CN215443109U - Bearing column pouring mold for building construction - Google Patents

Bearing column pouring mold for building construction Download PDF

Info

Publication number
CN215443109U
CN215443109U CN202121261544.5U CN202121261544U CN215443109U CN 215443109 U CN215443109 U CN 215443109U CN 202121261544 U CN202121261544 U CN 202121261544U CN 215443109 U CN215443109 U CN 215443109U
Authority
CN
China
Prior art keywords
frame
pouring mold
wall
bearing column
building construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202121261544.5U
Other languages
Chinese (zh)
Inventor
郑玉晖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202121261544.5U priority Critical patent/CN215443109U/en
Application granted granted Critical
Publication of CN215443109U publication Critical patent/CN215443109U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model belongs to the technical field of building construction accessories, in particular to a bearing column pouring mold for building construction, which comprises two installation frames, wherein the two installation frames are symmetrically distributed and used for wrapping a bearing column reinforcing steel frame, the front side wall and the rear side wall of each installation frame are respectively and fixedly provided with a connecting plate which is mutually contacted and used for connecting the two installation frames, the outer wall of each installation frame is fixedly provided with an installation seat used for connecting the ground, in the utility model, the two installation frames which are connected together from left to right form a pouring mold section, a plurality of pouring mold assembly sections form the bearing column pouring mold, when the upper pouring mold section and the lower pouring mold section are connected together, an outer clamping frame on the outer wall of the upper installation frame is clamped on the lower installation frame, then the upper installation frame and the lower installation frame can be connected together through a fixing bolt on the outer wall of the installation seat, the connection and fixation work between the pouring mold sections is completed, and the dismounting efficiency of the pouring mold is high, the workload of workers is reduced, and the working efficiency is improved.

Description

Bearing column pouring mold for building construction
Technical Field
The utility model belongs to the technical field of building construction accessories, and particularly relates to a bearing column pouring mold for building construction.
Background
The bearing column is the most main stressed body in a building, the function of the bearing column in the building is particularly important, the pressure which the bearing column can bear determines the volume and the height of the building, the construction of the bearing column is particularly important in the construction process of the building, the existing bearing column is a reinforced concrete structure, and the pouring work of the bearing column is completed through a pouring mold.
SUMMERY OF THE UTILITY MODEL
Present casting die utensil generally comprises the polylith plank, the polylith plank connects into a rectangle structure, live bearing post steel reinforcement frame parcel, the work is accomplished and pour to the mould is inside to the concrete pouring, work all need splice the plank again at every turn, the combined work of carrying out the mould, workman's work load has been increased, the work efficiency is reduced, and can't effectually fix a position and width control work between mould and the steel reinforcement frame, can increase the area of the bearing post of watering, the pouring and the result of use of bearing post have been reduced. The utility model provides a bearing column pouring mold for building construction, which has the characteristics of high assembly efficiency, convenience in positioning and width adjustment between a mold and a reinforcing steel bar frame, and improvement on applicability and working efficiency.
The utility model provides the following technical scheme: including two installing framves, two the installing frame is the symmetric distribution and is used for the parcel heel post reinforcing bar frame, two both sides wall all sets firmly mutual contact and is used for connecting two around the installing frame the connecting plate of installing frame, the installing frame outer wall sets firmly the mount pad that is used for connecting ground, the inside adjusting part who is used for centre gripping heel post reinforcing bar frame that sets firmly of installing frame, installing frame outer wall top sets firmly and is used for connecting the correspondence the installing frame with the outer card frame of mount pad.
Wherein, adjusting part includes adjusting screw, splint and kicking block, adjusting screw threaded connection correspond on the installing frame outer wall and be used for connecting splint, the top and the bottom of splint with adjusting screw's top and bottom are in the horizontality.
The clamping plate is rotatably connected to one end, extending into the inner side of the mounting frame, of the adjusting screw rod and used for mounting the ejector block.
The top plate is of an L-shaped structure and is connected to the top end of the clamping plate in a clamping mode.
The installation seat inner side wall and the installation frame outer wall are provided with a gap used for accommodating and corresponding to the outer clamping frame, and the width of the gap between the installation seat inner side wall and the installation frame outer wall is larger than that of the outer clamping frame.
The outer walls of four sides of the mounting seat are fixedly provided with two fixing bolts which are symmetrically distributed and used for connecting and corresponding to the outer clamping frame and the mounting frame, and the four side walls of the outer clamping frame are provided with two through holes used for accommodating and corresponding to the fixing bolts.
The mounting frame comprises a mounting frame body and is characterized in that a clamping block is fixedly connected to the top end of the mounting frame body, and a clamping groove used for containing the clamping block is formed in the bottom end of the mounting frame body.
And the clamping block is in interference fit with the clamping groove.
The utility model has the beneficial effects that:
1. according to the utility model, two installing frames which are connected together from left to right form a pouring mold section, a plurality of pouring mold section forms a bearing column pouring mold, when the upper and lower pouring mold sections are connected together, the outer clamping frame on the outer wall of the upper installing frame is clamped on the installing frame below the upper installing frame, the connecting installing frames can be positioned, the outer clamping frame is positioned between the installing seat at the bottom of the outer wall of the upper installing frame and the installing frame below the upper installing frame, then the upper and lower installing frames can be connected together through the fixing bolt on the outer wall of the installing seat, the connecting and fixing work between the pouring mold sections is completed, the dismounting efficiency of the pouring mold is high, the workload of workers is reduced, and the working efficiency is improved.
2. According to the utility model, the adjusting assembly consisting of the adjusting screw rod, the clamping plate and the ejector block is arranged on the outer wall of the mounting frame, the clamping plate and the ejector block can move back and forth in the mounting frame through the adjusting screw rod to adjust the positions of the clamping plate and the ejector block, the ejector block can be abutted against the outer surface of the steel bar frame through adjusting the positions of the clamping plate and the ejector block, the positioning work between the mold and the steel bar frame is realized, the ejector block is taken out after positioning to perform concrete pouring work, the position adjustment and the fixing work of the clamping plate and the ejector block are convenient to perform, the positioning and width adjustment work between the mold and the steel bar frame can be effectively performed, the pouring effect of the bearing column is improved, different distances can be separated between the two clamping plates to adapt to the pouring work of the bearing columns with different widths, and the applicability is improved.
3. According to the utility model, the clamping plate can move outwards under the driving of the adjusting screw, after the bearing column is completely solidified, the adjusting screw is rotated to drive the clamping plate to move outwards, so that the clamping plate is separated from the bearing column, then the screws for fixing the two connecting plates are taken down, and then the two mounting frames are pulled outwards to separate the pouring mold from the bearing column.
The parts of the device not involved are the same as or can be implemented using prior art.
Drawings
FIG. 1 is a schematic cross-sectional view of the front view of the present invention;
FIG. 2 is a schematic top view of the present invention;
FIG. 3 is an enlarged view of portion A of FIG. 2;
FIG. 4 is a schematic structural diagram of the assembled state of the present invention.
In the figure: 1. installing a frame; 11. a connecting plate; 12. a clamping block; 13. a card slot; 2. a mounting seat; 21. fixing the bolt; 3. an adjustment assembly; 31. adjusting the screw rod; 32. a splint; 33. a top block; 331. a top plate; 4. an outer clamping frame; 41. and a through hole.
Detailed Description
Referring to fig. 1-4, the present invention provides the following technical solutions: including two installing frames 1, two installing frames 1 are the symmetric distribution and are used for the parcel heel post reinforcing bar frame, both sides wall all sets firmly the connecting plate 11 that contacts each other and be used for connecting two installing frames 1 around two installing frames 1, and 1 outer wall of installing frame sets firmly the mount pad 2 that is used for connecting ground, and 1 inside adjusting part 3 that is used for centre gripping heel post reinforcing bar frame that sets firmly of installing frame, and 1 outer wall top of installing frame sets firmly the outer card frame 4 that is used for connecting corresponding installing frame 1 and mount pad 2.
In this embodiment: the two installation frames 1 form a pouring mould section, the installation frames 1 are made of stainless steel materials, the structural strength is high, the installation frames 1 are of a v-21274h-shaped structure, the left installation frame 1 and the right installation frame 1 can be placed on two sides of a bearing column steel bar frame, then, the opposite ends of the two mounting frames 1 are combined with each other, a rectangular structure is formed between the two mounting frames 1, the bearing column reinforcing steel bar frame can be wrapped so as to carry out subsequent bearing column pouring work, the connecting plates 11 are respectively arranged on the front side wall and the rear side wall of the mounting frame 1, the connecting plates 11 are steel plates, the structural strength is high, when the two mounting frames 1 are combined, the connecting plates 11 on the two mounting frames 1 are mutually attached together, then come two connecting plates 11 to fix together through the cooperation between screw and the nut, and then accomplish the fixed work of connection between two installing frames 1, the packaging efficiency is high, has improved the fastness after the combination of pouring mould section and stability when using.
The mounting seat 2 is installed to the outer wall of installing frame 1, and the bottom of mounting seat 2 can be with ground contact, then can fix mounting seat 2 subaerial through the screw, has realized the fixed work of being connected between the pouring mould section of below and the ground, has improved the fastness after the device installation and the stability when using, has improved subsequent effect of pouring.
The top of the outer wall of the mounting frame 1 is provided with the outer clamping frame 4, the outer clamping frame 4 is made of stainless steel materials and has high structural strength, a plurality of pouring module sections form a bearing column pouring mold, when the upper and lower pouring mold sections are connected together, the outer clamping frame 4 on the outer wall of the upper mounting frame 1 can be clamped at the top end of the lower mounting frame 1, the inner wall of the outer clamping frame 4 is in close contact with the outer wall of the lower mounting frame 1, the upper and lower two mounting frames 1 can be connected and positioned through the outer clamping frame 4, the upper and lower two pouring mold sections are connected together, a gap is formed between the inner side wall of the mounting seat 2 and the outer wall of the mounting frame 1, after the upper and lower pouring mold sections are connected together, the outer clamping frame 4 can enter the gap, the width of the gap between the inner side wall of the mounting seat 2 and the outer wall of the mounting frame 1 is larger than that of the outer clamping frame 4, and the fluency when the outer clamping frame 4 enters the gap is improved, two fixing bolts 21 that are the symmetric distribution are all installed to four side outer walls of mount pad 2, offer the through-hole 41 that is used for holding corresponding fixing bolt 21 on the four lateral walls of outer card frame 4, offer the fixed orifices that is used for cooperating fixing bolt 21 on the outer wall of installing frame 1, after outer card frame 4 enters into the clearance inside, inwards twist in proper order and move eight fixing bolt 21, make fixing bolt 21 pass corresponding through-hole 41, enter into the fixed orifices inside that corresponds on the outer wall of installing frame 1 in top, can link together two installing frames 1 from top to bottom through eight fixing bolt 21, the connection fixing work between the mould section of having realized pouring, therefore, the operation is simple, the equipment work of the mould is pour conveniently, the fastness after the mould equipment of pouring and the stability when using have been improved, the work load of the workman is reduced, and the work efficiency is improved.
The fixture block 12 is fixed on the top end of the mounting frame 1, the clamping groove 13 is formed in the bottom end of the mounting frame 1, when the mounting frame 1 is connected with the mounting frame 1 in an upper mode and the mounting frame in a lower mode, the fixture block 12 on the top end of the mounting frame 1 in the lower mode can enter the clamping groove 13 in the bottom end of the mounting frame 1 in the upper mode, the fixture block 12 and the clamping groove 13 are in interference fit, tightness of connection between the fixture block 12 and the clamping groove 13 can be achieved, and stability of combination of the mounting frame 1 in the upper mode and the lower mode can be improved through cooperation between the fixture block 12 and the clamping groove 13.
The adjusting component 3 is installed on the outer wall of the installation frame 1, the adjusting component 3 is composed of an adjusting screw 31, a clamping plate 32 and a top block 33, the clamping plate 32 and the top block 33 are both made of stainless steel materials, the structural strength is high, the top block 33 is connected to the right side wall of the clamping plate 32 through the clamping of a top L-shaped top plate 331, the top plate 331 is also made of stainless steel materials, the structural strength is high, the firmness of the top block 33 installed on the clamping plate 32 and the stability in use are improved, the clamping plate 32 is rotatably connected to one end of the adjusting screw 31 extending into the inner side of the installation frame 1, therefore, the clamping plate 32 and the top block 33 can move back and forth in the installation frame 1 by rotating the adjusting screw 31, the position adjusting work of the clamping plate 32 and the top block 33 is realized, the top block 33 can be enabled to abut against the outer surface of the steel bar frame by adjusting the positions of the clamping plate 32 and the top block 33, and the positioning work between a mold and the steel bar frame is realized, upwards pulling kicking block 33 takes out kicking block 33 after the location, then can carry out the work of pouring into of concrete, and easy operation conveniently carries out the position control and the fixed work of splint 32 and kicking block 33, can effectually fix a position and width control work between mould and the reinforcing bar frame, the pouring effect of bearing post has been improved, the workman is through the rotation adjusting screw 31 of different degrees, can make the interval of separately difference between two splint 32, with the work of pouring of the different width bearing posts of adaptation, the suitability has been improved.
The top and the bottom of splint 32 and adjusting screw 31 are in the horizontality, and two upper and lower pouring die section combinations back, and two upper and lower splint 32 contact each other, have improved the effect of pouring of follow-up heel post.
After the heel post solidifies completely, it makes adjusting screw 31 drive splint 32 and outwards removes to rotate adjusting screw 31, splint 32 outwards removes can separate with the heel post after solidifying, then upwards stimulate the combined casting die section together in proper order, come to separate casting die and heel post, can also directly go down the screw that is used for two fixed connection boards 11, can open two sets of die section splits, it is efficient to dismantle, conveniently pour the split work between die and the solidification back heel post, the work load of workman has been reduced, the work efficiency is improved, after the die section of will pouring takes off, take off fixing bolt 21 and can also separate two installing frames 1, it is efficient to dismantle, conveniently carry out subsequent use.
The working principle and the using process of the utility model are as follows: when the installation frame is used, a sufficient number of installation frames 1 are selected according to the height of a bearing column reinforcing steel bar frame, then the installation frames 1 are combined together from top to bottom, the installation frame 1 at the upper part is fixed on the installation frame 1 at the lower part through a fixing bolt 21, after the combination is completed, two groups of mould sections consisting of a plurality of installation frames 1 are placed at two sides of the bearing column reinforcing steel bar frame, then the two groups of mould sections are fixed together through a bolt and a nut to form a rectangular pouring mould, the pouring mould wraps the reinforcing steel bar frame, then the installation seat 2 is fixed on the ground through the bolt, after the fixation is completed, the adjusting screw 31 is rotated to enable the jacking block 33 to prop against the outer surface of the reinforcing steel bar frame, the positioning work between the mould and the reinforcing steel bar frame is realized, after the positioning, the jacking block 33 is pulled upwards to take out the jacking block 33, then concrete is poured into the pouring mould, after the bearing column is solidified, the adjusting screw 31 is rotated to enable the clamping plate 32 to move outwards, the clamping plate 32 moves outwards to be separated from the solidified bearing column, and then the screw is taken down to separate the two groups of die sections, so that subsequent use is facilitated.

Claims (8)

1. The utility model provides a mould is pour to heel post for construction which characterized in that: including two installing framves, two the installing frame is the symmetric distribution and is used for the parcel heel post reinforcing bar frame, two both sides wall all sets firmly mutual contact and is used for connecting two around the installing frame the connecting plate of installing frame, the installing frame outer wall sets firmly the mount pad that is used for connecting ground, the inside adjusting part who is used for centre gripping heel post reinforcing bar frame that sets firmly of installing frame, installing frame outer wall top sets firmly and is used for connecting the correspondence the installing frame with the outer card frame of mount pad.
2. The bearing column pouring mold for building construction according to claim 1, characterized in that: the adjusting component comprises an adjusting screw rod, a clamping plate and an ejector block, the adjusting screw rod is in threaded connection with the outer wall of the mounting frame and used for being connected with the clamping plate, and the top end and the bottom end of the clamping plate are in a horizontal state.
3. The bearing column pouring mold for building construction according to claim 2, characterized in that: the clamping plate is rotatably connected to one end, extending into the inner side of the mounting frame, of the adjusting screw rod and used for mounting the ejector block.
4. The bearing column pouring mold for building construction according to claim 2, characterized in that: the top of the top block is fixedly provided with a top plate used for being connected with the clamping plate, the top plate is of an L-shaped structure, and the top plate is connected to the top end of the clamping plate in a clamping mode.
5. The bearing column pouring mold for building construction according to claim 1, characterized in that: the mount pad inside wall with have between the installing frame outer wall and be used for holding the correspondence the clearance of outer card frame, the mount pad inside wall with the width in clearance is greater than between the installing frame outer wall the width of outer card frame.
6. The bearing column pouring mold for building construction according to claim 1, characterized in that: the outer walls of four sides of the mounting seat are fixedly provided with two fixing bolts which are symmetrically distributed and used for connecting and corresponding to the outer clamping frame and the mounting frame, and the four side walls of the outer clamping frame are provided with two through holes used for accommodating and corresponding to the fixing bolts.
7. The bearing column pouring mold for building construction according to claim 1, characterized in that: the mounting frame top fixedly connected with fixture block, the mounting frame bottom is seted up and is used for holding the draw-in groove that corresponds the fixture block.
8. The bearing column pouring mold for building construction according to claim 7, characterized in that: the clamping blocks are in interference fit with the clamping grooves.
CN202121261544.5U 2021-06-07 2021-06-07 Bearing column pouring mold for building construction Expired - Fee Related CN215443109U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121261544.5U CN215443109U (en) 2021-06-07 2021-06-07 Bearing column pouring mold for building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121261544.5U CN215443109U (en) 2021-06-07 2021-06-07 Bearing column pouring mold for building construction

Publications (1)

Publication Number Publication Date
CN215443109U true CN215443109U (en) 2022-01-07

Family

ID=79709981

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121261544.5U Expired - Fee Related CN215443109U (en) 2021-06-07 2021-06-07 Bearing column pouring mold for building construction

Country Status (1)

Country Link
CN (1) CN215443109U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115126228A (en) * 2022-06-30 2022-09-30 陕西帕源路桥建设有限公司 Installation and positioning module for diagonal combination die of stand column

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115126228A (en) * 2022-06-30 2022-09-30 陕西帕源路桥建设有限公司 Installation and positioning module for diagonal combination die of stand column
CN115126228B (en) * 2022-06-30 2023-08-15 陕西帕源路桥建设有限公司 Positioning module for mounting diagonal combination die of upright post

Similar Documents

Publication Publication Date Title
CN215443109U (en) Bearing column pouring mold for building construction
CN113719112A (en) Template fastener is used in construction engineering aluminium mould construction
CN217028053U (en) Side wall template for electric power well construction
CN215167228U (en) Shear force wall reinforcing bar positioner
CN202706554U (en) Adjustable bolt fastener for unilateral mould plate
CN110315030B (en) Cast iron resin sand casting riser tamping tool and process thereof
CN210282665U (en) U-shaped bolt type supporting die
CN2344147Y (en) Length adjustable prefabricated shear column die
CN216892504U (en) Pre-buried quick detach formula positioner in tower crane basis
CN220133510U (en) Civil engineering construction pouring template convenient to splice
CN213732381U (en) PC floor pouring die
CN221546360U (en) Reinforcing apparatus of template is pour to crossbeam
CN220978805U (en) Upright post steel mould fixing structure
CN218623316U (en) Cast in situ concrete slot component template reinforcing apparatus
CN220909115U (en) Building construction mould hanging tool capable of being quickly dismantled
CN217871813U (en) Framework column formwork structure with chamfer
CN221778301U (en) Road bridge template structure
CN220364871U (en) Bridge tower anchoring device
CN218437813U (en) Device for preventing shear force wall reinforcing bar aversion
CN211440454U (en) Precast concrete enclosure wall post pouring die
CN211818041U (en) Stupefied reinforcing apparatus of back of body
CN221442097U (en) Assembled aluminum template connection structure
CN215094476U (en) Concrete pouring rack for roads and bridges
CN210439684U (en) Novel whole beam die anchor clamps
CN210032580U (en) Shear wall half-tunnel formwork

Legal Events

Date Code Title Description
GR01 Patent grant