CN215615039U CN202120093725.5U CN202120093725U CN215615039U CN 215615039 U CN215615039 U CN 215615039U CN 202120093725 U CN202120093725 U CN 202120093725U CN 215615039 U CN215615039 U CN 215615039U
Authority
CN
China
Prior art keywords
ladle
steel
shell
emergency
precast block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120093725.5U
Other languages
Chinese (zh)
Inventor
李源源
刘远
顾琛
余辉
陈梁
沈明科
陆志坚
文震
陈�峰
刘光平
魏国平
陶群金
潘剑男
赵忠阳
潘小勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Zili High Temperature Technology Co ltd
Guangxi Liuzhou Iron and Steel Group Co Ltd
Guangxi Iron and Steel Group Co Ltd
Original Assignee
Zhejiang Zili High Temperature Technology Co ltd
Guangxi Liuzhou Iron and Steel Group Co Ltd
Guangxi Iron and Steel Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Zili High Temperature Technology Co ltd, Guangxi Liuzhou Iron and Steel Group Co Ltd, Guangxi Iron and Steel Group Co Ltd filed Critical Zhejiang Zili High Temperature Technology Co ltd
Priority to CN202120093725.5U priority Critical patent/CN215615039U/en
Application granted granted Critical
Publication of CN215615039U publication Critical patent/CN215615039U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model provides a lining structure of a steel-making emergency ladle, which comprises a ladle, a lining and a lining, wherein the ladle comprises a ladle wall structure and a ladle bottom structure arranged at the bottom of the ladle wall structure; and an inner lining structure comprising a 'well' -shaped prefabricated member arranged inside the wall-wrapping structure; the steel blocks cooled in the emergency ladle can be poured out conveniently; oxygen cutting is carried out along the position of the molten steel overflow port of the aluminum-magnesium precast block, the steel block can be easily divided into seven steel blocks, the gas consumption is small, the time consumption is short, the cutting is convenient, and the steel block is hoisted by a crane and is simple to carry; can meet the requirement of large-tonnage steel ladle steelmaking.

Description

Lining structure of steel-making emergency steel ladle
Technical Field
The utility model relates to the technical field of metallurgy, in particular to a lining structure of a steel-making emergency ladle.
Background
The steel-making emergency ladle is used as an emergency ladle or a spare ladle for intensively collecting and treating molten steel/molten iron in an accident state in a steel-making area, and if the problem of unbalanced use of the molten iron and the molten steel occurs in the initial production period of many newly-built steel mills at present or a continuous casting machine fails after molten steel of a converter enters the ladle, the molten steel in the ladle cannot be poured, the molten steel can be poured into the emergency ladle, and the emergency ladle is convenient to treat after cooling. The steel ladle does not participate in normal steelmaking operation, and is only used for temporarily containing and storing molten steel, the high-temperature molten steel is cooled in a steelmaking emergency steel ladle to form a large steel column or a round lump large steel block, the emergency steel ladle overturns to pour out the steel block, the steel block is recycled, and the steel block needs to be cut into small steel blocks with proper sizes by oxygen before being carried. The requirements of the masonry process and the service life of the steel-making emergency ladle are different from those of a normal production ladle, and the service life of the steel-making emergency ladle is only one time. The emergency steel ladle in the prior art is constructed by adopting a universal arc-shaped brick single layer, and a ladle wall and a ladle bottom are directly constructed by adopting clay bricks and yellow sand. The steel blocks in the small steel ladle emergency steel ladle are small, cutting and carrying are relatively convenient, the structure can meet the use requirements, the tonnage of the steel-making steel ladle is developed to be large-scale along with the development of metallurgical technology, a large number of steel plants begin to use steel ladles with the tonnage of more than 200 tons for steel making, the steel-making steel ladle of the Zhanjiang steel company Limited currently reaches 350 tons, and the steel ladle in the prior art accident can not meet the requirements of the current industry.
SUMMERY OF THE UTILITY MODEL
This section is for the purpose of summarizing some aspects of embodiments of the utility model and to briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section as well as in the abstract of the specification and the title of the application to avoid obscuring the purpose of this section, the abstract of the specification and the title of the application, and such simplifications or omissions are not intended to limit the scope of the utility model.
Therefore, the technical problem to be solved by the utility model is to overcome the defects that the emergency steel ladle in the prior art is simple in structure and the process of treating the cooled molten steel in the emergency steel ladle is complex, so that the lining structure of the steel-making emergency steel ladle is provided.
In order to solve the technical problems, the utility model provides the following technical scheme: the lining structure of the steel-making emergency ladle comprises a ladle, a steel-making emergency ladle and a steel-making emergency ladle, wherein the ladle comprises a ladle wall structure and a ladle bottom structure arranged at the bottom of the ladle wall structure; and an inner lining structure comprising a 'well' type preform arranged inside the containment wall structure.
As a preferable aspect of the lining structure of the steel-making emergency ladle of the present invention, wherein: the cladding wall structure comprises a cladding with an axis longitudinal section being U-shaped, a shell permanent layer is arranged on the inner side of the cladding in a clinging manner, a shell working layer is arranged on the inner side of the shell permanent layer, a gap is reserved between the shell permanent layer and the shell working layer, the gap distance is 0-170mm, and magnesia filler is filled in the gap; the permanent layer of the shell is made of a high-alumina casting material with the thickness of 110 mm; the working layer of the shell is built by arc-shaped high-alumina bricks with the thickness of 100 mm.
As a preferable aspect of the lining structure of the steel-making emergency ladle of the present invention, wherein: the ladle bottom structure comprises a bottom shell, a bottom permanent layer is arranged above the bottom shell, and a bottom working layer is arranged above the bottom permanent layer; the bottom permanent layer is made of high-alumina casting materials with the thickness of 200mm, and the bottom working layer is vertically built by square high-alumina bricks with the thickness of 120 mm.
As a preferable aspect of the lining structure of the steel-making emergency ladle of the present invention, wherein: the prefabricated part comprises two long prefabricated blocks and four short prefabricated blocks symmetrically arranged on two sides of the long prefabricated block; the long precast block and the short precast block are longitudinally divided into 4 or 5 same precast block units, the top of each precast block unit is provided with a concave type, the bottom of each precast block unit is correspondingly provided with a convex type for being embedded into a whole, and the joint is provided with aluminum magnesium refractory mortar.
As a preferable aspect of the lining structure of the steel-making emergency ladle of the present invention, wherein: and a molten steel overflow port with the size of 300mm multiplied by 300mm is reserved at the position close to the bottom part below the long precast block and the short precast block.
The utility model has the beneficial effects that: when the steel-making is abnormal, molten steel is poured into the intermediate groove of the long aluminum-magnesium precast block of the emergency steel ladle and uniformly flows into the emergency steel ladle through the molten steel overflow port, the molten steel is directly overturned relative to the emergency steel ladle after being cooled to form a large steel block, the arc-shaped high-alumina bricks on the working layer of the steel ladle wall, the magnesia packing between the permanent layer and the working layer and the square high-alumina bricks on the working layer of the ladle bottom are poured out along with the accident steel block, the steel block is convenient to pour out, oxygen is cut along the position of the molten steel overflow port of the aluminum-magnesium precast block, the steel block is very easily cut into seven steel blocks, the gas consumption is small during cutting, the time consumption is short, and the cutting is convenient. The steel blocks are hoisted by adopting a crane and are simple to carry.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings needed to be used in the description of the embodiments will be briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings based on these drawings without inventive exercise. Wherein:
fig. 1 is a schematic view of the overall structure of the lining structure of the steel-making emergency ladle according to the present invention;
fig. 2 is a plan view of an inner lining structure of a steel-making emergency ladle according to the present invention;
fig. 3 is a half sectional view of an inner lining structure of a steel-making emergency ladle according to the present invention;
FIG. 4 is a schematic view of the connection of the inner precast block units;
Detailed Description
In order to make the aforementioned objects, features and advantages of the present invention comprehensible, embodiments accompanied with figures are described in detail below.
In the following description, numerous specific details are set forth in order to provide a thorough understanding of the present invention, but the present invention may be practiced in other ways than those specifically described and will be readily apparent to those of ordinary skill in the art without departing from the spirit of the present invention, and therefore the present invention is not limited to the specific embodiments disclosed below.
Example 1
This embodiment provides an inner lining structure of a steel-making emergency ladle, as shown in fig. 1 to 4, including,
the ladle 100 comprises a ladle wall structure 101 and a ladle bottom structure 102 arranged at the bottom of the ladle wall structure 101; and an inner lining structure 200 comprising a "well" type preform 201 disposed inside the containment wall structure 101.
The cladding wall structure 101 comprises a cladding 101a with an axis longitudinal section being U-shaped, a shell permanent layer 101b is arranged on the inner side of the cladding 101a in a close fit manner, a shell working layer 101d is arranged on the inner side of the shell permanent layer 101b, a gap 101c is reserved between the shell permanent layer 101b and the shell working layer 101d, the interval of the gap 101c is 0-170mm, and magnesia filler is filled in the gap 101 c; the shell permanent layer 101b is made of a high-alumina casting material with the thickness of 110 mm; the shell working layer 101d is built by arc-shaped high-alumina bricks with the thickness of 100 mm; the bottom wrapping structure 102 comprises a bottom shell 102a, a bottom permanent layer 102b is arranged above the bottom shell 102a, and a bottom working layer 102c is arranged above the bottom permanent layer 102 b; the bottom permanent layer 102b is made of high-alumina casting material with the thickness of 200mm, and the bottom working layer 102c is vertically built by square high-alumina bricks with the thickness of 120 mm.
The high-alumina castable is a cement-bonded castable which takes high-alumina bauxite or mullite as a main raw material, and the volume density is more than or equal to 2.45g/cm3,Al2O3Not less than 60.00 percent and the normal temperature compressive strength not less than 30.0 MPa. Stirring the high-alumina castable by using a powerful stirrer on site, wherein the water addition amount of the high-alumina castable is 5.5-7.5% of the mass of the castable, and performing vibration pouring construction; the high-alumina brick is a phosphate-bonded high-alumina brick with high-alumina bauxite as a main raw material, the arc degree of the arc-shaped high-alumina brick of the ladle wall is the same as that of the ladle wall, and the volume density is more than or equal to 2.45g/cm3,Al2O3The high-alumina brick is built by adopting aluminum-magnesium refractory mortar on site, wherein the high-alumina brick is more than or equal to 65.00 percent, and the normal-temperature compressive strength is more than or equal to 50.0 MPa; the magnesite filler is sintered or fused magnesite with MgO content not less than 92.00% and is crushed into 0-3mm grains. Directly filled in the permanent layer of the shell in situAnd the gap between the working layer and the working layer is 0-170 mm.
The prefabricated part 201 comprises two long prefabricated blocks 201a and four short prefabricated blocks 201b symmetrically arranged at two sides of the long prefabricated block 201 a; the long precast block 201a and the short precast block 201b are longitudinally divided into 4 or 5 same precast block units 201c, the top of each precast block unit 201c is provided with a concave 201c-1, the bottom of each precast block unit 201c is correspondingly provided with a convex 201c-2 to be embedded into a whole, and the connection part is provided with aluminum magnesium refractory mortar. The aluminum-magnesium precast block is made by baking cement-bonded precast pieces with high bauxite or corundum as main raw material at a temperature of more than 400 ℃ before delivery, and the volume density is more than or equal to 2.65g/cm3,Al2O3+ MgO is more than or equal to 80.00 percent, and the normal-temperature compressive strength is more than or equal to 30.0 MPa; the Al-Mg refractory mortar is prepared with superfine alumina clinker or corundum powder, high-quality magnesite and additive2O3And the + MgO is more than or equal to 82.00 percent, and the bonding rupture strength is more than or equal to 2.0MPa at 1500 ℃ for 3 h. The aluminum magnesium refractory mortar is stirred by a slurry stirrer on site, the water addition amount of the aluminum magnesium refractory mortar is 21.0-25.0% of the mass of the aluminum magnesium refractory mortar, and the aluminum magnesium refractory mortar is constructed by a mortar clamp.
A300 mm x 300mm molten steel overflow port 202 is reserved at the position close to the bottom part below the long precast block 201a and the short precast block 201b, so that molten steel can flow in the emergency steel ladle conveniently.
The beneficial effects of this embodiment: the steel blocks cooled in the emergency ladle can be poured out conveniently; oxygen cutting is carried out along the position of the molten steel overflow port of the aluminum-magnesium precast block, the steel block can be easily divided into seven steel blocks, the gas consumption is small, the time consumption is short, the cutting is convenient, and the steel block is hoisted by a crane and is simple to carry; can meet the requirement of large-tonnage steel ladle steelmaking.
It is important to note that the construction and arrangement of the present application as shown in the various exemplary embodiments is illustrative only. Although only a few embodiments have been described in detail in this disclosure, those skilled in the art who review this disclosure will readily appreciate that many modifications are possible (e.g., variations in sizes, dimensions, structures, shapes and proportions of the various elements, values of parameters (e.g., temperatures, pressures, etc.), mounting arrangements, use of materials, colors, orientations, etc.) without materially departing from the novel teachings and advantages of the subject matter recited in this application. For example, elements shown as integrally formed may be constructed of multiple parts or elements, the position of elements may be reversed or otherwise varied, and the nature or number of discrete elements or positions may be altered or varied. Accordingly, all such modifications are intended to be included within the scope of this invention. The order or sequence of any process or method steps may be varied or re-sequenced according to alternative embodiments. In the claims, any means-plus-function clause is intended to cover the structures described herein as performing the recited function and not only structural equivalents but also equivalent structures. Other substitutions, modifications, changes and omissions may be made in the design, operating conditions and arrangement of the exemplary embodiments without departing from the scope of the present inventions. Therefore, the present invention is not limited to a particular embodiment, but extends to various modifications that nevertheless fall within the scope of the appended claims.
Moreover, in an effort to provide a concise description of the exemplary embodiments, all features of an actual implementation may not be described (i.e., those unrelated to the presently contemplated best mode of carrying out the utility model, or those unrelated to enabling the utility model).
It should be appreciated that in the development of any such actual implementation, as in any engineering or design project, numerous implementation-specific decisions may be made. Such a development effort might be complex and time consuming, but would nevertheless be a routine undertaking of design, fabrication, and manufacture for those of ordinary skill having the benefit of this disclosure, without undue experimentation.
It should be noted that the above-mentioned embodiments are only for illustrating the technical solutions of the present invention and not for limiting, and although the present invention has been described in detail with reference to the preferred embodiments, it should be understood by those skilled in the art that modifications or equivalent substitutions may be made on the technical solutions of the present invention without departing from the spirit and scope of the technical solutions of the present invention, which should be covered by the claims of the present invention.

Claims (5)

1. The utility model provides a lining structure of ladle for steelmaking emergency which characterized in that: comprises the steps of (a) preparing a mixture of a plurality of raw materials,
the ladle (100) comprises a ladle wall structure (101) and a ladle bottom structure (102) arranged at the bottom of the ladle wall structure (101); and the number of the first and second groups,
the lining structure (200) comprises a 'well' -shaped preform (201) arranged inside the containment wall structure (101).
2. The lining structure of a steelmaking emergency ladle according to claim 1, wherein: the cladding wall structure (101) comprises a cladding (101a) with an axis longitudinal section being U-shaped, a shell permanent layer (101b) is arranged on the inner side of the cladding (101a) in a clinging manner, a shell working layer (101d) is arranged on the inner side of the shell permanent layer (101b), a gap (101c) is reserved between the shell permanent layer (101b) and the shell working layer (101d), the distance between the gaps (101c) is 0-170mm, and magnesia filler is filled in the gap (101 c); the shell permanent layer (101b) is made of a high-alumina casting material with the thickness of 110 mm; the shell working layer (101d) is built by arc-shaped high-alumina bricks with the thickness of 100 mm.
3. The lining structure of a steelmaking emergency ladle as claimed in claim 2, wherein: the bottom wrapping structure (102) comprises a bottom shell (102a), a bottom permanent layer (102b) is arranged above the bottom shell (102a), and a bottom working layer (102c) is arranged above the bottom permanent layer (102 b); the bottom permanent layer (102b) is made of high-alumina casting materials with the thickness of 200mm, and the bottom working layer (102c) is vertically built by square high-alumina bricks with the thickness of 120 mm.
4. The lining structure of a steelmaking emergency ladle as claimed in claim 3, wherein: the prefabricated part (201) comprises two long prefabricated blocks (201a) and four short prefabricated blocks (201b) symmetrically arranged on two sides of the long prefabricated blocks (201 a); the long precast block (201a) and the short precast block (201b) are longitudinally divided into 4 or 5 same precast block units (201c), the top of each precast block unit (201c) is provided with a concave type (201c-1), the bottom of each precast block unit is correspondingly provided with a convex type (201c-2) so as to be embedded into a whole, and the connection part is provided with aluminum magnesium refractory mortar.
5. The lining structure of a steelmaking emergency ladle as claimed in claim 4, wherein: a molten steel overflow port (202) with the size of 300mm multiplied by 300mm is reserved at the position close to the bottom part below the long precast block (201a) and the short precast block (201 b).
CN202120093725.5U 2021-01-14 2021-01-14 Lining structure of steel-making emergency steel ladle Active CN215615039U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120093725.5U CN215615039U (en) 2021-01-14 2021-01-14 Lining structure of steel-making emergency steel ladle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120093725.5U CN215615039U (en) 2021-01-14 2021-01-14 Lining structure of steel-making emergency steel ladle

Publications (1)

Publication Number Publication Date
CN215615039U true CN215615039U (en) 2022-01-25

Family

ID=79888803

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120093725.5U Active CN215615039U (en) 2021-01-14 2021-01-14 Lining structure of steel-making emergency steel ladle

Country Status (1)

Country Link
CN (1) CN215615039U (en)

Similar Documents

Publication Publication Date Title
CN100522882C (en) Fire resistive material for desulfurization spray gun and producing technique for the desulfurization spray gun
CN106145964B (en) Dry ramming material for large ladle bottom working lining
CN105036773A (en) Steel ladle bottom concreting material
CN102744393B (en) Tundish flow control device for slab casting machine, preparation method thereof and slagging method using tundish flow control device
CN106083110B (en) High strength steel ladle-lining castable
CN1220653C (en) Manufacture method of functional refractory for steelmaking
CN109487036B (en) High-purity manganese 18 high-manganese steel and preparation method thereof
CN104972103A (en) Combined type steel ladle permanent layer casting body
Zhong et al. Post-mortem analysis of MgO–Al2O3–C bricks containing bauxite used in steel ladle walls
CN215615039U (en) Lining structure of steel-making emergency steel ladle
US3963815A (en) Method of lining molten metal vessels and spouts with refractories
CN112743068A (en) Lining structure of steel-making emergency steel ladle and building method thereof
CN113843411B (en) Low-cost composite dry material working lining for two-flow plate blank continuous casting tundish and construction method
CN112024861A (en) KR desulfurization ladle inside lining
CN115650747A (en) Magnesia-hercynite ladle wall gunning mix and preparation method thereof
CN114262232A (en) Preparation method of carbon-free castable added with graphite raw material for refining ladle working lining
CN113333724B (en) Square-round steel ladle and refractory material building method thereof
CN200978292Y (en) Integral pouring iron mixing vehicle splash guard
CN220265732U (en) RH refining furnace dip pipe of steel is prevented wearing
CN116143501B (en) Mechanical pressing tundish hanging plate and preparation method thereof
JP2005186280A (en) Precast block manufacturing method
JP3439909B2 (en) Lining structure of vacuum molten steel processing equipment
Biswas et al. BOF Refractory
JPS5926979A (en) Basic indefinite form refractories for molten metal vessel
CN116835992A (en) Unfired aluminum magnesia carbon brick and preparation method thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant