CN216042383U - Hang ceramic tile structure futilely - Google Patents

Hang ceramic tile structure futilely Download PDF

Info

Publication number
CN216042383U
CN216042383U CN202122641564.1U CN202122641564U CN216042383U CN 216042383 U CN216042383 U CN 216042383U CN 202122641564 U CN202122641564 U CN 202122641564U CN 216042383 U CN216042383 U CN 216042383U
Authority
CN
China
Prior art keywords
dry
steelframe
reinforcing
bolts
hang
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122641564.1U
Other languages
Chinese (zh)
Inventor
魏永江
马超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xi'an Jingfa Chengpin Building Decoration Co ltd
Original Assignee
Xi'an Jingfa Chengpin Building Decoration Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xi'an Jingfa Chengpin Building Decoration Co ltd filed Critical Xi'an Jingfa Chengpin Building Decoration Co ltd
Priority to CN202122641564.1U priority Critical patent/CN216042383U/en
Application granted granted Critical
Publication of CN216042383U publication Critical patent/CN216042383U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Finishing Walls (AREA)

Abstract

The utility model relates to a hang ceramic tile structure futilely, relate to the field of architectural decoration technique, it includes the steelframe, fixing device, installation device, the dry pendant, connecting device and ceramic tile, fixing device is used for fixing the steelframe on the outer wall, the dry pendant passes through installation device to be fixed on the steelframe, the one end that the steelframe was kept away from to the dry pendant is connected with connecting device, connecting device includes a plurality of leftover bits and viscose layer, set up the caulking groove that can supply the dry pendant to articulate on the leftover bits, the viscose layer sets up the one side of keeping away from the steelframe at the leftover bits, the ceramic tile passes through the viscose layer and installs on the leftover bits. This application passes through the leftover bits, under the effect on viscose layer, can realize the area of contact between increase dry pendant and the ceramic tile, reduces the use amount on viscose layer.

Description

Hang ceramic tile structure futilely
Technical Field
The application relates to the field of architectural decoration technology, in particular to a dry-hanging ceramic tile structure.
Background
With the improvement of the life quality of people, various architectural exterior wall decoration styles appear in a large number. In general, the exterior wall of a building is painted, tiled, steel plate, stone, etc. to improve the texture of the building surface. The ceramic tile is attractive in appearance and convenient to process, and is popular with people.
At present, the building wall is generally in a dry hanging type, holes are formed in the building wall, then a dry hanging piece is installed, and after the dry hanging piece is fixed, the ceramic tiles are fixed on the dry hanging piece through the related adhesive layer.
In view of the above-mentioned related technologies, the inventor believes that the contact area between the hanging part and the tile is small, and a large amount of adhesive layers are required to increase the adhesive force of the tile on the dry hanging part, which results in a large amount of adhesive layers.
SUMMERY OF THE UTILITY MODEL
In order to reduce the use amount of glue, this application provides a hang ceramic tile structure futilely.
The application provides a hang ceramic tile structure futilely adopts following technical scheme:
the utility model provides a hang ceramic tile structure futilely, includes steelframe, fixing device, installation device, dry pendant, connecting device and ceramic tile, fixing device is used for fixing the steelframe on the wall outward, dry pendant passes through the installation device to be fixed on the steelframe, dry pendant is kept away from the one end of steelframe with connecting device connects, connecting device includes a plurality of leftover bits and viscose layer, set up on the leftover bits and can supply dry pendant carries out the caulking groove that articulates, the viscose layer sets up the leftover bits are kept away from one side of steelframe, the ceramic tile passes through the viscose layer and installs on the leftover bits.
By adopting the technical scheme, the steel frame is adjusted during use, and the steel frame is fixed on the outer wall through the fixing device. And then adjusting the dry hanging pieces, and sequentially fixing the dry hanging pieces on the steel frame through the mounting device. Then, the leftover materials are sequentially adjusted, and the dry hanging pieces are inserted into the caulking grooves, so that the leftover materials are hung on the leftover materials, and the hanging connection of the leftover materials and the dry hanging pieces is further realized. Then, paint the viscose layer in the leftover bits one side of keeping away from the steelframe, then adjust the ceramic tile, bond the ceramic tile on the leftover bits, operate in proper order, realize the decoration of ceramic tile to the outer wall. Through leftover bits, under the effect on viscose layer, can increase the area of contact between dry pendant and the ceramic tile, can reduce the use amount on viscose layer.
Optionally, fixing device includes a plurality of brackets, expansion bolts and connecting piece, the bracket passes through expansion bolts to be fixed on the outer wall, the steelframe is fixed through the connecting piece on the bracket.
Through adopting above-mentioned technical scheme, when the installation steelframe, punch in the appointed place on the outer wall, then put into downthehole with expansion bolts, then adjust the bracket in proper order, fix the bracket on the outer wall. Then the connecting piece is adjusted, the steel frame is installed on the bracket, and the steel frame is fixed on the outer wall. The fixing device who sets up can be fixed the bracket on the wall outward, under the effect of connecting piece, can firmly fix the steelframe on the bracket, and then realizes the connection of dismantling of steelframe on the wall outward.
Optionally, the connecting piece includes connecting bolt and coupling nut, connecting bolt runs through bracket and steelframe setting, coupling nut is used for using with the connecting bolt cooperation.
Through adopting above-mentioned technical scheme, adjust connecting bolt, run through bracket and steelframe with connecting bolt, then through coupling nut, realize the steel frame fixed on the bracket. The connecting piece that sets up can realize dismantling of steelframe and bracket and be connected, is convenient for fix the steelframe on the bracket as required, makes the bracket support the steelframe, improves the flexibility of steelframe installation on the outer wall.
Optionally, the mounting device includes a plurality of mounting bolts and mounting nuts, the mounting bolts penetrate through the dry-hang element and the steel frame, and the mounting nuts are used for being used in cooperation with the mounting bolts.
By adopting the technical scheme, the mounting bolts are adjusted, penetrate through the dry hanging piece and the steel frame, and then the dry hanging piece is fixed on the steel frame through the mounting nuts. The installation device who sets up can realize the connection of dismantling of dry pendant on the steelframe, is convenient for fix the assigned position on the steelframe with dry pendant as required, and then improves the flexibility of dry pendant at the steel skeleton mounting.
Optionally, the corner trimming device further comprises a reinforcing device, wherein the reinforcing device comprises a plurality of supporting sheets and reinforcing pieces, the reinforcing pieces are used for fixing the horizontal sections of the supporting sheets on the dry hanging pieces, and the vertical sections of the supporting sheets are used for abutting against the corner trimming pieces.
By adopting the technical scheme, the supporting sheet is adjusted, the vertical section of the supporting sheet is abutted against the leftover materials, the reinforcing piece is adjusted, the supporting sheet is fixed on the dry hanging piece, the supporting sheet can support the leftover materials, and the connection performance of the leftover materials and the dry hanging piece is improved. The reinforcing device that sets up under the effect of reinforcement, can improve the stability of leftover bits on dry pendant, improves the connection performance of leftover bits and dry pendant.
Optionally, the reinforcing member includes a plurality of reinforcing bolts and reinforcing nuts, the reinforcing bolts penetrate through the pendant, and the reinforcing nuts are used for being matched with the reinforcing bolts for use.
By adopting the technical scheme, the reinforcing bolt is adjusted to penetrate through the dry hanging piece, and then the reinforcing nut is adjusted to fix the supporting piece on the dry hanging piece. The reinforcing piece that sets up under the effect of backing sheet, can improve the support intensity of dry pendant to leftover bits, and then improves the connection performance of dry pendant and leftover bits.
Optionally, a sliding groove is formed in the dry hanging piece, the sliding groove is formed in the length direction of the dry hanging piece, and the horizontal section of the supporting piece can slide along the sliding groove.
Through adopting above-mentioned technical scheme, the spout that sets up can lead and spacing to the motion of backing sheet horizontal segment, can restrict the horizontal segment of backing sheet in the caulking groove, and then increases the area of contact of backing sheet and dry pendant, improves the joint strength of backing sheet and dry pendant.
Optionally, an adhesive layer is arranged between the ceramic tiles.
By adopting the technical scheme, the adhesive layers are arranged among the ceramic tiles, so that the sealing property among the ceramic tiles can be enhanced; meanwhile, the connection strength between the ceramic tiles can be enhanced, and the use quality of the ceramic tiles is improved.
In summary, the present application includes at least one of the following beneficial technical effects:
by the aid of the leftover materials, under the action of the adhesive layer, the contact area between the dry hanging piece and the ceramic tile can be increased, and the using amount of the adhesive layer can be reduced;
the bracket can be fixed on the outer wall through the arranged fixing device, and the steel frame can be firmly fixed on the bracket under the action of the connecting piece, so that the steel frame can be detachably connected on the outer wall;
the arranged mounting device can realize the detachable connection of the dry hanging piece on the steel frame, so that the dry hanging piece can be conveniently fixed at a designated position on the steel frame according to the requirement, and the flexibility of mounting the dry hanging piece on the steel frame is further improved;
the reinforcing device that sets up under the effect of reinforcement, can improve the stability of leftover bits on dry pendant, improves the connection performance of leftover bits and dry pendant.
Drawings
Fig. 1 is a schematic overall structure diagram of a dry-hang tile structure according to an embodiment of the present application.
Fig. 2 is a partial schematic view of a dry-hang tile structure according to an embodiment of the present application.
Fig. 3 is an enlarged schematic view of a portion a of fig. 2.
Figure 4 is another perspective view schematic view of a dry-hang tile structure according to an embodiment of the present application.
Fig. 5 is an enlarged schematic view of a portion B in fig. 4.
Description of reference numerals: 1. a steel frame; 2. a fixing device; 21. a bracket; 22. an expansion bolt; 23. a connecting member; 231. a connecting bolt; 232. a connecting nut; 3. a mounting device; 31. installing a bolt; 32. mounting a nut; 4. a dry hanging part; 41. a chute; 5. a connecting device; 51. leftover materials; 511. caulking grooves; 52. an adhesive layer; 6. ceramic tiles; 7. a reinforcement device; 71. a support sheet; 72. a reinforcement; 721. a reinforcing bolt; 722. the nut is reinforced.
Detailed Description
The present application is described in further detail below with reference to figures 1-5.
The embodiment of the application discloses hang ceramic tile structure futilely. Referring to fig. 1 and 2, the dry-hanging tile structure comprises a steel frame 1, a plurality of fixing devices 2, a mounting device 3, dry-hanging pieces 4, a connecting device 5 and tiles 6, wherein the steel frame 1 can be fixed on an outer wall by the fixing devices 2, the dry-hanging pieces 4 are fixed on the steel frame 1 through the mounting device 3, and one ends, far away from the steel frame 1, of the dry-hanging pieces 4 are connected with the connecting device 5.
Referring to fig. 3, in order to increase the contact area between the drying hanger 4 and the tile 6, the amount of the adhesive layer 52 used is reduced. The connecting device 5 comprises a plurality of leftover materials 51 and an adhesive layer 52, wherein the leftover materials 51 are obtained from waste ceramic tiles 6 and are uniformly cut into the size of 8cm by 5 cm. The leftover material 51 is provided with an embedded groove 511 along the long edge direction, and the dry hanging part 4 can be hung in the embedded groove 511. The adhesive layer 52 is disposed in the caulking groove 511, and the adhesive layer 52 is disposed as AB glue or marble glue. The dry hangers 4 are then adjusted so that the dry hangers 4 are inserted into the nest 511. Then, the adhesive layer 52 is coated on the leftover materials 51 and one side of the dry hanging piece 4 far away from the steel frame 1, and the ceramic tiles 6 are adhered on the four corresponding leftover materials 51. The tiles 6 are also connected by an adhesive layer 52.
Referring to fig. 4 and 5, in order to realize the fixation of the dry hanging part 4 on the steel frame 1 and the connection of the steel frame 1 on the outer wall. The fixing device 2 includes a plurality of brackets 21, expansion bolts 22, and a connecting member 23, the expansion bolts 22 are disposed through the brackets 21, and then the expansion bolts 22 are inserted into holes on the outer wall, thereby fixing the brackets 21 on the outer wall. The steel frame 1 is fixed on the bracket 21 through the connecting piece 23, and the connecting piece 23 comprises two connecting bolts 231 and two connecting nuts 232. The connecting bolts 231 respectively penetrate through the corbels 21 and the steel frame 1, so that the connecting nuts 232 are matched with the connecting bolts 231 for use, and the steel frame 1 is fixed on the plurality of corbels 21.
Referring to fig. 5, in order to realize the installation of the dry hanging piece 4 on the steel frame 1, the installation device 3 comprises a plurality of installation bolts 31 and installation nuts 32, the installation bolts 31 penetrate through the dry hanging piece 4 and the steel frame 1, the installation nuts 32 are matched with the installation bolts 31 for use, the two installation nuts 32 are sequentially adjusted, and the detachable connection of the dry hanging piece 4 on the steel frame 1 can be realized.
Referring to fig. 5, in order to improve the connection performance between the dry hanging piece 4 and the leftover material 51, the dry hanging piece further comprises a reinforcing device 7, the reinforcing device 7 comprises two supporting pieces 71 and a reinforcing piece 72, a sliding groove 41 is formed in the horizontal section of the dry hanging piece 4, and the sliding groove 41 is distributed along the length direction of the horizontal section of the dry hanging piece 4. The horizontal section of the support piece 71 can slide along the chute 41, and the vertical section of the support piece 71 can abut against the leftover material 51. The reinforcement 72 includes a reinforcement bolt 721 and a reinforcement nut 722, the reinforcement bolt 721 is disposed through the bottom wall of the chute 41, and the reinforcement nut 722 cooperates with the reinforcement bolt 721. By adjusting the reinforcing bolts 721, the two support pieces 71 can be fixed on the pendant 4, the support of the support pieces 71 on the corner material 51 can be further reinforced, and the mounting quality of the corner material 51 can be further improved.
The implementation principle of the dry-hanging ceramic tile structure in the embodiment of the application is as follows: before the steel frame 1 is installed, a hole is drilled in a designated place on the outer wall, then the expansion bolt 22 penetrates through the bracket 21, then the expansion bolt 22 is inserted into the designated hole, and the bracket 21 is fixed on the outer wall under the action of the expansion bolt 22. Then adjusting the connecting bolt 231, penetrating the connecting bolt 231 through the bracket 21 and the steel frame 1, and then sequentially adjusting the connecting nut 232 to realize the fixation of the steel frame 1 on the bracket 21. And then adjusting the dry hanging piece 4, penetrating the mounting bolt 31 through the dry hanging piece 4 and the steel frame 1 by adjusting the mounting bolt 31, and then fixing the dry hanging piece 4 on the steel frame 1 by mounting a nut 32. Then, the trimmings 51 are sequentially adjusted, and the trimmings 51 are inserted into the caulking grooves 511.
The support piece 71 is adjusted in sequence to enable the support piece 71 to move along the sliding groove 41, when the vertical section of the support piece 71 abuts against the leftover materials 51, the reinforcing bolt 721 is adjusted to enable the reinforcing bolt 721 to penetrate through the dry hanging piece 4, then the reinforcing nut 722 is adjusted to enable the support piece 71 to be fixed on the dry hanging piece 4, and the connection performance of the leftover materials 51 and the dry hanging piece 4 is improved. Then, paint viscose layer 52 in the one side that dry suspension member 4 and leftover bits 51 kept away from steelframe 1, then adjust ceramic tile 6, bond ceramic tile 6 on four leftover bits 51, operate in proper order, also paint viscose layer 52 between the ceramic tile 6, and then realize the installation of ceramic tile 6 at the outer wall.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. The utility model provides a hang ceramic tile structure futilely which characterized in that: including steelframe (1), fixing device (2), installation device (3), dry pendant (4), connecting device (5) and ceramic tile (6), fixing device (2) are used for fixing steelframe (1) on the outer wall, dry pendant (4) are fixed through installation device (3) on steelframe (1), keep away from dry pendant (4) the one end of steelframe (1) with connecting device (5) are connected, connecting device (5) include a plurality of leftover bits (51) and viscose layer (52), seted up on leftover bits (51) and supplied caulking groove (511) that dry pendant (4) carried out hanging, viscose layer (52) set up leftover bits (51) are kept away from one side of steelframe (1), ceramic tile (6) are installed on leftover bits (51) through viscose layer (52).
2. A dry-hang tile structure as claimed in claim 1, wherein: fixing device (2) include a plurality of brackets (21), expansion bolts (22) and connecting piece (23), bracket (21) are fixed on the outer wall through expansion bolts (22), steelframe (1) is fixed through connecting piece (23) on bracket (21).
3. A dry-hang tile structure as claimed in claim 2, wherein: connecting piece (23) are including connecting bolt (231) and coupling nut (232), connecting bolt (231) run through bracket (21) and steelframe (1) set up, coupling nut (232) are used for using with connecting bolt (231) cooperation.
4. A dry-hang tile structure as claimed in claim 1, wherein: the mounting device (3) comprises a plurality of mounting bolts (31) and mounting nuts (32), the mounting bolts (31) penetrate through the dry hanging piece (4) and the steel frame (1), and the mounting nuts (32) are used for being matched with the mounting bolts (31) for use.
5. A dry-hang tile structure as claimed in claim 1, wherein: the drying and hanging piece is characterized by further comprising a reinforcing device (7), wherein the reinforcing device (7) comprises a plurality of supporting sheets (71) and reinforcing pieces (72), the reinforcing pieces (72) are used for fixing the horizontal sections of the supporting sheets (71) on the drying and hanging piece (4), and the vertical sections of the supporting sheets (71) are used for abutting against the leftover materials (51).
6. A dry-hang tile structure as claimed in claim 5, wherein: the reinforcing part (72) comprises a plurality of reinforcing bolts (721) and reinforcing nuts (722), the reinforcing bolts (721) penetrate through the pendant (4), and the reinforcing nuts (722) are used for being matched with the reinforcing bolts (721) for use.
7. A dry-hang tile structure as claimed in claim 5, wherein: the dry hanging piece (4) is provided with a sliding groove (41), the sliding groove (41) is arranged along the length direction of the dry hanging piece (4), and the horizontal section of the supporting piece (71) can slide along the sliding groove (41).
8. A dry-hang tile structure as claimed in claim 1, wherein: an adhesive layer (52) is arranged between the ceramic tiles (6).
CN202122641564.1U 2021-10-30 2021-10-30 Hang ceramic tile structure futilely Active CN216042383U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122641564.1U CN216042383U (en) 2021-10-30 2021-10-30 Hang ceramic tile structure futilely

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122641564.1U CN216042383U (en) 2021-10-30 2021-10-30 Hang ceramic tile structure futilely

Publications (1)

Publication Number Publication Date
CN216042383U true CN216042383U (en) 2022-03-15

Family

ID=80612817

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122641564.1U Active CN216042383U (en) 2021-10-30 2021-10-30 Hang ceramic tile structure futilely

Country Status (1)

Country Link
CN (1) CN216042383U (en)

Similar Documents

Publication Publication Date Title
CN101131002A (en) Mould-locking assembled water-proof heat-insulating slab and construction method thereof
CN217580989U (en) Assembled built-in integral bathroom structure
CN210369435U (en) Outer net piece formula wall body heat preservation system of decorating
CN206337788U (en) A kind of top surface moulding
CN216042383U (en) Hang ceramic tile structure futilely
CN202416777U (en) Installation fastener for building
CN1036540C (en) Anchor board system
KR101011782B1 (en) A aluminum plus molding and that of construction method
CN112900783A (en) Assembled wallboard dry hanging device and installation method thereof
CN112343293A (en) Foamed aluminum graphene geothermal floor
CN2856248Y (en) Dry hanging building decorative structure of movable fiber ceramic boards
CN111851898A (en) Wall body calcium silicate veneer hangs assembly system futilely
KR102007970B1 (en) Wall panel finishing apparatus of removable finishing panel structure
CN210395921U (en) Assembled dry-process fine-assembling system
CN110130520B (en) Assembly type wall surface strong magnetic installation system
CN211421942U (en) Toilet system capable of being assembled quickly
CN110952736B (en) Production method of decorative plate for dry hanging installation
CN203347055U (en) Building material curtain wall mounting fastener
CN111962790A (en) Dry hanging structure, veneer system and installation method of veneer system
CN214696612U (en) Kitchen wall and floor decoration structure
CN215888882U (en) Assembled furred ceiling
CN215253866U (en) End connection node structure of gypsum board suspended ceiling
CN214062185U (en) Colored coating knurling aluminum plate of self-adaptation environment
CN202577865U (en) Fastener for installation of construction materials
CN212957796U (en) Use assembled bathroom of ceramic sheet metal

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant