CN215671507U - Novel fender is enclosed in assembled construction - Google Patents

Novel fender is enclosed in assembled construction Download PDF

Info

Publication number
CN215671507U
CN215671507U CN202120744078.XU CN202120744078U CN215671507U CN 215671507 U CN215671507 U CN 215671507U CN 202120744078 U CN202120744078 U CN 202120744078U CN 215671507 U CN215671507 U CN 215671507U
Authority
CN
China
Prior art keywords
concrete foundation
fence
foundation pier
pier
type
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120744078.XU
Other languages
Chinese (zh)
Inventor
张义
李春
韩广魁
陈金奎
祖全亮
孔德吉
张振东
周骏
王慧
郑新波
赵盈盈
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinan Municipal Engineering Design and Research Institute Group Co Ltd
Original Assignee
Jinan Municipal Engineering Design and Research Institute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinan Municipal Engineering Design and Research Institute Group Co Ltd filed Critical Jinan Municipal Engineering Design and Research Institute Group Co Ltd
Priority to CN202120744078.XU priority Critical patent/CN215671507U/en
Application granted granted Critical
Publication of CN215671507U publication Critical patent/CN215671507U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a novel assembly type construction enclosure which is connected by simple connection modes such as a flange plate and a sliding bolt, the difficulty of field installation and disassembly work is greatly reduced, a long pipe can pass through a pipe hole formed by an embedded PVC pipe in the transportation process through the embedded PVC pipe at the position with the same height above square grooves at two sides, the transportation of manual and mechanical equipment is facilitated, the left side and the right side of the bottom surface of a concrete foundation pier are respectively provided with the square grooves, the position of the concrete foundation pier cannot be influenced by rainwater, fallen leaves and the like, a water accumulation pool or a sanitary dead angle is formed, and the impression of dirty, messy and poor position of the construction enclosure in the past is improved.

Description

Novel fender is enclosed in assembled construction
Technical Field
The utility model relates to the field of construction barriers, in particular to a novel assembly type construction barrier.
Background
With the continuous development of urbanization construction in China, every corner of a city is covered by a construction site, in order to reduce the influence of the construction site on the surrounding environment and the urban environment sanitation, according to the requirements of the current laws and regulations, a fence needs to be placed on the periphery of the construction site, so that a relatively closed space is formed on the construction site, and meanwhile, certain guarantee is provided for the safety of pedestrians outside the construction site. But because the fence lower part basis that the municipal construction used at present mostly is the field operation, mostly is the welding between the steel construction of upper portion, but most materials after the use do not possess the possibility of circulated use, enclose the fence because of demolising after the construction completion and produced a large amount of building rubbish, do not conform to green economic development's needs.
Meanwhile, in the installation process, due to the defects of the connection mode between the structures, after the enclosure is finished, the surface has the phenomena of gaps, dislocation and the like, and the overall visual sense is poor. Therefore, improvements in the current forms of fencing are needed.
SUMMERY OF THE UTILITY MODEL
Aiming at the defects in the prior art, the utility model aims to provide a novel assembly type construction enclosure, solves the problems of large gap and poor overall plane vision experience between the conventional construction enclosures, also solves the problems of resource waste and damage to the surrounding environment caused in the dismantling process of the conventional masonry structure masonry or concrete cast-in-place enclosure, and greatly shortens the construction period.
In order to achieve the purpose, the utility model adopts the following technical scheme:
the utility model provides a novel assembly type construction enclosure, which comprises a concrete foundation pier, enclosure stand columns vertically fixed on the concrete foundation pier, and an enclosure fence plate arranged between every two enclosure stand columns.
The concrete foundation pier is a reinforced concrete member prefabricated in a prefabrication factory and is divided into an A-type concrete foundation pier and a B-type concrete foundation pier.
Concrete foundation pier both sides extend vertically respectively to set up a square groove about the bottom surface, and the horizontal central axis who extends concrete foundation pier sets up a dovetail groove that link up the bottom surface, and the square groove of both sides has the same distance M with concrete foundation pier's both sides face, and the same high department all pre-buries a PVC pipe directly over the square groove of both sides.
The two concrete foundation piers are alternately connected, wherein a foundation bolt group and a base flange plate which are in the corresponding specification with a stiffening flange plate of the enclosure upright post are pre-embedded in the center of the top surface of the A-type concrete foundation pier and are used for connecting the enclosure upright post, so that the concrete foundation pier and the enclosure upright post are detachably connected; the bottom surfaces of the base flange plate and the stiffening flange plate are the same in specification and model; the foundation bolt group and the base flange plate are not pre-embedded in the center of the top surface of the B-type concrete foundation pier.
A type concrete foundation pier and B type concrete foundation pier have the same structural dimension, all pre-buried rag bolt group in top surface both ends, and the rag bolt group of tip and the side of A type concrete foundation pier and B type concrete foundation pier have the same distance, the A type concrete foundation pier and the B type concrete foundation pier that link to each other are through the connecting steel plate with the bolt hole of pre-buried rag bolt group quantity and overall arrangement adaptation with the left rag bolt group of A type concrete foundation pier top surface and the rag bolt group fixed connection on B type concrete foundation pier right side, make and realize seamless connection between A type concrete foundation pier and the B type concrete foundation pier.
The upper portion of the foundation bolt exposed out of the concrete is provided with threads, the upper portion of the foundation bolt exposed out of the concrete can be fixedly connected with related components through nuts, and the lower portion of the foundation bolt embedded in the concrete is bent into a hook shape, so that the drawing force of the foundation bolt relative to a concrete foundation pier is increased, and the anti-drawing performance of the foundation bolt is improved.
The foundation bolt group is composed of a plurality of foundation bolts and is symmetrically arranged about a transverse central axis of the concrete foundation pier, wherein the distance between the foundation bolts symmetrical about the transverse central axis of the concrete foundation pier is larger than the thickness of the barrier fence plate.
The enclosure upright post comprises an upper portion post body and a lower portion connecting piece, the upper portion post body is a steel square tube upright post, a plurality of groups of sliding bolt holes are symmetrically formed in the left side and the right side of the upper portion post body and are matched with the sliding bolt holes in the upright post of the enclosure fence plate for use, the enclosure upright post and the enclosure fence plate are tightly connected together through sliding bolts and nuts, and seamless connection between the enclosure upright post and the enclosure fence plate is achieved.
A plurality of groups of stiffening ribs are symmetrically arranged at the bottom of the enclosure upright post about the central axis of the steel square tube upright post, and two mutually vertical edges of the stiffening ribs are respectively welded on the upper post body and the lower connecting piece and are used for connecting the upper post body and the lower connecting piece; the stiffening rib complex number that prolongs horizontal setting sets up in pairs, and both have been about enclosing the vertical center axis symmetry of keeping off the stand and about enclosing the horizontal center axis symmetry of keeping off the stand, and apart from the distance of keeping apart between the nearest two sets of stiffening rib of horizontal center axis of keeping off the stand equals the gross thickness of fence board.
And the lower connecting piece adopts a stiffening flange plate which is matched with the A-type concrete foundation pier in number and layout and is embedded in the center of the top surface of the A-type concrete foundation pier, and is used for connecting the A-type concrete foundation pier.
Enclose and keep off the breast board and include field font frame and the various steel sheet of cover on the frame, field font frame is formed through the welding by pole setting and horizontal pole, pole setting and horizontal pole adopt steel square pipe, and the pole setting of enclosing the breast board both sides is equipped with multiunit bilateral symmetry's slip bolt hole, and the slip bolt hole cooperation that encloses on the fender stand uses, will enclose the fender stand and enclose the barrier board zonulae occludens together through slip bolt and nut, realizes enclosing the seamless connection between the stand and the fender breast board.
The longitudinal width of the enclosure upright post is greater than the thickness of the enclosure fence plate and is about twice the thickness of the enclosure fence plate.
The utility model has the beneficial effects that:
(1) the overall design idea of the utility model mainly takes factory prefabrication and on-site quick assembly and disassembly as core elements, effectively shortens the construction time in the early stage of the municipal construction process, reduces the influence on the sanitation of the surrounding environment caused by building the lower foundation of the enclosure on site, and meets the development requirement of resource circulation type economy advocated at the present stage.
(2) The concrete foundation pier is connected by adopting simple connection modes such as the flange plate, the sliding bolt and the like, the difficulty of field installation and disassembly is greatly reduced, the requirement on the technical experience of a disassembling worker is lower, the field construction period is greatly shortened, the field working efficiency is improved, and the long pipe can penetrate through the pipe hole formed by the embedded PVC pipe in the transportation process of the concrete foundation pier through the embedded PVC pipe at the same height position right above the square grooves at the two sides, so that the transportation of manual and mechanical equipment is facilitated.
(3) After the installation of the utility model is finished, the integral flatness and the visual effect of the enclosure are good, and the left side and the right side of the bottom surface of the concrete foundation pier are respectively provided with the square groove, so that the position of the concrete foundation pier is not influenced by rainwater, fallen leaves and the like, a water accumulation pool or a sanitary dead angle is formed, and the impression of dirty, messy and poor position of the construction enclosure in the past is improved.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this specification, are included to provide a further understanding of the utility model, and are incorporated in and constitute a part of this specification, illustrate exemplary embodiments of the utility model and together with the description serve to explain the utility model and not to limit the utility model.
FIG. 1 is an assembled schematic view of the construction fence of the present invention;
FIG. 2 is a schematic view of the connection between the enclosure pillar and the concrete pier of the construction enclosure of the present invention;
FIG. 3 is a cross-sectional view taken along line B-B of FIG. 2 in accordance with the present invention;
FIG. 4 is a cross-sectional view taken along line A-A of FIG. 2 in accordance with the present invention;
FIG. 5 is a schematic view of the anchor bolt connection of the construction fence of the present invention;
FIG. 6 is a top view of the fence post of the construction fence of the present invention;
FIG. 7 is a top view of the connecting steel plate of the construction fence of the present invention;
FIG. 8(a) is a schematic representation of the front face of a stiffener of the construction enclosure of the present invention;
FIG. 8(b) is a schematic side view of a stiffener of the construction enclosure of the present invention;
FIG. 9 is a schematic view of a fencing panel of the construction fence of the present invention;
FIG. 10 is a schematic view of a sliding bolted connection of the construction fence of the present invention;
the concrete foundation pier comprises a concrete foundation pier 1, a concrete foundation pier A, a concrete foundation pier B, a concrete foundation pier, a concrete foundation pier foundation B, a concrete foundation pier foundation B, a concrete foundation pier foundation B, a concrete foundation pier foundation B, a concrete foundation pier foundation, a concrete foundation B, a concrete foundation pier foundation, a concrete foundation pier foundation, a concrete foundation B, a concrete foundation pier foundation, a concrete foundation pier foundation B, a concrete foundation pier foundation, a concrete foundation pier foundation, a concrete foundation pier foundation, a concrete foundation pile, a concrete foundation pile, a.
Detailed Description
It is to be understood that the following detailed description is exemplary and is intended to provide further explanation of the utility model as claimed. Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs.
It is noted that the terminology used herein is for the purpose of describing particular embodiments only and is not intended to be limiting of exemplary embodiments according to the utility model. As used herein, the singular forms "a", "an", and/or "the" are intended to include the plural forms as well, and it should be understood that when the terms "comprises" and/or "comprising" are used in this specification, they specify the presence of stated features, steps, operations, devices, components, and/or combinations thereof;
term interpretation section: the terms "mounted," "connected," "fixed," and the like in the present invention are to be understood broadly, and may be, for example, fixed, detachable, or integrally connected; the two components can be directly connected or indirectly connected through an intermediate medium, or the two components can be connected internally or in an interaction relationship; to those skilled in the art, the above terms are to be understood as having the specific meanings of the present invention according to specific situations and not as being limiting.
The noun explains: the transverse direction is the direction of the connection and extension of the concrete foundation piers; the longitudinal direction is the direction of travel intercepted by the concrete pier.
Example (b):
the utility model is described in detail below with reference to the accompanying drawings and specific embodiments, and specifically, the structure is as follows:
the embodiment provides a novel fender is enclosed in assembly type construction, including concrete foundation pier, the vertical fixation enclose on concrete foundation pier keep off stand 3, per two enclose and be provided with between the fender stand and enclose fencing board 4.
The concrete foundation pier is a reinforced concrete member prefabricated in a prefabricating factory and is divided into an A-type concrete foundation pier 1 and a B-type concrete foundation pier 2, the two concrete foundation piers are alternately connected, and the concrete foundation pier can be directly moved according to the requirement of the placement position in the field operation process. The A-type concrete foundation pier 1 is pre-embedded with a top surface center foundation bolt group 5 and a base flange 8 which have the specifications corresponding to the stiffening flange 7 of the enclosure upright post 3 at the top surface center position, and is used for connecting the enclosure upright post 3 to enable the concrete foundation pier to be detachably connected with the enclosure upright post 3; the bottom surface specification model of the base flange plate 8 is the same as that of the stiffening flange plate 7; the foundation bolt group and the base flange plate are not pre-embedded in the center of the top surface of the B-type concrete foundation pier 2.
A type concrete foundation pier 1 and B type concrete foundation pier 2 have the same structural dimension, top surface both sides rag bolt group 6 all pre-buried at the top surface both ends, and top surface both sides rag bolt group 6 and A type concrete foundation pier 1 and the side of B type concrete foundation pier 2 have the same distance, A type concrete foundation pier 1 and B type concrete foundation pier 2 that link to each other are through having the connecting steel plate 9 with the bolt hole of top surface both sides rag bolt group quantity and overall arrangement adaptation with the left rag bolt group of A type concrete foundation pier 1 top surface and the rag bolt group fixed connection on B type concrete foundation pier 2 right side, make and realize seamless connection between A type concrete foundation pier 1 and the B type concrete foundation pier 2.
And the edge of the top surface of the concrete foundation pier adopts a fillet guiding process.
The upper portion of the foundation bolt 14 exposed out of the concrete is provided with threads, related parts can be fixedly connected through nuts, the lower portion of the foundation bolt 14 embedded in the concrete is bent into a hook shape, so that the drawing force of the foundation bolt 14 relative to a concrete foundation pier is increased, and the tensile resistance of the foundation bolt 14 is improved.
The top surface center anchor bolt group 5 and the top surface two side anchor bolt groups 6 are composed of a plurality of anchor bolts 14 and are symmetrically arranged about the transverse central axis of the concrete foundation pier, wherein the distance between the anchor bolts 14 symmetrical about the transverse central axis of the concrete foundation pier is larger than the thickness of the fence board 4.
The concrete foundation pier respectively sets up a square groove in the longitudinal direction of extending in both sides about the bottom surface, extend horizontal central axis and set up a dovetail groove that link up the bottom surface, make concrete foundation pier place department can not receive the influence of rainwater, fallen leaves etc. form ponding pond or sanitary dead angle, the square groove of both sides has the same distance M with the both sides face of concrete foundation pier, the equal pre-buried PVC pipe of same height department directly over the square groove of both sides for the concrete foundation pier can pass the connecting pipe/line in the PVC tube hole 10 that is formed by pre-buried PVC pipe in the transportation, be convenient for manual work and mechanical equipment's transport work.
The enclosure upright post 3 comprises an upper post body 15 and a lower connecting piece, the upper post body 15 is a steel square tube upright post, the left side and the right side of the upper post body are symmetrically provided with a plurality of groups of enclosure upright post sliding bolt holes 12 which are matched with sliding bolt holes on an enclosure upright post 17 for use, and the enclosure upright post 3 and the enclosure baffle 4 are tightly connected together through a sliding bolt 14 and a nut; realize enclosing the seamless connection between fender breast board and the fender stand.
A plurality of groups of stiffening ribs 13 are symmetrically arranged at the bottom of the enclosure upright post 3 about the central axis of the steel square tube upright post, and two mutually vertical edges of the stiffening ribs 13 are respectively welded on the upper post body 15 and the lower connecting piece and are used for connecting the upper post body 15 and the lower connecting piece; wherein, the plurality of stiffening ribs 13 arranged along the transverse direction are arranged in pairs, and are symmetrical about the longitudinal central axis of the enclosure upright post 3 and the transverse central axis of the enclosure upright post 3, and the distance between two groups of stiffening ribs nearest to the transverse central axis of the enclosure upright post 3 is equal to the total thickness of the enclosure fence board; and the lower connecting piece adopts a stiffening flange 7 which is matched with the A-type concrete foundation pier 1 in the number and the layout of the foundation bolt groups pre-embedded in the center of the top surface of the A-type concrete foundation pier.
Enclose fender breast board 4 and include field font frame and the various steel sheet 19 of cover on the frame, field font frame is formed through the welding by enclosing fender pole setting 17 and enclosing fender breast board horizontal pole 18, enclosing fender breast board pole setting 17 and enclosing fender breast board horizontal pole 18 all adopt the steel square pipe of same specification, and the pole setting of enclosing fender breast board 4 both sides is equipped with multiunit bilateral symmetry's fender breast board pole setting slip bolt hole 16, uses with the slip bolt hole cooperation on enclosing the stand 3, will enclose the stand and enclose fender breast board zonulae occludens together through slip bolt 14 and nut, realizes enclosing the seamless connection between fender breast board and the fender stand.
The longitudinal width of the enclosure upright post 3 is larger than the thickness of the enclosure fence plate and is about twice the thickness of the enclosure fence plate 4.
The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (10)

1. A novel fabricated construction fence is characterized by comprising a concrete foundation pier, fence upright posts vertically fixed on the concrete foundation pier, and fence boards arranged between every two fence upright posts;
concrete foundation pier respectively sets up a square groove in the vertical of extending concrete foundation pier in the bottom surface left and right sides, and the horizontal central axis who extends concrete foundation pier sets up a dovetail groove that link up the bottom surface, and the square groove of both sides has the same distance M with the both sides face of concrete foundation pier, respectively pre-buried a PVC pipe in the same height department directly over the square groove of both sides.
2. The novel fabricated construction fence as claimed in claim 1, wherein the concrete foundation piers are reinforced concrete members prefabricated in a prefabrication plant, and are divided into type a concrete foundation piers and type B concrete foundation piers; the two concrete foundation piers are alternately connected, wherein a foundation bolt group and a base flange plate which are in the corresponding specification with a stiffening flange plate of the enclosure upright post are pre-embedded in the center of the top surface of the A-type concrete foundation pier and are used for connecting the enclosure upright post, so that the concrete foundation pier and the enclosure upright post are detachably connected;
the bottom surfaces of the base flange plate and the stiffening flange plate are the same in specification and model;
and the center of the top surface of the B-type concrete foundation pier is not embedded with the foundation bolt group and the base flange plate.
3. The novel fabricated construction fence as claimed in claim 2, wherein the A-type concrete foundation pier and the B-type concrete foundation pier have the same structural size, the foundation bolt groups are embedded in two ends of the top surface, and the connected A-type concrete foundation pier and the B-type concrete foundation pier fixedly connect the foundation bolt group on the left side of the top surface of the A-type concrete foundation pier with the foundation bolt group on the right side of the B-type concrete foundation pier through the connecting steel plates of the bolt holes with the quantity and the layout adaptive to the embedded foundation bolt groups.
4. The novel fabricated construction fence as claimed in claim 3, wherein the upper part of the anchor bolt exposed out of the concrete is provided with screw threads, the relevant parts can be fixedly connected through nuts, and the lower part of the anchor bolt embedded in the concrete is bent into a hook shape.
5. The novel fabricated construction fence as claimed in claim 4, wherein the anchor bolt group is composed of a plurality of anchor bolts and is symmetrically disposed about a transverse central axis of the concrete foundation pier, wherein a distance between the anchor bolts symmetrical about the transverse central axis of the concrete foundation pier is greater than a thickness of the fence.
6. The assembly type construction fence as claimed in claim 1, wherein the fence post comprises an upper post body and a lower connecting piece, the upper post body is a square steel tube post, the left and right sides of the upper post body are symmetrically provided with a plurality of groups of sliding bolt holes, the sliding bolt holes are matched with the sliding bolt holes on the fence upright post, and the fence post and the fence are connected together through sliding bolts and nuts.
7. The novel assembly type construction fence as claimed in claim 1, wherein a plurality of groups of stiffening ribs are symmetrically arranged at the bottom of the fence upright post about the central axis of the steel square tube upright post, and two mutually perpendicular edges of the stiffening ribs are respectively welded on the upper post body and the lower connecting piece and are used for connecting the upper post body and the lower connecting piece; the stiffening rib complex number that prolongs horizontal setting sets up in pairs, and both have been about enclosing the vertical center axis symmetry of keeping off the stand and about enclosing the horizontal center axis symmetry of keeping off the stand, and apart from the distance of keeping apart between the nearest two sets of stiffening rib of horizontal center axis of keeping off the stand equals the gross thickness of fence board.
8. The novel fabricated construction fence as claimed in claim 6, wherein the lower connecting member is a stiffening flange plate adapted to the number and layout of the foundation bolt groups pre-embedded at the center of the top surface of the A-type concrete foundation pier, and is used for connecting the A-type concrete foundation pier.
9. The novel assembly type construction fence according to claim 1, wherein the fence comprises a frame shaped like a Chinese character 'tian' and color steel plates covered on the frame, the frame shaped like a Chinese character 'tian' is formed by welding vertical rods and cross rods, the vertical rods and the cross rods are square steel tubes, the vertical rods on two sides of the fence are provided with multiple sets of sliding bolt holes which are symmetrical left and right, the sliding bolt holes are matched with the sliding bolt holes on the fence, and the fence are connected together through sliding bolts and nuts.
10. The novel fabricated construction fence of claim 1, wherein the longitudinal width of said fence posts is greater than and about twice the thickness of said fence panel.
CN202120744078.XU 2021-04-12 2021-04-12 Novel fender is enclosed in assembled construction Active CN215671507U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120744078.XU CN215671507U (en) 2021-04-12 2021-04-12 Novel fender is enclosed in assembled construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120744078.XU CN215671507U (en) 2021-04-12 2021-04-12 Novel fender is enclosed in assembled construction

Publications (1)

Publication Number Publication Date
CN215671507U true CN215671507U (en) 2022-01-28

Family

ID=79970254

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120744078.XU Active CN215671507U (en) 2021-04-12 2021-04-12 Novel fender is enclosed in assembled construction

Country Status (1)

Country Link
CN (1) CN215671507U (en)

Similar Documents

Publication Publication Date Title
CN107419824A (en) The full precast shear wall structural system of regenerative steel skeleton and construction method
CN207017483U (en) The full precast shear wall structural system of regenerative steel skeleton
CN215671507U (en) Novel fender is enclosed in assembled construction
CN211849246U (en) Reverse hoisting system suitable for high-pile wharf
CN209760968U (en) Integrated louver-shaped fence
CN110924415A (en) Steel bar support frame structure for 4.5m thick large raft foundation and construction method thereof
CN213732502U (en) High-efficient prefabricated case roof beam field steel reinforcement cage ligature bench formwork
CN212154137U (en) Assembled support-free hanging die
CN202450793U (en) Grille type color plate ventilation fence for construction site
CN111648494A (en) Assembled both sides connection steel grid shear force wall convenient to replacement
CN220336447U (en) Balcony guardrail combined type template
CN214939361U (en) Adjustable cantilever operation platform
CN111075262A (en) Detachable type section steel column welding wind shield
CN212027401U (en) Movable prefabricated assembly type construction enclosure
CN215369949U (en) Middle plate and frame body reserved door type channel
CN220487281U (en) Protective railing structure convenient to dismantle
CN213953062U (en) Steel guardrail bar form convenient to disassemble
CN213654439U (en) Short rail connection structure in park timber apron edge
CN218538899U (en) Stand column structure and elevator shaft
CN218454336U (en) Pedestrian steel floating bridge
CN215123016U (en) Fast-assembling biological safety enclosure wall for livestock farm
CN212295921U (en) Assembled encloses fender temporarily
CN217500293U (en) Prefabricated square pile and photovoltaic support
CN215330944U (en) Reinforced concrete column with shaped steel core column and lattice angle steel column
CN215210561U (en) High-pier temporary steel tie beam bolt connecting device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant