CN215925687U - Steel case roof beam butt joint levelling device - Google Patents

Steel case roof beam butt joint levelling device Download PDF

Info

Publication number
CN215925687U
CN215925687U CN202121991231.5U CN202121991231U CN215925687U CN 215925687 U CN215925687 U CN 215925687U CN 202121991231 U CN202121991231 U CN 202121991231U CN 215925687 U CN215925687 U CN 215925687U
Authority
CN
China
Prior art keywords
supporting
supporting beam
welded
plate
jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121991231.5U
Other languages
Chinese (zh)
Inventor
黄振威
王安文
于策
李晔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
Original Assignee
Road and Bridge International Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN202121991231.5U priority Critical patent/CN215925687U/en
Application granted granted Critical
Publication of CN215925687U publication Critical patent/CN215925687U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a steel box girder butt-joint leveling device which comprises a supporting beam, a counter-force beam and a jack, wherein the rear end of the supporting beam is connected with one end of the counter-force beam through a bolt; a U-shaped clamp is welded at the front end of the supporting beam, the U-shaped clamp comprises a connecting plate, the connecting plate is welded with the front end of the supporting beam, two parallel clamping plates are welded at two sides of the connecting plate, and two fastening bolts penetrate through one clamping plate; a supporting plate vertical to the longitudinal axis of the supporting beam is welded on the supporting beam, an arc-shaped clamping groove is formed in the top edge of the supporting plate, the cylinder body of the jack is supported in the arc-shaped clamping groove in the supporting plate, and the base is supported on the counter-force beam. The utility model clamps the stiffening rib on the inner side of the installed steel box girder through the clamp, and the jack pushes the stiffening rib on the inner side of the steel box girder to be installed to level, so that the panel of the steel box girder is not damaged, and the installation and disassembly speed is high.

Description

Steel case roof beam butt joint levelling device
Technical Field
The utility model belongs to the technical field of bridge construction, and relates to an aligning and leveling device between sections when steel box girders or steel structure cable towers of a steel structure bridge are installed in sections.
Background
When the steel box girder is installed in sections, the end surfaces of two sections need to be aligned and then welded, and generally, when one section is installed, the crane lifts the other section to be in butt joint with the installed section. Because the crane can not accurately control the height of the beam section to be installed, an L-shaped reaction frame is generally welded on a panel of the installed steel beam section in construction, one end of the L-shaped reaction frame extends to the upper part of the beam section to be installed, a jack is arranged between the panel of the section to be installed and the L-shaped reaction frame, when the crane lifts the beam section to be installed to be slightly higher than the installed beam section, the beam section to be installed is pushed downwards by the jack, and the two beam sections are leveled through the matching of the crane and the jack. The method is easy to cause the deformation of the steel box girder panel, and secondary damage can be caused to the steel girder panel when the reaction frame is cut off after the butt joint is finished.
Disclosure of Invention
The utility model aims to solve the problems and provides a steel box girder butt joint leveling device which avoids damage to a steel box girder base metal.
The technical scheme of the utility model is as follows:
the utility model provides a steel case roof beam butt joint levelling device which characterized in that: the device comprises a supporting beam, a counter-force beam perpendicular to the supporting beam and a jack, wherein the rear end of the supporting beam is fixedly connected with one end of the counter-force beam through a bolt; a U-shaped clamp is welded at the front end of the supporting beam, the U-shaped clamp comprises a connecting plate, the connecting plate is perpendicular to the longitudinal axis of the supporting beam and is welded with the front end of the supporting beam, two clamping plates which are parallel to each other are welded on two sides of the connecting plate, and two fastening bolts penetrate through one clamping plate; the supporting beam is welded with a supporting plate vertical to the longitudinal axis of the supporting beam, the top edge of the supporting plate is provided with an arc-shaped clamping groove, the cylinder body of the jack is supported in the arc-shaped clamping groove in the supporting plate, and the base of the jack is supported on the counter-force beam.
The utility model clamps the stiffening rib on the inner side of the installed steel box girder through the clamp, and simultaneously the jack pushes the stiffening rib on the inner side of the steel box girder to be installed to level, so that the panel of the steel box girder is not damaged; the leveling device is not welded with the steel box girder, the mounting and dismounting speed is high, and the device can be used in a turnover way. The utility model can also be used for butt joint leveling when the steel structure cable tower is installed in sections.
Drawings
FIG. 1 is a schematic side view of the present invention;
FIG. 2 is a sectional view A-A of FIG. 1;
FIG. 3 is a cross-sectional view B-B of FIG. 1;
FIG. 4 is a forward-of-bridge state diagram of the present invention for leveling two steel box beams;
FIG. 5 is a cross-bridge state view of the present invention for leveling two steel box girders;
figure 6 is a state of use diagram of the present invention for leveling two steel tower segments.
Detailed Description
As shown in fig. 1, 2 and 3, the utility model comprises a supporting beam 1, a reaction beam 2 perpendicular to the supporting beam, and a jack 3, wherein the rear end of the supporting beam is fixedly connected with one end of the reaction beam through a 4-bolt; a U-shaped clamp is welded at the front end of the supporting beam 1, the U-shaped clamp comprises a connecting plate 5, the connecting plate is perpendicular to the longitudinal axis of the supporting beam and is welded with the front end of the supporting beam, two clamping plates 6 which are parallel to each other are welded on two sides of the connecting plate, and two fastening bolts 7 penetrate through one clamping plate 6; a supporting plate 8 perpendicular to the longitudinal axis of the supporting beam is welded on the supporting beam 1, an arc-shaped clamping groove is formed in the top edge of the supporting plate, the barrel body of the jack 3 is supported in the arc-shaped clamping groove in the supporting plate 8, and the base of the jack 3 is supported on the counter-force beam 2.
As shown in fig. 4 and 5, the present invention is used for leveling two butted steel box girder segments, wherein one girder segment is installed and fixed, the other girder segment is to be installed in a hoisting state, at the butt joint end of the two segments in the steel box girder, a ribbed plate 9 on the bottom plate of the installed girder segment 10 is placed between two clamping plates 6 of the U-shaped clamp, and two fastening bolts 7 are tightened to clamp the ribbed plate 9; the piston end of the jack 3 faces a ribbed plate on a bottom plate of the beam section 11 to be installed, the jack is started to push the beam section 11 to be installed downwards, and top plates of the two beam sections are leveled and then welded.
FIG. 6 shows the use state of the leveling device of the utility model for leveling two steel tower segments, the lower part is an installed steel tower segment 12, the upper part is a steel tower segment 13 to be installed, the inner wall of the side plate of the steel tower segment is also provided with a ribbed plate, the installation and working principle of the leveling device of the utility model is the same as the leveling of the steel box girder, and a jack 3 transversely pushes the steel tower segment 12 to be installed for leveling.

Claims (1)

1. The utility model provides a steel case roof beam butt joint levelling device which characterized in that: the device comprises a supporting beam, a counter-force beam perpendicular to the supporting beam and a jack, wherein the rear end of the supporting beam is fixedly connected with one end of the counter-force beam through a bolt; a U-shaped clamp is welded at the front end of the supporting beam, the U-shaped clamp comprises a connecting plate, the connecting plate is perpendicular to the longitudinal axis of the supporting beam and is welded with the front end of the supporting beam, two clamping plates which are parallel to each other are welded on two sides of the connecting plate, and two fastening bolts penetrate through one clamping plate; the supporting beam is welded with a supporting plate vertical to the longitudinal axis of the supporting beam, the top edge of the supporting plate is provided with an arc-shaped clamping groove, the cylinder body of the jack is supported in the arc-shaped clamping groove in the supporting plate, and the base of the jack is supported on the counter-force beam.
CN202121991231.5U 2021-08-23 2021-08-23 Steel case roof beam butt joint levelling device Active CN215925687U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121991231.5U CN215925687U (en) 2021-08-23 2021-08-23 Steel case roof beam butt joint levelling device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121991231.5U CN215925687U (en) 2021-08-23 2021-08-23 Steel case roof beam butt joint levelling device

Publications (1)

Publication Number Publication Date
CN215925687U true CN215925687U (en) 2022-03-01

Family

ID=80420289

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121991231.5U Active CN215925687U (en) 2021-08-23 2021-08-23 Steel case roof beam butt joint levelling device

Country Status (1)

Country Link
CN (1) CN215925687U (en)

Similar Documents

Publication Publication Date Title
CN211172382U (en) Steel beam connecting joint
CN102995571B (en) Method for prepressing single large-tonnage temporary steel pipe support and then resisting beam bottom during dismantling bridge beam body, and device thereof
CN103669218B (en) Novel steel-concrete combined section steel box girder module and assembling method thereof
CN214264430U (en) Take corbel H shaped steel roof beam butt joint crater adjusting device that staggers
CN215925687U (en) Steel case roof beam butt joint levelling device
CN215925671U (en) Quick butt joint levelling device of steel case roof beam
CN215696950U (en) Portable steel box girder welding assembly deformation straightening device
CN215291569U (en) Be used for steel construction to reform transform centre sill reinforcement hoisting device
CN113073563A (en) Fixing device for upper chord member and I-steel distribution beam of Bailey beam
CN220868875U (en) Temporary support secondary beam installation device for floor carrier plate
CN216194054U (en) Guide beam for steel box girder pushing construction
CN214879585U (en) Semi-mechanized construction hoisting point device
CN217652147U (en) Steel-pipe pile lateral wall bracket welding reinforced structure
CN218931504U (en) Steel tower column segment adjusting and positioning tool
CN221191233U (en) Multifunctional hoisting connecting device
CN215976865U (en) Alignment matching piece between beam sections
CN219175295U (en) Bailey beam combined deepwater cofferdam
CN217398221U (en) Auxiliary tool for hoisting large flue in limited space
CN215164721U (en) Fixing device for upper chord member and I-steel distribution beam of Bailey beam
CN212774320U (en) Trolley for tunnel construction
CN213134573U (en) H-shaped steel distortion correction clamp
CN211973861U (en) Connecting component for assembled steel structure building
CN217458425U (en) Lifting appliance for lifting bridge deck concrete baffle
CN215755917U (en) Exempt from to open hole girder steel hoisting device
CN220814547U (en) High-strength fracture-preventing steel beam

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant