CN215594815U CN202122478653.9U CN202122478653U CN215594815U CN 215594815 U CN215594815 U CN 215594815U CN 202122478653 U CN202122478653 U CN 202122478653U CN 215594815 U CN215594815 U CN 215594815U
Authority
CN
China
Prior art keywords
supporting leg
plate
fixed
frame
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122478653.9U
Other languages
Chinese (zh)
Inventor
赵峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202122478653.9U priority Critical patent/CN215594815U/en
Application granted granted Critical
Publication of CN215594815U publication Critical patent/CN215594815U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model relates to the technical field of fabricated scaffolds, in particular to a fabricated scaffold for constructional engineering. The steel pipe comprises a steel pipe and a connecting structure, wherein the connecting structure is arranged on the surface of the steel pipe and comprises a first supporting leg, the first supporting leg is fixedly connected with one end of the steel pipe, the surface of the first supporting leg is fixedly connected with a first sliding frame, the inner wall of the first sliding frame is connected with an inserting plate in a sliding mode, the surface of the inserting plate is rotatably connected with a clamping plate, the other end of the steel pipe is fixedly connected with a second supporting leg, a fixing plate is welded on the surface of the second supporting leg, a spring is fixedly connected to the inner wall of the inserting plate, the surface of the spring, far away from the inserting plate, is fixedly connected with a sliding plate, the sliding plate is movably connected with the inner wall of the clamping plate, and a fixing frame is welded on the surface of the second supporting leg. The problem of a scaffold area less, can lead to workman inconvenient operation in the course of the work is solved.

Description

Building engineering assembled scaffold
Technical Field
The utility model relates to the technical field of fabricated scaffolds, in particular to a fabricated scaffold for constructional engineering.
Background
The assembled scaffold for the construction engineering refers to an auxiliary instrument for helping workers to construct a higher position in the process of engineering construction.
The area of a common scaffold is small in the using process, so that a worker can operate inconveniently in the working process, and two scaffolds are directly put together, so that the two scaffolds are separated in the using process because the two scaffolds are not connected, and danger is generated.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the problem that the area of a scaffold is small in the prior art, which can cause inconvenience in operation of workers in the working process, and provides a fabricated scaffold for construction engineering.
In order to achieve the purpose, the utility model adopts the following technical scheme: the utility model provides a building engineering assembled scaffold, includes steel pipe and connection structure, the surface of steel pipe is provided with connection structure, connection structure includes first supporting leg, the one end fixed connection of first supporting leg and steel pipe, the first smooth frame of fixed surface of first supporting leg is connected with, the inner wall sliding connection of first smooth frame has the picture peg, the surface rotation of picture peg is connected with the cardboard, the other end fixed connection of steel pipe has the second supporting leg, the skin weld of second supporting leg has the fixed plate, in order to link together two scaffolds, can make the picture peg remove towards the direction of second supporting leg along first smooth frame to drive the cardboard and remove, until the cardboard passes the fixed plate, thereby link together first supporting leg and second supporting leg.
Preferably, the inner wall of the inserting plate is fixedly connected with a spring, the surface of the spring, which is far away from the inserting plate, is fixedly connected with a sliding plate, the sliding plate is movably connected with the inner wall of the clamping plate, the sliding plate can be pushed to move along the inner wall of the clamping plate through the elasticity of the spring, so that the clamping plate rotates, and the inserting plate can be fixed through the clamping plate.
Preferably, the surface welding of second supporting leg has the mount, the surperficial sliding connection of mount has the propelling movement frame, removes the propelling movement frame, makes the propelling movement frame move along the surface of mount towards the direction of first supporting leg, and then makes the surface contact of propelling movement frame and cardboard to make the cardboard rotate towards the direction of picture peg, then remove the picture peg towards the direction of keeping away from the second supporting leg again, in order to remove the fixed to first supporting leg and second supporting leg, just can be with two scaffold frame during separately.
Preferably, the surface welding of picture peg has the baffle, the inner wall fixedly connected with telescopic link of picture peg, the telescopic link is connected with the fixed surface of slide, can restrict cardboard pivoted angle through the baffle, can prevent through the telescopic link that the spring is crooked.
Preferably, the surface of first supporting leg and second supporting leg all is provided with fixed knot and constructs, fixed knot constructs including the smooth frame of second, the smooth frame of second is connected with the fixed surface of second supporting leg, the inner wall sliding connection of the smooth frame of second has the slider, the skin weld of slider has the fixed block, be provided with the long slab between fixed block and the steel pipe, promote the slider, make the slider remove towards the direction of steel pipe along the smooth frame of second, and then drive the fixed block and be close to towards the direction of steel pipe, until the long slab contact between fixed block and the steel pipe to fix the long slab.
Preferably, the surface welding of second supporting leg has the support frame, the inner wall threaded connection of support frame has the screw rod, rotates the screw rod, makes the screw rod remove the top of slider, just can fix the slider through the screw rod to prevent that the fixed block is not hard up.
Preferably, the fixed surface of screw rod is connected with the handle, the support frame has all been welded on the surface of first supporting leg and second supporting leg, can rotate the screw rod through the handle under the condition that does not need other instruments, moves the screw rod directly over the slider.
Compared with the prior art, the utility model has the advantages and positive effects that:
1. in the utility model, the inserting plate is moved to enable the inserting plate to move along the direction of the first sliding frame towards the fixed plate so as to drive the clamping plate to move, the clamping plate is enabled to be contacted with the fixed plate until the clamping plate penetrates through the fixed plate, at the moment, the sliding plate is pushed to move along the inner wall of the clamping plate through the elasticity of the spring, so that the clamping plate rotates, the first supporting leg and the second supporting leg can be connected together through the clamping plate and the fixed plate, the rotating angle of the clamping plate can be limited through the baffle plate, the fixing effect is improved, the spring is prevented from bending through the telescopic rod, the use is influenced, when two scaffolds are required to be separated, the pushing frame can be moved along the surface of the fixed frame towards the direction of the fixed plate, so that the pushing frame is enabled to be contacted with the surface of the clamping plate, the clamping plate rotates towards the direction of the inserting plate, then the inserting plate is moved towards the opposite direction, and the fixation of the first supporting leg and the second supporting leg can be released, two scaffolds can be connected together by arranging a connecting structure, so that the use area is increased, and the probability of danger is reduced.
2. In the utility model, when the scaffold is used, a long plate needs to be arranged on the surface of the scaffold to enable a worker to stand, when the long plate is arranged on the scaffold, the long plate is usually fixed by using screws, and tools are needed when the long plate is fixed by using the screws, so that the installation becomes troublesome, at the moment, the long plate can be placed between the fixed block and the steel pipe, then the sliding block is pushed, the sliding block moves downwards along the second sliding frame, so that the fixed block is driven to approach towards the direction of the long plate, the long plate can be fixed until the fixed block is contacted with the surface of the long plate, in the using process, the fixed block can be loosened to cause that the long plate cannot be fixed, so that danger occurs, therefore, after the long plate is installed, the screw rod is rotated by the handle to move to the position right above the sliding block, the sliding block can be fixed by the screw rod, thereby prevent that the fixed block is not hard up, through setting up a fixed knot structure, can fix the long slab convenient and fast.
Drawings
Fig. 1 is a schematic perspective view of a fabricated scaffold for construction engineering according to the present invention;
fig. 2 is a schematic view of a connection structure of the fabricated scaffold of the construction engineering shown in fig. 1 according to the present invention;
fig. 3 is a schematic structural view of the assembled scaffold for construction engineering shown at a in fig. 2;
fig. 4 is a schematic structural diagram of a fabricated scaffold for construction engineering shown at B in fig. 1.
Illustration of the drawings: 1. a steel pipe; 2. a connecting structure; 201. a first support leg; 202. a second support leg; 203. inserting plates; 204. a first slide frame; 205. a fixing plate; 206. a pushing frame; 207. a fixed mount; 208. a baffle plate; 209. clamping a plate; 210. a slide plate; 211. a spring; 212. a telescopic rod; 3. a fixed structure; 301. a long plate; 302. a second slide frame; 303. a support frame; 304. a screw; 305. a handle; 306. a slider; 307. and (5) fixing blocks.
Detailed Description
In order that the above objects, features and advantages of the present invention can be more clearly understood, the present invention will be further described with reference to the accompanying drawings and examples. It should be noted that the embodiments and features of the embodiments of the present application may be combined with each other without conflict.
In the following description, numerous specific details are set forth in order to provide a thorough understanding of the present invention, however, the present invention may be practiced in other ways than those specifically described herein, and thus the present invention is not limited to the specific embodiments of the present disclosure.
Referring to fig. 1-4, the present invention provides a technical solution: a fabricated scaffold for construction engineering comprises a steel pipe 1 and a connecting structure 2.
The specific arrangement and function of the connecting structure 2 and the fixing structure 3 will be described in detail below.
In this embodiment: the surface of steel pipe 1 is provided with connection structure 2, connection structure 2 includes first supporting leg 201, the one end fixed connection of first supporting leg 201 and steel pipe 1, the fixed surface of first supporting leg 201 is connected with first smooth frame 204, the inner wall sliding connection of first smooth frame 204 has picture peg 203, the surface rotation of picture peg 203 is connected with cardboard 209, the other end fixed connection of steel pipe 1 has second supporting leg 202, the skin weld of second supporting leg 202 has fixed plate 205, remove picture peg 203, make picture peg 203 move towards the direction of fixed plate 205 along first smooth frame 204, and then drive cardboard 209 and remove, make cardboard 209 and fixed plate 205 contact, until cardboard 209 passes fixed plate 205, just can link together first supporting leg 201 and second supporting leg 202 through cardboard 209 and fixed plate 205.
Specifically, the inner wall of the inserting plate 203 is fixedly connected with a spring 211, the surface of the spring 211 far away from the inserting plate 203 is fixedly connected with a sliding plate 210, the sliding plate 210 is movably connected with the inner wall of the clamping plate 209, the sliding plate 210 is pushed to move along the inner wall of the clamping plate 209 through the elasticity of the spring 211, so that the clamping plate 209 rotates, and the first supporting leg 201 and the second supporting leg 202 can be connected together through the clamping plate 209 and the fixing plate 205.
Specifically, a fixing frame 207 is welded on the surface of the second support leg 202, and a pushing frame 206 is connected to the surface of the fixing frame 207 in a sliding manner.
In this embodiment: when the two scaffolds need to be separated, the pushing frame 206 can be moved, the pushing frame 206 is moved along the surface of the fixing frame 207 towards the direction of the fixing plate 205, the pushing frame 206 is further contacted with the surface of the clamping plate 209, the clamping plate 209 is rotated towards the direction of the inserting plate 203, and then the inserting plate 203 is moved towards the opposite direction, so that the fixing of the first supporting leg 201 and the second supporting leg 202 can be released.
Specifically, the skin weld of picture peg 203 has baffle 208, and the inner wall fixedly connected with telescopic link 212 of picture peg 203, telescopic link 212 and slide 210's fixed surface are connected, can restrict cardboard 209 pivoted angle through baffle 208, improve fixed effect, prevent through telescopic link 212 that spring 211 is crooked to the influence is used.
In this embodiment: the surfaces of the first supporting leg 201 and the second supporting leg 202 are both provided with a fixing structure 3, the fixing structure 3 comprises a second sliding frame 302, the surfaces of the second sliding frame 302 and the second supporting leg 202 are fixedly connected, the inner wall of the second sliding frame 302 is connected with a sliding block 306 in a sliding mode, a fixing block 307 is welded on the surface of the sliding block 306, a long plate 301 is arranged between the fixing block 307 and the steel pipe 1, the long plate 301 is placed between the fixing block 307 and the steel pipe 1, then the sliding block 306 is pushed, the sliding block 306 moves downwards along the second sliding frame 302, and therefore the fixing block 307 is driven to approach the long plate 301 until the fixing block 307 contacts with the surface of the long plate 301, and the long plate 301 can be fixed.
Specifically, the support frame 303 is welded on the surface of the second support leg 202, the screw 304 is connected to the inner wall of the support frame 303 in a threaded manner, and in the using process, the long plate 301 may be loosened by the fixing block 307, so that the long plate 301 cannot be fixed, and therefore danger occurs, after the long plate 301 is installed, the screw 304 is rotated, the screw 304 is moved to the position right above the sliding block 306, and the sliding block 306 can be fixed through the screw 304, so that the fixing block 307 is prevented from being loosened.
Specifically, a handle 305 is fixedly connected to the surface of the screw 304, and the support frames 303 are welded to the surfaces of the first support leg 201 and the second support leg 202.
In this embodiment: the screw 304 is moved to a position just above the slider 306 by rotating the screw 304 with the handle 305.
The working principle is as follows: the inserting plate 203 is moved to enable the inserting plate 203 to move along the first sliding frame 204 towards the direction of the fixing plate 205, and then the clamping plate 209 is driven to move, so that the clamping plate 209 is contacted with the fixing plate 205 until the clamping plate 209 passes through the fixing plate 205, at this time, the sliding plate 210 is pushed to move along the inner wall of the clamping plate 209 through the elasticity of the spring 211, so that the clamping plate 209 rotates, the first supporting leg 201 and the second supporting leg 202 can be connected together through the clamping plate 209 and the fixing plate 205, the rotating angle of the clamping plate 209 can be limited through the baffle 208, the fixing effect is improved, the spring 211 is prevented from being bent through the telescopic rod 212, the use is influenced, when two scaffolds need to be separated, the pushing frame 206 can be moved to enable the pushing frame 206 to move along the direction of the fixing plate 205 along the surface of the fixing frame 207, so that the pushing frame 206 is contacted with the surface of the clamping plate 209, and then the clamping plate 209 rotates towards the direction of the inserting plate 203, then the inserting plate 203 is moved towards the opposite direction, so that the fixing of the first supporting leg 201 and the second supporting leg 202 can be released, when the scaffold is used, a long plate 301 needs to be installed on the surface of the scaffold to enable a worker to stand, when the long plate 301 is installed on the scaffold, the fixing is usually performed by using screws, and when the fixing is performed by using screws, tools are needed, so that the installation becomes troublesome, at this time, the long plate 301 can be placed between the fixing block 307 and the steel pipe 1, then the sliding block 306 is pushed, so that the sliding block 306 moves downwards along the second sliding frame 302, so that the fixing block 307 is driven to approach towards the direction of the long plate 301 until the fixing block 307 contacts with the surface of the long plate 301, the long plate 301 can be fixed, during the use, the fixing block 307 can be released from the long plate 301, so that the long plate 301 cannot be fixed, and therefore, danger occurs, therefore, after the long plate 301 is installed, the screw 304 is rotated by the handle 305, and the screw 304 moves to a position right above the slider 306, so that the slider 306 can be fixed by the screw 304, and the fixed block 307 is prevented from loosening.
The above description is only a preferred embodiment of the present invention, and not intended to limit the present invention in other forms, and any person skilled in the art may apply the above modifications or changes to the equivalent embodiments with equivalent changes, without departing from the technical spirit of the present invention, and any simple modification, equivalent change and change made to the above embodiments according to the technical spirit of the present invention still belong to the protection scope of the technical spirit of the present invention.

Claims (7)

1. The utility model provides a building engineering assembled scaffold, includes steel pipe (1) and connection structure (2), its characterized in that: the surface of steel pipe (1) is provided with connection structure (2), connection structure (2) are including first supporting leg (201), first supporting leg (201) and the one end fixed connection of steel pipe (1), the first smooth frame (204) of fixed surface of first supporting leg (201) is connected with, the inner wall sliding connection of first smooth frame (204) has picture peg (203), the surface rotation of picture peg (203) is connected with cardboard (209), the other end fixedly connected with second supporting leg (202) of steel pipe (1), the skin weld of second supporting leg (202) has fixed plate (205).
2. A construction work fabricated scaffold according to claim 1 wherein: the inner wall fixedly connected with spring (211) of picture peg (203), the fixed surface that picture peg (203) were kept away from in spring (211) is connected with slide (210), slide (210) and the inner wall swing joint of cardboard (209).
3. A construction work fabricated scaffold according to claim 1 wherein: a fixing frame (207) is welded on the surface of the second supporting leg (202), and a pushing frame (206) is connected to the surface of the fixing frame (207) in a sliding mode.
4. A construction work fabricated scaffold according to claim 2 wherein: the surface welding of picture peg (203) has baffle (208), the inner wall fixedly connected with telescopic link (212) of picture peg (203), telescopic link (212) are connected with the fixed surface of slide (210).
5. A construction work fabricated scaffold according to claim 1 wherein: the surface of first supporting leg (201) and second supporting leg (202) all is provided with fixed knot and constructs (3), fixed knot constructs (3) including the smooth frame of second (302), the smooth frame of second (302) is connected with the fixed surface of second supporting leg (202), the inner wall sliding connection of the smooth frame of second (302) has slider (306), the skin weld of slider (306) has fixed block (307), be provided with long board (301) between fixed block (307) and steel pipe (1).
6. A construction work fabricated scaffold according to claim 5 wherein: the surface welding of second supporting leg (202) has support frame (303), the inner wall threaded connection of support frame (303) has screw rod (304).
7. A construction work fabricated scaffold according to claim 6 wherein: the surface of the screw rod (304) is fixedly connected with a handle (305), and support frames (303) are welded on the surfaces of the first support leg (201) and the second support leg (202).
CN202122478653.9U 2021-10-14 2021-10-14 Building engineering assembled scaffold Active CN215594815U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122478653.9U CN215594815U (en) 2021-10-14 2021-10-14 Building engineering assembled scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122478653.9U CN215594815U (en) 2021-10-14 2021-10-14 Building engineering assembled scaffold

Publications (1)

Publication Number Publication Date
CN215594815U true CN215594815U (en) 2022-01-21

Family

ID=79870982

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122478653.9U Active CN215594815U (en) 2021-10-14 2021-10-14 Building engineering assembled scaffold

Country Status (1)

Country Link
CN (1) CN215594815U (en)

Similar Documents

Publication Publication Date Title
CN215594815U (en) Building engineering assembled scaffold
CN204510814U (en) Beam for building jacking
CN216881461U (en) Steel bar bending device for building construction
CN210211340U (en) Pipe bending mechanism and pipe bending machine
CN214996111U (en) Even wall steel reinforcement cage straight thread sleeve is with turning round tight device
CN215631803U (en) Novel masonry structure mortar joint closing device
CN218029191U (en) Light steel structure reinforcing apparatus for house ceiling
CN220925876U (en) Control cable pay-off rack
CN216144743U (en) Concrete pumping pipeline blocks up position detection device
CN210713790U (en) Exempt from to tear open cement template subassembly convenient to installation
CN210319138U (en) On-spot mapping device of building engineering cost
CN217975453U (en) Steel bar positioning device for civil engineering
CN218161580U (en) Communication engineering cable testing bridge convenient to installation
CN217028035U (en) Splicing type building template for constructional engineering
CN211103561U (en) Clamp for hardware fitting
CN214169853U (en) Construction scaffold
CN217052948U (en) Novel highway engineering template supports device
CN211803533U (en) Bending device for construction steel bars
CN216525597U (en) Building engineering concrete quality monitoring devices
CN217714335U (en) Clamping device for preventing engineering equipment from rotating
CN214538964U (en) Anchor clamps for construction
CN210614700U (en) Simple steel pipe straightening device for construction site
CN215803456U (en) Novel steel structure engineering support
CN214143703U (en) Static pressure press-fitting machine for building engineering
CN213533298U (en) Clamp for diamond cutting

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant