CN215318605U - Device for erecting power transmission line tower - Google Patents
Device for erecting power transmission line tower Download PDFInfo
- Publication number
- CN215318605U CN215318605U CN202121452144.2U CN202121452144U CN215318605U CN 215318605 U CN215318605 U CN 215318605U CN 202121452144 U CN202121452144 U CN 202121452144U CN 215318605 U CN215318605 U CN 215318605U
- Authority
- CN
- China
- Prior art keywords
- box
- power transmission
- transmission line
- line tower
- supporting rod
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Vibration Dampers (AREA)
Abstract
The utility model provides a device for erecting a power transmission line tower, which comprises: the shock absorption universal wheel is mounted on the lower surface of the base, the large tool placing box is mounted on the upper surface of the base, and the handle is mounted at the right end of the large tool placing box. Through setting up rope jack, make the rope of high-tension line tower erection usefulness can be packed up faster after using, promote work efficiency, avoid the rope to tie a knot simultaneously, the design of case, box, solid fixed ring and STB is placed to big instrument, make the multiple instrument of high-tension line tower erection needs can be placed by classification, promote the speed that constructor seeks specific instrument, promote constructor work efficiency, avoid the instrument to lose simultaneously.
Description
Technical Field
The utility model belongs to the field of electric power facility installation equipment, and particularly relates to a device for erecting a power transmission line tower.
Background
The high-voltage line generally refers to a power transmission line for transmitting voltage of more than 10KV (including 10KV), and the voltage grades of the high-voltage power transmission line in China are generally divided into: 35KV, 110KV, 220KV, 330KV, 500KV, 750KV, etc., when erecting high-voltage wires, a high-voltage wire tower must be erected in advance, the high-voltage wire tower is generally erected in the field, welding and assembling are performed on the field, and then a crane is used for erection, but a plurality of tools are needed for erecting the high-voltage wire tower in the field, the tools are various and different in type, a constructor usually consumes a long time for finding a specific tool, and meanwhile, when the erection work is completed, whether the tool falls down or not needs to be searched everywhere, the working efficiency of the constructor is reduced, and therefore, a device for erecting the power transmission line tower is needed urgently.
SUMMERY OF THE UTILITY MODEL
Aiming at the defects in the prior art, the utility model aims to provide a device for erecting a power transmission line tower, which solves the problems in the background technology.
The utility model is realized by the following technical scheme: an apparatus for power transmission line erection, comprising: the shock absorption universal wheel is mounted on the lower surface of the base, the large tool placing box is mounted on the upper surface of the base, the handle is mounted at the right end of the large tool placing box, the rope retracting and releasing mechanism is welded on the right side of the upper surface of the base and comprises a first supporting rod, a bearing mounting block, a spool, a crank and a second supporting rod;
the utility model discloses a set top box, including base upper surface, bearing installation piece, box upper surface, side box, fixed ring, top box, side box, storage tank, side box, top box lower extreme, the top box passes through the installation foot to be installed in the box, the storage tank sets up inside the top box.
As a preferred embodiment, the damping universal wheel is an inflatable wheel, the damping universal wheel is provided with four damping universal wheels, the four damping universal wheels are all provided with mechanical brake structures, and damping springs are arranged at the upper ends of the damping universal wheels.
As a preferred embodiment, the push-pull drawer is movably installed inside the large tool placing box, the handle is installed at the right end of the push-pull drawer, two layers of plastic plates are placed inside the push-pull drawer, and the upper surfaces of the plastic plates are provided with corresponding large tool placing grooves.
As a preferred embodiment, four drawers are installed inside the box body, the specifications of the four drawers are the same, a handle is arranged on the box door, and a locking buckle is installed on the box door.
As a preferred embodiment, a plurality of hooks are mounted on the lower surface of the fixing ring, a cross rod is arranged in the middle of the fixing ring, the connecting rod is arranged at the lower end of the cross rod, the fixing ring is mounted at the upper end of the box body through the connecting rod, four fixing holes are formed in the upper surface of the cross rod, and the top box is mounted on the upper surface of the cross rod through mounting feet and fixing holes.
As a preferred embodiment, the first support rod and the second support rod have the same specification, two bearing installation blocks are provided, and a ball bearing is installed in each of the two bearing installation blocks.
After the technical scheme is adopted, the utility model has the beneficial effects that: through setting up rope jack, make the rope of high-tension line tower erection usefulness can be packed up faster after using, promote work efficiency, avoid the rope to tie a knot simultaneously, the design of case, box, solid fixed ring and STB is placed to big instrument, make the multiple instrument of high-tension line tower erection needs can be placed by classification, promote the speed that constructor seeks specific instrument, promote constructor work efficiency, avoid the instrument to lose simultaneously.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a schematic view of the overall structure of a device for erecting a power transmission line tower according to the present invention.
Fig. 2 is a schematic view of a rope retraction mechanism for a power transmission line tower erection device according to the present invention.
Fig. 3 is a schematic diagram of a top box for a power transmission line tower erection device according to the present invention.
In the figure, 1-damping universal wheel, 2-base, 3-large tool placing box, 4-box door, 5-box body, 6-drawer, 7-hook, 8-fixing ring, 9-top box, 10-side box, 11-rope retracting mechanism, 12-handle, 13-supporting rod I, 14-bearing mounting block, 15-spool, 16-crank, 17-supporting rod II, 18-mounting foot and 19-storage groove.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1 to 3, the present invention provides a technical solution: an apparatus for power transmission line erection, comprising: the tool storage box comprises a damping universal wheel 1, a base 2, a large tool storage box 3, a box door 4, a box body 5, a drawer 6, a fixing ring 8, a top box 9, a side box 10 and a rope retracting mechanism 11, wherein the damping universal wheel 1 is installed on the lower surface of the base 2, the large tool storage box 3 is installed on the upper surface of the base 2, a handle 12 is installed at the right end of the large tool storage box 3, the rope retracting mechanism 11 is welded on the right side of the upper surface of the base 2, and the rope retracting mechanism 11 comprises a first support rod 13, a bearing installation block 14, a spool 15, a crank 16 and a second support rod 17;
the utility model discloses a set top box, including base 2 upper surface right side axle symmetry welding have bracing piece one 13, bracing piece two 17, bearing installation piece 14 is installed respectively at bracing piece one 13, bracing piece two 17 upper ends, install I-shaped wheel 15 between bracing piece one 13 upper ends and the bracing piece two 17 upper ends, crank 16 installs at the 15 rear ends of I-shaped wheel, 3 upper surface left sides welding of big instrument placement box has box 5, 5 front surfaces of box articulate has chamber door 4, 6 movable mounting of drawer are inside box 5, 5 lower extreme right surfaces of box, the left surface has welded side box 10 respectively, box 5 upper end is installed solid fixed ring 8, gu 8 lower surface mounting of fixed ring has couple 7, STB 9 movable mounting is in box 5 top, STB 9 lower extreme is equipped with installation foot 18, STB 9 installs in box 5 top through installation foot 18, storage tank 19 sets up inside STB 9.
Shock attenuation universal wheel 1 is a pneumatic wheel, and shock attenuation universal wheel 1 is equipped with four, and all installs mechanical brake structure on four shock attenuation universal wheels 1, and damping spring installs in 1 upper ends of shock attenuation universal wheel for whole device can normally advance in the field, can not be because of the unable gos forward of topography.
6 movable mounting of push-and-pull drawer is inside 3 cases are placed to big instrument, and the handle 12 is installed at 6 right-hand members of push-and-pull drawer, and two-layer plastic slab has been placed to 6 inside of push-and-pull drawer, and the plastic slab upper surface is equipped with the big instrument of correspondence and places the recess for deposit the mounting tool of great volume, avoid taking place between the instrument and collide with.
Four drawers 6 are arranged inside the box body 5, the specifications of the four drawers 6 are the same, a handle is arranged on the box door 4, and the locking buckle is arranged on the box door 4 and used for placing various small-sized installation tools.
The lower surface of the fixing ring 8 is provided with a plurality of hooks 7, the middle of the fixing ring 8 is provided with a cross rod, the connecting rod is arranged at the middle lower end of the cross rod, the fixing ring 8 is arranged at the upper end of the box body 5 through the connecting rod, the upper surface of the cross rod is provided with four fixing holes, and the top box 9 is arranged on the upper surface of the cross rod through the mounting feet 18 and the fixing holes and used for hanging a high-voltage wire tower to erect a common tool and is convenient to take.
The same with two specifications of support of bracing piece 13, bearing installation piece 14 is equipped with two, and all installs a ball bearing in two bearing installation pieces 14 for collect the rope, promote work efficiency.
As an embodiment of the present invention: utilize shock attenuation universal wheel 1 to remove whole device to appointed operating position after, with the locking of shock attenuation universal wheel 1, make whole device fix in situ, the instrument that needs is erect according to the high-voltage line tower afterwards, place case 3 and drawer 6 interior taking out from big instrument with instrument commonly used, in the side box 10 is placed to great instrument, less and the instrument that can hang is placed on couple 7, place the less instrument that can not hang in the top box 9, thus, be convenient for constructor selects suitable specific instrument, promote high-voltage line tower and erect efficiency, when needs change instrument, place original position with the instrument that gets off according to original position, prevent that the instrument from losing, the setting of rope jack 11, make the rope of high-voltage line tower usefulness can be packed up after the use sooner, promote work efficiency, avoid the rope to tie a knot simultaneously.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the utility model, and any modifications, equivalents, improvements and the like that fall within the spirit and principle of the present invention are intended to be included therein.
Claims (6)
1. An apparatus for power transmission line erection, comprising: damping universal wheel, base, big instrument place case, chamber door, box, drawer, solid fixed ring, STB, side box and rope jack, its characterized in that: the damping universal wheel is mounted on the lower surface of the base, the large tool placing box is mounted on the upper surface of the base, a handle is mounted at the right end of the large tool placing box, a rope retracting and releasing mechanism is welded on the right side of the upper surface of the base and comprises a first supporting rod, a bearing mounting block, an I-shaped wheel, a crank and a second supporting rod;
the multifunctional top box is characterized in that a first supporting rod and a second supporting rod are symmetrically welded on the right side of the upper surface of the base in a two-axis mode, bearing installation blocks are arranged at the upper ends of the first supporting rod and the second supporting rod respectively, a spool is installed between the upper end of the first supporting rod and the upper end of the second supporting rod, a crank is installed at the rear end of the spool, a box body is welded on the left side of the upper surface of the large-sized tool placing box, a box door is hinged to the front surface of the box body, a drawer is movably installed inside the box body, side boxes are welded on the right surface and the left surface of the lower end of the box body respectively, a fixing ring is installed at the upper end of the box body, a hook is installed on the lower surface of the fixing ring, a top box is movably installed above the box body, installation feet are arranged at the lower end of the top box, and a storage groove is formed in the top box.
2. A device for erecting a power transmission line tower according to claim 1, wherein: the shock attenuation universal wheel is one kind and aerifys the wheel, the shock attenuation universal wheel is equipped with four, and all installs mechanical brake structure on four shock attenuation universal wheels, damping spring is installed to shock attenuation universal wheel upper end.
3. A device for erecting a power transmission line tower according to claim 1, wherein: the large tool containing box is characterized in that a push-pull drawer is movably mounted inside the large tool containing box, a handle is mounted at the right end of the push-pull drawer, two layers of plastic plates are placed inside the push-pull drawer, and corresponding large tool containing grooves are formed in the upper surfaces of the plastic plates.
4. A device for erecting a power transmission line tower according to claim 1, wherein: four drawers are arranged inside the box body, the specifications of the four drawers are the same, a handle is arranged on the box door, and a locking buckle is arranged on the box door.
5. A device for erecting a power transmission line tower according to claim 1, wherein: the lower surface of the fixing ring is provided with a plurality of hooks, a cross rod is arranged in the middle of the fixing ring, a connecting rod is arranged at the lower end of the middle of the cross rod, the fixing ring is installed at the upper end of the box body through the connecting rod, four fixing holes are formed in the upper surface of the cross rod, and the top box is installed on the upper surface of the cross rod through installing feet and fixing holes.
6. A device for erecting a power transmission line tower according to claim 1, wherein: the first support rod and the second support rod are the same in specification, the two bearing installation blocks are arranged, and the two bearing installation blocks are internally provided with a ball bearing.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121452144.2U CN215318605U (en) | 2021-06-29 | 2021-06-29 | Device for erecting power transmission line tower |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121452144.2U CN215318605U (en) | 2021-06-29 | 2021-06-29 | Device for erecting power transmission line tower |
Publications (1)
Publication Number | Publication Date |
---|---|
CN215318605U true CN215318605U (en) | 2021-12-28 |
Family
ID=79562649
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202121452144.2U Active CN215318605U (en) | 2021-06-29 | 2021-06-29 | Device for erecting power transmission line tower |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN215318605U (en) |
-
2021
- 2021-06-29 CN CN202121452144.2U patent/CN215318605U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN215318605U (en) | Device for erecting power transmission line tower | |
CN210053056U (en) | Switching station base | |
CN210468582U (en) | Low-voltage draw-out type switch cabinet | |
CN210768572U (en) | Maintenance ladder for maintaining power transformation operation equipment | |
CN210454868U (en) | Transformer substation operation and maintenance integrated system | |
CN103368091A (en) | Ground lead and vehicle for loading safety tools and devices | |
CN209668689U (en) | Shift trolley | |
CN215577504U (en) | Novel line warning for optical fiber communication device | |
CN209448331U (en) | Auxiliary device is used in a kind of repairing of power equipment | |
CN206486187U (en) | A kind of crane hook device | |
CN109941918A (en) | Shift trolley | |
CN215827317U (en) | Finished product storage mechanism for porous brick production | |
CN218334966U (en) | Transformer substation is with overhauing fortune dimension dolly | |
CN202997374U (en) | Substation maintenance calibration stand | |
CN220749871U (en) | Multifunctional movable lighting device | |
CN217087245U (en) | Power equipment convenient to maintain | |
CN214379946U (en) | Intensive closed high-insulation bus duct capable of being rapidly assembled and disassembled | |
CN213139636U (en) | Placer for mechanical equipment with shock-absorbing function | |
CN219006015U (en) | Relay protection box of transformer substation | |
CN218973611U (en) | Multi-weighing-table combined metering device | |
CN215415709U (en) | Detector for power distribution network fault positioning | |
CN219477372U (en) | Power distribution cabinet bottom support | |
CN217893992U (en) | Storage goods shelf for cylindrical articles | |
CN216638801U (en) | Emergent vehicular modularization hanging flower basket device | |
CN220233909U (en) | High tension switchgear convenient to remove |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |