CN216076186U - Scaffold frame for building engineering construction of convenient regulation - Google Patents

Scaffold frame for building engineering construction of convenient regulation Download PDF

Info

Publication number
CN216076186U
CN216076186U CN202122645922.6U CN202122645922U CN216076186U CN 216076186 U CN216076186 U CN 216076186U CN 202122645922 U CN202122645922 U CN 202122645922U CN 216076186 U CN216076186 U CN 216076186U
Authority
CN
China
Prior art keywords
frame body
scaffold
building engineering
fixedly connected
engineering construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202122645922.6U
Other languages
Chinese (zh)
Inventor
查辉火
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Kuozheng Architectural Decoration Engineering Co ltd
Original Assignee
Shanghai Kuozheng Architectural Decoration Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Kuozheng Architectural Decoration Engineering Co ltd filed Critical Shanghai Kuozheng Architectural Decoration Engineering Co ltd
Priority to CN202122645922.6U priority Critical patent/CN216076186U/en
Application granted granted Critical
Publication of CN216076186U publication Critical patent/CN216076186U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model discloses a scaffold convenient to adjust and used for building engineering construction, which comprises a scaffold main body, wherein the scaffold main body is formed by mutually inserting an upper frame body, a middle frame body and a lower frame body from top to bottom in sequence; according to the technical scheme, the cover plate is used as a support for constructors to walk, construction articles such as a charging bucket can be stored on the upper surface of the storage basket, the constructors can store tools conveniently through the storage basket, so that the walking space of the scaffold main body is saved, the tools cannot fall off the scaffold main body easily during construction, and construction is simpler and more convenient.

