CN215999294U - Pre-buried processing frock - Google Patents

Pre-buried processing frock Download PDF

Info

Publication number
CN215999294U
CN215999294U CN202122449111.9U CN202122449111U CN215999294U CN 215999294 U CN215999294 U CN 215999294U CN 202122449111 U CN202122449111 U CN 202122449111U CN 215999294 U CN215999294 U CN 215999294U
Authority
CN
China
Prior art keywords
base
plate
buried
fixed mounting
limiting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122449111.9U
Other languages
Chinese (zh)
Inventor
熊鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Huiton Shenfa Steel Structure Co Ltd
Original Assignee
Guizhou Huiton Shenfa Steel Structure Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Huiton Shenfa Steel Structure Co Ltd filed Critical Guizhou Huiton Shenfa Steel Structure Co Ltd
Priority to CN202122449111.9U priority Critical patent/CN215999294U/en
Application granted granted Critical
Publication of CN215999294U publication Critical patent/CN215999294U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to an embedded part processing technology field specifically is a pre-buried processing frock, the on-line screen storage device comprises a base, fixed mounting has four spacing posts on the base, is located equal fixed mounting between two spacing posts on the same vertical line has a connecting plate, four pre-buried steel sheet has been placed at the top of spacing post, be provided with a plurality of crab-bolts on the pre-buried steel sheet, be provided with the stop gear who has the reinforcing plate on the base. Through setting up the base, four spacing posts and two connecting plates, can fix spacingly to embedded steel plate when carrying out the built-in fitting man-hour, conveniently carry out the welding operation of crab-bolt, compare in current mode, great improvement work efficiency, and saved the manual work, through setting up the limiting plate, lead to groove and gag lever post, when carrying out the built-in fitting man-hour, can be so that the crab-bolt is in the vertical state all the time, make manufacturing process stability also obtain the assurance, thereby the whole quality of built-in fitting processing has been improved, and structural configuration is simple, low in manufacturing cost is honest and clean.

Description

Pre-buried processing frock
Technical Field
The utility model relates to an embedded part processing technology field specifically is a pre-buried processing frock.
Background
Along with the continuous development of science and technology, in current production activity, including building, rail transit, construction sites such as utility tunnel, the rate of utilization and the range of application of built-in fitting are more and more extensive, the application emergency of product is more and more, in the face of service behavior's variety, for guaranteeing pre-buried effect, it is more and more strict to the pre-buried effect that used frock operation requirement of built-in fitting and reach, the built-in fitting is exactly the component of preinstallation in hidden engineering, be the structure accessory of settling when the structure is pour, overlap joint when being used for building superstructure, it is fixed to do benefit to the installation of external engineering equipment basis, the built-in fitting is mostly made by the metal, for example reinforcing bar or cast iron, also can use wood, rigid material such as plastics.
The existing embedded part machining mode needs two persons to cooperate to manufacture, one person holds up the reinforcing steel bar and one person welds, the mode is not convenient for fixing and operating the embedded part, the working efficiency is low, the time and the labor are wasted, the vertical precision of the anchor bolt is difficult to guarantee in the embedded part machining process, the stability of the manufacturing process is poor, and the overall quality of the embedded part is poor.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a pre-buried processing frock to solve the problem that proposes among the above-mentioned background art. In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a pre-buried processing frock, includes the base, fixed mounting has four spacing posts on the base, is located two on the same vertical line equal fixed mounting has a connecting plate, four between the spacing post pre-buried steel sheet has been placed at the top of spacing post, be provided with a plurality of crab-bolts on the pre-buried steel sheet, be provided with the stop gear who has the reinforcing plate on the base.
Preferably, stop gear includes the limiting plate, leads to groove and gag lever post, wherein two fixed mounting has the reinforcing plate between the spacing post, fixed mounting has two limiting plates on the reinforcing plate, two the bottom of limiting plate all runs through and has seted up logical groove, the gag lever post is through leading to groove movable mounting on the base.
Preferably, the limiting plate is provided with a plurality of through grooves which are uniformly distributed on the limiting plate, and the through grooves are semicircular.
Preferably, the limiting rod is cylindrical, the size of the limiting rod is matched with that of the through grooves, and the number of the limiting rods corresponds to that of the through grooves.
Preferably, the base, the limiting columns and the connecting plates are made of steel, and the two connecting plates are equally contacted with the two side faces of the embedded steel plate respectively.
Preferably, a plurality of through-holes are formed in the top of the embedded steel plate in a penetrating mode, and the anchor bolts are arranged on the embedded steel plate through the corresponding through-holes respectively.
Compared with the prior art, the beneficial effects of the utility model are that:
in the utility model, through the matching use of the base, the four limit columns and the two connecting plates, the embedded steel plate can be fixed and limited when the embedded part is processed, the welding operation of the anchor bolt is convenient to carry out, compared with the existing two-person operation mode, the operation is more convenient and faster, the work efficiency is greatly improved, and the labor is saved;
the utility model discloses in, use through the cooperation that sets up limiting plate, logical groove and gag lever post, when carrying out the built-in fitting man-hour, can be so that the crab-bolt is in the vertical state all the time for manufacturing process stability has also obtained the assurance, thereby has improved the whole quality of built-in fitting processing, and structural configuration is simple, low in manufacturing cost, simple operation.
Drawings
Fig. 1 is a schematic view of the structure of the present invention;
fig. 2 is a schematic top view of the base of the present invention;
fig. 3 is a schematic view of a top view structure of the connection between the limiting post and the embedded steel plate of the present invention;
fig. 4 is the utility model provides a limiting plate spatial structure schematic diagram.
In the figure: 1. a base; 2. a limiting column; 3. pre-burying a steel plate; 4. a through hole; 5. an anchor bolt; 6. a limiting plate; 7. a through groove; 8. a limiting rod; 9. a connecting plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by the staff of ordinary skill in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1 to 4, the present invention provides a technical solution: the utility model provides a pre-buried processing frock, the on-line screen storage device comprises a base 1, fixed mounting has four spacing posts 2 on the base 1, four spacing posts 2 set up four corners at base 1 respectively, equal fixed mounting has connecting plate 9 between two spacing posts 2 that are located same vertical line, the orthographic projection of connecting plate 9 is "L" shape, buried steel sheet 3 has been placed at four spacing post 2's top, four corners of buried steel sheet 3 are located corresponding spacing post 2 respectively, be provided with a plurality of crab-bolts 5 on the buried steel sheet 3 in advance, be provided with the stop gear who has the reinforcing plate on the base 1.
In this embodiment, as shown in fig. 1 and fig. 2, stop gear includes limiting plate 6, leads to groove 7 and gag lever post 8, and wherein fixed mounting has the reinforcing plate between two spacing posts 2, and fixed mounting has two limiting plates 6 on the reinforcing plate, and two limiting plates 6's bottom has all been run through and has been seted up logical groove 7, and gag lever post 8 is through leading to groove 7 movable mounting on base 1, two limiting plates 6 parallel arrangement each other.
In this embodiment, as shown in fig. 1 and 4, the limiting plate 6 is provided with a plurality of through grooves 7, the plurality of through grooves 7 are uniformly distributed on the limiting plate 6, and the plurality of through grooves 7 are semicircular.
In this embodiment, as shown in fig. 1 and 2, the limiting rod 8 is cylindrical, the size of the limiting rod 8 matches the size of the through groove 7, and the number of the limiting rods 8 corresponds to the number of the through grooves 7.
In this embodiment, as shown in fig. 1 and 3, the base 1, the limiting column 2, and the connecting plates 9 are made of steel, and the two connecting plates 9 are respectively in contact with two side surfaces of the embedded steel plate 3.
In this embodiment, as shown in fig. 3, a plurality of through holes 4 are formed through the top of the embedded steel plate 3, and a plurality of anchor bolts 5 are respectively disposed on the embedded steel plate 3 through the corresponding through holes 4.
The utility model discloses a use method and advantage: when the embedded part machining tool is used, the working process is as follows:
as shown in figures 1, 2, 3 and 4, when the device is used, firstly, the embedded steel plate 3 is placed between the tops of four limit columns 2, and the two sides of the embedded steel plate 3 are contacted with corresponding connecting plates 9, the embedded steel plate 3 can be fixed and limited when an embedded part is processed by matching the base 1, the four limit columns 2 and the two connecting plates 9, so that the welding operation of the anchor bolts 5 is convenient, compared with the existing two-person operation mode, the operation is more convenient and quicker, the working efficiency is greatly improved, the labor is saved, then a plurality of anchor bolts 5 are installed on the embedded steel plate 3 through corresponding through holes 4, then a plurality of limit rods 8 are inserted from one side of the base 1, so that the same limit rod 8 respectively penetrates through two through grooves 7 on the same vertical line on the two limit plates 6, and the limit rod 8 is limited, prevent the off tracking, repeated operation, then the welding operation of built-in fitting carries out, use through the clearance between two adjacent gag lever posts 8 and the cooperation of limiting plate 6, it is spacing to crab-bolt 5, through setting up limiting plate 6, it uses to lead to groove 7 and gag lever post 8 cooperation, when carrying out the built-in fitting man-hour, can be so that crab-bolt 5 is in the vertical state all the time, make manufacturing process stability also obtain the assurance, thereby the whole quality of built-in fitting processing has been improved, and structural configuration is simple, low manufacturing cost, and convenient operation.
The foregoing shows and describes the general principles, essential features, and advantages of the invention. It should be understood by those skilled in the art that the present invention is not limited by the above embodiments, and the description in the above embodiments and the description is only preferred examples of the present invention, and is not intended to limit the present invention, and that there may be various changes and modifications without departing from the spirit and scope of the present invention, and these changes and modifications all fall within the scope of the claimed invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (6)

1. The utility model provides a pre-buried processing frock, includes base (1), its characterized in that: fixed mounting has four spacing posts (2) on base (1), is located two on same vertical line equal fixed mounting has connecting plate (9), four between spacing post (2) pre-buried steel sheet (3) have been placed at the top of spacing post (2), be provided with a plurality of crab-bolts (5) on pre-buried steel sheet (3), be provided with the stop gear who has the reinforcing plate on base (1).
2. The pre-buried processing tool according to claim 1, characterized in that: stop gear includes limiting plate (6), leads to groove (7) and gag lever post (8), wherein two fixed mounting has the reinforcing plate between spacing post (2), fixed mounting has two limiting plate (6) on the reinforcing plate, two the bottom of limiting plate (6) all runs through and has seted up logical groove (7), gag lever post (8) are through leading to groove (7) movable mounting on base (1).
3. A pre-buried processing frock according to claim 2, characterized in that: the limiting plate (6) is provided with a plurality of through grooves (7), the through grooves (7) are evenly distributed on the limiting plate (6), and the through grooves (7) are semicircular.
4. A pre-buried processing frock according to claim 2, characterized in that: the limiting rod (8) is cylindrical, the size of the limiting rod (8) is matched with that of the through groove (7), and the number of the limiting rods (8) corresponds to that of the through grooves (7).
5. The pre-buried processing tool according to claim 1, characterized in that: base (1), spacing post (2) and connecting plate (9) are the steel preparation and form, two connecting plate (9) are equallyd divide and are do not touched with the both sides face of pre-buried steel sheet (3) mutually.
6. The pre-buried processing tool according to claim 1, characterized in that: a plurality of through holes (4) are formed in the top of the embedded steel plate (3) in a penetrating mode, and a plurality of anchor bolts (5) are arranged on the embedded steel plate (3) through the corresponding through holes (4) respectively.
CN202122449111.9U 2021-10-12 2021-10-12 Pre-buried processing frock Active CN215999294U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122449111.9U CN215999294U (en) 2021-10-12 2021-10-12 Pre-buried processing frock

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122449111.9U CN215999294U (en) 2021-10-12 2021-10-12 Pre-buried processing frock

Publications (1)

Publication Number Publication Date
CN215999294U true CN215999294U (en) 2022-03-11

Family

ID=80583605

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122449111.9U Active CN215999294U (en) 2021-10-12 2021-10-12 Pre-buried processing frock

Country Status (1)

Country Link
CN (1) CN215999294U (en)

Similar Documents

Publication Publication Date Title
CN215999294U (en) Pre-buried processing frock
CN212420249U (en) Quick positioning mould tool suitable for machining reinforcement cages with different diameters
CN216740781U (en) Small-size steel stand positioner
CN210342237U (en) Steel construction post roof beam connecting elements convenient to installation
CN211113703U (en) Container building module foundation position location connection structure
CN214885541U (en) Splicing assembly for mounting building templates
CN211735781U (en) Modular assembly type steel structure house body
CN110315267B (en) Tower crane slice type standard knot assembly welding positioning tool
CN210857536U (en) Connecting structure of building frame
CN210395642U (en) Detachable assembly type steel structure building connecting node
CN205496621U (en) Be used for crane girder rail hole processing frock structure
CN207026249U (en) Rush elongated hole die craft equipment on special-shaped angle steel
CN205443953U (en) Removable work platform is removed in construction of railway pier shaft
CN205005002U (en) T type tile photovoltaic adaptor
CN220954665U (en) Aluminum template connection structure
CN213417580U (en) Bridge support template
CN210888062U (en) Beam bottom supporting base of low-wall aluminum mold
CN210482558U (en) Connecting device for upright post and cross beam of heavy steel structure house
CN213918810U (en) A do not have reinforcing apparatus that draws for aluminum alloy pipe gallery mould
CN213653767U (en) Steel plate welding joint structure of low-rise assembly type composite wall house
CN212078695U (en) Building templates connection structure
CN112627511B (en) Adjustable template clamp for pouring box type column base and using method thereof
CN218205832U (en) Side support steel structure for factory building wall construction
CN217998392U (en) Prefabricated house convenient to equipment
CN213268379U (en) Steel member support column

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A kind of embedded processing tooling

Effective date of registration: 20221229

Granted publication date: 20220311

Pledgee: China Construction Bank Corporation Guiyang Huaxi sub branch

Pledgor: GUIZHOU HUITONG SHENFA STEEL STRUCTURE Co.,Ltd.

Registration number: Y2022980029511

PC01 Cancellation of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Granted publication date: 20220311

Pledgee: China Construction Bank Corporation Guiyang Huaxi sub branch

Pledgor: GUIZHOU HUITONG SHENFA STEEL STRUCTURE Co.,Ltd.

Registration number: Y2022980029511