CN215452448U - City piping lane construction is with pre-buried pipeline mounting groove - Google Patents

City piping lane construction is with pre-buried pipeline mounting groove Download PDF

Info

Publication number
CN215452448U
CN215452448U CN202121686997.2U CN202121686997U CN215452448U CN 215452448 U CN215452448 U CN 215452448U CN 202121686997 U CN202121686997 U CN 202121686997U CN 215452448 U CN215452448 U CN 215452448U
Authority
CN
China
Prior art keywords
fixed
groove
access cover
cell body
splice
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121686997.2U
Other languages
Chinese (zh)
Inventor
秦龙
秦霑齐
徐兴川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Daqin Electric Co ltd
Original Assignee
Jiangsu Daqin Electric Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Daqin Electric Co ltd filed Critical Jiangsu Daqin Electric Co ltd
Priority to CN202121686997.2U priority Critical patent/CN215452448U/en
Application granted granted Critical
Publication of CN215452448U publication Critical patent/CN215452448U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses an embedded pipeline mounting groove for urban pipe gallery construction, which comprises a groove body, wherein the front side and the rear side of the left end of the groove body are respectively fixed with a sub-eye-splice, the front side and the rear side of the right end of the groove body are respectively fixed with a female eye-splice matched with the sub-eye-splice, two end parts of the upper side of the groove body are respectively provided with a plurality of L-shaped clamping grooves uniformly distributed from left to right, the upper side of the groove body is provided with an access cover, the positions of the lower side of the access cover corresponding to the L-shaped clamping grooves are respectively fixed with L-shaped clamping blocks matched with each other, and the access cover is fixed on the groove body through a fixing component. Compared with the prior art, the method has the advantages that: the mounting groove is formed by splicing a plurality of groove bodies end to end, and the splicing is convenient, so that the length of the mounting groove can be adjusted according to requirements; the mounting groove is installed on the concrete after concrete placement finishes, is difficult for leading to the damaged and deformation of cell body, and through the structure of access cover part, can make things convenient for the maintenance of later stage circuit.

Description

City piping lane construction is with pre-buried pipeline mounting groove
Technical Field
The utility model relates to the technical field of pipeline installation, in particular to an embedded pipeline installation groove for urban pipe gallery construction.
Background
In the existing building structure, few pipelines are arranged in a clear walking mode. In the prior art, in a general cast-in-place structure, when reinforcing steel bars are bound, a wire pipe is fixed on a template and the reinforcing steel bars, and after concrete is poured, the wire pipe is positioned in a structural member, so that later threading is facilitated. In the in-service use, this structure is unfavorable for overhauing, need pull out the inside circuit of wire tube during the maintenance, and is comparatively troublesome, in addition, in concrete placement in-process, the wire tube appears damaged or takes place to warp easily, in case so, the wire tube will no longer possess waterproof ability. Therefore, in order to solve the problems, the embedded pipeline installation groove for urban pipe gallery construction is provided.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the technical problem of overcoming the technical difficulties and provides the embedded pipeline installation groove for urban pipe gallery construction, which can facilitate later-stage line maintenance and can not be damaged or deformed in the concrete pouring process.
In order to solve the technical problems, the technical scheme provided by the utility model is as follows: the utility model provides a city piping lane construction is with pre-buried pipeline mounting groove, includes the cell body, both sides are fixed with sub-eye-splice respectively around the cell body left end, and both sides are fixed with respectively and are detained with sub-eye-splice matched with box around the cell body right-hand member, and a plurality of L shape draw-in groove from left to right evenly distributed is seted up respectively at the both ends of cell body upside, and the cell body upside is equipped with the access cover, the position that the access cover downside corresponds each L shape draw-in groove is fixed with matched with L shape fixture block respectively, and the access cover is fixed on the cell body through fixed subassembly.
As an improvement, a horizontal positioning block is fixed on the horizontal section at the left end of the tank body, a horizontal positioning groove is formed in the position, corresponding to the horizontal positioning block, of the right end of the tank body, vertical positioning blocks are fixed on the two vertical sections at the left end of the tank body respectively, and vertical positioning grooves are formed in the positions, corresponding to the two vertical positioning blocks, of the right end of the tank body respectively.
As an improvement, a plurality of wall grabbing rods are respectively fixed on the front side and the rear side of the groove body.
As an improvement, the fixed subassembly includes nut and hexagon socket head cap screw, the access cover upside is fixed with the nut, both sides are equipped with the otic placode of fixing both sides around the cell body respectively around the nut, and nut screw cup joints on hexagon socket head cap screw, hexagon socket head cap screw passes two otic placodes.
As an improvement, a rubber sealing layer positioned on the access cover is arranged at the joint of the access cover and the groove body, so that the joint is sealed, and the joint is waterproof.
Compared with the prior art, the utility model has the advantages that: the mounting groove is formed by splicing a plurality of groove bodies end to end, and the splicing is convenient, so that the length of the mounting groove can be adjusted according to requirements; the mounting groove is installed on the concrete after concrete placement finishes, is difficult for leading to the damaged and deformation of cell body, and through the structure of access cover part, can make things convenient for the maintenance of later stage circuit.
Drawings
Fig. 1 is a schematic structural view in the main view direction of an embedded pipeline installation groove for urban pipe gallery construction.
Fig. 2 is a schematic structural diagram of an overhead direction of an embedded pipeline installation groove for urban pipe gallery construction.
As shown in the figure: 1. the device comprises a groove body, 2, a sub-inserting buckle, 3, a female inserting buckle, 4, an L-shaped clamping groove, 5, an access cover, 6, an L-shaped clamping block, 7, a transverse positioning block, 8, a transverse positioning groove, 9, a vertical positioning block, 10, a vertical positioning groove, 11, a wall grabbing rod, 12, a nut, 13, an ear plate, 14 and an inner hexagon bolt.
Detailed Description
In the description of the present invention, it is to be understood that the terms "center", "lateral", "upper", "lower", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc., indicate orientations or positional relationships based on those shown in the drawings, and are used only for convenience in describing the present invention and for simplicity in description, and do not indicate or imply that the referenced devices or elements must have a particular orientation, be constructed in a particular orientation, and be operated, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first", "second" and "first" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of the present invention, "a plurality" means two or more unless otherwise specified. Furthermore, the term "comprises" and any variations thereof is intended to cover non-exclusive inclusions.
The present invention will be described in further detail with reference to the accompanying drawings.
The utility model provides a city piping lane construction is with pre-buried pipeline mounting groove, includes cell body 1, both sides are fixed with sub-eye-splice 2 respectively around the 1 left end of cell body, and both sides are fixed with respectively with sub-eye-splice 2 matched with female eye-splice 3 around the 1 right-hand member of cell body. A horizontal positioning block 7 is fixed on the horizontal section of the left end of the tank body 1, a horizontal positioning groove 8 is formed in the position, corresponding to the horizontal positioning block 7, of the right end of the tank body 1, vertical positioning blocks 9 are fixed on the two vertical sections of the left end of the tank body 1 respectively, and vertical positioning grooves 10 are formed in the positions, corresponding to the two vertical positioning blocks 9, of the right end of the tank body 1 respectively. The transverse positioning block 7 and the vertical positioning block 9 can play a role in splicing the two adjacent groove bodies 1 to reinforce.
A plurality of L-shaped clamping grooves 4 which are uniformly distributed from left to right are respectively formed in the two end portions of the upper side of the groove body 1, an access cover 5 is arranged on the upper side of the groove body 1, matched L-shaped clamping blocks 6 are respectively fixed at the positions, corresponding to the L-shaped clamping grooves 4, of the lower side of the access cover 5, and the access cover 5 is fixed on the groove body 1 through a fixing assembly. Specifically, fixed subassembly includes nut 12 and hexagon socket head cap screw 14, and 5 upsides in the access cover are fixed with nut 12, both sides are equipped with the otic placode 13 of fixing both sides around the cell body 1 respectively around nut 12, and 12 screw threads of nut have cup jointed on the hexagon socket head cap screw 14, hexagon socket head cap screw 14 passes two otic placodes 13.
The front side and the rear side of the tank body 1 are respectively fixed with a plurality of wall grabbing rods 11, so that the tank body 1 can be firmly fixed in concrete. And a rubber sealing layer positioned on the access cover 5 is arranged at the joint of the access cover 5 and the tank body 1.
When the installation method is implemented specifically, the installation grooves are spliced according to the required length before installation, specifically, two adjacent groove bodies 1 are spliced end to end, so that the male plug-in buckle 2 is in clamping fit with the female plug-in buckle 3, the transverse positioning block 7 is matched with the transverse positioning groove 8, and the vertical positioning block 9 is matched with the vertical positioning groove 10. During the installation, after concrete pouring is finished and before solidification, the mounting groove that will splice is installed to concrete structure predetermined area, when waiting that the later stage needs the circuit installation, lays the circuit in the mounting groove, then covers access cover 5 for L shape fixture block 6 and the cooperation of 4 joints of L shape draw-in groove, then realize through screwing up hexagon socket head cap screw 14 that access cover 5 is fixed to cell body 1 on, the installation finishes. When the maintenance is needed, after the hexagon socket head cap screw 14 is screwed off, the maintenance cover 5 can be directly taken off, and then the line can be conveniently maintained.
The present invention and its embodiments have been described above, and the description is not intended to be limiting, and the drawings are only one embodiment of the present invention, and the actual structure is not limited thereto. In summary, those skilled in the art should appreciate that they can readily use the disclosed conception and specific embodiments as a basis for designing or modifying other structures for carrying out the same purposes of the present invention without departing from the spirit and scope of the utility model as defined by the appended claims.

Claims (5)

1. The utility model provides a city piping lane construction is with pre-buried pipeline mounting groove which characterized in that: including cell body (1), both sides are fixed with sub-eye-splice (2) respectively around cell body (1) left end, and both sides are fixed with respectively with sub-eye-splice (2) matched with female eye-splice (3) around cell body (1) right-hand member, and L shape draw-in groove (4) that a plurality of from left to right evenly distributed are seted up respectively at the both ends of cell body (1) upside, and cell body (1) upside is equipped with access cover (5), the position that access cover (5) downside corresponds each L shape draw-in groove (4) is fixed with matched with L shape fixture block (6) respectively, and access cover (5) are fixed on cell body (1) through fixed subassembly.
2. The embedded pipeline installation groove for urban pipe gallery construction according to claim 1, characterized in that: a horizontal positioning block (7) is fixed on the horizontal section of the left end of the tank body (1), a horizontal positioning groove (8) is formed in the position, corresponding to the horizontal positioning block (7), of the right end of the tank body (1), vertical positioning blocks (9) are fixed on the two vertical sections of the left end of the tank body (1) respectively, and vertical positioning grooves (10) are formed in the positions, corresponding to the two vertical positioning blocks (9), of the right end of the tank body (1) respectively.
3. The embedded pipeline installation groove for urban pipe gallery construction according to claim 1, characterized in that: the front side and the rear side of the tank body (1) are respectively fixed with a plurality of wall grabbing rods (11).
4. The embedded pipeline installation groove for urban pipe gallery construction according to claim 1, characterized in that: the fixed subassembly includes nut (12) and hexagon socket head cap screw (14), access cover (5) upside is fixed with nut (12), both sides are equipped with otic placode (13) of fixing both sides around cell body (1) respectively around nut (12), and nut (12) screw thread cup joints on hexagon socket head cap screw (14), hexagon socket head cap screw (14) pass both otic placodes (13).
5. The embedded pipeline installation groove for urban pipe gallery construction according to claim 1, characterized in that: and a rubber sealing layer positioned on the access cover (5) is arranged at the joint of the access cover (5) and the tank body (1).
CN202121686997.2U 2021-07-23 2021-07-23 City piping lane construction is with pre-buried pipeline mounting groove Active CN215452448U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121686997.2U CN215452448U (en) 2021-07-23 2021-07-23 City piping lane construction is with pre-buried pipeline mounting groove

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121686997.2U CN215452448U (en) 2021-07-23 2021-07-23 City piping lane construction is with pre-buried pipeline mounting groove

Publications (1)

Publication Number Publication Date
CN215452448U true CN215452448U (en) 2022-01-07

Family

ID=79683990

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121686997.2U Active CN215452448U (en) 2021-07-23 2021-07-23 City piping lane construction is with pre-buried pipeline mounting groove

Country Status (1)

Country Link
CN (1) CN215452448U (en)

Similar Documents

Publication Publication Date Title
RU2550124C2 (en) Wind power plant and segment of wind power plant tower
KR101975763B1 (en) Precast Concrete Culvert and Method for Constructing the Same
CN105113789A (en) Bare concrete bay window steel formwork structural body device
CN215452448U (en) City piping lane construction is with pre-buried pipeline mounting groove
KR20190012801A (en) Formwork for tunnel lining and forming method for precast concrete bracket for supporting airpit slab
CN205046844U (en) Clear water concrete window steel form structure device that wafts
CN108571012B (en) Piping lane construction joint integrated installation mold construction technology
KR20140058076A (en) Construction method for connecting new and old concrete
CN210067479U (en) Building piping erection equipment
CN112609963B (en) Installation anchoring device of composite heat-insulation template and use method thereof
CN209195011U (en) A kind of draining waterstop joint fixed device under the construction system based on aluminum alloy mould plate
JP6585390B2 (en) Basic block
CN208586757U (en) Prefabricated components connector, prefabricated components and prefabricated components connecting node
CN211114443U (en) Reinforcing bar pre-embedding auxiliary device
CN113529975A (en) Wall-pulling reinforcement assembly and construction method thereof
CN210976098U (en) Underground pipe gallery pre-buried support
CN209585295U (en) A kind of tower crane attached wall built-in fitting
CN208571545U (en) A kind of armored concrete cable channel cover plate
CN215097127U (en) Subway contact net built-in fitting and subway contact net stand
CN209323972U (en) A kind of fixed device of deformation joint root formwork and a kind of deformation joint root formwork system
CN206800801U (en) A kind of double sleeve steel concrete supporting devices
CN206607753U (en) After pour beam steel anchor
CN220014183U (en) Precast concrete member
CN217680585U (en) Encapsulating construction supporting structure
JPH09296611A (en) Support-fixing device for safety fence to be installed during construction of concrete structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant