CN215715319U - Structure for replacing post-cast strip with underground ultra-long concrete - Google Patents
Structure for replacing post-cast strip with underground ultra-long concrete Download PDFInfo
- Publication number
- CN215715319U CN215715319U CN202122164378.3U CN202122164378U CN215715319U CN 215715319 U CN215715319 U CN 215715319U CN 202122164378 U CN202122164378 U CN 202122164378U CN 215715319 U CN215715319 U CN 215715319U
- Authority
- CN
- China
- Prior art keywords
- top end
- pouring
- fixed
- fixedly connected
- vertical pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The utility model provides a structure that underground overlength concrete replaces post-cast strip, belongs to building cast strip apparatus equipment technical field, including pouring riser, fixed branch pipe, connecting a piece, strutting arrangement, adjusting device, fixed snap ring, sealed jam, its characterized in that: the device comprises fixed branch pipes, fixed support blocks, a supporting device, an adjusting device, a fixed snap ring, a sealing plug and a pouring device, wherein the fixed branch pipes are symmetrically and fixedly connected with the lower part of the surface of the top end of the side of the pouring vertical pipe in a bilateral symmetry mode, the fixed support blocks are symmetrically and fixedly connected with the front part and the rear part of the middle part of the surface of the top end of the side of the pouring vertical pipe in a front-back symmetry mode, the supporting device is inserted into the middle part of the surface of the top end of the outer side of each fixed support block, the adjusting device is inserted into the circle center of the surface of the top end of the side of the pouring vertical pipe, the fixed snap ring is inserted into the circle center of the surface of the top end of the side of the pouring vertical pipe, the sealing plug is inserted into the circle center of the surface of the top end of the pouring vertical pipe, a worker can insert the pouring device into the ground when paving the ground, and can quickly connect the pouring device together at any time.
Description
Technical Field
The utility model relates to a structure for replacing a post-cast strip by underground super-long concrete, belonging to the technical field of casting strip instruments for building construction.
Background
In long-term work practice, in the process of pouring in underground gaps, the existing pouring device cannot pour at the bottom due to the fact that a nozzle of the pouring device is deep in the underground gaps, and the existing connecting type pouring device needs a large amount of time for installation of workers, so that the operation and the use of the workers are inconvenient, and the work efficiency is reduced.
SUMMERY OF THE UTILITY MODEL
The purpose of the utility model is as follows: in order to solve the staff and pouring the in-process in the gap with the underground, the staff can insert the ground seam with pouring the ware when paving ground in to the staff can be quick at any time with pouring the ware and link together, make things convenient for the staff to operate and use and improve work efficiency, its technical scheme as follows:
the utility model provides a structure of underground overlength concrete replacement post-cast strip, it is including pouring riser 1, fixed branch pipe 2, connecting a piece 3, strutting arrangement 4, adjusting device 5, fixed snap ring 6, sealed jam 7, its characterized in that: the lower part of the surface of the top end of the side of the pouring riser 1 is fixedly connected with fixed branch pipes 2 in a bilateral symmetry manner, the middle part of the surface of the top end of the side of the pouring riser 1 is fixedly connected with fixed support blocks 3 in a front-back symmetry manner, a support device 4 is inserted in the middle part of the surface of the top end of the outer side of each fixed support block 3, an adjusting device 5 is inserted in the center of a circle above the surface of the top end of the side of the pouring riser 1, a fixed snap ring 6 is fixedly inserted in the center of a circle above the surface of the top end of the side of the pouring riser 1, a sealing plug 7 is inserted in the center of a circle on the surface of the top end of the pouring riser 1, the pouring riser 1 comprises a main pipe 1-1, a screwed pipe 1-2, a through hole 1-3 and an internal thread 1-4, the center of the surface of the top end of the main pipe 1-1 is fixedly connected with the screwed pipe 1-2, and the through holes 1-3 are arranged in a bilateral symmetry manner below the surface of the side of the top end of the main pipe 1, the lower edge of the top end surface of the inner side of the main pipe 1-1 is provided with an internal thread 1-4, the fixed branch pipe 2 is fixedly connected inside the through hole 1-3, the supporting device 4 comprises a connecting plate 4-1, a rotating shaft 4-2, clamping blocks 4-3 and anti-slip strips 4-4, the rotating shaft 4-2 is inserted in the middle of the inner edge of the top end surface of the side of the connecting plate 4-1, the clamping blocks 4-3 are fixedly connected in the middle of the top end surface of the outer side of the connecting plate 4-1, the anti-slip strips 4-4 are fixedly connected in a vertical row in the middle of the top end surface of the outer side of the clamping blocks 4-3, the connecting plate 4-1 and the fixed branch blocks 3 are mutually connected through the rotating shaft 4-2, the adjusting device 5 comprises an inserting ring 5-1, a push ring 5-2, a rubber mat 5-3 and clamping columns 5-4, the lower edge of the top end surface of the side of the insert ring 5-1 is fixedly inserted with a push ring 5-2, the push ring 5-2 is symmetrically and fixedly connected with rubber mats 5-3 at the front edge and the rear edge of the bottom end surface of the push ring 5-1, the circle center of the bottom end surface of each rubber mat 5-3 is fixedly connected with a clamping column 5-4, and the insert ring 5-1 is inserted on the main pipe 5-1.
The utility model has the beneficial effects that: in order to solve the problem that the pouring process is carried out in the underground gap by workers, the workers can insert the pouring device into the underground gap when the ground is paved, and the pouring device can be connected by the workers quickly at any time, so that the workers can operate and use conveniently and the working efficiency is improved.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
fig. 2 is a schematic structural view of the pouring riser 1 of the present invention;
FIG. 3 is a schematic view of the structure of the supporting device 4 of the present invention;
fig. 4 is a schematic structural diagram of the adjusting device 5 of the present invention.
Detailed Description
Referring to fig. 1, fig. 2, fig. 3 and fig. 4, the structure for replacing the post-cast strip with the underground ultra-long concrete comprises a pouring vertical pipe 1, a fixed branch pipe 2, a connecting branch block 3, a supporting device 4, an adjusting device 5, a fixed snap ring 6 and a sealing plug 7, and is characterized in that: the lower part of the surface of the top end of the side of the pouring riser 1 is fixedly connected with fixed branch pipes 2 in a bilateral symmetry manner, the middle part of the surface of the top end of the side of the pouring riser 1 is fixedly connected with fixed support blocks 3 in a front-back symmetry manner, a support device 4 is inserted in the middle part of the surface of the top end of the outer side of each fixed support block 3, an adjusting device 5 is inserted in the center of a circle above the surface of the top end of the side of the pouring riser 1, a fixed snap ring 6 is fixedly inserted in the center of a circle above the surface of the top end of the side of the pouring riser 1, a sealing plug 7 is inserted in the center of a circle on the surface of the top end of the pouring riser 1, the pouring riser 1 comprises a main pipe 1-1, a screwed pipe 1-2, a through hole 1-3 and an internal thread 1-4, the center of the surface of the top end of the main pipe 1-1 is fixedly connected with the screwed pipe 1-2, and the through holes 1-3 are arranged in a bilateral symmetry manner below the surface of the side of the top end of the main pipe 1, the lower edge of the top end surface of the inner side of the main pipe 1-1 is provided with an internal thread 1-4, the fixed branch pipe 2 is fixedly connected inside the through hole 1-3, the supporting device 4 comprises a connecting plate 4-1, a rotating shaft 4-2, clamping blocks 4-3 and anti-slip strips 4-4, the rotating shaft 4-2 is inserted in the middle of the inner edge of the top end surface of the side of the connecting plate 4-1, the clamping blocks 4-3 are fixedly connected in the middle of the top end surface of the outer side of the connecting plate 4-1, the anti-slip strips 4-4 are fixedly connected in a vertical row in the middle of the top end surface of the outer side of the clamping blocks 4-3, the connecting plate 4-1 and the fixed branch blocks 3 are mutually connected through the rotating shaft 4-2, the adjusting device 5 comprises an inserting ring 5-1, a push ring 5-2, a rubber mat 5-3 and clamping columns 5-4, the lower edge of the top end surface of the side of the insert ring 5-1 is fixedly inserted with a push ring 5-2, the push ring 5-2 is symmetrically and fixedly connected with rubber mats 5-3 at the front edge and the rear edge of the bottom end surface of the push ring 5-1, the circle center of the bottom end surface of each rubber mat 5-3 is fixedly connected with a clamping column 5-4, and the insert ring 5-1 is inserted on the main pipe 5-1.
When the device is used, a main pipe 1-1 on a pouring stand pipe 1 is inserted into a ground seam through digital display, then an inserting ring 5-1 on a sliding adjusting device 5 slides downwards on the main pipe 1-1, meanwhile, a push ring 5-2 pushes connecting plates 4-1 on two supporting devices 4, meanwhile, the connecting plates 4-1 rotate on a fixed supporting block 3 by taking a rotating shaft 4-1 as a circle center, meanwhile, two clamping blocks 4-3 are fixed on the inner side surface of the ground seam, meanwhile, anti-slip strips 4-4 can prevent the clamping blocks 4-3 from moving, then a grouting pipe is inserted into a threaded pipe 1-2, slurry is injected into the main pipe 1-1 and is injected into the ground seam through a through hole 1-3 and a fixed branch pipe 2, and finally, a sealing plug 7 covers the threaded pipe 1-2 after grouting is finished.
For example, when the ground seam is deep, the other main pipe 1-1 can be inserted into the threaded column 1-2 on the lower main pipe 1-1 and screwed.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.
Claims (4)
1. The utility model provides a structure of underground overlength concrete replacement post-cast strip, includes pouring riser (1), fixed branch pipe (2), connects a piece (3), strutting arrangement (4), adjusting device (5), fixed snap ring (6), seals up (7), its characterized in that: the device is characterized in that fixed branch pipes (2) are fixedly connected in a bilateral symmetry mode below the surface of the top end of the side of the pouring vertical pipe (1), fixed support blocks (3) are fixedly connected in a front-back symmetry mode in the middle of the surface of the top end of the side of the pouring vertical pipe (1), supporting devices (4) are inserted in the middle of the surface of the top end of the outer side of each fixed support block (3), an adjusting device (5) is inserted in the circle center of the top surface of the side of the pouring vertical pipe (1), a fixed clamping ring (6) is fixed in the circle center of the top surface of the side of the pouring vertical pipe (1) in an inserting mode, and a sealing plug (7) is inserted in the circle center of the top surface of the upper top end of the pouring vertical pipe (1).
2. The structure of claim 1, in which the underground super-long concrete replaces a post-cast strip, characterized in that: pour riser (1) including being responsible for (1-1), screwed pipe (1-2), through-hole (1-3) and internal thread (1-4), be responsible for (1-1) and go up top surface centre of a circle department fixedly connected with screwed pipe (1-2), be responsible for (1-1) side top surface below department bilateral symmetry and be equipped with through-hole (1-3), be responsible for (1-1) inside side top surface lower limb department and be equipped with internal thread (1-4), fixed branch pipe (2) fixed connection is in inside through-hole (1-3).
3. The structure of claim 1, in which the underground super-long concrete replaces a post-cast strip, characterized in that: the supporting device (4) comprises a connecting plate (4-1), a rotating shaft (4-2), clamping blocks (4-3) and anti-slip strips (4-4), the rotating shaft (4-2) is inserted in the middle of the inner edge of the side top end surface of the connecting plate (4-1), the clamping blocks (4-3) are fixedly connected in the middle of the outer side top end surface of the connecting plate (4-1), the anti-slip strips (4-4) are fixedly distributed in the middle of the outer side top end surface of the clamping blocks (4-3) in a vertical and evenly distributed mode, and the connecting plate (4-1) and the fixed supporting blocks (3) are connected with each other through the rotating shaft (4-2).
4. The structure of underground ultra-long concrete replacing post-cast strip according to claim 2, wherein: the adjusting device (5) comprises an inserting ring (5-1), a push ring (5-2), rubber pads (5-3) and clamping columns (5-4), the push ring (5-2) is fixedly inserted at the lower edge of the side top end surface of the inserting ring (5-1), the push ring (5-2), the rubber pads (5-3) are symmetrically and fixedly connected at the front edge and the rear edge of the lower top end surface of the push ring (5-1), the clamping columns (5-4) are fixedly connected at the circle center of the lower top end surface of each rubber pad (5-3), and the inserting ring (5-1) is inserted on the main pipe (5-1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202122164378.3U CN215715319U (en) | 2021-09-08 | 2021-09-08 | Structure for replacing post-cast strip with underground ultra-long concrete |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202122164378.3U CN215715319U (en) | 2021-09-08 | 2021-09-08 | Structure for replacing post-cast strip with underground ultra-long concrete |
Publications (1)
Publication Number | Publication Date |
---|---|
CN215715319U true CN215715319U (en) | 2022-02-01 |
Family
ID=80016806
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202122164378.3U Active CN215715319U (en) | 2021-09-08 | 2021-09-08 | Structure for replacing post-cast strip with underground ultra-long concrete |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN215715319U (en) |
-
2021
- 2021-09-08 CN CN202122164378.3U patent/CN215715319U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206540552U (en) | A kind of concealed observation pier | |
CN207121928U (en) | A kind of new prefabricated assembled piping lane | |
CN215715319U (en) | Structure for replacing post-cast strip with underground ultra-long concrete | |
CN212176569U (en) | Floor preformed hole plugging device | |
CN108560579A (en) | The pre-buried parallels construction method of spring | |
CN211174152U (en) | Temporary support device is used in tunnel construction in pit | |
CN104344086B (en) | A kind of pipeline buttress device and using method | |
CN210263929U (en) | A preformed hole template for building civil engineering | |
CN208501662U (en) | A kind of device for independent cushion cap periphery backfill rammed earth | |
CN204801846U (en) | Civil engineering pipe fitting rack | |
CN211621118U (en) | A assembled template for road surface is laid | |
CN205172037U (en) | Building support frame | |
CN211285610U (en) | Water conservancy water and electricity construction fastening processing apparatus | |
CN208293603U (en) | The pre-buried parallels device of spring | |
CN209855288U (en) | Combined supporting pile for civil engineering | |
CN210459909U (en) | Auxiliary device for building indoor construction | |
CN210596954U (en) | Leveling device for highway construction | |
CN207862787U (en) | A kind of pin-connected panel slideway | |
CN216923442U (en) | Natural gas line strutting arrangement | |
CN211112958U (en) | Sleeper laying structure for railway tunnel | |
CN214883945U (en) | Slip casting self-balancing load box | |
CN216641327U (en) | Self-leveling large-area construction slurry layer positioning and leveling device | |
CN216196573U (en) | Hydraulic self-creeping formwork with suspension bracket assembly | |
CN214687109U (en) | Quick installation mould of cable pit capping | |
CN218881822U (en) | Protective structure is used in construction of side slope geological disaster |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |