CN215364608U - Material conveying and lifting equipment for bridge construction of bridge engineering - Google Patents
Material conveying and lifting equipment for bridge construction of bridge engineering Download PDFInfo
- Publication number
- CN215364608U CN215364608U CN202120312539.6U CN202120312539U CN215364608U CN 215364608 U CN215364608 U CN 215364608U CN 202120312539 U CN202120312539 U CN 202120312539U CN 215364608 U CN215364608 U CN 215364608U
- Authority
- CN
- China
- Prior art keywords
- fixedly connected
- bin
- face
- storage box
- base
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000000463 material Substances 0.000 title claims description 15
- 238000010276 construction Methods 0.000 title claims description 13
- 238000009434 installation Methods 0.000 claims abstract description 15
- 230000005540 biological transmission Effects 0.000 claims abstract description 14
- 239000004035 construction material Substances 0.000 claims abstract description 4
- 238000004804 winding Methods 0.000 claims description 8
- 238000005192 partition Methods 0.000 claims description 5
- 238000000034 method Methods 0.000 abstract description 10
- 239000007787 solid Substances 0.000 abstract description 4
- 238000005381 potential energy Methods 0.000 abstract description 3
- 230000002035 prolonged effect Effects 0.000 abstract description 3
- 230000001174 ascending effect Effects 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 3
- 239000004566 building material Substances 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The application discloses lifting device is transported to bridge construction material of bridge engineering, including base, support column, linking arm, fixing base, installation piece, bin, supporting shoe and transmission case, the fixedly connected with support column is located at the top end face center of base, the right side top fixedly connected with linking arm of support column, first pulley is installed to the right-hand member of linking arm, the second pulley is installed on the top of support column, the top end face left side fixedly connected with fixing base of base. This application rotates through motor drive wind-up roll and drives the haulage rope and remove, and then drives installation piece rebound to accomplish the ascending of bin, solid fixed ring that is equipped with through the bin both sides mutually supports with the couple, the bin of being convenient for tends towards stably at the in-process that rises, elastic potential energy through first spring and second spring acts on T type pole and supporting shoe, is convenient for reduce the bin and falls to the ground the impact that receives, has prolonged the life of bin.
Description
Technical Field
The application relates to a material conveying lifting device, in particular to a material conveying lifting device for bridge construction of bridge engineering.
Background
The bridge engineering refers to the working process of bridge surveying, designing, constructing, maintaining and checking, and the scientific and engineering technology for researching the process, and is a branch of civil engineering.
But the lifting means is transported to bridge construction material of current bridge engineering can't transport multiple material simultaneously when transporting the material, and can receive great impact when the bin falls to the ground after transporting the material, influences life. Therefore, a material transporting and lifting device for bridge construction in bridge construction is proposed to solve the above problems.
Disclosure of Invention
A material conveying and lifting device for bridge construction of bridge engineering comprises a base, a supporting column, a connecting arm, a fixed seat, an installation block, a storage box, a supporting block and a transmission box, wherein the center of the top end face of the base is fixedly connected with the supporting column, the top end of the right side of the supporting column is fixedly connected with the connecting arm, the right end of the connecting arm is provided with a first pulley, the top end of the supporting column is provided with a second pulley, the left side of the top end face of the base is fixedly connected with the fixed seat, the rear end face of the fixed seat is fixedly connected with a control box, an inner cavity of the control box is fixedly provided with a motor, the output end of the motor is fixedly connected with a rotating shaft, the other end of the rotating shaft is rotatably connected with a bearing arranged on the front side of the inner wall of the fixed seat, a winding roller is sleeved on the rotating shaft, the installation block is arranged below the first pulley and is respectively fixedly connected with the top ends of four hooks through four traction ropes, the below of installation piece is equipped with the bin, the below of bin is equipped with four supporting shoes, four the first spring of the equal fixedly connected with in bottom of supporting shoe inner chamber, the top of first spring and the bottom fixed connection of T type pole, the top of T type pole runs through the top of supporting shoe and the bottom terminal surface fixed connection of bin, the inner wall sliding connection of bin has the baffle, the rear end terminal surface fixedly connected with transmission case of bin, the left side inner wall of transmission case passes through the bearing and is connected with the left end rotation of lead screw, the right-hand member of lead screw runs through the right side terminal surface and the carousel fixed connection of transmission case, it is connected with the sliding sleeve to rotate on the lead screw, the rear end terminal surface and the baffle fixed connection of bin are run through to the one end of sliding sleeve.
Further, the bottom end face fixed mounting of base has four universal wheels, the both sides end face fixed mounting of base has hydraulic push rod, hydraulic push rod's bottom fixedly connected with balancing weight.
Furthermore, a traction rope is fixedly connected to the winding roller, and the other end of the traction rope is fixedly connected with the top end of the mounting block through a first pulley and a second pulley.
Further, the equal fixedly connected with two solid fixed rings of both sides terminal surface of bin, four solid fixed ring suits with four couples respectively.
Furthermore, the bottom end of the T-shaped rod is connected with the inner wall of the supporting block in a sliding mode, a second spring is sleeved on the top of the T-shaped rod, the top end of the second spring is fixedly connected with the bottom end of the storage box, and the bottom end of the second spring is fixedly connected with the top end of the supporting block.
Further, the front side inner wall of bin inner chamber is equipped with T type groove, the front side end face fixedly connected with T type piece of baffle, T type piece and T type groove sliding connection, one side fixed mounting of T type piece and the contact of T type groove has the ball, the rear side end face of bin is equipped with spacing spout, sliding sleeve and spacing spout sliding connection.
The beneficial effect of this application is: the application provides a lifting means is transported to bridge construction material of bridge engineering convenient to transport.
Drawings
In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings needed to be used in the description of the embodiments or the prior art will be briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present application, and it is obvious for those skilled in the art that other drawings can be obtained according to the drawings without inventive exercise.
FIG. 1 is a schematic overall perspective view of an embodiment of the present application;
FIG. 2 is a schematic diagram of the overall internal structure of an embodiment of the present application;
FIG. 3 is a schematic top view of a storage case according to an embodiment of the present application;
FIG. 4 is a schematic diagram of a side view of a base according to an embodiment of the present application;
fig. 5 is a schematic diagram of a partial enlarged structure at a in fig. 2 according to an embodiment of the present application.
In the figure: 1. the base, 2, the support column, 3, the linking arm, 4, first pulley, 5, the second pulley, 6, the fixing base, 7, the motor, 8, the pivot, 9, the wind-up roll, 10, the installation piece, 11, the couple, 12, the bin, 13, solid fixed ring, 14, the supporting shoe, 15, first spring, 16, T type pole, 17, the second spring, 18, the baffle, 19, T type groove, 20, T type piece, 21, the transmission case, 22, spacing spout, 23, the lead screw, 24, the sliding sleeve.
Detailed Description
In order to make the technical solutions better understood by those skilled in the art, the technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application, and it is obvious that the described embodiments are only partial embodiments of the present application, but not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present application.
It should be noted that the terms "first," "second," and the like in the description and claims of this application and in the drawings described above are used for distinguishing between similar elements and not necessarily for describing a particular sequential or chronological order. It should be understood that the data so used may be interchanged under appropriate circumstances such that embodiments of the application described herein may be used. Furthermore, the terms "comprises," "comprising," and "having," and any variations thereof, are intended to cover a non-exclusive inclusion, such that a process, method, system, article, or apparatus that comprises a list of steps or elements is not necessarily limited to those steps or elements expressly listed, but may include other steps or elements not expressly listed or inherent to such process, method, article, or apparatus.
In this application, the terms "upper", "lower", "left", "right", "front", "rear", "top", "bottom", "inner", "outer", "middle", "vertical", "horizontal", "lateral", "longitudinal", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings. These terms are used primarily to better describe the present application and its embodiments, and are not used to limit the indicated devices, elements or components to a particular orientation or to be constructed and operated in a particular orientation.
Moreover, some of the above terms may be used to indicate other meanings besides the orientation or positional relationship, for example, the term "on" may also be used to indicate some kind of attachment or connection relationship in some cases. The specific meaning of these terms in this application will be understood by those of ordinary skill in the art as appropriate.
Furthermore, the terms "mounted," "disposed," "provided," "connected," and "sleeved" are to be construed broadly. For example, it may be a fixed connection, a removable connection, or a unitary construction; can be a mechanical connection, or an electrical connection; may be directly connected, or indirectly connected through intervening media, or may be in internal communication between two devices, elements or components. The specific meaning of the above terms in the present application can be understood by those of ordinary skill in the art as appropriate.
It should be noted that the embodiments and features of the embodiments in the present application may be combined with each other without conflict. The present application will be described in detail below with reference to the embodiments with reference to the attached drawings.
Referring to fig. 1-5, a material conveying and lifting device for bridge construction of bridge engineering comprises a base 1, a support column 2, a connecting arm 3, a fixing seat 6, an installation block 10, a storage box 12, a support block 14 and a transmission box 21, wherein the support column 2 is fixedly connected to the center of the top end surface of the base 1, the connecting arm 3 is fixedly connected to the top end of the right side of the support column 2, a first pulley 4 is installed at the right end of the connecting arm 3, a second pulley 5 is installed at the top end of the support column 2, the fixing seat 6 is fixedly connected to the left side of the top end surface of the base 1, a control box is fixedly connected to the rear end surface of the fixing seat 6, a motor 7 is fixedly installed in the inner cavity of the control box, the output end of the motor 7 is fixedly connected to a rotating shaft 8, the other end of the rotating shaft 8 is rotatably connected to a bearing arranged on the front side of the inner wall of the fixing seat 6, the winding roll 9 is sleeved on the rotating shaft 8, an installation block 10 is arranged below the first pulley 4, the installation block 10 is respectively fixedly connected with the top ends of four hooks 11 through four traction ropes, a storage box 12 is arranged below the installation block 10, four support blocks 14 are arranged below the storage box 12, first springs 15 are fixedly connected with the bottom ends of inner cavities of the four support blocks 14, the top end of each first spring 15 is fixedly connected with the bottom end of a T-shaped rod 16, the top end of the T-shaped rod 16 penetrates through the top end of the support block 14 and is fixedly connected with the bottom end face of the storage box 12, a partition plate 18 is slidably connected with the inner wall of the storage box 12, a transmission box 21 is fixedly connected with the rear end face of the storage box 12, the inner wall of the left side of the transmission box 21 is rotatably connected with the left end of a lead screw 23 through a bearing, and the right end face of the lead screw 23 penetrates through the right end face of the transmission box 21 and is fixedly connected with a turntable, the screw rod 23 is rotatably connected with a sliding sleeve 24, and one end of the sliding sleeve 24 penetrates through the rear end face of the storage box 12 and is fixedly connected with the partition plate 18.
Four universal wheels are fixedly mounted on the bottom end face of the base 1, hydraulic push rods are fixedly mounted on the end faces of two sides of the base 1, and balancing weights are fixedly connected to the bottom ends of the hydraulic push rods, so that the working is facilitated; a traction rope is fixedly connected to the winding roller 9, and the other end of the traction rope is fixedly connected with the top end of the mounting block 10 through the first pulley 4 and the second pulley 5, so that the connection is facilitated; two fixing rings 13 are fixedly connected to the end faces of the two sides of the storage box 12, and the four fixing rings 13 are respectively matched with the four hooks 11 and are convenient to connect; the bottom end of the T-shaped rod 16 is slidably connected with the inner wall of the supporting block 14, a second spring 17 is sleeved at the top of the T-shaped rod 16, the top end of the second spring 17 is fixedly connected with the bottom end of the storage box 12, and the bottom end of the second spring 17 is fixedly connected with the top end of the supporting block 14, so that the connection is facilitated; the front side inner wall of bin 12 inner chamber is equipped with T type groove 19, the front side end face fixedly connected with T type piece 20 of baffle 18, T type piece 20 and T type groove 19 sliding connection, one side fixed mounting of T type piece 20 and the contact of T type groove 19 has the ball, the rear side end face of bin 12 is equipped with spacing spout 22, sliding sleeve 24 and spacing spout 22 sliding connection are convenient for connect.
When the storage box is used, electrical elements appearing in the application are externally connected with a power supply and a control switch, the motor 7 drives the winding roller 9 to rotate to drive the traction rope to move, and then the mounting block 10 is driven to move upwards, so that the storage box 12 is lifted upwards, the fixing rings 13 arranged on two sides of the storage box 12 are matched with the hooks 11, the storage box 12 tends to be stable in the lifting process, the elastic potential energy of the first spring 15 and the second spring 17 acts on the T-shaped rod 16 and the supporting block 14, the impact on the storage box 12 when falling is reduced, the service life of the storage box 12 is prolonged, the rotating disc is rotated to drive the lead screw 23 to rotate, and then the sliding sleeve 24 drives the partition plate 18 to move in the storage box 12, so that a worker can adjust the space in the storage box 12 according to actual conditions, and further, the different building materials can be transported simultaneously, the balls arranged on the T-shaped blocks 20 are connected with the T-shaped grooves 19 in a sliding mode, friction between the partition plate 18 and the storage box 12 is reduced, the hydraulic push rod drives the balancing weight to move up and down, the base 1 is convenient to jack up and put down, and therefore the base 1 is convenient to stabilize during working and move during non-working.
The application has the advantages that:
1. according to the storage box, the motor drives the winding roller to rotate to drive the traction rope to move, so that the mounting block is driven to move upwards, the storage box is lifted upwards, the fixing rings arranged on the two sides of the storage box are matched with the hooks, the storage box is convenient to stabilize in the lifting process, elastic potential energy of the first spring and the second spring acts on the T-shaped rod and the supporting block, impact on the storage box when the storage box falls to the ground is reduced, and the service life of the storage box is prolonged;
2. this application drives the lead screw through rotating the carousel and rotates, and then makes the sliding sleeve drive the baffle and remove in the bin, and the staff of being convenient for adjusts the space in the bin according to actual conditions, and then is convenient for transport different building materials simultaneously, has the ball and the T type groove sliding connection of installation on the T type piece again, has reduced the friction of baffle with the bin.
It is well within the skill of those in the art to implement, without undue experimentation, the present application is not directed to software and process improvements, as they relate to circuits and electronic components and modules.
The above description is only a preferred embodiment of the present application and is not intended to limit the present application, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, improvement and the like made within the spirit and principle of the present application shall be included in the protection scope of the present application.
Claims (6)
1. The utility model provides a lifting means is transported to bridge construction material of bridge engineering which characterized in that: comprises a base (1), a supporting column (2), a connecting arm (3), a fixing seat (6), an installation block (10), a storage box (12), a supporting block (14) and a transmission case (21), wherein the top end face center of the base (1) is fixedly connected with the supporting column (2), the right top end of the supporting column (2) is fixedly connected with the connecting arm (3), the right end of the connecting arm (3) is provided with a first pulley (4), the top end of the supporting column (2) is provided with a second pulley (5), the left side of the top end face of the base (1) is fixedly connected with the fixing seat (6), the rear end face of the fixing seat (6) is fixedly connected with a control box, the inner cavity of the control box is fixedly provided with a motor (7), the output end of the motor (7) is fixedly connected with a rotating shaft (8), the other end of the rotating shaft (8) is rotatably connected with a bearing arranged on the front side of the inner wall of the fixing seat (6), the winding roll (9) is sleeved on the rotating shaft (8), an installation block (10) is arranged below the first pulley (4), the installation block (10) is respectively fixedly connected with the top ends of four hooks (11) through four traction ropes, a storage box (12) is arranged below the installation block (10), four supporting blocks (14) are arranged below the storage box (12), four first springs (15) are fixedly connected to the bottom ends of inner cavities of the supporting blocks (14), the top ends of the first springs (15) are fixedly connected with the bottom end of a T-shaped rod (16), the top end of the T-shaped rod (16) penetrates through the top ends of the supporting blocks (14) and the bottom end face of the storage box (12), a partition plate (18) is slidably connected to the inner wall of the storage box (12), and a transmission box (21) is fixedly connected to the rear side end face of the storage box (12), the left side inner wall of transmission case (21) passes through the bearing and is connected with the left end rotation of lead screw (23), the right-hand member of lead screw (23) runs through the right side terminal surface and the carousel fixed connection of transmission case (21), it is connected with sliding sleeve (24) to rotate on lead screw (23), the rear side terminal surface and baffle (18) fixed connection of bin (12) are run through to the one end of sliding sleeve (24).
2. The material conveying and lifting device for bridge construction of bridge engineering according to claim 1, characterized in that: the bottom end face of base (1) fixed mounting has four universal wheels, the both sides end face fixed mounting of base (1) has hydraulic push rod, hydraulic push rod's bottom fixedly connected with balancing weight.
3. The material conveying and lifting device for bridge construction of bridge engineering according to claim 1, characterized in that: and a traction rope is fixedly connected to the winding roller (9), and the other end of the traction rope is fixedly connected with the top end of the mounting block (10) through a first pulley (4) and a second pulley (5).
4. The material conveying and lifting device for bridge construction of bridge engineering according to claim 1, characterized in that: two fixed rings (13) of equal fixedly connected with of both sides terminal surface of bin (12), four fixed ring (13) suit with four couple (11) respectively.
5. The material conveying and lifting device for bridge construction of bridge engineering according to claim 1, characterized in that: the bottom end of the T-shaped rod (16) is connected with the inner wall of the supporting block (14) in a sliding mode, a second spring (17) is sleeved on the top of the T-shaped rod (16), the top end of the second spring (17) is fixedly connected with the bottom end of the storage box (12), and the bottom end of the second spring (17) is fixedly connected with the top end of the supporting block (14).
6. The material conveying and lifting device for bridge construction of bridge engineering according to claim 1, characterized in that: the front side inner wall of bin (12) inner chamber is equipped with T type groove (19), the front side end face fixedly connected with T type piece (20) of baffle (18), T type piece (20) and T type groove (19) sliding connection, one side fixed mounting that T type piece (20) and T type groove (19) contacted has the ball, the rear side end face of bin (12) is equipped with spacing spout (22), sliding sleeve (24) and spacing spout (22) sliding connection.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120312539.6U CN215364608U (en) | 2021-02-03 | 2021-02-03 | Material conveying and lifting equipment for bridge construction of bridge engineering |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120312539.6U CN215364608U (en) | 2021-02-03 | 2021-02-03 | Material conveying and lifting equipment for bridge construction of bridge engineering |
Publications (1)
Publication Number | Publication Date |
---|---|
CN215364608U true CN215364608U (en) | 2021-12-31 |
Family
ID=79622358
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202120312539.6U Expired - Fee Related CN215364608U (en) | 2021-02-03 | 2021-02-03 | Material conveying and lifting equipment for bridge construction of bridge engineering |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN215364608U (en) |
-
2021
- 2021-02-03 CN CN202120312539.6U patent/CN215364608U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110254487B (en) | Pipeline placing vehicle for civil engineering | |
CN110834686B (en) | Method for vertically climbing steps by transport robot | |
CN215364608U (en) | Material conveying and lifting equipment for bridge construction of bridge engineering | |
CN216922091U (en) | Oil pumping unit convenient for balance adjustment | |
CN211986956U (en) | Basketball processing conveyer | |
CN106043395B (en) | One kind climbing building power-assisted trolley | |
CN214270073U (en) | Building engineering material lifting machine | |
CN107934411A (en) | A kind of compact lifts swing mechanism | |
CN216583985U (en) | Elevating gear for civil engineering | |
CN214828168U (en) | Rope breakage protection device for building construction elevator | |
CN113247758B (en) | Plate hoisting device for building construction and use method | |
CN211282425U (en) | Miniature flat belt conveyor line | |
CN206395774U (en) | A kind of mobile type electric construction lifting platform with roller | |
CN216235689U (en) | Civil engineering uses novel conveying equipment | |
CN221165741U (en) | Crane box counterweight | |
CN219730351U (en) | Lifting frame with good stability | |
CN220033914U (en) | Goods lifting machine with stable operation | |
CN220566031U (en) | Drilling tower | |
CN214733974U (en) | Loading and unloading device for electrical equipment | |
CN214834908U (en) | Discharge apparatus for construction | |
CN216235521U (en) | High maintenance elevating gear for building engineering of security | |
CN109018793A (en) | A kind of new energy automatic battery storage transportation system | |
CN215402712U (en) | A hoisting structure for high-order commodity circulation conveying equipment | |
CN212403289U (en) | Novel hoist engine hoist and mount subassembly | |
CN212924287U (en) | Lifting type feeding device for oil washing of bearing steel balls |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20211231 |