upper surface of the dredging block 8 is arc-shaped, the pile foundation can be conveniently moved into a carrying plate 11 through an arc-shaped surface, a slide rail 9 is mounted at one side, adjacent to the dredging block 8, of the top of the conveying seat 1, the conveying plate 11 can be conveniently moved towards two sides, the device can simultaneously carry a plurality of pile foundations, a conveying plate 11 is arranged above the slide rail 9, a limiting block 10 is arranged at one end of the slide rail 9, to prevent the carrier plate 11 from sliding down to the sides of the carrier plate 4.
Further, installation spiral shell piece 13 is all installed at the both ends of fortune support plate 11, and installation spiral shell piece 13 surface is provided with changes piece 16, changes 16 covers on the surface of installation spiral shell piece 13 of piece, changes top one side of piece 16 and installs second limiting plate 17, can make the pile foundation more stable in the transport.
Furthermore, one side of the loading plate 4 close to the dredging block 8 is provided with a first limiting plate 6, a screw hole 5 is formed in one side of the loading plate 4, a bolt 7 is arranged in the bottom of the first limiting plate 6, the first limiting plate 6 is installed on one side of the loading plate 4 through the bolt 7, and the screw hole 5 is matched with the bolt 7 to prevent the pile from rolling when being lifted off from the transport vehicle.
Specifically, the bottom parts of the two ends of the carrying plate 11 are respectively provided with a sliding block 14, and the sliding blocks 14 are matched with the sliding rails 9, so that the carrying plate 11 can be conveniently installed on the sliding rails 9 by workers.
It is worth to be noted that, the hanging blocks 12 are installed on two ends of the carrying plate 11 adjacent to one side of the mounting screw blocks 13, and the number of the hanging blocks 12 is four, so that the worker can conveniently connect the rope on the crane with the hanging blocks 12 and stably dismount the carrying plate 11.
Further, the inside locating pin 15 that is provided with in commentaries on classics piece 16 bottom, changes piece 16 and cooperatees with installation spiral shell piece 13 through locating pin 15, makes things convenient for second limiting plate 17 to fix the more stable of pile foundation.
The working principle and the using process of the utility model are as follows: when the pile foundation transporting device is used, the transporting seat 1 is moved to the rear of a vehicle for transporting pile foundations through the universal wheels 2, the first limiting plate 6 is installed on one side of the bearing plate 4 through the bolts 7, the bearing plate 4 is supported to the position below the pile foundation to be transported through the telescopic rods 3, the pile foundation is moved into the bearing plate 4, the bearing plate 4 is moved to the same horizontal plane with the dredging blocks 8 through the telescopic rods 3, then the transporting plate 11 is placed in the sliding rail 9 through the sliding blocks 14, the first limiting plate 6 and the bearing plate 4 are detached, the pile foundation is pushed, the pile foundation is moved into the transporting plate 11 through the dredging blocks 8, the transporting plate 11 is slid to one side of the limiting blocks 10 through the sliding blocks 14, and other transporting plates 11 are repeatedly placed above the sliding rail 9;
after unloading is finished, the transport base 1 is moved to a proper position, the rotating block 16 is installed in the installation screw block 13, the rotating block 16 is rotated again, the second limiting plate 17 moves to the position above the pile foundation, the rotating block 16 is fixed through the positioning pin 15, the transport plate 11 is lifted through the lifting block 12, and the pile foundation is unloaded.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a handling device is used in hydraulic engineering pile foundation construction which characterized in that: including transportation seat (1), universal wheel (2) are installed to the bottom of transportation seat (1), inside telescopic link (3) of being provided with in the top of transportation seat (1), loading board (4) are installed at the top of telescopic link (3), one side of the adjacent telescopic link in top (3) of transportation seat (1) is installed and is dredged guide block (8), slide rail (9) are installed to the adjacent one side of leading guide block (8) in top of transportation seat (1), the top of slide rail (9) is provided with fortune support plate (11), the one end of slide rail (9) is provided with stopper (10).
2. The carrying device for the construction of the hydraulic engineering pile foundation of claim 1, wherein: installation spiral shell piece (13) are all installed at the both ends of fortune support plate (11), installation spiral shell piece (13) surface is provided with changes piece (16), second limiting plate (17) are installed to the top one side of changing piece (16).
3. The carrying device for the construction of the hydraulic engineering pile foundation of claim 1, wherein: one side that loading board (4) is close to and dredges guide block (8) is provided with first limiting plate (6), screw (5) have been seted up to one side inside of loading board (4), the bottom inside of first limiting plate (6) is provided with bolt (7), screw (5) cooperate with bolt (7).
4. The carrying device for the construction of the hydraulic engineering pile foundation of claim 1, wherein: the bottom parts of the two ends of the carrying plate (11) are respectively provided with a sliding block (14), and the sliding blocks (14) are matched with the sliding rails (9).
5. The carrying device for the construction of the hydraulic engineering pile foundation of claim 1, wherein: the lifting blocks (12) are mounted on one sides of the two ends of the carrying plate (11) adjacent to the mounting screw blocks (13), and the number of the lifting blocks (12) is four.
6. The carrying device for the construction of the hydraulic engineering pile foundation of claim 2, wherein: the rotary block is characterized in that a positioning pin (15) is arranged inside the bottom of the rotary block (16), and the rotary block (16) is matched with the mounting screw block (13) through the positioning pin (15).
CN202121885046.8U 2021-08-12 2021-08-12 Handling device is used in hydraulic engineering pile foundation construction Withdrawn - After Issue CN216269401U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121885046.8U CN216269401U (en) 2021-08-12 2021-08-12 Handling device is used in hydraulic engineering pile foundation construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121885046.8U CN216269401U (en) 2021-08-12 2021-08-12 Handling device is used in hydraulic engineering pile foundation construction

Publications (1)

Publication Number Publication Date
CN216269401U true CN216269401U (en) 2022-04-12

Family

ID=81060357

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121885046.8U Withdrawn - After Issue CN216269401U (en) 2021-08-12 2021-08-12 Handling device is used in hydraulic engineering pile foundation construction

Country Status (1)

Country Link
CN (1) CN216269401U (en)

Similar Documents

Publication Publication Date Title
CN203623675U (en) Penstock transportation trolley in hole
CN202298606U (en) Descending frame for mounting reinforcement cage of pile foundation
CN216269401U (en) Handling device is used in hydraulic engineering pile foundation construction
CN203255887U (en) Movable simple gantry lifting device
CN107499850A (en) A kind of conveying device for rolling stock maintenance production
CN202283926U (en) Portable carrier loader
CN202609773U (en) Bolt-type suspension point
CN110127509B (en) Large building block hoisting device and using method
CN1500954A (en) Block curtain wall hanging and carrying and installing system
CN201473240U (en) Lifting carriage for disassembly and assembly of large elements
CN212269333U (en) Reverse chain return pushing jacking device
CN213676487U (en) Heavy equipment transfer device
CN220908406U (en) Top bracket for reinforcement cage construction and construction equipment thereof
CN221141062U (en) Cutter disc center block disassembling device of assembled shell-discarding disassembly shield machine
CN213923239U (en) Conveying device for transporting muddy water
CN216783350U (en) Scrap iron dumper
CN216945404U (en) Unloading platform with transmission function
CN220364231U (en) Device for hoisting heating surface module of waste heat boiler in place
CN216915946U (en) Plate transport trolley
CN211255049U (en) Indoor overhead pipeline lifting mechanism
CN214450866U (en) Movable slope lifting limiting device for wheel
CN215322701U (en) Engineering building material transfer device
CN220662807U (en) Steel plate conveying device for ship construction
CN210850203U (en) Support is deposited temporarily to steel-pipe pile
CN215160411U (en) Hoisting device for maintenance of Euro cabin equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20220412