CN215562757U - Steel structure foundation for building factory building - Google Patents

Steel structure foundation for building factory building Download PDF

Info

Publication number
CN215562757U
CN215562757U CN202122107408.7U CN202122107408U CN215562757U CN 215562757 U CN215562757 U CN 215562757U CN 202122107408 U CN202122107408 U CN 202122107408U CN 215562757 U CN215562757 U CN 215562757U
Authority
CN
China
Prior art keywords
building
steel structure
factory building
structure foundation
disc
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202122107408.7U
Other languages
Chinese (zh)
Inventor
倪耀君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wenzhou Tianshun Construction And Installation Engineering Co ltd
Original Assignee
Wenzhou Tianshun Construction And Installation Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wenzhou Tianshun Construction And Installation Engineering Co ltd filed Critical Wenzhou Tianshun Construction And Installation Engineering Co ltd
Priority to CN202122107408.7U priority Critical patent/CN215562757U/en
Application granted granted Critical
Publication of CN215562757U publication Critical patent/CN215562757U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses a steel structure foundation for building a factory building, and particularly relates to the field of steel structures of the factory building. When the top disc is normally used, the fixing table is pre-buried into the ground, then the upper surface of the fixing table is leaked, the top disc is supported above the fixing table through the plurality of supporting rods, the limiting blocks at the bottom ends of the supporting rods are inserted into the limiting grooves, then the supporting rods are sealed through concrete pouring, and then the other ends of the supporting rods are inserted into the slots in the lower surface of the top disc.

Description

Steel structure foundation for building factory building
Technical Field
The utility model relates to the technical field of steel structures of plants, in particular to a steel structure foundation for building plants.
Background
The steel structure factory building mainly means that main bearing components are made of steel materials and comprise steel columns, steel beams, steel structure foundations, steel roof trusses (the span of the factory building is larger, and the steel roof trusses are basically steel structure roof trusses), steel roof covers and walls paying attention to the steel structures can be protected by brick walls.
However, in practical use, the existing steel structure foundation of the factory building is simply poured with concrete in a bolt embedding mode, and the safety and the stability are low.
SUMMERY OF THE UTILITY MODEL
In order to overcome the above-mentioned drawbacks of the prior art, embodiments of the present invention provide a steel structure foundation for building a factory building, so as to solve the above-mentioned problems in the background art.
In order to achieve the purpose, the utility model provides the following technical scheme: the utility model provides a steel construction basis for building factory building, includes fixed station and top dish, the fixed station with fix and insert and be equipped with the bolt between the top dish, evenly be equipped with the bracing piece between fixed station and the top dish is in opposite directions, the surface of fixed station is close to bottom department fixed mounting and has the fixed disk, a plurality of spacing grooves have been seted up to the upper surface of fixed station, the bottom fixed mounting of bracing piece has the stopper that is located spacing inslot portion, the lower surface of top dish seted up a plurality of with bracing piece top fixed connection's slot.
Preferably, the outer surface of the fixed table is fixedly provided with at least two bosses, and the upper surfaces of the bosses are provided with pressurizing grooves.
Preferably, the upper surface of the fixed disc is provided with a channel, and the inner wall of the channel is fixedly provided with a filter screen.
Preferably, the centers of the fixed table and the top disc are provided with thread grooves screwed with the bolts, and the bolts penetrate through the top disc and extend to the outer part of the lower surface of the fixed table.
Preferably, a stop block fixedly connected with the top end of the bolt is arranged at the center of the top surface of the top plate, and the diameter of the stop block is larger than that of the thread groove.
Preferably, the lower surface of the top disc is provided with a plurality of fixing blocks sleeved on the outer surface of the supporting rod, and the diameter of each fixing block is larger than that of each slot.
Preferably, the limiting groove is convex, and the diameter of the limiting block is larger than the diameter of the opening of the limiting groove.
The utility model has the technical effects and advantages that:
1. compared with the prior art, can make the device be convenient for support through setting up the bracing piece, when the device normally used, at first with the fixed station pre-buried ground that advances, then spill the upper surface of fixed station, support the top of fixed station with a plurality of bracing pieces with the top dish after that, at first inject the stopper of bracing piece bottom into the spacing groove, after that with concrete placement sealing, then inject the other end of bracing piece inside the lower surface slot of top dish.
2. Compared with the prior art, through setting up boss and pressure boost groove and can make the stationary table stability has when pre-buried, prevent to rock, when formally starting to pour the concrete, can increase the equilibrium with pressure boost groove packing when passing the boss.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention.
Fig. 2 is a front sectional view of the present invention.
Fig. 3 is an enlarged schematic view of the structure at a in fig. 2 according to the present invention.
The reference signs are: 1. a fixed table; 2. a top tray; 3. a bolt; 301. a thread groove; 4. a stopper; 5. a support bar; 6. fixing the disc; 7. a limiting groove; 8. a limiting block; 9. a slot; 10. a fixed block; 11. a boss; 12. a pressurizing tank; 13. a channel; 14. and (5) filtering by using a filter screen.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the utility model and are not intended to limit the utility model.
As shown in attached figures 1-3, a steel structure foundation for building a factory building comprises a fixed platform 1 and a top plate 2, a bolt 3 is fixed and inserted between the fixed platform 1 and the top plate 2, supporting rods 5 are evenly arranged between the opposite surfaces of the fixed platform 1 and the top plate 2, a fixed plate 6 is fixedly arranged on the outer surface of the fixed platform 1 close to the bottom end, a plurality of limiting grooves 7 are arranged on the upper surface of the fixed platform 1, limiting blocks 8 positioned in the limiting grooves 7 are fixedly arranged at the bottom ends of the supporting rods 5, a plurality of inserting grooves 9 fixedly connected with the top ends of the supporting rods 5 are arranged on the lower surface of the top plate 2, the device is convenient to support by arranging the supporting rods 5, when the device is normally used, the fixed platform 1 is firstly pre-embedded into the ground, then the upper surface of the fixed platform 1 is leaked, then the top plate 2 is supported above the fixed platform 1 by the supporting rods 5, and is firstly inserted into the limiting blocks 8 at the bottom ends of the supporting rods 5, then, concrete is poured and sealed, and then the other end of the support rod 5 is inserted into the lower surface insertion groove 9 of the top plate 2.
At least two bosses 11 are fixedly arranged on the outer surface of the fixing platform 1, the pressurizing grooves 12 are formed in the upper surface of the bosses 11, and the bosses 11 and the pressurizing grooves 12 can enable the fixing platform 1 to be stable when being embedded and prevent shaking.
Channel 13 has been seted up through the upper surface that sets up fixed disk 6, and the inner wall fixed mounting of channel 13 has filter screen 14, when beginning to carry out pre-buried with fixed station 1, needs the outer surface pouring concrete of fixed station 1, at this moment earlier with the inside earth that fills of channel 13, then pours into the channel 13 that has filled up soil with the concrete from filter screen 14 and seals, seals filter screen 14 simultaneously, continues upwards watering, guarantees the firm of fixed station 1 bottom.
All set up the thread groove 301 that closes mutually with bolt 3 through the center department that sets up fixed station 1 and top dish 2, and bolt 3 runs through top dish 2 and extends to the lower surface of fixed station 1 outside, can be convenient for place bolt 3, simultaneously can fixing bolt 3's bottom, prevent that the device is whole can rock.
The stop block 4 fixedly connected with the top end of the bolt 3 is arranged at the center of the top surface of the top disc 2, and the diameter of the stop block 4 is larger than that of the thread groove 301, so that the bolt 3 can be conveniently and fixedly installed.
The lower surface of the top plate 2 is provided with a plurality of fixing blocks 10 which are sleeved on the outer surface of the supporting rod 5, and the diameter of each fixing block 10 is larger than that of the corresponding slot 9, so that the upper surface of each fixing block 10 can support the top plate 2 to support in an auxiliary mode.
Through setting up spacing groove 7 to be the convex, and stopper 8's diameter is greater than the opening part diameter of spacing groove 7, the fixed mounting bracing piece 5 of can being convenient for.
The working principle of the utility model is as follows: when the device is normally used, firstly, the fixed platform 1 is pre-embedded into the ground, then the upper surface of the fixed platform 1 is leaked, then the top plate 2 is supported above the fixed platform 1 by a plurality of supporting rods 5, firstly, the limiting blocks 8 at the bottom ends of the supporting rods 5 are inserted into the limiting grooves 7, then, the supporting rods are cast and sealed by concrete, then, the other ends of the supporting rods 5 are inserted into the lower surface inserting grooves 9 of the top plate 2, then, the upper surface of the fixed block 10 is tightly attached to the lower surface of the top plate 2 to be used as an auxiliary support, then, the bolts 3 are inserted from the center of the top surface of the top plate 2, the threaded grooves 301 penetrating into the center of the upper surface of the fixed platform 1 extend to the outer part of the lower surface of the fixed platform 1 to be connected with the inner part of the ground, finally, concrete is poured from the fixed plate 6, the channels 13 are filled with soil, then, the concrete is poured downwards from the filter screens 14, and then the concrete is poured continuously to the upper surface of the fixed platform 1, each boss 11 is sealed in concrete, and in addition, the pressurizing grooves 12 can increase the stability of the burying of the fixing table 1.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. The utility model provides a steel construction basis for building factory building, includes fixed station (1) and top dish (2), its characterized in that: the fixing table is characterized in that a bolt (3) is fixedly inserted between the fixing table (1) and the top disc (2), a supporting rod (5) is uniformly arranged between the fixing table (1) and the top disc (2) in opposite directions, a fixing disc (6) is fixedly mounted on the outer surface of the fixing table (1) close to the bottom, a plurality of limiting grooves (7) are formed in the upper surface of the fixing table (1), limiting blocks (8) located in the limiting grooves (7) are fixedly mounted at the bottom of the supporting rod (5), and a plurality of slots (9) fixedly connected with the top end of the supporting rod (5) are formed in the lower surface of the top disc (2).
2. The steel structure foundation for building a factory building according to claim 1, wherein: the outer surface of the fixed table (1) is fixedly provided with at least two bosses (11), and the upper surfaces of the bosses (11) are provided with pressurizing grooves (12).
3. The steel structure foundation for building a factory building according to claim 1, wherein: channel (13) have been seted up to the upper surface of fixed disk (6), the inner wall fixed mounting of channel (13) has filter screen (14).
4. The steel structure foundation for building a factory building according to claim 1, wherein: the center department of fixed station (1) and paring disc (2) all sets up thread groove (301) that closes mutually with bolt (3), and bolt (3) run through paring disc (2) and extend to the lower surface outside of fixed station (1).
5. The steel structure foundation for building a factory building according to claim 1, wherein: the top surface center of the top disc (2) is provided with a stop block (4) fixedly connected with the top end of the bolt (3), and the diameter of the stop block (4) is larger than that of the thread groove (301).
6. The steel structure foundation for building a factory building according to claim 1, wherein: the lower surface of the top disc (2) is provided with a plurality of fixing blocks (10) sleeved on the outer surface of the supporting rod (5), and the diameter of each fixing block (10) is larger than that of each slot (9).
7. The steel structure foundation for building a factory building according to claim 1, wherein: the limiting groove (7) is convex, and the diameter of the limiting block (8) is larger than the diameter of the opening of the limiting groove (7).
CN202122107408.7U 2021-09-02 2021-09-02 Steel structure foundation for building factory building Expired - Fee Related CN215562757U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122107408.7U CN215562757U (en) 2021-09-02 2021-09-02 Steel structure foundation for building factory building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122107408.7U CN215562757U (en) 2021-09-02 2021-09-02 Steel structure foundation for building factory building

Publications (1)

Publication Number Publication Date
CN215562757U true CN215562757U (en) 2022-01-18

Family

ID=79846174

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122107408.7U Expired - Fee Related CN215562757U (en) 2021-09-02 2021-09-02 Steel structure foundation for building factory building

Country Status (1)

Country Link
CN (1) CN215562757U (en)

Similar Documents

Publication Publication Date Title
CN208039267U (en) A kind of support connection structure of subway foundation pit steel purlin
CN210439313U (en) A side slope reinforcerment system for basic building engineering
CN210658419U (en) Deep buried foundation for solar street lamp
CN215562757U (en) Steel structure foundation for building factory building
CN114908739A (en) Ground photovoltaic power plant cast-in-place concrete pile foundation structure and pouring device thereof
CA1217348A (en) Retaining wall for earth and similar materials
CN108612129A (en) Based on the top-down construction method that can have enough to meet the need steel platform
CN212742561U (en) Foundation pit supporting structure convenient to modularization installation
CN206591535U (en) Combined type cofferdam
CN214832844U (en) Small-size antidumping assembled pile structure
CN212175673U (en) Retaining wall for hydraulic engineering
CN214459574U (en) View bridge pier
CN208650088U (en) A kind of street lamp post installation armored concrete prefabricated foundation structure
CN209603153U (en) A kind of vertical barricade slope retaining construction of prefabricated anchor pole rib column formula frid
CN211421036U (en) Hydraulic engineering side slope protection prefabrication device
CN210482503U (en) Wall-mounted toilet bowl mounting and reinforcing structure
CN208717919U (en) A kind of road based on contrary sequence method changes bridge section foundation pit supporting construction
CN205676917U (en) A kind of steel frame basis of tower mast structure
CN216380255U (en) High-stability support column for underground space
CN221297888U (en) Deep foundation pit pile anchor supporting structure
CN114427189B (en) High-stability concrete structure with protective structure and construction method
CN209839509U (en) Equipment support built with retaining wall
CN221345606U (en) Foundation pit supporting device
CN217001165U (en) Electronic information engineering communication tower connecting device
CN218438568U (en) Electric power tower

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20220118

CF01 Termination of patent right due to non-payment of annual fee