CN215760803U - Tower convenient for rapid first-aid repair for electric power engineering - Google Patents
Tower convenient for rapid first-aid repair for electric power engineering Download PDFInfo
- Publication number
- CN215760803U CN215760803U CN202120317189.2U CN202120317189U CN215760803U CN 215760803 U CN215760803 U CN 215760803U CN 202120317189 U CN202120317189 U CN 202120317189U CN 215760803 U CN215760803 U CN 215760803U
- Authority
- CN
- China
- Prior art keywords
- tower
- plate
- hanging rod
- power engineering
- electric power
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 230000007246 mechanism Effects 0.000 claims abstract description 43
- 239000002184 metal Substances 0.000 claims description 10
- 238000010276 construction Methods 0.000 abstract description 9
- 238000000034 method Methods 0.000 abstract description 9
- 239000007769 metal material Substances 0.000 description 2
- 241000282326 Felis catus Species 0.000 description 1
- 230000002411 adverse Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 230000015556 catabolic process Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
Images
Landscapes
- Suspension Of Electric Lines Or Cables (AREA)
Abstract
The utility model provides a tower convenient and rapid to repair for electric power engineering.A mounting plate is arranged on the side wall of a tower rod of the tower, a strip-shaped hole is formed in the mounting plate, a hanging rod bearing a safety hook can move up and down on the strip-shaped hole by utilizing the principle similar to a sliding rail, a rotatable hanging rod bearing mechanism is also arranged between the mounting plates, so that the hanging rod can move upwards without limitation, and the hanging rod is prevented from falling downwards when an accident occurs, thereby protecting the safety of workers; when the staff need climb down the shaft tower after finishing the construction, also only need upwards overturn peg bearing mechanism and can put down the peg to next level peg bearing mechanism, avoided the many times repeated step of hanging and detaining the safety hook and hang the danger that detains the in-process probably appears many times.
Description
Technical Field
The utility model relates to the field of electric power engineering, in particular to a tower convenient and rapid to repair for electric power engineering.
Background
Under adverse weather environment, the transmission line that erects between the electric power tower can take place the broken string, trouble such as short circuit leads to having a power failure, economic loss for furthest reduces the power failure and causes, need maintain the circuit that breaks down in the fastest time, the staff is when upper and lower shaft tower, need dress safety clothes and safety hook, safety hook directly hangs the knot usually on the cat ladder, every upper and lower one section distance just need hang the knot again in new position, troublesome poeration and time consuming, the efficiency of breakdown maintenance has been reduced, therefore, need one kind under the prerequisite of assurance safety, can make things convenient for the quick shaft tower that reciprocates of staff.
SUMMERY OF THE UTILITY MODEL
In order to solve the defects of the prior art, the utility model provides a tower convenient and rapid to repair for electric power engineering.
The technical scheme provided by the utility model is as follows: a tower convenient for rapid first-aid repair for electric power engineering comprises a tower body, wherein the left side and the right side of the side wall of one side of a tower rod of the tower body are respectively and fixedly connected with a mounting plate extending from the bottom to the top of the tower rod; the two mounting plates are provided with strip-shaped holes extending from the lower parts to the tops of the mounting plates; a hanging rod for bearing the safety hook is movably arranged in the strip-shaped hole; a plurality of hanging rod bearing mechanisms at fixed intervals are hinged between the bottoms of the two mounting plates and can upwards rotate for 90 degrees by taking the hinged point as the circle center.
According to the tower convenient and rapid to repair for the electric power engineering, the mounting plates are arranged on the side walls of the tower poles of the tower, the mounting plates are provided with the strip-shaped holes, the hanging rods bearing the safety hooks can move up and down on the strip-shaped holes by utilizing the principle similar to a sliding rail, the rotatable hanging rod bearing mechanism is further arranged between the mounting plates, so that the hanging rods can move upwards without limitation, and the hanging rods are prevented from falling downwards when accidents occur, so that the safety of workers is protected; when the staff need climb down the shaft tower after finishing the construction, also only need upwards overturn peg bearing mechanism and can put down the peg to next level peg bearing mechanism, avoided the many times repeated step of hanging and detaining the safety hook and hang the danger that detains the in-process probably appears many times. Specifically, the tower convenient and rapid to repair for the power engineering comprises a tower body, wherein the tower body refers to a common power tower in the prior art, and the specific structure of the tower is not limited by the utility model. The left and right sides of one side lateral wall of the tower pole of shaft tower body is fixedly connected with respectively and extends to the mounting panel at top from the tower pole bottom, and the mounting panel is the metal material, with tower pole welded fastening. Be equipped with the bar hole that extends to the top from the mounting panel low part on two mounting panels, the downthehole movable mounting of bar has the peg that is used for bearing safety hook, when carrying out the operation, staff's safety hook is hung and is buckled on the peg, and the peg can reciprocate along the bar hole. Articulated between the bottom of two mounting panels have a plurality of peg bearing mechanism of interval fixed distance, peg bearing mechanism is used for supporting the peg, and peg bearing mechanism can use the pin joint to upwards rotate 90 degrees as the centre of a circle, upwards rotates 90 degrees after can downwards rotate the reconversion. In the process that the hanging rod moves upwards along the strip-shaped hole, the hanging rod bearing mechanism at the upper stage is upwards supported and passes the hanging rod bearing mechanism, so that the hanging rod can be moved to the hanging rod bearing mechanism at the higher position, and the hanging rod is supported by the hanging rod bearing mechanism until the hanging rod reaches the construction position. After the construction is finished, in the descending process, the hanging rod bearing mechanism for supporting the hanging rod is rotated upwards, the hanging rod is put down to the hanging rod bearing mechanism at the next stage, then the hanging rod bearing mechanism can move downwards, the steps are repeated until the bottom of the electric power pole is reached, and finally the safety hook on the hanging rod is taken down.
The beneficial technical effects of the utility model are as follows:
according to the tower convenient and rapid to repair for the power engineering, the mounting plate is arranged on the side wall of the tower pole of the tower, the mounting plate is provided with the strip-shaped hole, the hanging rod bearing the safety hook can move up and down on the strip-shaped hole by utilizing the principle similar to a sliding rail, the rotatable hanging rod bearing mechanism is further arranged between the mounting plates, so that the hanging rod can move upwards without limitation, and the hanging rod is prevented from falling downwards when an accident occurs, and the safety of workers is protected; when the staff need climb down the shaft tower after finishing the construction, also only need upwards overturn peg bearing mechanism and can put down the peg to next level peg bearing mechanism, avoided the many times repeated step of hanging and detaining the safety hook and hang the danger that detains the in-process probably appears many times.
Drawings
FIG. 1 is a schematic view of a front view structure of a tower for electric power engineering convenient and fast repair;
FIG. 2 is a schematic diagram of a side view profile structure of a tower for electric power engineering convenient and fast repair
FIG. 3 is a schematic structural view of a hanging rod of the preform of the present invention;
FIG. 4 is a schematic structural view of a hanger bar load bearing mechanism of the present invention;
fig. 5 is a schematic top sectional view of the mounting plate of the present invention.
In the drawings: 1. the tower comprises a tower body, 2, a mounting plate, 3, a hanging rod bearing mechanism, 4, a hanging rod, 5, a strip-shaped hole, 21, an outer plate, 22, an inner plate, 31, a top plate, 32, a support plate, 33 and a mounting column.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the utility model and are not intended to limit the utility model.
In the description of the present invention, it is to be understood that the terms "length", "width", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", and the like, indicate orientations or positional relationships based on the orientations or positional relationships illustrated in the drawings, and are used merely for convenience in describing the present invention and for simplicity in description, and do not indicate or imply that the devices or elements referred to must have a particular orientation, be constructed in a particular orientation, and be operated, and thus, are not to be construed as limiting the present invention. Further, in the description of the present invention, "a plurality" means two or more unless specifically defined otherwise.
Example 1
As shown in fig. 1 and 5, a tower for electric power engineering, which is convenient for fast first-aid repair, comprises a tower body, wherein the left side and the right side of the side wall of one side of a tower pole 1 of the tower body are respectively and fixedly connected with an installation plate 2 extending from the bottom to the top of the tower pole 1; the two mounting plates 2 are provided with strip-shaped holes 5 extending from the lower parts to the tops of the mounting plates 2; a hanging rod 4 for bearing a safety hook is movably arranged in the strip-shaped hole 5; a plurality of hanging rod bearing mechanisms 3 with fixed intervals are hinged between the bottoms of the two mounting plates 2, and the hanging rod bearing mechanisms 3 can upwards rotate for 90 degrees by taking a hinged point as a circle center.
According to the tower convenient and rapid to repair for the electric power engineering, the mounting plates are arranged on the side walls of the tower poles of the tower, the mounting plates are provided with the strip-shaped holes, the hanging rods bearing the safety hooks can move up and down on the strip-shaped holes by utilizing the principle similar to a sliding rail, the rotatable hanging rod bearing mechanism is further arranged between the mounting plates, so that the hanging rods can move upwards without limitation, and the hanging rods are prevented from falling downwards when accidents occur, so that the safety of workers is protected; when the staff need climb down the shaft tower after finishing the construction, also only need upwards overturn peg bearing mechanism and can put down the peg to next level peg bearing mechanism, avoided the many times repeated step of hanging and detaining the safety hook and hang the danger that detains the in-process probably appears many times. Specifically, as shown in fig. 1 and 5, the tower for electric power engineering, which is convenient and fast to first-aid repair, comprises a tower body, wherein the tower body refers to an electric power tower which is common in the prior art, and the specific structure of the tower is not limited by the utility model. The left and right sides of one side lateral wall of the tower pole 1 of shaft tower body is fixedly connected with respectively and extends to the mounting panel 2 at top from 1 bottom of tower pole, and mounting panel 2 is the metal material, and is welded fastening with tower pole 1. Be equipped with on two mounting panels 2 and extend to the bar hole 5 at top from 2 low portions of mounting panel, movable mounting has peg 4 that is used for bearing the safety hook in the bar hole 5, when carrying out the operation, staff's safety hook detains on peg 4, and peg 4 can reciprocate along bar hole 5. Articulated between the bottom of two mounting panels 2 have a plurality of peg bearing mechanism 3 of interval fixed distance, peg bearing mechanism 3 is used for supporting peg 4, and peg bearing mechanism 3 can use the pin joint to upwards rotate 90 degrees as the centre of a circle, upwards rotates 90 degrees after can downwards rotate the reconversion. In the process that the hanging rod 4 wants to move upwards along the strip-shaped hole 5, the hanging rod 4 bearing mechanism 3 at the upper stage is upwards supported and passes over the hanging rod 4 bearing mechanism, so that the hanging rod 4 can be moved to the hanging rod bearing mechanism 3 at a higher position, and the hanging rod 4 is supported by the hanging rod bearing mechanism 3 until the construction position is reached. After the construction is finished, in the descending process, the hanging rod bearing mechanism 3 for supporting the hanging rod 4 rotates upwards, the hanging rod 4 is put down to the hanging rod bearing mechanism 3 of the next stage, then the hanging rod 4 can move downwards, the steps are repeated until the bottom of the electric power pole tower is reached, and finally the safety hook on the hanging rod 4 is taken down.
Further, as shown in fig. 2 and 4, the hanging rod bearing mechanism 3 includes a top plate 31, a support plate 32 and a mounting column 33; the top plate 31 is a rectangular metal plate, and the length is 9 cm; the supporting plate 32 is a triangular metal plate, two right-angle sides of which are 4.5cm long respectively, and is fixed at the rear end of the lower surface of the top plate 31 and is vertical to the lower surface of the top plate 31; the mounting posts 33 are cylindrical metal posts fixed to rear ends of left and right side walls of the top plate 31, respectively. When the support plate 32 is perpendicular to the side wall of the tower pole 1, the rear side wall of the support plate 32 abuts against the side wall of the tower pole 1, and the support plate 32 is supported so as not to rotate downward.
Further, as shown in fig. 5, the mounting plate 2 includes an outer plate 21 and an inner plate 22; the height of the outer plate 21 is 10cm, the bottom end of the outer plate is fixed at the tail end of the side wall of the tower pole 1 and is vertical to the side wall of the tower pole 1, the top of the outer plate 21 is bent by 90 degrees in the direction vertical to the central axis of the side wall of the tower pole 1 and extends for 3-5cm, and then bent by 90 degrees in the direction vertical to the side wall of the tower pole 1 and extends for 3 cm; the height of the inner plate 22 is 5cm, the bottom end is vertical and fixed on the side wall of the tower pole 1, and the distance between the bottom end and the outer plate 21 is 3-5 cm.
Further, as shown in fig. 3, the hanging rod 4 is composed of a metal rod with threads carved on both ends and nuts fixedly installed on both ends of the metal rod.
Further, as shown in fig. 2 and 4, the strip-shaped hole is formed by a gap between the top end of the outer panel 21 and the top end of the inner panel 22, and has a width of 2 cm; the two ends of the hanging rod 4 and the nuts are positioned in the cavity formed by the outer plate 21 and the inner plate 22.
Obviously, according to the tower convenient and rapid to repair for the power engineering, the mounting plates are arranged on the side walls of the tower poles of the tower, the strip-shaped holes are formed in the mounting plates, the hanging rods bearing the safety hooks can move up and down on the strip-shaped holes by utilizing the principle similar to a sliding rail, and the rotatable hanging rod bearing mechanism is further arranged between the mounting plates, so that the hanging rods can move upwards without limitation, and the hanging rods are prevented from falling downwards when accidents occur, and the safety of workers is protected; when the staff need climb down the shaft tower after finishing the construction, also only need upwards overturn peg bearing mechanism and can put down the peg to next level peg bearing mechanism, avoided the many times repeated step of hanging and detaining the safety hook and hang the danger that detains the in-process probably appears many times.
The foregoing is a preferred embodiment of the present invention, and it should be understood that those skilled in the art can derive the related technical solutions through logic analysis, reasoning or experiment based on the concepts of the present invention without creative efforts, and therefore, the related technical solutions should be within the protection scope of the present claims.
Claims (5)
1. A tower convenient for rapid first-aid repair for electric power engineering comprises a tower body and is characterized in that the left side and the right side of the side wall of one side of a tower rod (1) of the tower body are respectively and fixedly connected with a mounting plate (2) extending from the bottom to the top of the tower rod (1); the two mounting plates (2) are provided with strip-shaped holes (5) extending from the lower parts to the tops of the mounting plates (2); a hanging rod (4) for bearing the safety hook is movably arranged in the strip-shaped hole (5); a plurality of hanging rod bearing mechanisms (3) with fixed intervals are hinged between the bottoms of the two mounting plates (2), and the hanging rod bearing mechanisms (3) can upwards rotate for 90 degrees by taking a hinged point as a circle center.
2. The tower for the power engineering convenient and fast emergency repair as claimed in claim 1, wherein the hanging rod bearing mechanism (3) comprises a top plate (31), a support plate (32) and a mounting column (33); the top plate (31) is a rectangular metal plate, and the length of the top plate is 9 cm; the supporting plate (32) is a triangular metal plate, is fixed at the rear end of the lower surface of the top plate (31) and is vertical to the lower surface of the top plate (31); the mounting posts (33) are cylindrical metal posts and are fixed to the rear ends of the left and right side walls of the top plate (31), respectively.
3. The tower for electric power engineering convenient and fast first-aid repair according to claim 2, characterized in that the mounting plate (2) comprises an outer plate (21) and an inner plate (22); the height of the outer plate (21) is 10cm, the bottom end of the outer plate is fixed to the tail end of the side wall of the tower pole (1) and is vertical to the side wall of the tower pole (1), the top of the outer plate (21) is bent by 90 degrees in the direction vertical to the central axis of the side wall of the tower pole (1) and extends for 3-5cm, and then bent by 90 degrees in the direction vertical to the side wall of the tower pole (1) and extends for 3 cm; the height of the inner plate (22) is 5cm, the bottom end is vertical and fixed on the side wall of the tower pole (1), and the distance between the bottom end and the outer plate (21) is 3-5 cm.
4. The tower for electric power engineering convenient and fast first-aid repair as claimed in claim 3, wherein the hanging rod (4) is composed of a metal rod with two ends engraved with threads and nuts fixedly mounted on two ends of the metal rod.
5. The tower for electric power engineering convenient and fast first-aid repair as claimed in claim 4, wherein the strip-shaped holes are formed by a gap between the top end of the outer plate (21) and the top end of the inner plate (22); two ends of the hanging rod (4) and the screw cap are positioned in a cavity formed by the outer plate (21) and the inner plate (22).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120317189.2U CN215760803U (en) | 2021-02-04 | 2021-02-04 | Tower convenient for rapid first-aid repair for electric power engineering |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120317189.2U CN215760803U (en) | 2021-02-04 | 2021-02-04 | Tower convenient for rapid first-aid repair for electric power engineering |
Publications (1)
Publication Number | Publication Date |
---|---|
CN215760803U true CN215760803U (en) | 2022-02-08 |
Family
ID=80071712
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202120317189.2U Expired - Fee Related CN215760803U (en) | 2021-02-04 | 2021-02-04 | Tower convenient for rapid first-aid repair for electric power engineering |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN215760803U (en) |
-
2021
- 2021-02-04 CN CN202120317189.2U patent/CN215760803U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209975993U (en) | Suspension cage | |
CN215760803U (en) | Tower convenient for rapid first-aid repair for electric power engineering | |
CN2771160Y (en) | Elevation operating cradle for elevator mounting | |
CN219471505U (en) | Rail type hanging device of electric hanging basket | |
CN215858977U (en) | Bearing structure fixed on steel material shed | |
CN217054267U (en) | Protection device construction structure | |
CN213143808U (en) | Scaffold for constructional engineering | |
CN210041118U (en) | Maintenance auxiliary device for overhead high-voltage direct-current transmission line | |
CN112796498A (en) | Double-column type electric construction platform with truss girder and working method thereof | |
CN112049017A (en) | Bailey frame integral frame falling device for cast-in-place box girder and construction process | |
CN206857906U (en) | Elevator rescue instrument and elevator rescue tool group | |
CN214462523U (en) | Guide rail structure for hydraulic creeping formwork | |
CN221701003U (en) | Super-large flexible jacket construction lifting device | |
CN217087472U (en) | Supplementary ladder of medium-low speed magnetic levitation contact rail arrester installation | |
CN217269966U (en) | Offshore wind power construction cat ladder | |
CN214532761U (en) | Tower machine cat ladder conversion equipment | |
CN217173075U (en) | High-voltage line protection frame | |
CN203895804U (en) | Multifunctional overhaul platform for isolating switch | |
CN218203893U (en) | Width-adjustable cover beam safety protection frame | |
CN211239246U (en) | Strain clamp convenient to change | |
CN219098451U (en) | Car of construction elevator with telescopic ladder | |
CN210918489U (en) | Protective guard device of supporting platform | |
CN220502518U (en) | Tower crane platform convenient to disassemble and assemble | |
CN215331451U (en) | Hydraulic self-climbing formwork for narrow space | |
CN210238283U (en) | Portable simple and easy basket of hanging |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20220208 |