- CN216007010U CN216007010U CN202121658543.4U CN202121658543U CN216007010U CN 216007010 U CN216007010 U CN 216007010U CN 202121658543 U CN202121658543 U CN 202121658543U CN 216007010 U CN216007010 U CN 216007010U
- Authority
- CN
- China
- Prior art keywords
- well
- pipe
- precipitation
- construction structure
- sand gravel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Sewage (AREA)
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
A sand gravel section forepoling well precipitation construction structure relates to the field of building construction. The device comprises a precipitation well and a rainwater inspection well, wherein a well mouth of the precipitation well is provided with a well cover of the precipitation well, a well cover of the inspection well is arranged at a well mouth of the rainwater inspection well, a water filter pipe is arranged at the bottom position in the precipitation well, and a gravel layer is filled between the water filter pipe and the precipitation well; the top opening of the water filtering pipe is butted with a well pipe, a drainage branch pipe is led out from the well pipe and is connected into a rainwater inspection well, and a construction dewatering drainage pipe and a municipal rainwater main pipe are led and connected onto the rainwater inspection well. The utility model has the beneficial effects that: the construction structure comprises the dewatering well and the rainwater inspection well, the structure is reasonable, the sectional construction is convenient, the normal excavation of earthwork in the foundation pit can be ensured, the safety of engineering is improved, and the total amount of extracted underground water is minimum and the engineering investment is most economical on the premise of achieving the dewatering of the foundation pit.
Description
Technical Field
A sand gravel section forepoling well precipitation construction structure relates to the field of building construction.
Background
At present, a foundation pit is excavated in a sand gravel section, and the defects that underground burial is shallow, surface water is rich, the construction period is influenced by precipitation, construction processes and the like, the problems of foundation pit settlement, slope collapse, substrate water seepage and the like frequently occur in construction, and the influence is brought to the construction operation stage. The existing solutions include measures such as water intercepting tanks, impervious walls, sheet piles or grouting curtains, drooping skirts and the like, and although the methods can block underground water, the methods have the disadvantages of large water pumping amount, large construction difficulty and poor economic benefit.
Disclosure of Invention
The utility model aims to solve the problems that the water pumping quantity is relatively small and the construction difficulty is reduced. The technical scheme is as follows:
a sand gravel section leading pipe well dewatering construction structure is characterized by comprising a dewatering well and a rainwater inspection well, wherein the mouth of the dewatering well is provided with a cover of the dewatering well, the mouth of the rainwater inspection well is provided with a cover of the inspection well, a water filter pipe is arranged at the bottom in the dewatering well, and a gravel layer is filled between the water filter pipe and the dewatering well; the top opening of the water filtering pipe is butted with a well pipe, a drainage branch pipe is led out from the well pipe and is connected into a rainwater inspection well, and a construction dewatering drainage pipe and a municipal rainwater main pipe are led and connected onto the rainwater inspection well.
The bottom of the strainer is wrapped with a nylon net.
The submersible pump is installed in the water filtering pipe, and the drainage branch pipe is connected to the drainage end of the submersible pump.
The dewatering well is composed of a concrete pipe with the inner diameter of 300-500 mm.
The strainer is of an annular structure.
Compared with the prior art, the utility model has the beneficial effects that:
1. the construction structure comprises the dewatering well and the rainwater inspection well, the structure is reasonable, the segmental construction is convenient, and the normal excavation of earthwork in the foundation pit can be ensured.
2. The sand gravel section forepoling well precipitation construction structure enables the underground water level to be kept below the bottom of the foundation pit by 2m during foundation pit excavation and underground structure construction, improves the safety of engineering, and enables the total amount of extracted underground water to be minimum and the engineering investment to be most economical on the premise of achieving foundation pit precipitation.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without inventive exercise.
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic representation of a tube well configuration of the present invention;
FIG. 3 is a schematic view of the drainage pipe structure of dewatering well according to the present invention;
FIG. 4 is a schematic view of the drainage pipe structure of the rainwater inspection well of the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1 to 4, a sand gravel section leading pipe well precipitation construction structure comprises a precipitation well 4 and a rainwater inspection well 7, wherein a precipitation well cover 5 is arranged at the mouth of the precipitation well, an inspection well cover 8 is arranged at the mouth of the rainwater inspection well, a water filter pipe 2 is arranged at the bottom in the precipitation well 4, a gravel layer 3 formed by gravel is filled between the water filter pipe 2 and the precipitation well 4, and the gravel layer 3 plays a role of filtering; butt joint well casing 1 is welded in the top mouthful position of strainer 2, draws forth water drainage branch 6 and inserts to rainwater inspection shaft 7 in from well casing 1, draws on rainwater inspection shaft 7 to connect and has construction precipitation drain pipe 9 and municipal rainwater main pipe 10, realizes the rainwater outward emission based on construction precipitation drain pipe 9 and municipal rainwater main pipe 10.
The bottom of the strainer 2 is wrapped with a nylon net for filtering.
A submersible pump 11 is arranged in the strainer 2, and a branch drain pipe 6 is connected to the drain end of the submersible pump 11.
The dewatering well 4 is composed of a concrete pipe with the inner diameter of 300-500 mm.
The distance between the top opening of the well pipe 1 and the wellhead of the dewatering well 4 is 200-300 mm.
The strainer 2 is of an annular structure.
The filter pipes 2 are arranged on the inner wall of the precipitation well 4 at certain intervals. Namely, a section of the water filtering pipe 2 is arranged at a distance for facilitating water filtering.
Claims (7)
1. A sand gravel section leading pipe well precipitation construction structure is characterized by comprising a precipitation well (4) and a rainwater inspection well (7), wherein the mouth of the precipitation well is provided with a precipitation well cover (5), the mouth of the rainwater inspection well is provided with an inspection well cover (8), a water filter pipe (2) is arranged at the bottom in the precipitation well (4), and a gravel layer (3) is filled between the water filter pipe (2) and the precipitation well (4); the top opening of the water filtering pipe (2) is butted with the well pipe (1), a drainage branch pipe (6) is led out from the well pipe (1) and is connected into a rainwater inspection well (7), and the rainwater inspection well (7) is connected with a construction rainfall drainage pipe (9) and a municipal rainwater main pipe (10).
2. The sand gravel section forepoling well precipitation construction structure is characterized in that the bottom of the water filter pipe (2) is wrapped with a nylon net.
3. The sand gravel section forepoling well precipitation construction structure is characterized in that a submersible pump (11) is installed in the strainer pipe (2), and the drain branch pipe (6) is connected to the drain end of the submersible pump (11).
4. The sand gravel section forepoling well precipitation construction structure is characterized in that the precipitation well (4) is composed of a concrete pipe with the inner diameter of 300-500 mm.
5. The sand gravel section forepoling well precipitation construction structure is characterized in that the distance from the top opening of the well pipe (1) to the wellhead of the precipitation well (4) is 200-300 mm.
6. The sand gravel section forepoling well precipitation construction structure is characterized in that the strainer pipe (2) is of an annular structure.
7. The sand gravel section forepoling well precipitation construction structure is characterized in that the filter pipes (2) are arranged at intervals on the inner wall of the precipitation well (4).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121658543.4U CN216007010U (en) | 2021-07-20 | 2021-07-20 | Sand gravel section leading pipe well precipitation construction structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121658543.4U CN216007010U (en) | 2021-07-20 | 2021-07-20 | Sand gravel section leading pipe well precipitation construction structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN216007010U true CN216007010U (en) | 2022-03-11 |
Family
ID=80590366
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202121658543.4U Active CN216007010U (en) | 2021-07-20 | 2021-07-20 | Sand gravel section leading pipe well precipitation construction structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN216007010U (en) |
-
2021
- 2021-07-20 CN CN202121658543.4U patent/CN216007010U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102418347B (en) | Drainage construction method for blind drain and sump wells in deep foundation pit | |
CN103046565B (en) | Draining method for ultra-deep batholith deep foundation pit | |
CN212896422U (en) | Deep foundation pit water intercepting and draining device | |
CN109736340B (en) | Dewatering device and method for guaranteeing integrity of cushion layer by reserving dewatering well on foundation slab | |
CN102383437A (en) | Well point positioned pumping tubular well and well point positioned pumping method | |
CN202730786U (en) | Well-sealing waterproof construction structure of dewatering well | |
CN209723004U (en) | Built-in precipitation structure of raft and shut-in well structure of precipitation well | |
CN202247920U (en) | Construction structure for water drainage of blind ditch and water collecting wells in deep foundation pit | |
CN204080839U (en) | A kind of Yield rainfall relation device | |
CN105672335A (en) | Construction method for sump precipitation | |
CN216007010U (en) | Sand gravel section leading pipe well precipitation construction structure | |
CN214143998U (en) | Sewage collecting pipe network arrangement structure for households along river | |
CN108625402A (en) | Foundation pit fertilizer slot ponding processing method | |
CN209115282U (en) | A kind of offshore waters area automatic water pumping device for water | |
CN203284787U (en) | Composite pipe well precipitation system | |
CN212896367U (en) | Can effectively prevent building foundation ditch of rainwater infiltration | |
CN214884227U (en) | Prevent that ground from sinking and causing construction equipment of damage to municipal drainage pipe network | |
CN214460675U (en) | Construction structures is used safely to old basement | |
CN218405510U (en) | Water collecting port of downcomer well | |
CN212316962U (en) | Basement drainage device that falls | |
CN218322828U (en) | Hidden type external drainage precipitation well | |
CN212270980U (en) | Cage device in cage of subway station bottom plate drainage open well | |
CN219639656U (en) | Municipal administration pipeline rainy season anti-floating device | |
CN103669333A (en) | Slide-resistant pile facilitating vacuum rainfall | |
CN218970049U (en) | Deep foundation pit piping drainage device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |