CN215443165U - Building construction is with pouring device - Google Patents

Building construction is with pouring device Download PDF

Info

Publication number
CN215443165U
CN215443165U CN202121280998.7U CN202121280998U CN215443165U CN 215443165 U CN215443165 U CN 215443165U CN 202121280998 U CN202121280998 U CN 202121280998U CN 215443165 U CN215443165 U CN 215443165U
Authority
CN
China
Prior art keywords
chute
pouring device
fixed
conveying
baffle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202121280998.7U
Other languages
Chinese (zh)
Inventor
王长刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202121280998.7U priority Critical patent/CN215443165U/en
Application granted granted Critical
Publication of CN215443165U publication Critical patent/CN215443165U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model belongs to the technical field of construction machinery, and particularly relates to a pouring device for building construction. According to the concrete feeding device, the water inlet is formed in the surface of the first material pipe, so that water can be conveniently injected from the first material pipe, the chute is formed in the charging bucket, the baffle is installed in the chute, the baffle is pulled to close the wall by using the first handle when the conveying chute is cleaned, the baffle shields the conveying chute, water is injected into the conveying chute from the water inlet to clean and discharge concrete in the discharging chute, the concrete is prevented from being solidified in the conveying chute and the conveying pipe, the use of equipment is prevented from being influenced, and the use cost of the equipment is reduced.

Description

Building construction is with pouring device
Technical Field
The utility model relates to the technical field of construction machinery, in particular to a pouring device for building construction.
Background
The building pouring refers to the construction process of pouring the stirred concrete material into a bin, leveling the bin and tamping the concrete material to be compact. In the construction process of the building, concrete slurry is required to be injected into the building through a pouring device, so that the structural rigidity, the overall stability and the service life of the building are improved to a certain extent
The prior concrete pouring process mostly has the following problems:
1. must carry out long-time vibration to the concrete at the building pouring in-process, because the inside of concrete can form a large amount of gas pockets and the concrete is inhomogeneous, this kind of bubble and inhomogeneous can greatly reduced the cohesiveness of concrete, can reduce holistic life yet, all adopt artifical mode of vibrating to guarantee the concrete at the pouring in-process after pouring at the conventional pouring in-process at present, but in-service use is because manual operation's instability and uncertainty, workman's work load is great, the effect is relatively poor etc..
2. Although current building slip casting machine can carry out effectual slip casting operation to the building, at the slip casting in-process, after stopping the slip casting, slip casting shower nozzle and slip casting high-pressure pipe can have the slip casting material, and the dry back of slip casting material is great with the possibility that slip casting high-pressure pipe and slip casting shower nozzle blockked up, and the slip casting efficiency that causes this slip casting machine is lower, and the equipment use is maintained the degree of difficulty and is big.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Aiming at the defects of the prior art, the utility model provides a pouring device for building construction, which solves the problems that the net in concrete contains a plurality of bubbles and the concrete is not uniform.
The second technical proposal.
The utility model specifically adopts the following technical scheme for realizing the purpose:
the utility model provides a construction is with pouring device, includes frame construction's underframe, the upper surface of underframe is fixed with vibrations platform and storage bucket through vibrations bolt group, the bottom and the vibrations platform fixed connection of storage bucket, the one end of storage bucket is provided with the installation panel, the fixed surface of installation panel has the vibrations motor that is used for the storage bucket vibrations, the side of storage bucket is connected with a material pipe, the surface of a material pipe is provided with the water inlet that is used for wasing the intaking, the bottom of storage bucket is provided with the defeated silo of conveying thick liquids, the inside wall of storage bucket is provided with the spout, the baffle of the useful shutoff defeated silo of inside sliding connection of spout, baffle fixed surface has a handle that is used for spuring the baffle.
Furthermore, one end of the first material pipe is fixedly connected with a second extension pipe through threads, and the second extension pipe is split and is formed by fixing and combining through bolts.
Furthermore, a material conveying motor is fixed on one side of the charging bucket close to the vibration motor, and a control cabinet is fixed on the upper surface of the vibration table.
Further, the surface of underframe is rotated and is connected with the main wheel, the underframe lower surface is provided with the universal wheel that is convenient for turn to near the one end of switch board.
Furthermore, a second handle for pushing the equipment is fixed on the upper surface of the bottom frame.
Further, the surface of the second extension pipe is provided with a pressure gauge for monitoring the slurry conveying pressure.
(III) advantageous effects
Compared with the prior art, the utility model provides a pouring device for building construction, which has the following beneficial effects:
1. according to the utility model, the panel and the charging basket are connected and fixedly installed on the upper surface of the bottom frame by using the vibration bolt group, the vibration motor is installed on the vibration table on the surface of the charging basket, slurry is injected into the charging basket, the vibration motor is started, and the vibration bolt group is used for connecting the vibration table, the charging basket and the bottom frame, so that the vibration motor can increase the vibration of the charging basket, bubbles in the slurry are reduced by the vibration of the charging basket, and the viscosity of the slurry is increased.
2. According to the concrete feeding device, the water inlet is formed in the surface of the first material pipe, so that water can be conveniently injected from the first material pipe, the chute is formed in the charging bucket, the baffle is installed in the chute, the baffle is pulled to close the wall by using the first handle when the conveying chute is cleaned, the baffle shields the conveying chute, water is injected into the conveying chute from the water inlet to clean and discharge concrete in the discharging chute, the concrete is prevented from being solidified in the conveying chute and the conveying pipe, the use of equipment is prevented from being influenced, and the use cost of the equipment is reduced.
Drawings
FIG. 1 is a schematic perspective view of the present invention;
FIG. 2 is a side view of the present invention;
FIG. 3 is a schematic perspective view of the present invention;
FIG. 4 is an enlarged view of the structure of FIG. 3 according to the present invention.
In the figure: 1. a bottom frame; 2. a vibration bolt group; 3. a vibration table; 4. a charging bucket; 5. installing a panel; 6. a vibration motor; 7. a first material pipe; 8. a water inlet; 9. a material conveying groove; 10. a chute; 11. a baffle plate; 12. a first handle; 13. a second extension tube; 14. a material conveying motor; 15. a control cabinet; 16. a main wheel; 17. a universal wheel; 18. a second handle; 19. and a pressure gauge.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Examples
As shown in fig. 1, 3 and 4, the pouring device for building construction of the present invention comprises a bottom frame 1 of a frame structure, wherein a vibration table 3 and a material barrel 4 are fixed on the upper surface of the bottom frame 1 through a vibration bolt set 2, the bottom of the material barrel 4 is fixedly connected with the vibration table 3, one end of the material barrel 4 is provided with a mounting panel 5, the surface of the mounting panel 5 is fixed with a vibration motor 6 for vibrating the material barrel 4, the side surface of the material barrel 4 is connected with a first material pipe 7, the surface of the first material pipe 7 is provided with a water inlet 8 for cleaning water, the bottom of the material barrel 4 is provided with a delivery chute 9 for delivering slurry, the inner side wall of the material barrel 4 is provided with a chute 10, the inside of the chute 10 is slidably connected with a baffle 11 for plugging the delivery chute 9, the surface of the baffle 11 is fixed with a first handle 12 for pulling the baffle 11, the vibration table 3 and the material barrel 4 are connected and fixed by using the vibration bolt set 2 on the upper surface of the bottom frame 1, a vibration motor 6 is arranged on an installation panel 5 on the surface of the charging basket 4, slurry is injected into the charging basket 4, the vibration motor 6 is started, the vibration table 3, the charging basket 4 and the bottom frame 1 are connected by a vibration bolt group 2, so that the vibration motor 6 can increase the vibration of the charging basket 4, air bubbles in the slurry are reduced by the vibration of the charging basket 4, the viscosity of the slurry is increased, the water inlet 8 is arranged on the surface of the first material pipe 7, so that water can be conveniently injected from the first material pipe 7, at 4 inside spout 10 that set up of storage bucket to installation baffle 11 in spout 10, use a handle 12 to stimulate baffle 11 and close the jade when wasing defeated silo 9, make baffle 11 shelter from defeated silo 9, from water inlet 8 to defeated silo 9 in water injection with the concrete washing and the discharge in the blown down tank, prevent that the concrete from solidifying in defeated silo 9 and defeated silo, influence the use of equipment, reduction equipment use cost. .
As shown in fig. 3, in some embodiments, one end of the first material pipe 7 is fixedly connected with a second extension pipe 13 through threads, and the second extension pipe 13 is split and is fixedly combined through bolts; the second extension pipe 13 increases the conveying pressure of the slurry, so that the equipment can have farther conveying capacity, and meanwhile, the split second extension pipe 13 is convenient to detach and overhaul.
As shown in fig. 1, in some embodiments, a material conveying motor 14 is fixed on one side of the material barrel 4 close to the vibration motor 6, and a control cabinet 15 is fixed on the upper surface of the vibration table 3; through the fixed connection of the material conveying motor 14 and the material barrel 4, the material conveying motor 14 is convenient to use, and the influence on the conveying of slurry while the equipment is vibrated is prevented.
As shown in fig. 1, in some embodiments, the surface of the base frame 1 is rotatably connected with a main wheel 16, and one end of the lower surface of the base frame 1, which is close to the control cabinet 15, is provided with a universal wheel 17 for facilitating steering; the main wheels 16 and the castor wheels 17 facilitate the movement of the apparatus, and the castor wheels 17 facilitate the steering of the apparatus.
As shown in fig. 1, in some embodiments, a second handle 18 for pushing the device is fixed on the upper surface of the bottom frame 1; movement of the device is facilitated by the second handle 18.
As shown in fig. 3, in some embodiments, the surface of extension tube number two 13 is provided with a pressure gauge 19 for monitoring the slurry delivery pressure; the pressure gauge 19 can detect the pressure in the material conveying pipe in real time, effectively detect the running condition of the equipment and prevent the equipment from being damaged due to overlarge pressure in the material conveying pipe.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that changes may be made in the embodiments and/or equivalents thereof without departing from the spirit and scope of the utility model. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (6)

1. The utility model provides a construction is with pouring device, includes frame construction's underframe (1), its characterized in that: the upper surface of the bottom frame (1) is fixed with a vibration table (3) and a charging basket (4) through a vibration bolt group (2), the bottom of the charging basket (4) is fixedly connected with the vibration table (3), one end of the charging basket (4) is provided with an installation panel (5), a vibration motor (6) used for vibrating the charging basket (4) is fixed on the surface of the mounting panel (5), a first material pipe (7) is connected to the side surface of the charging bucket (4), a water inlet (8) for cleaning inlet water is arranged on the surface of the first material pipe (7), a material conveying groove (9) for conveying slurry is arranged at the bottom of the charging basket (4), a chute (10) is arranged on the inner side wall of the charging bucket (4), a baffle (11) for plugging the material conveying chute (9) is connected in the chute (10) in a sliding manner, a first handle (12) used for pulling the baffle (11) is fixed on the surface of the baffle (11).
2. The pouring device for building construction according to claim 1, wherein: one end of the first material pipe (7) is fixedly connected with a second extension pipe (13) through threads, and the second extension pipe (13) is split and is formed by fixedly combining bolts.
3. The pouring device for building construction according to claim 1, wherein: a material conveying motor (14) is fixed on one side of the charging bucket (4) close to the vibration motor (6), and a control cabinet (15) is fixed on the upper surface of the vibration table (3).
4. The pouring device for building construction according to claim 1, wherein: the surface of underframe (1) is rotated and is connected with main wheel (16), the one end that underframe (1) lower surface is close to switch board (15) is provided with universal wheel (17) of being convenient for turn to.
5. The pouring device for building construction according to claim 1, wherein: a second handle (18) for pushing the equipment is fixed on the upper surface of the bottom frame (1).
6. The pouring device for building construction according to claim 2, wherein: and a pressure gauge (19) for monitoring the slurry conveying pressure is arranged on the surface of the second extension pipe (13).
CN202121280998.7U 2021-06-08 2021-06-08 Building construction is with pouring device Expired - Fee Related CN215443165U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121280998.7U CN215443165U (en) 2021-06-08 2021-06-08 Building construction is with pouring device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121280998.7U CN215443165U (en) 2021-06-08 2021-06-08 Building construction is with pouring device

Publications (1)

Publication Number Publication Date
CN215443165U true CN215443165U (en) 2022-01-07

Family

ID=79710535

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121280998.7U Expired - Fee Related CN215443165U (en) 2021-06-08 2021-06-08 Building construction is with pouring device

Country Status (1)

Country Link
CN (1) CN215443165U (en)

Similar Documents

Publication Publication Date Title
CN201148384Y (en) Powdery lime automatic metering and preparing apparatus
CN215443165U (en) Building construction is with pouring device
CN203403420U (en) Concrete vertical conveying pouring system
CN113003685A (en) Rotary flocculation reagent adding device of sedimentation tank for large-scale sewage treatment
CN110841523A (en) Multifunctional loam matrix spray-seeding equipment for mine restoration
CN110624679A (en) Portable construction waste treatment device
CN216640306U (en) Crack reinforcing equipment for roads and bridges
CN216181649U (en) Concrete pole residual slurry recycling device
CN215823401U (en) Steel member travelling car is sprayed to high efficiency of being convenient for
CN208627930U (en) A kind of cleaning device of concrete mixer truck
CN213790617U (en) Environment-friendly dust removal device for gold mining
CN209430215U (en) A kind of tunnel construction cement transportation equipment
CN209362693U (en) A kind of assembled architecture waste material collection device
CN111993574A (en) Automatic abluent mortar mixer
CN205926401U (en) Machine part washs filling device
CN220424913U (en) Spray dust device
CN113430976A (en) Leveling device for repairing roads and facilitating waste cleaning
CN210856063U (en) Unloader is used in fermented glutinous rice production
CN208347793U (en) It is a kind of to facilitate the pulp shooting machine for collecting refractory gunning equipment
CN110682846A (en) Continuous delivery wagon
CN218712071U (en) Highway grouting device
CN218111214U (en) Stirring device for building block forming machine
CN205112091U (en) Do benefit to mortar exhaust mortar jar
CN212919906U (en) Be used for building engineering concrete mixing device
CN213890550U (en) Automatic abluent mortar mixer

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20220107