Description

Scaffold frame for building engineering construction of convenient regulation
Technical Field
The utility model relates to the technical field of door type scaffolds, in particular to a scaffold convenient to adjust and used for building engineering construction.
Background
The portal scaffold is one of scaffolds for buildings and is widely applied, the main frame is in a portal shape, so the portal scaffold is called a portal or portal scaffold, also called a scaffold or a portal frame, the portal scaffold mainly comprises a main frame, a cross frame, cross inclined struts, a scaffold board, an adjustable base and the like, the portal scaffold is a construction tool which is firstly developed in the end of the fifty years in the United states, and the portal scaffold has the advantages of simplicity in assembly and disassembly, convenience in movement, good bearing capacity, safety and reliability in use, good economic benefit and the like, so the development speed is very high.
The prior art has the following defects or problems:
1. when the outer wall of a low-rise building such as a villa is constructed, a large amount of soil is easily accumulated on the ground around the building under the influence of earth excavation, or the ground is pure soil, and a common scaffold is sunk into the soil during construction, so that the scaffold body is inclined and stressed unevenly;
2. present door-type scaffold is difficult to interconnect between the frame, proposes the position that need constantly move the frame during the construction, brings inconvenience for doing over again work.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a scaffold for building engineering construction, which is convenient to adjust and aims to solve the problems in the prior art.
In order to achieve the purpose, the utility model provides the following technical scheme:
a scaffold convenient to adjust for building engineering construction comprises a scaffold main body, wherein the scaffold main body is formed by mutually inserting an upper frame body, a middle frame body and a lower frame body from top to bottom, one end of the scaffold main body is movably connected with a storage component, two upper lantern rings are fixedly connected with two sides of the lower end of the upper frame body and the middle frame body, the upper ends of the middle frame body and the lower frame body are fixedly connected with two lower lantern rings, the lower end of the lower frame body is inserted with a supporting component, the supporting component is divided into a flat ground leg and a positioning leg, the positioning leg comprises a positioning column, a base plate, a binding column, a movable sleeve and a pressing sleeve, the lower end of the positioning column is fixedly connected with a backing plate, the lower end of the backing plate is fixedly connected with a binding column, the outer wall of the binding column is connected with a movable sleeve in a sliding mode, the outer wall of the movable sleeve is fixedly connected with a pressing sleeve, and the movable sleeve is installed on the outer wall of the binding column through a bolt.
Optionally, the storage assembly comprises a cover plate and a storage basket, the cover plate is inserted into the middle of the upper surface of the upper frame body and the middle frame body, and the storage basket is connected to the inner walls of the tops of the upper frame body and the lower frame body in a sliding mode.
Optionally, the upper surfaces of the upper frame body and the middle frame body are fixedly connected with guard rails, and the total length of the guard rails is not less than two thirds of the length of the upper surfaces of the upper frame body and the middle frame body.
Optionally, the same fixedly connected with reference column of upper surface of flat lower margin, the constant head tank with reference column size looks adaptation is all seted up at the bottom edge of lower support body.
Optionally, the size of the upper lantern ring is the same as that of the lower lantern ring, and the size of the inner wall of the upper lantern ring on the same side is matched with that of the outer wall of the upper lantern ring on the other side.
Optionally, a plurality of threaded holes matched with the outer wall of the movable sleeve are formed in two ends of the outer wall of the binding column, and the bottom of the binding column is a conical angle.
Optionally, the shape of the pressing sleeve is similar to that of a lampshade, and the pressing sleeve is made of metal.
Optionally, the outer wall of well support body and lower support body all encircles fixedly connected with bracing, the lower surface of going up support body and lower support body is the fretwork dress and is transversely filled by many rectangular columns.
Compared with the prior art, the utility model provides the scaffold for building engineering construction, which is convenient to adjust and has the following beneficial effects:
1. the scaffold main body is supported and built on the ground through the flat ground feet and the positioning feet, the flat ground feet are used for being used when the ground is stable such as cement ground, when soil is accumulated on the ground or the strength is poor, the flat ground feet at the positions of the scaffold main body are taken down and replaced by the positioning feet, the positioning columns are inserted into the lower side of the lower frame body to enable the positioning feet to be stable, the positioning feet are inserted into the ground through the binding columns, the positions of the movable sleeves and the pressing sleeves are adjusted to be matched with the outer walls of the binding columns to assist in fixing the positioning feet, the depth of the positioning feet in the soil is stabilized, the structure of the device is stable, the pressing sleeves can be pressed with the soil to enable the positioning feet to be stable in height, the multiple groups of scaffold main bodies can be mutually inserted through the upper sleeve rings and the lower sleeve rings, the multiple groups of scaffold main bodies are integrated, and convenience is brought to the movement of constructors on the surfaces of the scaffold main bodies so as to facilitate construction;
2. the cover plate is used as a support for constructors to walk, construction articles such as a charging bucket can be stored on the upper surface of the storage basket, the constructors can conveniently store tools through the storage basket, so that the walking space of the scaffold main body is saved, the tools cannot easily fall off the scaffold main body during construction, and the construction is simpler and more convenient.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the structures shown in the drawings without creative efforts.
FIG. 1 is a schematic elevation view of the present invention;
FIG. 2 is a schematic view of the periphery of the cover plate of the upper frame body according to the present invention;
FIG. 3 is a schematic view of the periphery of a shelf storage basket according to the present invention;
FIG. 4 is a schematic view of a positioning leg according to the present invention.
In the figure: 100. a scaffold main body; 1. an upper frame body; 2. a middle frame body; 3. a lower frame body; 4. an upper collar; 5. a lower collar; 10. a storage component; 11. a cover plate; 12. a storage basket; 20. a support assembly; 21. flattening ground feet; 22. a positioning leg; 221. a positioning column; 222. a base plate; 223. binding the column; 224. a movable sleeve; 225. and (5) pressing the sleeve.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "vertical", "upper", "lower", "horizontal", and the like indicate orientations or positional relationships based on those shown in the drawings, and are only for convenience of describing the present invention and simplifying the description, but do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention.
In the description of the present invention, it should be further noted that, unless otherwise specifically stated or limited, the terms "disposed," "mounted," "connected," and "connected" are to be construed broadly and may be, for example, fixedly connected, detachably connected, integrally connected, mechanically connected, electrically connected, directly connected, connected through an intermediate medium, or connected through the insides of two elements. The specific meanings of the above terms in the present invention can be understood by those skilled in the art according to specific situations.
Referring to fig. 1-4, in this embodiment: a scaffold convenient to adjust for building engineering construction comprises a scaffold main body 100, the scaffold main body 100 is formed by an upper frame body 1, a middle frame body 2 and a lower frame body 3 which are inserted into one another from top to bottom in sequence, one end of the scaffold main body 100 is movably connected with a storage assembly 10, two upper lantern rings 4 are fixedly connected to two sides of the lower ends of the upper frame body 1 and the middle frame body 2, two lower lantern rings 5 are fixedly connected to the upper ends of the middle frame body 2 and the lower frame body 3, a support assembly 20 is inserted into the lower end of the lower frame body 3, the support assembly 20 is divided into a flat ground foot 21 and a positioning foot 22, the positioning foot 22 comprises a positioning column 221, a backing plate 222, a binding column 223, a movable sleeve 224 and a pressing sleeve 225, a backing plate 222 is fixedly connected to the lower end of the positioning column 221, a binding column 223 is fixedly connected to the lower end of the backing plate 222, a movable sleeve 224 is slidably connected to the outer wall of the binding column 223, a pressing sleeve 225 is fixedly connected to the outer wall of the movable sleeve 224, the movable sleeve 224 is mounted on the outer wall of the binding column 223 through bolts; scaffold frame main part 100 is through flat lower margin 21 and location foot 22 as supporting to build on ground, flat lower margin 21 is used for stabilizing on ground and uses when like cement ground, the downside of frame body 3 makes location foot 22 stable down inserted by reference column 221, location foot 22 pricks into ground through pricking post 223, through adjusting movable sleeve 224 and pressure cover 225 auxiliary fixed position foot 22 in the position of pricking post 223 outer wall, stabilize the degree of depth of location foot 22 in soil, so that the device stable in structure, pressure cover 225 can make location foot 22 highly stable with the soil crimping, can also peg graft each other between multiunit scaffold frame main part 100 through last lantern ring 4 and lower lantern ring 5, form a plurality of scaffold frame main parts 100 wholly, be convenient for constructor is at scaffold frame main part 100 surface activity, so that the construction.
The storage assembly 10 comprises a cover plate 11 and a storage basket 12, the cover plate 11 is inserted in the middle of the upper surface of the upper frame body 1 and the middle frame body 2, and the storage basket 12 is connected to the inner walls of the tops of the middle frame body 2 and the lower frame body 3 in a sliding manner; the support when apron 11 walks as the constructor, the upper surface of storing basket 12 can be deposited construction articles for use like the storage bucket, can be convenient for constructor through storing basket 12 and deposit the instrument to save scaffold frame main part 100's walking space, scaffold frame main part 100 can not fall easily to the instrument when the construction, makes the construction more simple and convenient.
The upper surfaces of the upper frame body 1 and the middle frame body 2 are fixedly connected with guard rails, and the total length of the guard rails is not less than two thirds of the length of the upper surfaces of the upper frame body 1 and the middle frame body 2; the safety of the device is better.
The upper surface of the flat ground leg 21 is also fixedly connected with a positioning column 221, and the bottom corners of the lower frame body 3 are provided with positioning grooves matched with the positioning column 221 in size; the positioning feet 22 are more stable at the lower end of the lower frame body 3, so that the structural strength is convenient to improve.
The sizes of the upper lantern ring 4 and the lower lantern ring 5 are the same, and the size of the inner wall of the upper lantern ring 4 positioned on the same side is matched with the size of the outer wall of the upper lantern ring 4 on the other side; facilitating the interconnection between the multiple sets of scaffold bodies 100.
A plurality of threaded holes matched with the outer wall of the movable sleeve 224 are formed in the two ends of the outer wall of the binding column 223, and the bottom of the binding column 223 is a conical angle; so that the positioning foot 22 can be easily pricked into the ground.
The shape of the pressing sleeve 225 is similar to that of a lampshade, and the pressing sleeve 225 is made of metal; facilitating stabilization of the press sleeve 225 to the ground surface.
The outer walls of the middle frame body 2 and the lower frame body 3 are fixedly connected with inclined struts in a surrounding mode, and the lower surfaces of the upper frame body 1 and the lower frame body 3 are hollowed and transversely filled with a plurality of rectangular columns; the structure of the device is more stable.
The working principle and the using process of the utility model are as follows: the scaffold main body 100 is supported and built on the ground through the flat ground feet 21 and the positioning feet 22, the flat ground feet 21 are used for stabilizing the ground such as cement ground, when soil is accumulated on the ground or the strength is poor, the flat ground feet 21 at the position of the scaffold main body 100 are taken down and replaced by the positioning feet 22, the positioning columns 221 are inserted into the lower sides of the lower frame bodies 3 to stabilize the positioning feet 22, the positioning feet 22 are inserted into the ground through the binding columns 223, the positioning feet 22 are fixed in an auxiliary mode through adjusting the positions of the movable sleeves 224 and the pressing sleeves 225 on the outer walls of the binding columns 223, the depth of the positioning feet 22 in the soil is stabilized, the structure of the device is stabilized, the pressing sleeves 225 can be pressed with the soil to stabilize the height of the positioning feet 22, a plurality of groups of scaffold main bodies 100 can be inserted into each other through the upper sleeve rings 4 and the lower sleeve rings 5, the plurality of scaffold main bodies 100 are integrated, and construction personnel can move on the surface of the scaffold main body 100 conveniently, construction articles such as storage bucket can be deposited to the upper surface of storing basket 12 as the support of constructor when walking of apron 11, through storing basket 12 can be convenient for constructor deposit the instrument to save scaffold frame main part 100's walking space.
The above description is only a preferred embodiment of the present invention, and is not intended to limit the scope of the present invention, and all modifications and equivalents of the present invention, which are made by the contents of the present specification and the accompanying drawings, or directly/indirectly applied to other related technical fields, are included in the scope of the present invention.

Claims (8)

1. The utility model provides a scaffold frame for building engineering construction of convenient regulation, includes scaffold frame main part (100), its characterized in that: the scaffold comprises a scaffold main body (100) and is characterized in that the scaffold main body (100) sequentially comprises an upper frame body (1), a middle frame body (2) and a lower frame body (3) which are mutually inserted from top to bottom, one end of the scaffold main body (100) is movably connected with a storage assembly (10), two upper lantern rings (4) are fixedly connected to two sides of the lower end of the upper frame body (1) and the middle frame body (2), two lower lantern rings (5) are fixedly connected to the upper ends of the middle frame body (2) and the lower frame body (3), a supporting assembly (20) is inserted into the lower end of the lower frame body (3), the supporting assembly (20) is divided into a flat ground foot (21) and a positioning foot (22), the positioning foot (22) comprises a positioning column (221), a backing plate (222), a binding column (223), a movable sleeve (224) and a pressing sleeve (225), the lower end of the positioning column (221) is fixedly connected with the backing plate (222), the lower end of the backing plate (222) is fixedly connected with the binding column (223), the outer wall of the binding column (223) is connected with a movable sleeve (224) in a sliding mode, the outer wall of the movable sleeve (224) is fixedly connected with a pressing sleeve (225), and the movable sleeve (224) is installed on the outer wall of the binding column (223) through a bolt.
2. The scaffold convenient to adjust for building engineering construction according to claim 1, wherein: storage component (10) are including apron (11) and storing basket (12), apron (11) are pegged graft at the upper surface middle part of last support body (1) and well support body (2), storing basket (12) sliding connection is in well support body (2) and lower support body (3) top inner wall department.
3. The scaffold convenient to adjust for building engineering construction according to claim 1, wherein: the upper surface of the upper frame body (1) and the upper surface of the middle frame body (2) are fixedly connected with guard railings, and the total length of the guard railings is not less than two thirds of the length of the upper surfaces of the upper frame body (1) and the middle frame body (2).
4. The scaffold convenient to adjust for building engineering construction according to claim 1, wherein: the same fixedly connected with reference column (221) of upper surface of flat lower margin (21), the constant head tank with reference column (221) size looks adaptation is all seted up to the bottom edge of lower support body (3).
5. The scaffold convenient to adjust for building engineering construction according to claim 1, wherein: the size of the upper lantern ring (4) is the same as that of the lower lantern ring (5), and the size of the inner wall of the upper lantern ring (4) on the same side is matched with the size of the outer wall of the upper lantern ring (4) on the other side.
6. The scaffold convenient to adjust for building engineering construction according to claim 1, wherein: a plurality of threaded holes matched with the outer wall of the movable sleeve (224) are formed in two ends of the outer wall of the binding column (223), and the bottom of the binding column (223) is a conical angle.
7. The scaffold convenient to adjust for building engineering construction according to claim 1, wherein: the shape of the pressing sleeve (225) is similar to that of a lampshade, and the pressing sleeve (225) is made of metal.
8. The scaffold convenient to adjust for building engineering construction according to claim 1, wherein: the outer walls of the middle frame body (2) and the lower frame body (3) are all surrounded by fixedly connected with inclined struts, and the lower surfaces of the upper frame body (1) and the lower frame body (3) are all hollowed out and filled with a plurality of rectangular columns in a transverse mode.
CN202122645922.6U 2021-11-01 2021-11-01 Scaffold frame for building engineering construction of convenient regulation Expired - Fee Related CN216076186U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122645922.6U CN216076186U (en) 2021-11-01 2021-11-01 Scaffold frame for building engineering construction of convenient regulation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122645922.6U CN216076186U (en) 2021-11-01 2021-11-01 Scaffold frame for building engineering construction of convenient regulation

Publications (1)

Publication Number Publication Date
CN216076186U true CN216076186U (en) 2022-03-18

Family

ID=80643072

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122645922.6U Expired - Fee Related CN216076186U (en) 2021-11-01 2021-11-01 Scaffold frame for building engineering construction of convenient regulation

Country Status (1)

Country Link
CN (1) CN216076186U (en)

Similar Documents

Publication Publication Date Title
CN216076186U (en) Scaffold frame for building engineering construction of convenient regulation
CN215858944U (en) Platform structure for steel structure construction operation
CN213741115U (en) Integrated structure of underground foundation and foundation pit supporting structure
CN206667826U (en) A kind of wayside pavilion
CN210500860U (en) Secondary structure constructional column top bar planting assistor
CN207647137U (en) A kind of movable operation platform for indoor high-rise working
CN210741497U (en) Mapping device for hydraulic and hydroelectric engineering
CN209975981U (en) Civil engineering construction is with scaffold frame of adjustable mounted position
CN218934302U (en) Climbing device for building engineering
CN212866769U (en) Firm type construction scaffolding
CN210828260U (en) A portable stand for fitment
CN213509623U (en) Formwork structure for construction of building main body structure
CN110671581A (en) Construction machinery damping platform
CN217711604U (en) Civil engineering construction support
CN210975823U (en) Steel purlin of steel bearing structure
CN214463823U (en) Anti-tilting safety ladder
CN213654271U (en) Reinforcing bar installation supporting tool
CN217711637U (en) Supporting structure of attached intelligent climbing frame
CN219529051U (en) Safety protection canopy is used in construction of tunnel inside
CN213686068U (en) Combined mounting rack for building intellectualization
CN212614452U (en) Cat ladder structure for housing construction
CN213575948U (en) Pipeline bearing structure for hydraulic engineering
CN217300059U (en) Assembled steel structure for high seismic region
CN210563361U (en) Pole setting connecting device based on lifting foot hand rack
CN212249148U (en) Supplementary platform of placing of scaffold board construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20220318