CN215406275U - Rainwater collecting system is piled to raw ore - Google Patents

Rainwater collecting system is piled to raw ore Download PDF

Info

Publication number
CN215406275U
CN215406275U CN202023058333.XU CN202023058333U CN215406275U CN 215406275 U CN215406275 U CN 215406275U CN 202023058333 U CN202023058333 U CN 202023058333U CN 215406275 U CN215406275 U CN 215406275U
Authority
CN
China
Prior art keywords
rainwater
raw ore
rainwater collecting
hardened ground
rainwater collection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202023058333.XU
Other languages
Chinese (zh)
Inventor
尹广顺
谷文斌
淳勋
李腾飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xin Barag Right Banner Rongda Mining Co ltd
Original Assignee
Xin Barag Right Banner Rongda Mining Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xin Barag Right Banner Rongda Mining Co ltd filed Critical Xin Barag Right Banner Rongda Mining Co ltd
Priority to CN202023058333.XU priority Critical patent/CN215406275U/en
Application granted granted Critical
Publication of CN215406275U publication Critical patent/CN215406275U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use
    • Y02A20/108Rainwater harvesting

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model relates to a raw ore heap rainwater collection system, and belongs to the field of mine solid waste treatment; the raw ore heap rainwater collecting system comprises a hardened ground, a ditch and a rainwater collecting pool, wherein the rainwater collecting pool is arranged on the hardened ground, the ditch communicated with the rainwater collecting pool is arranged on the hardened ground, and a submersible pump connected with a water storage tank is arranged in the rainwater collecting pool; according to the utility model, the hardened ground of the raw ore storage yard is built, rainwater can be prevented from leaching to the underground of the storage yard to enrich heavy metal in soil, and the rainwater collecting pool is arranged, so that the problem that rainwater leaches heavy metal in the underground of the storage yard and the soil of the peripheral grassland can be effectively solved, and the potential risk of environmental protection is eliminated.

Description

Rainwater collecting system is piled to raw ore
Technical Field
The utility model relates to a raw ore heap rainwater collection system, and belongs to the field of mine solid waste treatment.
Background
In the existing ore dressing plant raw ore storage yard, the ground is a soil layer which is not hardened and has no rainwater collection facility, rainwater is leached to the underground of the storage yard every time, solid wastes such as residual building wastes can cause the enrichment of heavy metal in soil, and the redundant waste and waste steel influence the peripheral environment of the grassland, so that the potential hazard of environmental protection risk exists. Therefore, it is necessary to harden the ground of the raw ore yard and construct a rainwater collection facility.
SUMMERY OF THE UTILITY MODEL
In order to overcome the problems in the background art, the utility model can prevent rainwater from leaching underground of the storage yard to cause the enrichment of heavy metal in soil by building a hardened ground of the raw ore storage yard, and the rainwater collection pool is arranged to effectively solve the problem that rainwater leaches heavy metal in the underground of the storage yard and the soil of the peripheral grassland, thereby eliminating the hidden danger of environmental protection risk.
In order to overcome the problems in the background art and solve the problems, the utility model is realized by the following technical scheme:
the raw ore heap rainwater collection system comprises a hardened ground, a ditch and a rainwater collection tank, wherein the hardened ground is provided with the rainwater collection tank, the hardened ground is provided with the ditch communicated to the rainwater collection tank, and the rainwater collection tank is internally provided with a submersible pump connected with a water storage tank.
Preferably, the hardened ground comprises a rammed earth base layer, a natural gravel cushion layer, a graded gravel base layer and a concrete surface layer, wherein the rammed earth base layer, the natural gravel cushion layer, the graded gravel base layer and the concrete surface layer are sequentially poured from bottom to top.
The utility model has the beneficial effects that:
according to the utility model, the hardened ground of the raw ore storage yard is built, rainwater can be prevented from leaching to the underground of the storage yard to enrich heavy metal in soil, and the rainwater collecting pool is arranged, so that the problem that rainwater leaches heavy metal in the underground of the storage yard and the soil of the peripheral grassland can be effectively solved, and the potential risk of environmental protection is eliminated.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of a hardened ground structure according to the present invention.
The reference numbers in the figures are: 1-hardened ground, 2-ditch, 3-rainwater collecting pool, 4-rammed earth base layer, 5-natural gravel cushion layer, 6-graded gravel base layer, 7-concrete surface layer, 8-submersible pump and 9-water storage tank.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, preferred embodiments of the present invention will be described in detail below with reference to the accompanying drawings to facilitate understanding of the skilled person.
As shown in fig. 1-2, the raw ore heap rainwater collection system includes a hardened ground 1, a trench 2, and a rainwater collection pool 3, wherein the hardened ground 1 is provided with the rainwater collection pool 3, and the hardened ground 1 is provided with the trench 2 communicated to the rainwater collection pool 3, in this embodiment, the trench 2130m is long and 500mm wide, and the size of the rainwater collection pool 3 is 8m 5m 3.5 m. The rainwater collecting tank 3 is internally provided with a submersible pump connected with a water storage tank. Whole sclerosis ground 1 designs for outside a week is higher, and inboard a week is lower has the structure of slope, consequently collects the rainwater 1 inboard a week rainwater catch pit 3 on sclerosis ground, sets up irrigation canals and ditches 2 and immersible pump 8 simultaneously, retrieves to water storage tank 9 to be used for the workshop production with the clear water after filtering.
Hardened ground 1 includes tamped soil base layer 4, natural gravel bed course 5, graded grit base layer 6, concrete surface course 7, pours tamped soil base layer 4 by bottom to top in proper order, natural gravel bed course 5, graded grit base layer 6, concrete surface course 7, and hardened ground 1 divides into four layers, and in this embodiment, first layer tamped soil base layer 4, second floor 150mm natural gravel bed course 5, third layer 250mm graded grit base layer 6, the thick C30 concrete surface course 7 of fourth layer 250 mm.
The measurer combines the original height of the ground to determine the height difference and slope ratio in the whole yard. The hooking machine enters the field to dig and support the original ground by 0.25M, leveling is carried out, the road roller is matched with the original ground which is leveled by the hooking machine to roll and tamp, the ground is leveled according to the design requirement, and the slope is five per thousand. The construction positioning line is mainly used for controlling the elevation of the channel steel side die, the designed thickness of concrete is 250mm, the channel steel side die is used, the top surface of channel steel is arranged on the top surface of the laid-off elevation, and the place with insufficient height is filled with stones and leveled. After fixing, the elevation of the top of the template is checked by a level gauge. The method comprises the steps of sequentially pouring a rammed concrete base layer 4, a natural gravel cushion layer 5, a graded gravel base layer 6 and a concrete surface layer 7, wherein the concrete is type C30 concrete, the concrete is constructed in a longitudinal strip division mode, a vibrating rod is used for vibrating after the concrete is poured, a scraping machine is placed on channel steel, and the concrete surface is scraped by an operator. After the concrete is leveled and compacted, the concrete is statically stopped for about 4 hours to make the concrete in a critical initial setting period, and the judging method comprises the following steps: the foot is stepped on the upper surface and the foot print sinks by 5 mm. And (3) carrying out surface slurry lifting, brushing, compacting, unloading a sand table, directly starting mechanical polishing by using the trowelling machine, brushing after polishing is finished, curing after concrete is poured for 24 hours, covering by adopting geotextile, and spraying water for curing. In order to overcome the crack generated by the temperature change, a cutting machine is required to be used for cutting on the poured concrete ground perpendicular to the pouring direction of the concrete. The time of slitting should be controlled strictly, and premature slitting can loosen the stones and damage the edges. The seam is difficult to cut too late, and the two ends of the seam are easy to crack irregularly. The compressive strength of the concrete reaches 6-10 MPa in a proper time. And performing slotting construction after curing for 3 days in the season.
According to the relevant parameters of the foundation, the central axes of the ditch 2 and the collecting pool are discharged by an instrument, the corresponding elevation is measured, the milepost number and the elevation are marked on the ground, the corresponding contour line of the ditch is pulled out by lime or a wire rope according to the bottom crossing result, and the corresponding opening control depth is shown. And (3) according to the corresponding contour lines, placing the edge lines of the trench bottom trench, drawing the edge lines on the ground by using lime, excavating by using a manually-matched excavating machine, transporting by using a dump truck, and excavating to 10-15cm away from the designed dimension by using manual excavation. And manually trimming to the designed size, so that the ditch bottom and the original soil layer of the slope cannot be disturbed, and overexcavation is not allowed. After the foundation trench is excavated, firstly self-checking is carried out, after mutual checking is qualified, a project department reports to a field supervision engineer for checking, and after all checking is qualified, concrete pouring work of the ditch 2 and the collecting tank is accurately carried out.
The material can be used after being detected to be qualified when entering a field, and concrete is prepared strictly according to the construction mixing proportion, so that the sufficient stirring time is ensured, and various indexes of the concrete, such as slump and the like, need to meet the standard requirements. The concrete is transported by using a self-unloading tricycle, and the concrete is manually injected into the template. The vibration adopts an inserted vibrator, the vibration points are required to be uniform in the vibration process, and the vibration time is suitable for preventing the concrete surface from sinking and preventing bubbles from rising from the side edge of the template. The surface of the concrete is kept wet all the time within 7-10 days after the concrete is poured. The plastic film is used for covering and wrapping in the health preserving process, watering is ensured to be carried out more than twice every day, and the watering frequency is properly increased in hot days, so that the surface of the concrete is preferably kept in a wet state.
According to the utility model, the hardened ground of the raw ore storage yard is built, rainwater can be prevented from leaching to the underground of the storage yard to enrich heavy metal in soil, and the rainwater collecting pool is arranged, so that the problem that rainwater leaches heavy metal in the underground of the storage yard and the soil of the peripheral grassland can be effectively solved, and the potential risk of environmental protection is eliminated.
Finally, it is noted that the above-mentioned preferred embodiments illustrate rather than limit the utility model, and that, although the utility model has been described in detail with reference to the above-mentioned preferred embodiments, it will be understood by those skilled in the art that various changes in form and detail may be made therein without departing from the scope of the utility model as defined by the appended claims.

Claims (2)

1. The utility model provides a rainwater collecting system is piled to raw ore which characterized in that: the raw ore heap rainwater collection system comprises a hardened ground, a ditch and a rainwater collection tank, wherein the hardened ground is provided with the rainwater collection tank, the hardened ground is provided with the ditch communicated to the rainwater collection tank, and the rainwater collection tank is internally provided with a submersible pump connected with a water storage tank.
2. The raw ore heap rainwater collection system of claim 1 wherein: the sclerosis ground is including rammed earth basic unit, natural gravel bed course, gradation grit basic unit, and the concrete surface course is pour rammed earth basic unit, natural gravel bed course, gradation grit basic unit, concrete surface course in proper order by bottom to top.
CN202023058333.XU 2020-12-18 2020-12-18 Rainwater collecting system is piled to raw ore Active CN215406275U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202023058333.XU CN215406275U (en) 2020-12-18 2020-12-18 Rainwater collecting system is piled to raw ore

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202023058333.XU CN215406275U (en) 2020-12-18 2020-12-18 Rainwater collecting system is piled to raw ore

Publications (1)

Publication Number Publication Date
CN215406275U true CN215406275U (en) 2022-01-04

Family

ID=79637267

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202023058333.XU Active CN215406275U (en) 2020-12-18 2020-12-18 Rainwater collecting system is piled to raw ore

Country Status (1)

Country Link
CN (1) CN215406275U (en)

Similar Documents

Publication Publication Date Title
CN112523270B (en) Anti-floating blind ditch for deep foundation pit in water-rich area and construction process thereof
CN106759126B (en) Construction method of side slope support drainage channel
CN102677661A (en) Reinforcement method for foundation of silt soft-based cast-in-place box girder support
CN110886317B (en) Foundation trench earthwork backfill construction method for steel sheet pile supporting structure of urban comprehensive pipe gallery
CN113186766A (en) Shallow soft soil foundation foam light soil embankment structure and construction method
CN110056000B (en) Construction method and structure of counter weight type retaining wall
CN110761316B (en) Prefabricated foundation ring beam prefabricating method and storage tank construction method applying prefabricated foundation ring beam prefabricating method
CN111778941A (en) High-standard farmland channel construction method and structure
CN112695763A (en) Deep sludge stratum foundation pit excavation method
CN109706952A (en) Large-scale well-sinking construction method
CN102182866A (en) Backfilling process for large ultra-deep circulating water pipe
CN108277777A (en) Wave wall substep pouring construction process
CN114232587A (en) Construction method for preventing settlement and cracking of large-area ground
CN214090013U (en) Anti blind ditch that floats to deep basal pit in rich water area
CN107137913B (en) The construction technology in tennis court and tennis court
CN215406275U (en) Rainwater collecting system is piled to raw ore
CN112813756A (en) Roadbed based on municipal soft soil and construction method
CN115030146A (en) Solidified soil composite foundation technology for pile mud capable of being solidified in situ to form pile body material
CN210797245U (en) Structure is backfilled to bridgehead abutment back of body
CN113174904A (en) Construction method for ecological landscape open channel for downward seepage and stagnation storage in sponge city
CN113322967A (en) Coastline soft foundation in-situ curing method and curing structure
CN111236170A (en) Quick construction method for buried rock concrete gravity dam
CN217105104U (en) Coastline soft base normal position solidification structure
CN114688347B (en) Method for embedding flexible pipeline by using controllable low-strength material prefabricated block
CN212801050U (en) Municipal administration road bad soil foundation stabilization structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant