CN216105700U - Tower crane that easily sets up attaches operation platform for wall - Google Patents

Tower crane that easily sets up attaches operation platform for wall Download PDF

Info

Publication number
CN216105700U
CN216105700U CN202122596682.5U CN202122596682U CN216105700U CN 216105700 U CN216105700 U CN 216105700U CN 202122596682 U CN202122596682 U CN 202122596682U CN 216105700 U CN216105700 U CN 216105700U
Authority
CN
China
Prior art keywords
platform
assembly
standard
bracket
tower crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122596682.5U
Other languages
Chinese (zh)
Inventor
段万国
刘凯
龚黎明
鲍诗坤
周青青
李俊楠
黄素芹
田恒涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Technology Construction Co Ltd
Original Assignee
China Construction Eighth Engineering Division Technology Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Technology Construction Co Ltd filed Critical China Construction Eighth Engineering Division Technology Construction Co Ltd
Priority to CN202122596682.5U priority Critical patent/CN216105700U/en
Application granted granted Critical
Publication of CN216105700U publication Critical patent/CN216105700U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses an easily-erected tower crane wall-attached operating platform, which comprises a plurality of operating platform main bodies, wherein the plurality of trusses are sequentially overlapped from bottom to top through clamping plates (6); each operating platform main body comprises a platform standard joint (1), an operating platform assembly (2), a platform bracket (3) and a containment assembly (4); the platform standard sections are rectangular columnar frame structures erected by steel pipes, and the platform standard sections of two adjacent operation platform main bodies are vertically connected through clamping plates; a mounting groove is formed in the platform bracket, and the vertical rods of the platform standard knot are connected with the platform bracket in a penetrating way through the mounting groove, so that a plurality of platform brackets are arranged along the circumferential direction of the top of the platform standard knot; the operating platform assembly is fixed on the platform brackets and is of an annular structure and circumferentially surrounds the outer side of the platform standard knot; the enclosure assembly is arranged at the edges of the outer ring and the inner ring of the operation platform assembly. The utility model can improve the dismounting efficiency of the operation platform, thereby being beneficial to the installation of the tower crane attached to the wall.

Description

Tower crane that easily sets up attaches operation platform for wall
Technical Field
The utility model relates to a building construction operation platform, in particular to an operation platform for a tower crane wall attachment, which is easy to erect.
Background
The attached tower crane is widely applied to high-rise and super high-rise building construction, a plurality of attached walls need to be arranged during construction according to the model and the building height of the tower crane, and an operation platform for attaching the walls needs to be erected during site construction in order to ensure safe construction of the attached walls. Currently, the current practice is. Wall-attached operating platform in construction generally adopts steel pipe fastener to set up, and it is troublesome to take and tear open, and the unable reuse of platform of setting up takes a lot of work and time, and simultaneously, high altitude, the danger of high-altitude operation is great.
Disclosure of Invention
The utility model aims to provide an operating platform for a tower crane wall attachment, which is easy to erect, and can improve the dismounting efficiency of the operating platform, thereby being beneficial to the installation of the tower crane wall attachment.
The utility model is realized by the following steps:
an easily-erected tower crane wall-attached operating platform comprises a plurality of operating platform main bodies which are sequentially overlapped from bottom to top through clamping plates; each operating platform main body comprises a platform standard section, an operating platform assembly, a platform bracket and a containment assembly; the platform standard sections are rectangular columnar frame structures erected by steel pipes, and the platform standard sections of two adjacent operation platform main bodies are vertically connected through clamping plates; a mounting groove is formed in the platform bracket, and the vertical rods of the platform standard knot are connected with the platform bracket in a penetrating way through the mounting groove, so that a plurality of platform brackets are arranged along the circumferential direction of the top of the platform standard knot; the operating platform assembly is fixed on the platform brackets and is of an annular structure and circumferentially surrounds the outer side of the platform standard knot; the enclosure assembly is arranged at the edges of the outer ring and the inner ring of the operation platform assembly.
The operating platform assembly comprises a platform frame and a platform screen plate; the platform frame is a rectangular annular frame structure erected by steel pipes, and the inner ring of the platform frame is installed on the platform standard knot through a plurality of platform brackets, so that the platform frame is horizontally arranged on the outer side of the platform standard knot in a surrounding manner; the platform screen is laid on the platform frame.
The side of mounting groove be formed with the wedge draw-in groove, the matching inlays in the wedge draw-in groove and is equipped with the steel sheet wedge, makes the steel sheet wedge chucking between the vertical pole of platform standard festival and platform bracket.
The top surface of platform standard festival be higher than the top surface of platform bracket, the top surface downwardly extending of wedge draw-in groove from the platform standard festival makes the steel sheet wedge insert and establishes between platform standard festival and platform bracket to the top surface below of platform bracket.
The enclosure assembly comprises upright posts, cross rods and skirting boards, the upright posts and the cross rods are respectively and vertically connected into an enclosure structure, and the lower ends of the upright posts are arranged on the platform frame; the skirting board is connected with the bottoms of the upright posts and is arranged along the edge of the bottom of the enclosure assembly.
The clamp plate is provided with two transverse rod slots which are longitudinally arranged, and the bottom transverse rod of the platform standard section above and the top transverse rod of the platform standard section below are respectively matched and inserted in the two transverse rod slots, so that the two adjacent platform standard sections are vertically connected through the clamp plate.
Compared with the prior art, the utility model has the following beneficial effects:
1. the utility model adopts steel pipes, mesh plates and the like to assemble and form a single independent operation platform main body, and can integrally hoist the operation platform main body, thereby improving the installation efficiency of the operation platform main body, reducing high-altitude and high-altitude assembly operation and ensuring the construction safety.
2. According to the utility model, the steel pipes, the screen plates and the like are assembled to form the independent operation platform main bodies, the operation platform main bodies are spliced through the clamping plates, the connection mode is simple and convenient, the disassembly and the assembly are convenient, the appearance is neat and attractive after the assembly, the orderly construction is facilitated, the operation platform main bodies can be recycled after the disassembly, the consumption of materials is reduced, and the construction cost is reduced.
3. The operation platform main body is formed by assembling the steel pipes, the screen plates and the like, materials are easy to obtain and manufacture, the operation platform main body is convenient and safe to erect, the erecting working hours are reduced, and the construction efficiency and the mounting and positioning precision are improved.
Drawings
FIG. 1 is an installation top view of a platform standard knot in an operation platform for attaching a wall to a tower crane, which is easy to erect in the utility model;
FIG. 2 is an installation top view of an operation platform assembly in the operation platform for attaching the wall to the tower crane, which is easy to erect in the utility model;
FIG. 3 is a front view of a containment assembly in an operating platform for attaching a wall to a tower crane, which is easy to erect according to the utility model;
FIG. 4 is a schematic connection diagram of a platform standard knot and a platform bracket in an operation platform for attaching a wall to a tower crane, which is easy to erect, according to the utility model;
fig. 5 is a front view of a clamp plate in the tower crane wall-attached operation platform easy to set up.
In the figure, 1 platform standard section, 2 operation platform assembly, 21 platform frame, 22 platform otter board, 3 platform corbels, 4 enclosure assemblies, 41 upright rods, 42 cross rods, 43 skirting boards, 5 steel plate wedges, 6 clamping plates and 61 transverse rod slots.
Detailed Description
The utility model is further described with reference to the following figures and specific examples.
Referring to fig. 1 to 5, an easy-to-erect operating platform for a tower crane wall attachment comprises a plurality of operating platform bodies sequentially overlapped from bottom to top through clamping plates 6; each operating platform main body comprises a platform standard section 1, an operating platform assembly 2, a platform bracket 3 and a containment assembly 4; the platform standard joints 1 are rectangular columnar frame structures erected by steel pipes, and the platform standard joints 1 of two adjacent operating platform bodies are vertically connected through a clamping plate 6; an installation groove (not shown in the figure) is formed in the platform bracket 3, and the vertical rods of the platform standard knot 1 penetrate through the platform bracket 3 through the installation groove, so that the platform brackets 3 are arranged along the circumferential direction of the top of the platform standard knot 1; the operating platform assembly 2 is fixed on the platform brackets 3, and the operating platform assembly 2 is of an annular structure and circumferentially surrounds the outer side of the platform standard knot 1; the enclosure assembly 4 is arranged at the edge of the outer ring and the edge of the inner ring of the operation platform assembly 2. Each operating platform main body can be assembled on the ground and integrally hoisted through a tower crane, so that the operation platform is convenient and quick to disassemble and assemble, and is favorable for turnover use.
Referring to fig. 1 and 2, the operation platform assembly includes a platform frame 21 and a platform screen 22; the platform frame 21 is a rectangular annular frame structure erected by steel pipes, the inner ring of the platform frame 21 is installed on the platform standard knot 1 through a plurality of platform brackets 3, and the platform frame 21 is horizontally arranged on the outer side of the platform standard knot 1 in a surrounding mode; the platform screen 22 is laid on the platform frame 21. The platform frame 21 can be formed by lapping round steel pipes commonly used in a construction site through fasteners, and a steel mesh plate commonly used in the construction site is used as the platform mesh plate 22 to be laid on the platform frame 21 and fixed through bolts. The size and shape of the platform frame 21 and the platform screen 22 can be adjusted according to actual construction requirements.
Referring to fig. 4, a wedge-shaped slot (not shown) is formed beside the mounting groove, and a steel plate wedge 5 is embedded in the wedge-shaped slot through a screw rod in a matching manner, so that the steel plate wedge 5 is tightly clamped between a vertical rod of the platform standard knot 1 and the platform bracket 3. The installation stability and the levelness of the platform bracket 3 attached to the platform standard knot 1 can be improved through the arrangement of the steel plate wedges 5. Set up the screw at the top of steel sheet wedge 5 and the top of platform bracket 3, make through the screw rod messenger of screw in, can control steel sheet wedge 5 and move down or rebound to make 5 chucking platform standard festival 1 of steel sheet wedge and platform bracket 3.
The top surface of platform standard festival 1 be higher than the top surface of platform bracket 3, the wedge draw-in groove extends to platform bracket 3's top surface below from the top surface downwardly extending of platform standard festival 1, makes steel sheet wedge 5 insert and establishes between platform standard festival 1 and platform bracket 3 to ensure that steel sheet wedge 5 has sufficient regulation time.
Referring to fig. 3, the enclosure assembly 4 includes upright posts 41, cross bars 42 and skirting boards 43, the upright posts 41 and the cross bars 42 are respectively vertically connected to form a fence structure, the fence structure may be in a grid form, and the lower ends of the upright posts 41 are installed on the platform frame 21; skirting boards 43 are connected to the bottoms of the upright rods 41, and the skirting boards 43 are arranged along the bottom edge of the enclosure assembly 4. The enclosure assembly 4 can play a role in peripheral protection, and a steel wire mesh can be additionally arranged on the enclosure structure formed by connecting the vertical rods 41 and the cross rods 42 according to needs, so that a further protection effect is achieved.
Referring to fig. 5, two longitudinal transverse rod slots 61 are formed in the clamping plate 6, and the bottom transverse rod of the platform standard knot 1 located above and the top transverse rod of the platform standard knot 1 located below are respectively inserted into the two transverse rod slots 61 in a matching manner, so that two adjacent platform standard knots 1 are vertically connected through the clamping plate 6. Two adjacent sections of platform standard festival 1 pass through splint 6 high-speed joint, and it is convenient to dismantle, can reuse after the dismantlement.
The construction method comprises the following steps:
according to different tower crane sizes, the number of required steel pipes and the number of steel screens are selected, and the steel pipes are connected by utilizing connecting pieces such as arc-shaped clamping pieces 6 and bolts to form a platform standard knot 1, a platform frame 21 and a fence structure. The number of the platform bracket 6 can be increased or decreased according to the size and the bearing requirement of the platform standard knot 1, and the number of the steel plate wedges 5 is consistent with that of the platform bracket 6.
Aligning to a horizontal marking line of the platform standard knot 1, inserting a vertical rod of the platform standard knot 1 into a mounting groove of the platform bracket 6, inserting a steel plate wedge 5 into a wedge-shaped clamping groove, and screwing through a screw rod to enable the steel plate wedge 5 to tightly clamp the platform standard knot 1 and the platform bracket 6. The platform frame 21 is placed on the platform bracket 6 and fixed by bolts, and then the platform mesh plate 22 is paved on the platform frame 21 at the desired position of the platform and the passage. Finally, the enclosure assembly 4 is mounted on the platform frame 21.
All the operation platform bodies can be assembled on the ground, when in hoisting, a first operation platform body is hoisted in place, bottom steel pipes and middle upright columns are punched according to different design schemes and actual field requirements, the bottom steel pipes and the middle upright columns are fixed by using clamping pieces 6, then a second operation platform body is hoisted, a transverse rod at the bottom of a platform standard section 1 of the second operation platform body is inserted into a transverse rod slot 61 of the top of a platform standard section 1 of the first operation platform body, and finally the two adjacent operation platform bodies are fixed by connecting pieces such as bolts and the like, so that the two adjacent operation platform bodies are connected and fixed. And sequentially connecting all the operation platform main bodies according to the method.
After the tower crane is mounted on the wall, a tower crane is used for hanging one operation platform body which needs to be firstly dismantled, namely the highest position, the clamping plate 6 is dismounted, the operation platform body is separated from the operation platform body below and then hoisted to a designated position on the ground, and then the operation platform bodies are sequentially dismounted from top to bottom in the same way until all the operation platform bodies are dismounted and hoisted to the ground. And cleaning and trimming the operating platform main body, and then transporting the operating platform main body to a storage place for further use next time.
The present invention is not limited to the above embodiments, and any modifications, equivalent replacements, improvements, etc. within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (6)

1. The utility model provides an easily tower crane that sets up attaches wall and uses operation platform which characterized by: comprises a plurality of operation platform bodies which are sequentially overlapped from bottom to top through clamping plates (6); each operating platform main body comprises a platform standard joint (1), an operating platform assembly (2), a platform bracket (3) and a containment assembly (4); the platform standard sections (1) are rectangular columnar frame structures erected by steel pipes, and the platform standard sections (1) of two adjacent operating platform bodies are vertically connected through clamping plates (6); an installation groove is formed in the platform bracket (3), and a vertical rod of the platform standard knot (1) penetrates through the platform bracket (3) through the installation groove, so that the platform brackets (3) are circumferentially arranged along the top of the platform standard knot (1); the operating platform assembly (2) is fixed on the platform brackets (3), and the operating platform assembly (2) is of an annular structure and circumferentially surrounds the outer side of the platform standard knot (1); the enclosure assembly (4) is arranged at the edges of the outer ring and the inner ring of the operation platform assembly (2).
2. The tower crane wall-attached operating platform easy to erect as claimed in claim 1, wherein: the operation platform assembly comprises a platform frame (21) and a platform screen plate (22); the platform frame (21) is a rectangular annular frame structure erected by steel pipes, the inner ring of the platform frame (21) is installed on the platform standard knot (1) through a plurality of platform brackets (3), and the platform frame (21) is horizontally arranged on the outer side of the platform standard knot (1) in a surrounding mode; the platform net plate (22) is laid on the platform frame (21).
3. The tower crane wall-attached operating platform easy to erect as claimed in claim 1, wherein: the side of mounting groove be formed with the wedge draw-in groove, the matching inlays in the wedge draw-in groove and is equipped with steel sheet wedge (5), makes steel sheet wedge (5) chucking between vertical pole and platform bracket (3) of platform standard festival (1).
4. The tower crane wall-attached operating platform easy to erect as claimed in claim 3, wherein: the top surface of platform standard festival (1) be higher than the top surface of platform bracket (3), the top surface downwardly extending of wedge draw-in groove from platform standard festival (1) to the top surface below of platform bracket (3) makes steel sheet wedge (5) insert and establish between platform standard festival (1) and platform bracket (3).
5. The tower crane wall-attached operating platform easy to erect as claimed in claim 1, wherein: the enclosure assembly (4) comprises upright posts (41), cross rods (42) and skirting boards (43), the upright posts (41) and the cross rods (42) are respectively vertically connected into a fence structure, and the lower ends of the upright posts (41) are installed on the platform frame (21); the skirting board (43) is connected to the bottoms of the upright posts (41), and the skirting board (43) is arranged along the edge of the bottom of the enclosure assembly (4).
6. The tower crane wall-attached operating platform easy to erect as claimed in claim 1, wherein: the clamp plate (6) is provided with two transverse rod slots (61) which are longitudinally arranged, and a bottom transverse rod of the platform standard section (1) which is positioned above and a top transverse rod of the platform standard section (1) which is positioned below are respectively matched and inserted in the two transverse rod slots (61), so that the two adjacent platform standard sections (1) are vertically connected through the clamp plate (6).
CN202122596682.5U 2021-10-27 2021-10-27 Tower crane that easily sets up attaches operation platform for wall Active CN216105700U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122596682.5U CN216105700U (en) 2021-10-27 2021-10-27 Tower crane that easily sets up attaches operation platform for wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122596682.5U CN216105700U (en) 2021-10-27 2021-10-27 Tower crane that easily sets up attaches operation platform for wall

Publications (1)

Publication Number Publication Date
CN216105700U true CN216105700U (en) 2022-03-22

Family

ID=80710113

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122596682.5U Active CN216105700U (en) 2021-10-27 2021-10-27 Tower crane that easily sets up attaches operation platform for wall

Country Status (1)

Country Link
CN (1) CN216105700U (en)

Similar Documents

Publication Publication Date Title
KR19990072014A (en) Lift-up method for building buildings from above to the ground
CN109098338A (en) A kind of assembled abnormity structural system of roof and its construction method
CN216105700U (en) Tower crane that easily sets up attaches operation platform for wall
CN211498507U (en) Whole reassembling type protection rack
KR101365236B1 (en) Prefabricated modular foundation for fixing column
CN216811161U (en) Modular structure of airport terminal corridor
CN210342875U (en) Outdoor tent support structure
CN111472536B (en) Template support, steel template and spliced single-side vertical die structure
CN211396781U (en) Assembled facility of having a rest temporarily
CN114725859A (en) Tunnel cable installing support
CN208981607U (en) A kind of assembled abnormity structural system of roof
CN103195079A (en) Installation type templates, installation type template group and set of installation type template devices
CN113175196A (en) Cable net construction platform
CN202559727U (en) Load-bearing support structure of template of overhead long-span floor slab of building
CN205531402U (en) Steel construction temporary remove lattice column butting positioning device
CN212688719U (en) Bridge vase-shaped pier body protective bracket
CN220645154U (en) Socket type disc buckle type shaping tripod outer protection frame
CN211286957U (en) Construction enclosure
CN220522070U (en) Foundation pit guardrail convenient to install and dismantle
CN215562776U (en) Easily build formula tower crane foundation structure with prevent falling
CN216076621U (en) Guardrail for construction
CN217998886U (en) Narrow space climbing platform
CN214943077U (en) Interim rail guard of construction is built in room convenient to dismouting
CN217998874U (en) Mounting platform that tower machine was used
CN215211507U (en) Prestressed concrete bent device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant