CN216049910U - Wall body correcting unit in work progress - Google Patents
Wall body correcting unit in work progress Download PDFInfo
- Publication number
- CN216049910U CN216049910U CN202122397120.8U CN202122397120U CN216049910U CN 216049910 U CN216049910 U CN 216049910U CN 202122397120 U CN202122397120 U CN 202122397120U CN 216049910 U CN216049910 U CN 216049910U
- Authority
- CN
- China
- Prior art keywords
- wall
- insertion rod
- rod
- upright post
- stabilizer bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Length-Measuring Instruments Using Mechanical Means (AREA)
Abstract
The utility model discloses a wall body correcting device in a construction process, which comprises an insertion rod, wherein the insertion rod is L-shaped, and the short wall of the insertion rod is used for being fixed in a double-sided wall; the lower side wall of the insertion rod is provided with an upright post which is used for being attached to a wall surface; the inserting rod is provided with one end of a vertical line, and the other end of the vertical line is provided with a vertical line pendant; be equipped with the one end of auxiliary stabilization pole on the stand, and auxiliary stabilization pole is in same vertical plane with the pole that inserts, set up the triangle-shaped recess on the auxiliary stabilization pole, through setting up the plumb line stabilizing mean like the triangle-shaped recess, reduce the plumb line and stabilize required time to cooperate the location of plumb line more easily. And through the scale measurement structure of folding setting, can carry out the perpendicular angle measurement of plumb line as required to realize the quick correction of wall body in the work progress.
Description
Technical Field
The utility model relates to the technical field of wall construction, in particular to a correcting device in the construction of a double-skin wall prefabricated wall.
Background
In the process of erecting a building engineering template and hoisting a prefabricated wall, a large amount of key time is usually occupied in the correction of the template and the prefabricated wall, and mechanical and human resources are consumed. Meanwhile, after the prefabricated wall is hoisted in place, the prefabricated wall needs to be adjusted repeatedly up and down, the detection ruler needs to occupy personnel, and a large amount of time is needed for the stabilization of the vertical line. And the site operation is mostly the hoist and mount operation, and the measuring tape destroys the frequency extremely high, and measurement accuracy is unstable yet.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a wall body correcting device in a construction process, and aims to solve the problem that the existing double-skin wall correcting tool is inaccurate in measurement precision.
In order to achieve the purpose, the utility model provides the following technical scheme: a wall body correcting device in the construction process comprises an insertion rod, wherein the insertion rod is L-shaped, and the short wall of the insertion rod is used for being fixed in a double-faced wall; the lower side wall of the insertion rod is provided with an upright post which is used for being attached to a wall surface; the inserting rod is provided with one end of a vertical line, and the other end of the vertical line is provided with a vertical line pendant; the stand is provided with one end of an auxiliary stabilizer bar, the auxiliary stabilizer bar and the insertion rod are located in the same vertical plane, and the auxiliary stabilizer bar is provided with a triangular groove.
Preferably, the other end of the auxiliary stabilizer bar is hinged with an extension rod, the rotation direction of the extension rod and the insertion rod are in the same vertical plane, and the extension rod is provided with scale marks.
Preferably, the scale marks are inverted on the extension rod.
Preferably, the upright column is a square column and is of a hollow structure, a sliding groove is formed in the side wall of the upright column, a displacement block is connected to the inner wall of the upright column in a sliding manner, and the displacement block is fixed with the auxiliary stabilizer bar;
the displacement piece is provided with a threaded hole, a screw rod is screwed in the threaded hole, and the screw rod is rotatably connected to the lower side wall of the insertion rod.
Preferably, the round hole has been seted up on the inserted bar, and the round hole internal rotation is connected with the dwang, the lower extreme and the screw rod of dwang are fixed mutually, and the upper end of dwang is equipped with the knob.
Compared with the prior art, the utility model has the beneficial effects that:
through setting up the perpendicular stable mechanism who is the triangle-shaped recess, reduce the required time of perpendicular stable to the location of the perpendicular of more cooperating. And through the scale measurement structure of folding setting, can carry out the perpendicular angle measurement of plumb line as required to realize the quick correction of wall body in the work progress.
Through designing into height-adjustable's mechanism with auxiliary stabilization rod and extension rod, conveniently cooperate the not wall body of co-altitude to rectify to through screw thread mechanism's cooperation, only need can accomplish through rotatory dwang and increase or turn down, reduced the required time among the correction process.
Drawings
FIG. 1 is a schematic structural view of a wall body correction device in the construction process of the present invention.
FIG. 2 is a top sectional view of the wall correction apparatus during construction of the present invention.
Figure 3 is a schematic view of the extension pole of the present invention when deployed.
Fig. 4 is a schematic view of the extension pole of the present invention when folded.
FIG. 5 is a schematic cross-sectional view of the screw of the present invention.
1. An insertion rod; 2. a column; 3. a vertical line; 4. a plumb bob; 5. an auxiliary stabilizer bar; 6. a triangular groove; 7. an extension pole; 8. scale marks; 9. a chute; 10. a displacement block; 11. a threaded hole; 12. a screw; 13. rotating the rod.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-5, the present invention provides a technical solution: a wall body correcting device in the construction process comprises an insertion rod 1, wherein the insertion rod 1 is L-shaped, and the short wall of the insertion rod 1 is used for being fixed in a double-faced wall to play a positioning effect; the lower side wall of the insertion rod 1 is provided with an upright post 2, and the upright post 2 is used for being attached to a wall surface; insert pole 1 and install the one end of plumb line 3, the plumb line weighs down 4 is installed to the other end of plumb line 3, weighs down 4 when steady can realize the measurement to the wall body straightness that hangs down. The upright post 2 is provided with one end of an auxiliary stabilizer bar 5, and the auxiliary stabilizer bar 5 and the insertion rod 1 are positioned in the same vertical plane. The auxiliary stabilizer bar 5 is provided with a triangular groove 6, and the cross section of the vertical line 3 is circular, so that the auxiliary stabilizer bar can be positioned and stabilized more quickly when being clamped in the triangular groove 6, and the auxiliary stabilizer bar can be used for quickly correcting the state of the wall body in construction through the vertical line 3 and the vertical line weight 4.
The other end of the auxiliary stabilizer bar 5 is hinged with an extension rod 7, the rotation direction of the extension rod 7 and the insertion rod 1 are in the same vertical plane, and the extension rod 7 is provided with scale marks 8. The scale marks 8 are inverted on the extension rod 7, the use state of the extension rod 7 is shown in figures 3-4, when the plumb bob 4 is required to be quickly stabilized, the extension rod 7 is kept in the state shown in figure 3, and therefore the plumb bob 3 can be clamped in the triangular groove 6 to realize quick stabilization. When the angle measurement of plumb line 3 needs to be carried out, need rotate extension rod 7 and make it take on auxiliary stabilization pole 5, scale 8 can present forward state this moment, can realize the correction of wall body in the construction fast through observing the coincident position of scale 8 and plumb line 3.
Since the height of the wall body in the building construction is not determined, when the wall body is corrected, the heights of the auxiliary stabilizer bar 5 and the extension bar 7 need to be adjusted. Upright 2 is square post, and is hollow structure, spout 9 has been seted up to the lateral wall of upright 2, the inner wall sliding connection of upright 2 has displacement piece 10, and supplementary stabilizer bar 5 passes spout 9 and displacement piece 10 and fixed mutually, when displacement piece 10 slides from top to bottom at the inner wall of upright 2, can drive supplementary stabilizer bar 5 and extension rod 7 displacement from top to bottom.
Since the height of the displacement block 10 in the column 2 is not stable, an elevation mechanism is required to adjust the height of the displacement block 10. The displacement block 10 is provided with a threaded hole 11, a screw 12 is screwed in the threaded hole 11, and the screw 12 is rotatably connected to the lower side wall of the insertion rod 1. The round hole has been seted up on the inserted bar 1, and the round hole internal rotation is connected with dwang 13, the lower extreme and the screw rod 12 of dwang 13 are fixed mutually, and the upper end of dwang 13 is equipped with the knob. Because stand 2 is square post, can play directional effect, when rotatory screw rod 12, can lift or reduce displacement piece 10 through the cooperation between the screw thread, the user can accomplish the operation through rotatory knob.
The working principle is as follows: need insert the intermediate level of two leather walls with the shortwall that inserts pole 1 during the use to guarantee that stand 2 laminates the wall, plumb line 3 will receive the influence that plumb line weighs down 4 gravity to be in the state on perpendicular to ground, because plumb line 3 need guarantee to be static can only rectify, this moment only need with its card at triangle-shaped recess 6 can. When the wall is completely static, the extension rod 7 is rotated, and whether the wall is in a completely vertical state can be measured through the scale marks 8.
When the height of the wall body to be measured changes, the knob only needs to be rotated, the height adjustment of the displacement block 10 is completed through the matching between the threads, the auxiliary stabilizing rod 5 and the extension rod 7 can be driven to move up and down, and at the moment, the vertical line 3 only needs to be properly wound on the inserting rod 1.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.
Claims (5)
1. The utility model provides a wall body correcting unit in work progress which characterized in that: the double-faced wall fixing device comprises an insertion rod (1), wherein the insertion rod (1) is L-shaped, and the short wall of the insertion rod (1) is used for being fixed in a double-faced wall; the lower side wall of the insertion rod (1) is provided with an upright post (2), and the upright post (2) is used for being attached to a wall surface; one end of a vertical line (3) is installed on the insertion rod (1), and a vertical line pendant (4) is installed on the other end of the vertical line (3); the upright post (2) is provided with one end of an auxiliary stabilizer bar (5), the auxiliary stabilizer bar (5) and the insertion rod (1) are located in the same vertical plane, and the auxiliary stabilizer bar (5) is provided with a triangular groove (6).
2. The in-construction wall correction device according to claim 1, wherein: the other end of the auxiliary stabilizer bar (5) is hinged with an extension rod (7), the rotation direction of the extension rod (7) and the insertion rod (1) are located in the same vertical plane, and scale marks (8) are arranged on the extension rod (7).
3. The in-construction wall correction device according to claim 2, wherein: the scale marks (8) are inverted on the extension rod (7).
4. The in-construction wall correction device according to claim 1, wherein: the upright post (2) is a square post and is of a hollow structure, a sliding groove (9) is formed in the side wall of the upright post (2), a displacement block (10) is connected to the inner wall of the upright post (2) in a sliding mode, and the displacement block (10) is fixed with the auxiliary stabilizer bar (5);
the displacement block (10) is provided with a threaded hole (11), a screw rod (12) is screwed in the threaded hole (11), and the screw rod (12) is rotatably connected to the lower side wall of the insertion rod (1).
5. The in-construction wall correction device according to claim 4, wherein: the round hole has been seted up on inserted bar (1), and the round hole internal rotation is connected with dwang (13), the lower extreme and screw rod (12) of dwang (13) are fixed mutually, and the upper end of dwang (13) is equipped with the knob.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202122397120.8U CN216049910U (en) | 2021-09-30 | 2021-09-30 | Wall body correcting unit in work progress |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202122397120.8U CN216049910U (en) | 2021-09-30 | 2021-09-30 | Wall body correcting unit in work progress |
Publications (1)
Publication Number | Publication Date |
---|---|
CN216049910U true CN216049910U (en) | 2022-03-15 |
Family
ID=80607953
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202122397120.8U Active CN216049910U (en) | 2021-09-30 | 2021-09-30 | Wall body correcting unit in work progress |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN216049910U (en) |
-
2021
- 2021-09-30 CN CN202122397120.8U patent/CN216049910U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205333053U (en) | Automatic right formula surveyor's level measurment scale | |
CN211425458U (en) | High accuracy cadastral survey centering rod | |
CN216049910U (en) | Wall body correcting unit in work progress | |
CN116678387B (en) | Combined mapping device for geotechnical engineering | |
CN208269881U (en) | A kind of simple angle guiding ruler of civil engineering | |
CN215803300U (en) | Ground leveling auxiliary device for building construction | |
CN216593037U (en) | Building slope is surveyed and drawing chi for measurement | |
CN214748013U (en) | Gradient measuring device for building detection | |
CN114777752A (en) | Perpendicularity measuring instrument for shear wall template | |
CN212482495U (en) | Building engineering is with straightness detection device that hangs down | |
CN211954127U (en) | Levelness detection device for construction | |
CN209557978U (en) | A kind of surveying instrument supporting frame convenient for leveling | |
CN209802377U (en) | House wall body straightness detection device that hangs down | |
CN218881599U (en) | Improved formwork support upright rod | |
CN112723164A (en) | Building tower crane verticality detection device | |
CN216012239U (en) | A sopwith staff for measuring floor roof range | |
CN214308754U (en) | Vertical mapping device of geographical survey convenient to it is fixed | |
CN221752146U (en) | Auxiliary support for installing fire hydrant box | |
CN221095920U (en) | Portable detachable adjustable leather number pole | |
CN219038012U (en) | Survey and drawing data acquisition device | |
CN216483040U (en) | Be used for face elevation detection device | |
CN212718991U (en) | Extended structure convenient to fix for supervision and level | |
CN220583403U (en) | Real measuring tool for rapidly measuring perpendicularity actual measurement of template | |
CN220016614U (en) | Geological compass with deployment foot rest | |
CN221147615U (en) | Wall column template verticality measuring device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |