CN215443023U - Installation device for large-span inclined roof floating awning curtain wall - Google Patents

Installation device for large-span inclined roof floating awning curtain wall Download PDF

Info

Publication number
CN215443023U
CN215443023U CN202023304176.6U CN202023304176U CN215443023U CN 215443023 U CN215443023 U CN 215443023U CN 202023304176 U CN202023304176 U CN 202023304176U CN 215443023 U CN215443023 U CN 215443023U
Authority
CN
China
Prior art keywords
crank
fixedly connected
curtain wall
pulley groove
fixed mounting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202023304176.6U
Other languages
Chinese (zh)
Inventor
李常松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liaoning Shuyuan Construction Technology Group Co ltd
Original Assignee
Liaoning Hongming Curtain Wall Decoration Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liaoning Hongming Curtain Wall Decoration Engineering Co ltd filed Critical Liaoning Hongming Curtain Wall Decoration Engineering Co ltd
Priority to CN202023304176.6U priority Critical patent/CN215443023U/en
Application granted granted Critical
Publication of CN215443023U publication Critical patent/CN215443023U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Power-Operated Mechanisms For Wings (AREA)

Abstract

The utility model relates to the technical field of building construction devices, in particular to a large-span inclined roof floating awning curtain wall mounting device which comprises a support frame, wherein the bottom of the support frame is fixedly connected with a steel corbel, the top of the support frame is fixedly connected with an inclined steel framework, the upper end of the steel corbel is fixedly connected with a first pulley groove, one end, far away from the support frame, of the inclined steel framework is fixedly connected with a second pulley groove, and an operation table is arranged between the first pulley groove and the second pulley groove. The utility model has the advantages that: set up three crank elevating gear through the inside at the operation panel to every crank elevating gear all is provided with the footboard, when first motor operation, will once drive crank elevating gear and go up and down, and the operator can adjust a suitable height in the course of the work and install the fluffy curtain that wafts, the effectual practicality that improves this equipment, and on the other hand has avoided the operator because of too high or the tired of low production in the course of the work.

Description

Installation device for large-span inclined roof floating awning curtain wall
Technical Field
The utility model relates to the technical field of building construction devices, in particular to a large-span inclined roof floating awning curtain wall mounting device.
Background
Along with the diversification of building models, the floating awning curtain wall is widely applied to the exterior of building engineering, and the installation device of the large-span inclined roof floating awning curtain wall is an installation tool used for installing a floating window curtain wall, and aims to solve the building engineering with complex model, higher height and larger area. However, most of operation platforms of the existing installation devices for the floating awning curtain walls have no lifting function, so that workers are very inconvenient under the condition that the height of the operation platforms cannot be adjusted when installing the floating awning curtain walls.
SUMMERY OF THE UTILITY MODEL
The utility model aims to overcome the defects of the prior art and provide a large-span inclined roof awning curtain wall mounting device.
The purpose of the utility model is realized by the following technical scheme: the large-span inclined roof floating awning curtain wall mounting device comprises a support frame, wherein the bottom of the support frame is fixedly connected with a steel corbel, the top of the support frame is fixedly connected with an inclined rigid framework, the upper end of the steel corbel is fixedly connected with a first pulley groove, one end of the inclined steel framework, which is far away from the support frame, is fixedly connected with a second pulley groove, an operation table is arranged between the first pulley groove and the second pulley groove, guard rails are fixedly connected with the two sides of the operation table, the bottom of the operation table is fixedly connected with a mounting table, a first crank is fixedly mounted on one side of the mounting table, a second crank is fixedly mounted on one side of the first crank, through holes are formed in the middle parts of the first crank and the second crank and are connected through round pins, a sliding block is fixedly mounted at the bottom of the second crank, and a threaded hole is formed in the sliding block, the top parts of the first crank and the second crank are fixedly provided with crank lifting devices, the top ends of the crank lifting devices are fixedly provided with pedals, the bottom part of one side of the operating platform is provided with a lead screw through hole, one side of the operating platform is fixedly provided with a first motor, the output end of the first motor penetrates to one side of the operating platform close to the crank lifting devices through the lead screw through hole, the output end of the first motor is fixedly connected with a lead screw matched with a threaded hole, the outer surface of the lead screw is in threaded connection with a first ejector block and a second ejector block, the inner parts of the first ejector block and the second ejector block are both provided with inner threads matched with the lead screw, the upper surface of the operating platform is fixedly provided with a second motor, the output end of the second motor is fixedly connected with a gear, one side of the oblique steel skeleton close to the second chute is fixedly provided with a rack matched with the gear, the bottom fixedly connected with of operation panel and the first slider of first pulley groove adaptation, the top fixedly connected with of operation panel and the second slider of second pulley groove adaptation, the inside fixed mounting of first slider has first wheel, the inside fixed mounting of second slider has the second wheel.
Optionally, the crank lifting device has three, three the equal fixed mounting footboard in crank lifting device's top, three equal fixed mounting of crank lifting device's bottom has mount table and sliding block, and is three only one is seted up threaded hole in the sliding block other two and is the through-hole.
Optionally, the first ejector block and the second ejector block are both arranged on the side, away from the crank lifting device, of the opposite sliding block.
Optionally, first crank is connected through round pin and mount table, the second crank is connected through round pin and sliding block, the inside both sides of operation panel all are provided with crank elevating gear.
Optionally, the second motor is fixedly mounted on the upper surface of the operating platform through four screws, and both ends of the rack are fixedly mounted on the upper surface of the oblique steel skeleton through screws.
Optionally, the first wheel has two and not more than first pulley grooves, both of the first wheels slide inside the first pulley grooves, the second wheel has two and not more than second pulley grooves, and both of the second wheels slide inside the second pulley grooves.
Optionally, the length of the lead screw is not greater than the length of the operating table.
The utility model has the following advantages:
1. this large-span slope roof awning curtain installation device that wafts, the inside through at the operation panel sets up three crank elevating gear, and every crank elevating gear all is provided with the footboard, when first motor operation, will once drive crank elevating gear and go up and down, the operator can adjust a suitable height in the course of the work and install awning curtain, the effectual practicality that improves this equipment, on the other hand has avoided the operator because of too high or the tired of low production in the course of the work.
2. This large-span slope roof canopy curtain installation device that wafts sets up second motor and gear through the top at the operation panel, and the top of slant steel skeleton is provided with the rack, can remove the operation panel through the cooperation of gear and rack, can effectually improve the efficiency of work, is provided with the rail guard in the both sides of operation panel, has improved operating personnel's security.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic structural view of the present invention;
FIG. 3 is a schematic structural diagram of an operating device according to the present invention;
fig. 4 is a schematic structural diagram of the operation table of the present invention.
In the figure: 1-support frame, 2-steel bracket, 3-oblique steel skeleton, 4-first pulley groove, 5-second pulley groove, 6-operation table, 7-protective guard, 8-installation table, 9-first crank, 10-second crank, 11-sliding block, 12-threaded hole, 13-crank lifting device, 14-pedal, 15-first motor, 16-lead screw, 17-first top block, 18-second top block, 19-second motor, 20-gear, 21-rack, 22-first sliding block, 23-second sliding block, 24-first wheel and 25-second wheel.
Detailed Description
The utility model will be further described with reference to the accompanying drawings, but the scope of the utility model is not limited to the following.
As shown in fig. 1-4, the installation device for a large-span inclined roof awning curtain wall comprises a support frame 1, a steel corbel 2 fixedly connected to the bottom of the support frame 1, an inclined rigid framework 3 fixedly connected to the top of the support frame 1, a first pulley groove 4 fixedly connected to the upper end of the steel corbel 2, a second pulley groove 5 fixedly connected to the end of the inclined steel framework 3 away from the support frame 1, a first pulley groove 4 and a second pulley groove 5 cooperating with a first pulley 24 and a second pulley 25 to move an operating platform 6, an operating platform 6 arranged between the first pulley groove 4 and the second pulley groove 5, the operating platform 6 allowing a worker to work on the operating platform 6, guard rails 7 fixedly connected to both sides of the operating platform 6, the guard rails 7 preventing the worker from falling off, an installation platform 8 fixedly connected to the bottom of the operating platform 6, a first crank 9 fixedly installed on one side of the installation platform 8, a second crank 10 is fixedly arranged on one side of the first crank 9, through holes are arranged in the middle of the first crank 9 and the second crank 10 and are connected through round pins, a sliding block 11 is fixedly arranged at the bottom end of the second crank 10, a threaded hole 12 is formed in the sliding block 11, crank lifting devices 13 are fixedly arranged at the top parts of the first crank 9 and the second crank 10, a first top block 17 and a second top block 18 are arranged on one side, far away from the crank lifting devices 13, of the opposite sliding block 11, the first crank 9 is connected with the mounting table 8 through round pins, the second crank 10 is connected with the sliding block 11 through round pins, crank lifting devices 13 are arranged on two sides in the operating table 6, pedals 14 are fixedly arranged at the top ends of the crank lifting devices 13, a worker can work on the pedals 14, screw rod through holes 14 are formed in the bottom part on one side of the operating table 6, and three crank lifting devices 13 are arranged, pedals 14 are fixedly arranged at the tops of the three crank lifting devices 13, mounting platforms 8 and sliding blocks 11 are fixedly arranged at the bottoms of the three crank lifting devices 13, only one of the three sliding blocks 11 is provided with a threaded hole 12, the other two sliding blocks are through holes, a first motor 15 is fixedly arranged at one side of the operating platform 6, the three crank lifting devices 13 are arranged in the operating platform 6, each crank lifting device 13 is provided with a pedal 14, when the first motor 15 runs, the crank lifting devices 13 are driven to lift once, an operator can adjust a proper height to mount a awning curtain wall in the working process, the practicability of the equipment is effectively improved, on the other hand, the fatigue of the operator caused by too high or too low in the working process is avoided, the output end of the first motor 15 penetrates through the screw rod through hole 14 to one side of the operating platform 6 close to the crank lifting devices 13, the output end of the first motor 15 is fixedly connected with a lead screw 16 matched with the threaded hole 12, the length of the lead screw 16 is not more than that of the operating platform 6, the outer surface of the lead screw 16 is in threaded connection with a first ejector block 17 and a second ejector block 18, inner threads matched with the lead screw 16 are arranged inside the first ejector block 17 and the second ejector block 18, a second motor 19 is fixedly arranged on the upper surface of the operating platform 6, the second motor 19 is fixedly arranged on the upper surface of the operating platform 6 through four screws, the output end of the second motor is fixedly connected with a gear 20, a rack 21 matched with the gear 20 is fixedly arranged on one side, close to the second chute 5, of the oblique steel framework 3, two ends of the rack 21 are fixedly arranged on the upper surface of the oblique steel framework 3 through screws, the second motor 19 and the gear 20 are arranged on the top of the operating platform 6, the rack 21 is arranged on the top of the oblique steel framework 3, the operating platform 6 can be moved through the matching of the gear 20 and the rack 21, can be effectual the efficiency of work of having improved, both sides at operation panel 6 are provided with rail guard 7, operating personnel's security has been improved, the bottom fixedly connected with of operation panel 6 and the first slider 22 of first pulley groove 4 adaptation, the second slider 23 of the top fixedly connected with of operation panel 6 and the adaptation of second pulley groove 5, the inside fixed mounting of first slider 22 has first wheel 24, the inside fixed mounting of second slider 23 has second wheel 25, first wheel 24 has two and is not more than first pulley groove 4, two first wheels 24 all slide in the inside of first pulley groove 4, second wheel 25 has two and is not more than second pulley groove 5, two second wheels 25 slide in the inside of second pulley groove 5.
The working process of the utility model is as follows: the worker enters the operation table 6, the first motor 15 operates to drive the screw rod 16 to rotate, the sliding block 11 with the threaded hole 12, the first ejector block 17 and the second ejector block 18 can be driven to move at one time through the rotation of the screw rod 16, the crank lifting device 13 at the inner end is lifted when the sliding block 11 with the threaded hole 12 moves, when the first ejector block 17 moves to the sliding block 11 without the threaded hole 12 in the middle, the first ejector block 17 pushes the sliding block 11 to move, the crank lifting device 13 in the middle is lifted, when the second ejector block 18 moves to the sliding block 11 without the threaded hole 12 at the outer end, the second ejector block 18 pushes the sliding block 11 to move, the crank lifting device 13 at the outer end is lifted, the operator can adjust the height by the first motor 15, the gear 20 is connected through the output end of the second motor 19, and the upper end of the oblique steel framework 3 is provided with the rack 21, the operation table 6 is moved by engaging the gear 20 with the rack 21 and by the rotation of the second motor 19.
In summary, the following steps: according to the installation device for the large-span inclined roof floating awning curtain wall, the three crank lifting devices 13 are arranged inside the operating platform 6, each crank lifting device 13 is provided with the pedal 14, when the first motor 15 operates, the crank lifting devices 13 are driven to lift once, an operator can adjust a proper height in the working process to install the floating awning curtain wall, the practicability of the equipment is effectively improved, and on the other hand, the fatigue of the operator caused by too high or too low in the working process is avoided; this large-span slope roof canopy curtain installation device that wafts through the top at operation panel 6 sets up second motor 19 and gear 20, and the top of slant steel skeleton 3 is provided with rack 21, can remove operation panel 6 through the cooperation of gear 20 and rack 21, can effectually improve the efficiency of work, is provided with rail guard 7 in the both sides of operation panel 6, has improved operating personnel's security.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. Installation device for large-span inclined roof floating awning curtain wall comprises a support frame (1) and is characterized in that: the steel bracket is characterized in that a steel bracket (2) is fixedly connected to the bottom of the support frame (1), an oblique steel skeleton (3) is fixedly connected to the top of the support frame (1), a first pulley groove (4) is fixedly connected to the upper end of the steel bracket (2), a second pulley groove (5) is fixedly connected to the end, far away from the support frame (1), of the oblique steel skeleton (3), an operation table (6) is arranged between the first pulley groove (4) and the second pulley groove (5), guard rails (7) are fixedly connected to the two sides of the operation table (6), an installation table (8) is fixedly connected to the bottom of the operation table (6), a first crank (9) is fixedly installed on one side of the installation table (8), a second crank (10) is fixedly installed on one side of the first crank (9), through holes are formed in the middle parts of the first crank (9) and the second crank (10) and are connected through round pins, the bottom fixed mounting of second crank (10) has sliding block (11), threaded hole (12) is seted up to the inside of sliding block (11), the top fixed mounting of first crank (9) and second crank (10) has crank elevating gear (13), the top fixed mounting of crank elevating gear (13) has footboard (14), the lead screw via hole has been seted up to the bottom of operation panel (6) one side, one side fixed mounting of operation panel (6) has first motor (15), the output of first motor (15) runs through to one side that operation panel (6) is close to crank elevating gear (13) through the lead screw via hole, the output fixed connection of first motor (15) has lead screw (16) with threaded hole (12) adaptation, the surface threaded connection of lead screw (16) has first kicking block (17) and second kicking block (18), the internal thread with lead screw (16) adaptation is all seted up to the inside of first kicking block (17) and second kicking block (18), the last fixed surface of operation panel (6) installs second motor (19), the output end fixedly connected with gear (20) of second motor, one side fixed mounting that slant steel skeleton (3) are close to second pulley groove (5) have with gear (20) adaptation rack (21), the bottom fixedly connected with of operation panel (6) and first slider (22) of first pulley groove (4) adaptation, the top fixedly connected with of operation panel (6) and second slider (23) of second pulley groove (5) adaptation, the inside fixed mounting of first slider (22) has first wheel (24), the inside fixed mounting of second slider (23) has second wheel (25).
2. The large span inclined roof awning curtain wall installation apparatus as claimed in claim 1, wherein: crank elevating gear (13) have threely, three the equal fixed mounting footboard (14) in top of crank elevating gear (13) are three the equal fixed mounting in bottom of crank elevating gear (13) has mount table (8) and sliding block (11), and is three only in sliding block (11) two in addition of set up threaded hole (12) are the through-hole.
3. The large span inclined roof awning curtain wall installation apparatus as claimed in claim 1, wherein: the first ejector block (17) and the second ejector block (18) are arranged on the side, far away from the crank lifting device (13), of the opposite sliding block (11).
4. The large span inclined roof awning curtain wall installation apparatus as claimed in claim 1, wherein: first crank (9) are connected through round pin and mount table (8), second crank (10) are connected through round pin and sliding block (11), the inside both sides of operation panel (6) all are provided with crank elevating gear (13).
5. The large span inclined roof awning curtain wall installation apparatus as claimed in claim 1, wherein: the second motor (19) is fixedly installed on the upper surface of the operating platform (6) through four screws, and two ends of the rack (21) are fixedly installed on the upper surface of the oblique steel skeleton (3) through screws.
6. The large span inclined roof awning curtain wall installation apparatus as claimed in claim 1, wherein: the first wheels (24) are provided with two pulley grooves (4) which are not larger than the first pulley grooves, the two first wheels (24) slide in the first pulley grooves (4), the second wheels (25) are provided with two pulley grooves (5) which are not larger than the second pulley grooves, and the two second wheels (25) slide in the second pulley grooves (5).
7. The large span inclined roof awning curtain wall installation apparatus as claimed in claim 1, wherein: the length of the lead screw (16) is not more than that of the operating platform (6).
CN202023304176.6U 2020-12-30 2020-12-30 Installation device for large-span inclined roof floating awning curtain wall Active CN215443023U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202023304176.6U CN215443023U (en) 2020-12-30 2020-12-30 Installation device for large-span inclined roof floating awning curtain wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202023304176.6U CN215443023U (en) 2020-12-30 2020-12-30 Installation device for large-span inclined roof floating awning curtain wall

Publications (1)

Publication Number Publication Date
CN215443023U true CN215443023U (en) 2022-01-07

Family

ID=79681576

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202023304176.6U Active CN215443023U (en) 2020-12-30 2020-12-30 Installation device for large-span inclined roof floating awning curtain wall

Country Status (1)

Country Link
CN (1) CN215443023U (en)

Similar Documents

Publication Publication Date Title
CN215443023U (en) Installation device for large-span inclined roof floating awning curtain wall
CN114751344B (en) Aluminum alloy climbing frame auxiliary moving lifting equipment and use method
CN214527517U (en) Tower crane pedestrian passageway device
CN210366899U (en) Lifting platform
CN215167804U (en) Building electrical construction erection equipment
CN214576658U (en) Rolling slats door convenient to installation
CN212269375U (en) Electromechanical device mounting frame
CN212387691U (en) Elevator device for power equipment maintenance
CN114275704A (en) Steel structure mounting rack and using method thereof
CN212248943U (en) Support tool for construction of green building energy-saving roof
CN110340629B (en) Automatic mounting machine for fire fighting pipe
CN210649408U (en) Unscrewing machine
CN208966191U (en) A kind of safety is ascended a height station
CN112482792A (en) Auxiliary device is used in installation of steel construction factory building
CN2503474Y (en) Tomato sampling device
CN220368416U (en) Large cable bridge capable of carrying load adjustment
CN220014372U (en) Building construction support
CN214003975U (en) Guide tracked lift platform lift gate
CN219711265U (en) Plug-in type breaking-proof knife convenient to install of flexible stacking door
CN220393210U (en) Hydraulic jack
CN220316998U (en) Damping type elevator car roof fixing structure
CN219771577U (en) Hoisting equipment for building construction
CN220014381U (en) Construction operation device of ascending a height
CN221027064U (en) Auxiliary equipment for lifting elevator
CN219260148U (en) Quenching device for aluminum door and window production

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 110000 gate 1, No. 58, Kaifa 25th Road, Shenyang Economic and Technological Development Zone, Tiexi District, Shenyang City, Liaoning Province

Patentee after: Liaoning Shuyuan Construction Technology Group Co.,Ltd.

Address before: 110000 gate 1, No. 58, Kaifa 25th Road, Shenyang Economic and Technological Development Zone, Tiexi District, Shenyang City, Liaoning Province

Patentee before: Liaoning Hongming curtain wall decoration Engineering Co.,Ltd.

CP01 Change in the name or title of a patent holder