CN216072847U - Building material lifting device for super high-rise building construction - Google Patents

Building material lifting device for super high-rise building construction Download PDF

Info

Publication number
CN216072847U
CN216072847U CN202121291767.6U CN202121291767U CN216072847U CN 216072847 U CN216072847 U CN 216072847U CN 202121291767 U CN202121291767 U CN 202121291767U CN 216072847 U CN216072847 U CN 216072847U
Authority
CN
China
Prior art keywords
fixed
mounting
plate
lifting device
mounting plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121291767.6U
Other languages
Chinese (zh)
Inventor
高宇甲
翟国政
莫江峰
张文明
霍继炜
牛彦平
李静
朱栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Fourth Construction Co Ltd of China Construction Seventh Engineering Co Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Fourth Construction Co Ltd of China Construction Seventh Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd, Fourth Construction Co Ltd of China Construction Seventh Engineering Co Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN202121291767.6U priority Critical patent/CN216072847U/en
Application granted granted Critical
Publication of CN216072847U publication Critical patent/CN216072847U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model provides a building material lifting device for super high-rise building construction, which belongs to the technical field of building materials and comprises a mounting plate, wherein the upper end of the mounting plate is fixedly connected with a first fixing plate, and the top end of the mounting plate is provided with a mounting groove; the clamping mechanism is arranged on the upper side of the mounting plate and comprises a limiting pull rod and a clamping assembly, the limiting pull rod and the clamping assembly are both arranged on the upper side of the mounting plate, and the limiting pull rod and the clamping assembly achieve the effect of limiting and facilitating mounting; and the blanking mechanism comprises two material discharging boxes and a blanking assembly, the material discharging boxes and the blanking assembly are arranged in the mounting grooves, and the material discharging boxes and the blanking assembly are used for realizing the descending and ascending functions of materials.

Description

Building material lifting device for super high-rise building construction
Technical Field
The utility model belongs to the technical field of building materials, and particularly relates to a building material lifting device for super high-rise building construction.
Background
The building engineering refers to an engineering entity formed by the construction of various building buildings and their auxiliary facilities and the installation activities of lines, pipelines and equipment matched with the building buildings, wherein the building buildings refer to a top cover, a beam column, a wall, a foundation and an inner space capable of being formed, and the engineering required by production, living, study and public activities of people is met.
Its hopper of current material hoisting device generally is connected through wire rope directness and hoisting device, is mostly fixed connection between hopper and the wire rope, and it is comparatively inconvenient when dismantling the hopper follow-up, is not convenient for follow-up carry out certain transport with the material in the hopper on the plane, has reduced the use convenience of device, and its wire rope's of current material hoisting device winding section of thick bamboo lacks certain limit function.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a building material lifting device for super high-rise building construction, and aims to solve the problems that in the prior art, a hopper is inconvenient to disassemble subsequently, materials in the hopper are inconvenient to convey on a plane subsequently, and the use convenience of the device is reduced.
In order to achieve the purpose, the utility model provides the following technical scheme:
a building material lifting device for super high-rise building construction, comprising:
the mounting plate is fixedly connected with a first fixing plate at the upper end, and a mounting groove is formed in the top end of the mounting plate;
the clamping mechanism is arranged on the upper side of the mounting plate and comprises a limiting pull rod and a clamping assembly, the limiting pull rod and the clamping assembly are both arranged on the upper side of the mounting plate, and the limiting pull rod and the clamping assembly achieve the effect of limiting and facilitating mounting; and
the blanking mechanism comprises two material discharging boxes and a blanking assembly, the material discharging boxes and the blanking assembly are arranged in the mounting grooves, and the material discharging boxes and the blanking assembly are used for achieving descending and ascending of materials.
As a preferred scheme of the utility model, the clamping assembly comprises two semicircular clamping blocks, two springs, two fixed pull rods and two slide rods, the front inner wall of the second mounting groove is provided with a first chute, the two slide rods are respectively connected to the lower inner wall of the first chute in a sliding manner, the two semicircular clamping blocks are respectively fixedly connected to the rear ends of the two slide rods, the two springs are respectively sleeved on the circumferential surfaces of the two slide rods and are fixedly connected to the rear inner walls of the two mounting grooves, and the two fixed pull rods are respectively fixedly connected to the circumferential surfaces of the two semicircular clamping blocks.
As a preferable scheme of the present invention, the discharging assembly includes a third fixing plate, a second limiting arc plate, a first rope, a first limiting arc plate and a first fixing plate, the first fixing plate and the third fixing plate are both fixedly connected to the top end of the mounting plate, the ends of the first fixing plate and the third fixing plate that are close to each other are rotatably connected to a first rotating rod, the first rope is wound on the circumferential surface of the first rotating rod, the discharging box located at the rear side is fixedly connected to the circumferential surface of the first rope, and the second limiting arc plate and the first limiting arc plate are both fixedly connected to the circumferential surface of the first rotating rod.
As a preferable scheme of the present invention, a second fixed block and a second fixed plate are fixedly connected to the top end of the mounting plate, respectively, the ends of the second fixed plate and the second fixed block that are close to each other are rotatably connected to a second rotating rod, a second rope is wound around the circumferential surface of the second rotating rod, and the emptying box located at the lower side is fixedly connected to the circumferential surface of the second rope.
As a preferred embodiment of the present invention, a motor is fixedly connected to the top end of the mounting plate, a first spool is fixedly connected to a circumferential surface of an output end of the motor, a transmission belt is engaged and driven to the circumferential surface of the first spool, a second spool is engaged and driven to a circumferential inner wall of the transmission belt, the second spool is fixedly connected to a circumferential surface of the second rotating rod, and an output shaft of the motor movably penetrates through one end of the first fixing plate and is fixedly connected to a side end of the first rotating rod
As a preferable scheme of the present invention, a plurality of bolt holes are formed in the top end of the mounting plate, and bolts are threadedly connected in the plurality of threaded holes.
As a preferable scheme of the present invention, the left inner walls of the two first sliding grooves are both provided with a second sliding groove, the lower inner walls of the second sliding grooves are both connected with a sliding sheet in a sliding manner, and the sliding sheet is fixedly connected to the circumferential surfaces of the two sliding bars.
Compared with the prior art, the utility model has the beneficial effects that:
1. in this scheme, the second dwang can be accomplished the secondary and goes up and down to reach the rising and the decline of material, the material and the first rope that the second rope adopted are imitative, the blowing case that is located the downside adopts the cavity design, make the material of transmission become more, the preceding inner wall at the second mounting groove is installed to the spring, tensile semicircle fixture block makes the spring shrink and reaches spacing effect through the second mounting groove, semicircle fixture block drives fixed pull rod and slides at the upper end inner wall of first spout when loosening fixed pull rod, the distance through first spout itself reaches spacing effect when sliding to a certain extent.
2. In this scheme, the output shaft of motor plays the effect that drives first dwang and makes it rotate, drives the first I-shaped wheel of circumference fixed surface when the output shaft rotates for first I-shaped wheel meshing transmission band, and then the transmission band drives the second I-shaped wheel, makes the second I-shaped wheel drive the second dwang and rotates.
Drawings
The accompanying drawings, which are included to provide a further understanding of the utility model and are incorporated in and constitute a part of this specification, illustrate embodiments of the utility model and together with the description serve to explain the principles of the utility model and not to limit the utility model. In the drawings:
FIG. 1 is a first cross-sectional view of the present invention;
FIG. 2 is a perspective view of the present invention;
FIG. 3 is a second cross-sectional view of the present invention;
fig. 4 is a partial enlarged view of the utility model at a in fig. 3.
In the figure: 1. mounting a plate; 2. a motor; 3. a first spool; 4. a conveyor belt; 5. a second spool; 6. a first fixing plate; 7. a first limiting arc plate; 8. a first rope; 9. a second limiting arc plate; 10. a third fixing plate; 11. a limiting pull rod; 12. a slide bar; 13. a semicircular clamping block; 14. a spring; 15. fixing a pull rod; 16. a material placing box; 17. a second rope; 18. a second fixing plate; 19. and (4) sliding a sheet.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example 1
Referring to fig. 1-4, the present invention provides the following technical solutions:
a building material lifting device for super high-rise building construction, comprising:
the mounting plate comprises a mounting plate 1, wherein the upper end of the mounting plate 1 is fixedly connected with a first fixing plate 6, and the top end of the mounting plate 1 is provided with a mounting groove;
the clamping mechanism is arranged on the upper side of the mounting plate 1 and comprises a limiting pull rod 11 and a clamping assembly, the limiting pull rod 11 and the clamping assembly are both arranged on the upper side of the mounting plate 1, and the limiting pull rod 11 and the clamping assembly achieve the effect of limiting and facilitating mounting; and
the blanking mechanism comprises two material discharging boxes 16 and a blanking assembly, the material discharging boxes 16 and the blanking assembly are arranged in the mounting grooves, and the material discharging boxes 16 and the blanking assembly achieve descending and ascending effects of materials.
In the specific embodiment of the present invention, the mounting plate 1 made of stainless steel can effectively stabilize the device, and the service life of the device is greatly prolonged when the device is exposed to rain, the surface of the material box 16 is rounded to avoid scratching workers, the second fixing plate 18 and the first fixing plate 6 function as fixing devices, the limiting pull rod 11 functions as limiting, and it is avoided that the material box 16 drops off due to the device being unable to be locked, which is likely to cause a dangerous accident, the first i-shaped wheel 3 and the transmission belt 4 function to drive the second i-shaped wheel 5, the second i-shaped wheel 5 functions to drive the second rotating rod to rotate more stably, and the fixing pull rod 15 functions to pull the semicircular fixture block 13, thereby driving the clamping assembly to open the device to complete disassembly, which needs to be explained: the specific type of the motor 2 is selected by a person skilled in the art, and the motor 2 and the like belong to the prior art, and the detailed description thereof is omitted.
Specifically, referring to fig. 1-4, the clamping assembly includes two semicircular clamping blocks 13, two springs 14, two fixing pull rods 15 and two slide rods 12, a first sliding groove is formed in a front inner wall of the second mounting groove, the two slide rods 12 are respectively slidably connected to a lower inner wall of the first sliding groove, the two semicircular clamping blocks 13 are respectively and fixedly connected to rear ends of the two slide rods 12, the two springs 14 are respectively sleeved on circumferential surfaces of the two slide rods 12 and are fixedly connected to rear inner walls of the two mounting grooves, and the two fixing pull rods 15 are respectively and fixedly connected to circumferential surfaces of the two semicircular clamping blocks 13.
In this embodiment: the unloading subassembly includes third fixed plate 10, the spacing arc 9 of second, first rope 8, first spacing arc 7 and first fixed plate 6, the equal fixed connection in mounting panel 1's of first fixed plate 6 and third fixed plate 10 top, the end rotation that is close to mutually of first fixed plate 6 and third fixed plate 10 is connected with first pivot pole, first rope 8 twines in the circumferential surface of first pivot pole, 16 fixed connection in the circumferential surface of first rope 8 of blowing case that are located the rear side, the equal fixed connection in the circumferential surface of first pivot pole of the spacing arc 9 of second and first spacing arc 7.
Referring to fig. 1-4 specifically, the blanking assembly includes a third fixing plate 10, a second limiting arc plate 9, a first rope 8, a first limiting arc plate 7 and a first fixing plate 6, wherein the first fixing plate 6 and the third fixing plate 10 are both fixedly connected to the top end of the mounting plate 1, the ends of the first fixing plate 6 and the third fixing plate 10, which are close to each other, are rotatably connected with a first rotating rod, the first rope 8 is wound on the circumferential surface of the first rotating rod, a discharging box 16 located at the rear side is fixedly connected to the circumferential surface of the first rope 8, and the second limiting arc plate 9 and the first limiting arc plate 7 are both fixedly connected to the circumferential surface of the first rotating rod.
In this embodiment: the third fixing plate 10 rotates on the circumferential surface of the first fixing block to achieve a stabilizing effect, and the degree of the first rope 8 wound on the circumferential surface of the first rotating rod achieves a fixing effect, so that the discharge box 16 ascends or descends.
Specifically referring to fig. 1, a second fixed block and a second fixed plate 18 are fixedly connected to the top end of the mounting plate 1, a second rotating rod is rotatably connected to the end, close to the second fixed block, of the second fixed plate 18, a second rope 17 is wound around the circumferential surface of the second rotating rod, and a discharge box 16 located on the lower side is fixedly connected to the circumferential surface of the second rope 17.
In this embodiment: the second dwang can accomplish the rise and the decline that the secondary goes up and down to reach the material, and the material that second rope 17 adopted is similar with first rope 8, and the blowing case 16 that is located the downside adopts the cavity design, makes the more of transmitted material.
Referring to fig. 1-4, a motor 2 is fixedly connected to a top end of a mounting plate 1, a first spool 3 is fixedly connected to a circumferential surface of an output end of the motor 2, a transmission belt 4 is engaged and driven to the circumferential surface of the first spool 3, a second spool 5 is engaged and driven to a circumferential inner wall of the transmission belt 4, the second spool 5 is fixedly connected to a circumferential surface of a second rotating rod, and an output shaft of the motor 2 movably penetrates through one end of a first fixing plate 6 and is fixedly connected to a side end of the first rotating rod.
In this embodiment: the output shaft of the motor 2 plays a role in driving the first rotating rod to rotate, and the output shaft drives the first spool 3 with the fixed circumferential surface when rotating, so that the first spool 3 is meshed with the transmission belt 4, and then the transmission belt 4 drives the second spool 5, and the second spool 5 drives the second rotating rod to rotate.
Specifically referring to fig. 1, a plurality of bolt holes are formed at the top end of the mounting plate 1, and bolts are connected to the plurality of threaded holes in a threaded manner.
In this embodiment: fix the whole of this device through the bolt for it is more stable when stretching the blowing case 16, avoid the device to produce acutely and shake, influence operating condition.
Specifically, referring to fig. 1, the left inner walls of the two first sliding grooves are both provided with a second sliding groove, the lower inner walls of the second sliding grooves are both connected with a sliding sheet 19 in a sliding manner, and the sliding sheet 19 is fixedly connected to the circumferential surfaces of the two sliding bars 12.
In this embodiment: the sliding sheet 19 plays a limiting role, the sliding rod 12 plays a role in driving the semicircular clamping block 13 and the spring 14, the spring 14 is contracted when the sliding rod is pulled, and the semicircular clamping block 13 is pulled out from the circular hole to achieve the dismounting effect.
The working principle and the using process of the utility model are as follows: when the device is used, the output shaft of the motor 2 drives the first I-shaped wheel 3 fixed on the circumferential surface, the first I-shaped wheel 3 is meshed with the transmission belt 4, the transmission belt 4 drives the second I-shaped wheel 5 on the circumferential inner wall, the second I-shaped wheel 5 drives the second rotating rod to rotate, the second I-shaped wheel rotates and simultaneously drives the second rope 17 on the surface, the second rope 17 drives the material discharging box 16 on the rear side to ascend or descend, when the output shaft of the motor 2 drives the first rotating rod to rotate between the material discharging box 16 and the third fixing plate 10, the first rope 8 wound on the surface is transferred, the first rope 8 drives the material discharging box 16 on the circumferential surface to ascend or descend, when the first rotating rod is inserted into the second square groove formed at the upper end of the mounting plate 1 through the third fixing plate 10 during installation, the semicircular fixture block 13 is extruded and the spring 14 is driven to contract, so that the fixing pull rod 15 slides in the first sliding groove, when the fixing plate is inserted to a certain degree, the elasticity of the spring 14 drives the semicircular clamping block 13 to be clamped into the clamping grooves at the left end and the right end of the third fixing plate 10, so that the fixing effect is achieved.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that changes may be made in the embodiments and/or equivalents thereof without departing from the spirit and scope of the utility model. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (7)

1. A building material lifting device for super high-rise building construction, comprising:
the mounting plate comprises a mounting plate (1), wherein the upper end of the mounting plate (1) is fixedly connected with a first fixing plate (6), and the top end of the mounting plate (1) is provided with a mounting groove;
the clamping mechanism is arranged on the upper side of the mounting plate (1) and comprises a limiting pull rod (11) and a clamping assembly, the limiting pull rod (11) and the clamping assembly are both arranged on the upper side of the mounting plate (1), and the limiting pull rod (11) and the clamping assembly achieve the effect of limiting and facilitating mounting; and
the blanking mechanism comprises two material discharging boxes (16) and a blanking assembly, wherein the material discharging boxes (16) and the blanking assembly are arranged in the mounting grooves, and the material discharging boxes (16) and the blanking assembly are used for realizing descending and ascending of materials.
2. The building material lifting device for super high-rise building construction as claimed in claim 1, wherein: the joint subassembly includes semicircle fixture block (13), spring (14), fixed pull rod (15) and slide bar (12) and all is equipped with two, first spout has all been seted up to the preceding inner wall of second mounting groove, two slide bar (12) sliding connection respectively in the lower inner wall of first spout, two semicircle fixture block (13) fixed connection respectively in the rear end of two slide bars (12), two spring (14) overlap respectively and establish the circumference surface and the fixed connection in the back inner wall of two mounting grooves of two slide bars (12), two fixed pull rod (15) fixed connection respectively in the circumference surface of two semicircle fixture blocks (13).
3. The building material lifting device for super high-rise building construction as claimed in claim 2, wherein: unloading subassembly includes third fixed plate (10), the spacing arc of second (9), first rope (8), first spacing arc (7) and first fixed plate (6), the equal fixed connection in the top of mounting panel (1) of first fixed plate (6) and third fixed plate (10), the end rotation that is close to mutually of first fixed plate (6) and third fixed plate (10) is connected with first pivot pole, first rope (8) twine in the circumference surface of first pivot pole, are located the rear side blowing case (16) fixed connection in the circumference surface of first rope (8), the equal fixed connection in the circumference surface of first pivot pole of the spacing arc of second (9) and first spacing arc (7).
4. The building material lifting device for super high-rise building construction as claimed in claim 3, wherein: the top of mounting panel (1) is fixedly connected with second fixed block and second fixed plate (18) respectively, the end rotation that is close to mutually of second fixed plate (18) and second fixed block is connected with the second dwang, the circumference surface winding of second dwang has second rope (17), is located the downside blowing case (16) fixed connection in the circumference surface of second rope (17).
5. The building material lifting device for super high-rise building construction as claimed in claim 4, wherein: the top fixedly connected with motor (2) of mounting panel (1), the first I-shaped wheel of circumference fixed surface (3) of the output of motor (2) is connected with, the circumference surface meshing transmission of first I-shaped wheel (3) has transmission band (4), the circumference inner wall meshing transmission of transmission band (4) has second I-shaped wheel (5), second I-shaped wheel (5) fixed connection is in the circumference surface of second dwang, the output shaft activity of motor (2) runs through the one end and the fixed connection in the side of first dwang of first fixed plate (6).
6. The building material lifting device for super high-rise building construction as claimed in claim 5, wherein: a plurality of bolt holes are formed in the top end of the mounting plate (1), and a plurality of bolts are connected in the threaded holes in a threaded mode through equal threads.
7. The building material lifting device for super high-rise building construction as claimed in claim 6, wherein: two the second spout has all been seted up to the left inner wall of first spout, the equal sliding connection of the lower inner wall of second spout has gleitbretter (19), gleitbretter (19) fixed connection is in the circumferential surface of two slide bars (12).
CN202121291767.6U 2021-06-10 2021-06-10 Building material lifting device for super high-rise building construction Active CN216072847U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121291767.6U CN216072847U (en) 2021-06-10 2021-06-10 Building material lifting device for super high-rise building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121291767.6U CN216072847U (en) 2021-06-10 2021-06-10 Building material lifting device for super high-rise building construction

Publications (1)

Publication Number Publication Date
CN216072847U true CN216072847U (en) 2022-03-18

Family

ID=80663286

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121291767.6U Active CN216072847U (en) 2021-06-10 2021-06-10 Building material lifting device for super high-rise building construction

Country Status (1)

Country Link
CN (1) CN216072847U (en)

Similar Documents

Publication Publication Date Title
CN109823963B (en) Hoisting equipment for prefabricated components of fabricated building
CN216072847U (en) Building material lifting device for super high-rise building construction
CN103390869B (en) A kind of high-tension cable repairing crossing frame
CN210710381U (en) Attached lifting scaffold for building
CN213976873U (en) Lifting device for maintaining cliff painting
CN110761581A (en) Movable support frame convenient for building light steel
CN203438386U (en) Easily disassembled and assembled tubular pile die with reinforcing rib
CN212334378U (en) Lifting tool capable of realizing air overturning of escalator truss
CN215731211U (en) Stabilizing device suitable for transformer installation
CN112193967A (en) Reciprocating type lifting material conveying mechanism with protection function for construction engineering
CN221743625U (en) Hoisting type indoor LED full-color large screen
CN209193362U (en) A kind of cradle for constructional engineering being convenient for material transportation
CN112761386A (en) Assembled stage
CN110844716A (en) Device convenient and fast to install cable
CN211733488U (en) Device is used in road lighting engineering construction
CN205637537U (en) A auto -lock draw bridge frame for climbing frame
CN210973528U (en) Automatic hoisting structure of metal material
CN211752517U (en) Multifunctional stage suspender
CN219623757U (en) Chain type electric lifting hanger
CN215798150U (en) Flat support and electric block
CN212339086U (en) Emergency lighting indicator lamp
CN221541965U (en) Helicopter rescue lifting device
CN218024939U (en) Stable lifting device for steel structure machining
CN215287800U (en) Building engineering material lifting machine
CN208561604U (en) A kind of suspender belt reel structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant