CN215760349U - Combined scaffold platform capable of being carried quickly - Google Patents

Combined scaffold platform capable of being carried quickly Download PDF

Info

Publication number
CN215760349U
CN215760349U CN202121471413.XU CN202121471413U CN215760349U CN 215760349 U CN215760349 U CN 215760349U CN 202121471413 U CN202121471413 U CN 202121471413U CN 215760349 U CN215760349 U CN 215760349U
Authority
CN
China
Prior art keywords
scaffold
rod
scaffold platform
platform
combination
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121471413.XU
Other languages
Chinese (zh)
Inventor
林钧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huarun Dadong Dockyard Co ltd
Original Assignee
Huarun Dadong Dockyard Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huarun Dadong Dockyard Co ltd filed Critical Huarun Dadong Dockyard Co ltd
Priority to CN202121471413.XU priority Critical patent/CN215760349U/en
Application granted granted Critical
Publication of CN215760349U publication Critical patent/CN215760349U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to the technical field of scaffolds, in particular to a combined scaffold platform capable of being carried quickly. The utility model provides a combination formula scaffold platform that can carry on fast, includes scaffold platform, its characterized in that: the scaffold platform be formed by connecting a plurality of scaffold modules end to end in proper order, be located scaffold platform center and be equipped with and put the tube hole, the scaffold module include connecting rod, ejector pin, screw rod, pull rod, bracing, connecting rod one side connect the ejector pin, be equipped with screw rod one end in the ejector pin, the screw rod other end runs through the connecting rod, is located ejector pin one side below and rotates and connect bracing one end, the bracing other end is equipped with the roof, is located bracing other end top and connects pull rod one end, the ejector pin is connected to the pull rod other end. Compared with the prior art, the assembling and disassembling are convenient, the complex flow of welding and disassembling the horse board in the traditional mode is avoided, and the erecting efficiency is improved. And can make up scaffold module according to the diameter flexibility of jacket, can satisfy multiple pipe diameter and close up the construction requirement, the commonality is strong.

Description

Combined scaffold platform capable of being carried quickly
Technical Field
The utility model relates to the technical field of scaffolds, in particular to a combined scaffold platform capable of being carried quickly.
Background
A scaffold platform needs to be erected when the position of a jacket closure seam is constructed, a scaffold horse board is generally welded on a jacket body directly at present, then the horse board is fixed through a supporting structure, and finally scaffold pipes are erected to complete the assembly of the scaffold platform. Because the horse board is fixed by adopting a welding mode. Not only can destroy the paint on the outer surface of the jacket, but also needs repair welding and polishing after the horse board is removed, and then the paint is coated again, so that the process is complicated, and the production efficiency is reduced. Certain manpower and material resources are wasted.
Disclosure of Invention
The combined scaffold platform can be quickly carried, is convenient to disassemble and assemble, avoids complex processes of welding and disassembling a horse board in the traditional mode, and improves the scaffold building efficiency. And can make up scaffold module according to the diameter flexibility of jacket, can satisfy multiple pipe diameter and close up the construction requirement, the commonality is strong.
In order to realize the above-mentioned purpose, design a combination formula scaffold platform that can carry on fast, including scaffold platform, its characterized in that: the scaffold platform be formed by connecting a plurality of scaffold modules end to end in proper order, be located scaffold platform center and be equipped with and put the tube hole, the scaffold module include connecting rod, ejector pin, screw rod, pull rod, bracing, connecting rod one side connect the ejector pin, be equipped with screw rod one end in the ejector pin, the screw rod other end runs through the connecting rod, is located ejector pin one side below and rotates and connect bracing one end, the bracing other end is equipped with the roof, is located bracing other end top and connects pull rod one end, the ejector pin is connected to the pull rod other end.
And the adjacent scaffold modules are connected through bolts.
The scaffold platform is characterized in that a protection device is arranged above the scaffold platform and is formed by connecting a plurality of protection modules.
The protection module comprises a movable railing and a steel wire ring protection rope, a railing socket is arranged at the outer edge of the upper end of the connecting rod, the movable railing is connected in the railing socket, a connecting ring is arranged on the movable railing, and a steel wire rope protection ring is arranged in the connecting ring.
The number and the positions of the protection modules are matched with those of the scaffold modules.
And a scaffold board is arranged above the ejector rod.
The screw rod and the connecting rod are fastened through a first nut.
The pull rod and the ejector rod are fastened through a second nut.
The number of the ejector rods is two, and the two ejector rods are connected through a fixing rod.
The shape of the scaffold platform is octagonal.
Compared with the prior art, the utility model has the advantages of convenient assembly and disassembly, avoids the complex processes of welding and disassembling the horse board in the traditional mode, and improves the erection efficiency. And can make up scaffold module according to the diameter flexibility of jacket, can satisfy multiple pipe diameter and close up the construction requirement, the commonality is strong.
Drawings
Fig. 1 is a schematic structural view of the scaffold platform and the protection device of the present invention.
Fig. 2 is a schematic structural diagram of the scaffold module of the present invention.
Fig. 3 is a schematic structural diagram of the protection module of the present invention.
Fig. 4 is a schematic structural view of the assembled scaffold module and protection module of the present invention.
Fig. 5 is a front view of the assembled scaffold module and protection module of the present invention.
Fig. 6 is a side view of the assembled scaffold module and protection module of the present invention.
Fig. 7 is a top view of the assembled scaffold module and protection module of the present invention.
FIG. 8 is a schematic view of the structure of the scaffold platform of the present invention.
Fig. 9 is a front view of the present invention scaffold platform in use.
Figure 10 is a side view of the present invention scaffold platform in use.
Figure 11 is a top view of the present invention scaffold platform in use.
Referring to fig. 1 to 11, wherein 1 is a pipe placing hole, 2 is a protection module, 2-1 is a movable rail, 2-2 is a connecting ring, 2-3 is a steel wire rope retainer, 3 is a scaffold module, 3-1 is a connecting rod, 3-2 is a top rod, 3-3 is a screw rod, 3-4 is a pull rod, 3-5 is an inclined strut, 3-6 is a top plate, 3-7 is a first nut, and 3-8 is a second nut. 3-9 is a fixing rod, 3-10 is a railing socket, and 4 is a main conduit.
Detailed Description
The utility model is further illustrated below with reference to the accompanying drawings.
As shown in fig. 1 to 7, the scaffold platform is formed by sequentially connecting a plurality of scaffold modules 3 end to end, a tube placing hole 1 is arranged at the center of the scaffold platform, each scaffold module 3 comprises a connecting rod 3-1, a top rod 3-2, a screw rod 3-3, a pull rod 3-4 and an inclined strut 3-5, one side of the connecting rod 3-1 is connected with the top rod 3-2, one end of the screw rod 3-3 is arranged in the top rod 3-2, the other end of the screw rod 3-3 penetrates through the connecting rod 3-1, one end of the inclined strut 3-5 is rotatably arranged below one side of the top rod 3-2, the other end of the inclined strut 3-5 is provided with a top plate 3-6, one end of the pull rod 3-4 is arranged above the other end of the inclined strut 3-5, and the other end of the pull rod 3-4 is connected with the top rod 3-2.
The adjacent scaffold modules 3 are connected through bolts.
A protection device is arranged above the scaffold platform and is formed by connecting a plurality of protection modules 2.
The protection module 2 comprises a movable railing and a steel wire ring protection rope, a railing socket 3-10 is arranged at the outer edge of the upper end of the connecting rod 3-1, the movable railing 2-1 is connected in the railing socket 3-10, a connecting ring 2-2 is arranged on the movable railing 2-1, and the steel wire ring protection rope 2-3 is arranged in the connecting ring 2-2.
The number and the positions of the protection modules 2 are matched with those of the scaffold modules 3.
A scaffold board is arranged above the mandril 3-2.
The screw rod 3-3 and the connecting rod 3-1 are fastened through a first nut 3-7.
The pull rod 3-4 and the ejector rod 3-5 are fastened through a second nut 3-8.
The number of the top rods 3-2 is two, and the two top rods 3-2 are connected through a fixing rod 3-9.
The shape of the scaffold platform is octagonal.
When the movable railing is used, the movable railing 2-1 is provided with a plurality of connecting rings at different heights, and each connecting ring is sleeved with a steel wire rope guard ring 2-3, so that a plurality of layers of steel wire rope guard rings 2-3 are arranged outside the movable railing 2-1.
When the special pull rod is used, the pull rod 3-4 can be a screw rod.
When the scaffold platform is used, as shown in fig. 8 to 11, a plurality of scaffold modules 3 are sequentially connected end to end according to the diameter of the jacket main conduit 4 to be constructed, so that a scaffold platform with a polygonal frame is formed. The scaffold platform is sleeved into the construction position outside the main duct 4 by a crane, and the main duct 4 is positioned in the tube placing hole 4 in the center of the scaffold platform. Then an electric wrench is used for ejecting the screw rod 3-3 out of the ejector rod 3-2 and ejecting the screw rod to the outer surface of the main conduit 4 until the ejector rod is not moved. And then the pull rod 3-4 is tightened until the top plate 3-6 of the inclined strut 3-5 is contacted with the outer surface of the main catheter 4 immovably, thereby completing the fixation between the scaffold platform and the main catheter 4. Then the movable railing 2-1 is inserted into the railing socket 3-10, and the steel wire retainer is threaded into the connecting ring 2-2. And finally, paving a scaffold board above the ejector rods 3-2 to complete the construction of the scaffold platform. When the scaffold platform is dismantled, the steel wire rope guard ring 2-1, the movable railing 2-1, the loosening pull rod 3-4 and the screw rod 3-3 are respectively dismantled to complete the dismantling.
The utility model has convenient disassembly and assembly, avoids the complex flow of welding and disassembling the horse board in the traditional mode and improves the racking efficiency. And can make up scaffold module according to the diameter flexibility of jacket, can satisfy multiple pipe diameter and close up the construction requirement, the commonality is strong.

Claims (10)

1. The utility model provides a combination formula scaffold platform that can carry on fast, includes scaffold platform, its characterized in that: the scaffold platform is formed by sequentially connecting a plurality of scaffold modules (3) end to end, a tube placing hole (1) is formed in the center of the scaffold platform, each scaffold module (3) comprises a connecting rod (3-1), a push rod (3-2), a screw rod (3-3), a pull rod (3-4) and an inclined strut (3-5), one side of the connecting rod (3-1) is connected with the push rod (3-2), one end of the screw rod (3-3) is arranged in the push rod (3-2), the other end of the screw rod (3-3) penetrates through the connecting rod (3-1), one end of the inclined strut (3-5) is rotatably connected below one side of the push rod (3-2), the other end of the inclined strut (3-5) is provided with a top plate (3-6), and one end of the pull rod (3-4) is connected above the other end of the inclined strut (3-5), the other end of the pull rod (3-4) is connected with the ejector rod (3-2).
2. The quickly loadable combination scaffold platform of claim 1, wherein: the adjacent scaffold modules (3) are connected through bolts.
3. The quickly loadable combination scaffold platform of claim 1, wherein: the scaffold platform is characterized in that a protection device is arranged above the scaffold platform and is formed by connecting a plurality of protection modules (2).
4. A quickly loadable combination scaffold platform according to claim 3, characterized in that: the protection module (2) comprises a movable railing and a steel wire ring protection rope, a railing socket (3-10) is arranged at the outer edge of the upper end of the connecting rod (3-1), the movable railing (2-1) is connected in the railing socket (3-10), a connecting ring (2-2) is arranged on the movable railing (2-1), and the steel wire ring protection ring (2-3) is arranged in the connecting ring (2-2).
5. A quickly loadable combination scaffold platform according to claim 3, characterized in that: the number and the positions of the protection modules (2) are matched with those of the scaffold modules (3).
6. The quickly loadable combination scaffold platform of claim 1, wherein: a scaffold board is arranged above the ejector rod (3-2).
7. The quickly loadable combination scaffold platform of claim 1, wherein: the screw rod (3-3) and the connecting rod (3-1) are fastened through a first nut (3-7).
8. The quickly loadable combination scaffold platform of claim 1, wherein: the pull rod (3-4) and the ejector rod (3-5) are fastened through a second nut (3-8).
9. The quickly loadable combination scaffold platform of claim 1, wherein: the number of the ejector rods (3-2) is two, and the two ejector rods (3-2) are connected through a fixing rod (3-9).
10. The quickly loadable combination scaffold platform of claim 1, wherein: the shape of the scaffold platform is octagonal.
CN202121471413.XU 2021-06-30 2021-06-30 Combined scaffold platform capable of being carried quickly Active CN215760349U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121471413.XU CN215760349U (en) 2021-06-30 2021-06-30 Combined scaffold platform capable of being carried quickly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121471413.XU CN215760349U (en) 2021-06-30 2021-06-30 Combined scaffold platform capable of being carried quickly

Publications (1)

Publication Number Publication Date
CN215760349U true CN215760349U (en) 2022-02-08

Family

ID=80103088

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121471413.XU Active CN215760349U (en) 2021-06-30 2021-06-30 Combined scaffold platform capable of being carried quickly

Country Status (1)

Country Link
CN (1) CN215760349U (en)

Similar Documents

Publication Publication Date Title
CN102817484B (en) Heavy multifunctional combined supporting frame
CN102102344B (en) Method for quickly assembling assembled corrugated culvert
CN104481194B (en) A kind of flip-chip method of vertical type tubular equipment
CN215760349U (en) Combined scaffold platform capable of being carried quickly
CN207618963U (en) It is a kind of using fork truck at the top of basement pipe laying device
CN210049676U (en) Detachable construction guardrail
US4199906A (en) Cooling tower
CN109441101B (en) Construction platform for high-altitude operation concrete circular roof
CN214834994U (en) Safety rope upright post for H-shaped steel
CN209838282U (en) Connecting device between manual ladder stand and pier column
CN205293909U (en) Mobilizable assembled transport auxiliary device
CN204277366U (en) For the hydraulic lifting apparatus of vertical type tubular equipment upside-down mounting
CN210316439U (en) Movable operating platform for installing high-altitude pipeline equipment
CN113137079A (en) Safety rope upright post used on H-shaped steel and using method
CN206988799U (en) A kind of concentric double pipe structure
CN212453950U (en) Device for assisting in installing railing
CN111099430B (en) Cross-road cable paying-off system
CN209942709U (en) Rotary ladder stand
CN107902606A (en) It is a kind of using fork truck at the top of basement pipe laying method and device
CN214658943U (en) Standard knot main part and standard knot
CN104234189A (en) Four-pipe truss structure of prefabricated house
CN213439439U (en) Quick connecting tool for threaded flange plate and pipe body
CN108868298B (en) Steel column assembling device and use method thereof
CN214196140U (en) Ladder for overhauling vaporization flue of converter
CN219409012U (en) Simple lifting device for installing main shaft of photovoltaic power generation field

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant