CN215886192U - Lifting device for building capable of performing overweight early warning - Google Patents

Lifting device for building capable of performing overweight early warning Download PDF

Info

Publication number
CN215886192U
CN215886192U CN202122452814.7U CN202122452814U CN215886192U CN 215886192 U CN215886192 U CN 215886192U CN 202122452814 U CN202122452814 U CN 202122452814U CN 215886192 U CN215886192 U CN 215886192U
Authority
CN
China
Prior art keywords
lifting
basket
overweight
lifting device
hanging basket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122452814.7U
Other languages
Chinese (zh)
Inventor
李慧
张旭军
白旭军
周旭勇
夏烨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Construction Engineering Group Co Ltd
Original Assignee
Shanxi Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Construction Engineering Group Co Ltd filed Critical Shanxi Construction Engineering Group Co Ltd
Priority to CN202122452814.7U priority Critical patent/CN215886192U/en
Application granted granted Critical
Publication of CN215886192U publication Critical patent/CN215886192U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Control And Safety Of Cranes (AREA)

Abstract

The utility model discloses a lifting device for building capable of warning overweight, which belongs to the technical field of lifting devices and comprises a supporting seat, a supporting frame is arranged at the top of the supporting seat, a connecting frame is arranged at the top of the supporting frame, a lifting component is arranged on the connecting frame, an auxiliary component is arranged on a hanging basket, the lifting device comprises an overload induction alarm device which is arranged at the inner side of the hanging basket and used for monitoring bearing materials in real time, and a buffer column which is connected with the bottom of the hanging basket and is matched with a guide groove through a limiting seat, the hanging basket is guided and limited, so that the hanging basket can be stably lifted and descended when the hoister works, the condition of left and right shaking is avoided, moreover, the overload induction alarm device carries materials to monitor in real time, prevents the carried materials from being overweight to influence the safe operation of the equipment, and the arrangement of the buffer column, can play the effect of buffering when the hanging flower basket falls, prevent that the hanging flower basket direct contact ground from causing the damage to the hanging flower basket.

Description

Lifting device for building capable of performing overweight early warning
Technical Field
The utility model relates to the technical field of constructional engineering, in particular to a lifting device for a building, which can perform overweight early warning.
Background
At present, hydraulic tower climbing, wall-attached lifting machines and the like are mostly adopted in high-rise building construction vertical transportation machinery in the building industry, and the equipment has high efficiency, safety and reliability, but high equipment maintenance cost and strict use conditions; the used simple tower cranes, derrick cranes, climbing poles and the like have poor self stability, relatively high requirements on construction sites and low efficiency, so the use is limited.
Patent application number CN201920588986.7 provides a material lifting device for building, including the stage body, the equal fixedly connected with support column in bottom of the stage body left and right sides, two sets of the equal fixedly connected with base in bottom of support column. This material lifting device for building, through setting up the rack, the rolling gear, hydraulic push rod, first buckle, first fixture block, the second buckle, the second fixture block, insert rod and baffle, thereby make and put into the standing groove with the material, cover the case lid with the material and make it can not spill, rolling gear rotates and drives the fly leaf rebound, the fly leaf removes and drives the connecting plate and removes, it removes to drive and place the case, when placing the case and removing relevant position, thereby control hydraulic push rod promotes the stock and drives and place the case and remove forward, will insert the rod and extract from between second fixture block and the second buckle, the material can flow in the through-hole can be followed, or also can lift the case lid and will place the case slope and also can accomplish the pouring, the effect of conveniently promoting the material has been reached from this.
However, the lifting device cannot perform overload early warning on conveyed materials, when the lifted materials are too heavy, the lifting device can be inclined, safety accidents can occur in serious situations, and certain potential safety hazards exist.
SUMMERY OF THE UTILITY MODEL
This section is for the purpose of summarizing some aspects of embodiments of the utility model and to briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section as well as in the abstract of the specification and the title of the application to avoid obscuring the purpose of this section, the abstract of the specification and the title of the application, and such simplifications or omissions are not intended to limit the scope of the utility model.
The present invention has been made in view of the above and/or other problems with the conventional lifting apparatus.
Therefore, the utility model aims to provide a lifting device for a building, which can perform overweight early warning and solve the problems that the conventional lifting device cannot perform overload early warning on conveyed materials, the lifting device is inclined when the lifted materials are overweight, safety accidents occur seriously and certain potential safety hazards exist.
To solve the above technical problem, according to an aspect of the present invention, the present invention provides the following technical solutions:
a lifting device for buildings capable of overweight early warning, which comprises: the device comprises a supporting seat, a supporting frame, a lifting assembly and an auxiliary assembly;
a supporting seat;
the supporting frame is arranged at the top of the supporting seat, and the connecting frame is arranged at the top of the supporting frame;
the lifting assembly is arranged on the connecting frame and comprises a lifter, a steel strand and a hanging basket for conveying materials, and the lifting assembly is used for lifting the materials;
the auxiliary assembly is arranged on the hanging basket and comprises an overload induction alarm device and a buffer column, wherein the overload induction alarm device is arranged on the inner side of the hanging basket and used for monitoring bearing materials in real time, and the buffer column is connected to the bottom of the hanging basket.
As a preferable scheme of the lifting device for buildings capable of performing overweight pre-warning in the utility model, the following steps are included: the lifting machine is installed at the top of the connecting frame, the output end of the lifting machine is connected with the steel strand and drives the steel strand to work, the end part of the steel strand is connected with the limiting seat, and the outer side of the limiting seat is connected with the hanging basket.
As a preferable scheme of the lifting device for buildings capable of performing overweight pre-warning in the utility model, the following steps are included: the guide way has all been seted up to the support frame left and right sides, spacing seat and guide way sliding connection, and in the guide way from last to being linear equidistance down and setting up a plurality of guide holders.
As a preferable scheme of the lifting device for buildings capable of performing overweight pre-warning in the utility model, the following steps are included: the buffering post is equipped with a plurality ofly, and a plurality of buffering posts are annular equidistance along the hanging flower basket bottom and arrange the setting.
As a preferable scheme of the lifting device for buildings capable of performing overweight pre-warning in the utility model, the following steps are included: the supporting seat is rectangular and is provided with a plurality of threaded holes matched with external fastening bolts.
Compared with the prior art: through spacing seat and guide way cooperation, it is spacing to lead to the hanging flower basket, guarantees that the lifting machine is at the during operation, and the hanging flower basket goes up and down steadily, the condition of rocking about can not appearing to, bear the material through overload induction alarm device and carry out real-time supervision, prevent that the material that bears is overweight, influence equipment safety work, and the setting of buffering post, can play the effect of buffering when the hanging flower basket whereabouts, prevent that hanging flower basket direct contact ground from causing the damage to the hanging flower basket.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the present invention will be described in detail with reference to the accompanying drawings and detailed embodiments, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings without inventive exercise. Wherein:
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic front view of the present invention;
FIG. 3 is a schematic top view of the present invention.
In the figure: 100 supporting seats, 200 supporting frames, 210 guide grooves, 220 connecting frames, 300 lifting components, 310 lifting machines, 320 steel stranded wires, 330 limiting seats, 340 hanging baskets, 400 auxiliary components, 410 overload induction alarm devices and 420 buffer columns.
Detailed Description
In order to make the aforementioned objects, features and advantages of the present invention comprehensible, embodiments accompanied with figures are described in detail below.
In the following description, numerous specific details are set forth in order to provide a thorough understanding of the present invention, but the present invention may be practiced in other ways than those specifically described herein, and it will be apparent to those of ordinary skill in the art that the present invention may be practiced without departing from the spirit and scope of the present invention, and therefore the present invention is not limited to the specific embodiments disclosed below.
Next, the present invention will be described in detail with reference to the drawings, wherein for convenience of illustration, the cross-sectional view of the device structure is not enlarged partially according to the general scale, and the drawings are only examples, which should not limit the scope of the present invention. In addition, the three-dimensional dimensions of length, width and depth should be included in the actual fabrication.
In order to make the objects, technical solutions and advantages of the present invention more apparent, embodiments of the present invention will be described in detail with reference to the accompanying drawings.
The utility model provides a lifting device for buildings capable of performing overweight early warning, which is characterized in that a limiting seat is matched with a guide groove to guide and limit a hanging basket, so that the hanging basket is ensured to stably lift and descend when a lifting machine works, the left and right shaking condition is avoided, materials borne by an overload sensing alarm device are monitored in real time, the phenomenon that the borne materials are overweight to influence the safe work of equipment is prevented, and the lifting device for buildings, disclosed by reference to fig. 1-3, comprises a supporting seat 100, a supporting frame 200, a lifting assembly 300 and an auxiliary assembly 400;
referring to fig. 1-2, the support base 100;
with continued reference to fig. 1-2, the supporting frame 200 is disposed on the top of the supporting base 100, the guiding grooves 210 are disposed on both left and right sides of the supporting frame 200, the limiting base 330 is slidably connected with the guiding grooves 210, and the hanging basket 340 is guided and limited by the matching of the limiting base 330 and the guiding grooves 210, so that the hanging basket 340 is stably lifted and lowered without left and right shaking when the elevator 310 is in operation, a plurality of guiding bases 230 are linearly and equidistantly disposed in the guiding grooves 210 from top to bottom, and the top of the supporting frame 200 is welded to the connecting frame 220;
with reference to fig. 1-3, the lifting assembly 300 is disposed on the connecting frame 220, and includes a lifting machine 310, a steel strand 320, and a basket 340 for conveying materials, the lifting assembly 300 is used for lifting materials, the lifting machine 310 is screwed on the top of the connecting frame 220, the output end of the lifting machine 310 is connected to the steel strand 320 and drives the steel strand 320 to work, the end of the steel strand 320 is connected to the limiting seat 330, and the outer side of the limiting seat 330 is connected to the basket 340;
with reference to fig. 1-3, the auxiliary assembly 400 is disposed on the basket 340, the auxiliary assembly 400 includes an overload sensing alarm device 410 disposed inside the basket 340 for monitoring the load in real time, and a plurality of buffer posts 420 connected to the bottom of the basket 340, the plurality of buffer posts 420 are arranged in an annular and equidistant manner along the bottom of the basket 340, the load of the load sensing alarm device 410 is monitored in real time, the load is prevented from being overweight, the safety of the device is prevented from being affected, and the buffer posts 420 can buffer when the basket 340 falls, so as to prevent the basket 340 from being damaged by the direct contact of the basket 340 with the ground.
The working principle is as follows: the utility model discloses a when using, cooperate through spacing seat 330 and guide way 210, it is spacing to lead to hanging flower basket 340, guarantee lifting machine 310 at the during operation, hanging flower basket 340 goes up and down steadily, the condition of rocking about can not appearing, and, bear the material through overload induction alarm device 410 and carry out real-time supervision, prevent that the material that bears is overweight, influence equipment safety work, and the setting of buffering post 420, can be when hanging flower basket 340 whereabouts, play the effect of buffering, prevent that hanging flower basket 340 direct contact ground from causing the damage to hanging flower basket 430.
While the utility model has been described above with reference to an embodiment, various modifications may be made and equivalents may be substituted for elements thereof without departing from the scope of the utility model. In particular, the various features of the disclosed embodiments of the utility model may be used in any combination, provided that no structural conflict exists, and the combinations are not exhaustively described in this specification merely for the sake of brevity and resource conservation. Therefore, it is intended that the utility model not be limited to the particular embodiments disclosed, but that the utility model will include all embodiments falling within the scope of the appended claims.

Claims (5)

1. A lifting device for building capable of performing overweight early warning is characterized by comprising: the support comprises a support seat (100), a support frame (200), a lifting assembly (300) and an auxiliary assembly (400);
a support base (100);
the supporting frame (200) is arranged at the top of the supporting seat (100), and the connecting frame (220) is arranged at the top of the supporting frame (200);
the lifting assembly (300) is arranged on the connecting frame (220) and comprises a lifter (310), a steel strand (320) and a hanging basket (340) for conveying materials, and the lifting assembly (300) is used for lifting the materials;
the auxiliary assembly (400) is arranged on the hanging basket (340), and the auxiliary assembly (400) comprises an overload induction alarm device (410) which is arranged on the inner side of the hanging basket (340) and used for monitoring bearing materials in real time, and a buffer column (420) connected to the bottom of the hanging basket (340).
2. The lifting device for buildings capable of pre-warning overweight according to claim 1, characterized in that the lifter (310) is installed on top of the connecting frame (220), the output end of the lifter (310) is connected with the steel strand (320) and drives the steel strand (320) to work, the end of the steel strand (320) is connected with the limiting seat (330), and the outer side of the limiting seat (330) is connected with the hanging basket (340).
3. The lifting device capable of pre-warning overweight for buildings according to claim 2, characterized in that the left and right sides of the supporting frame (200) are both provided with guide grooves (210), the limiting seat (330) is connected with the guide grooves (210) in a sliding way, and a plurality of guide seats (230) are arranged in the guide grooves (210) from top to bottom in a linear equidistant way.
4. A lifting device for building capable of pre-warning overweight according to claim 1, characterized in that the buffer columns (420) are provided in plurality, and the plurality of buffer columns (420) are arranged in annular and equidistant arrangement along the bottom of the basket (340).
5. The lifting device for buildings capable of pre-warning overweight according to claim 1, characterized in that the supporting seat (100) is rectangular and provided with a plurality of threaded holes adapted to external fastening bolts.
CN202122452814.7U 2021-10-12 2021-10-12 Lifting device for building capable of performing overweight early warning Active CN215886192U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122452814.7U CN215886192U (en) 2021-10-12 2021-10-12 Lifting device for building capable of performing overweight early warning

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122452814.7U CN215886192U (en) 2021-10-12 2021-10-12 Lifting device for building capable of performing overweight early warning

Publications (1)

Publication Number Publication Date
CN215886192U true CN215886192U (en) 2022-02-22

Family

ID=80250000

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122452814.7U Active CN215886192U (en) 2021-10-12 2021-10-12 Lifting device for building capable of performing overweight early warning

Country Status (1)

Country Link
CN (1) CN215886192U (en)

Similar Documents

Publication Publication Date Title
CN203053686U (en) Hanging basket safety lock detecting bench
CN102786004B (en) Integrally moving on-load hydraulic lifting system without mooring rope and lifting method
CN202577925U (en) Lifting type platform in elevator shaft
CN202808123U (en) Double-guide-pillar large load capacity hoisting lifting equipment
CN202369333U (en) Wall mounting elevator
CN215886192U (en) Lifting device for building capable of performing overweight early warning
CN107777615B (en) Oil storage barrel device transportation lifting platform
CN207108405U (en) Portable light-duty jacking apparatus
CN104192681B (en) A kind of building hoist integration actuating device
CN210313386U (en) High-safety elevator
CN114050500B (en) Power transmission line climbing tower manned chair along anti-falling track
CN105236249A (en) Elevator without machine room
CN213895027U (en) Suspension crane convenient to overhaul
CN115030692A (en) Vertical modular closed pumping unit
CN210825179U (en) Anti-falling device of construction elevator
CN212076092U (en) Building elevator
CN210483091U (en) Building platform of unloading
CN110748140A (en) Track beam hanging basket special for stepped curtain wall
CN207497867U (en) A kind of building machinery lifts machine support
CN210767779U (en) Safety protection platform lift
CN201406250Y (en) Multiple standard joint increasing and decreasing device for lifter
CN219136198U (en) Tower crane anti-climbing device
CN216340787U (en) Multifunctional construction hanging basket
CN201010496Y (en) Large-tonnage lifting device using through jack as power
CN218205624U (en) Deep foundation pit construction work platform