CN215197999U - Adjustable pipeline paint high-efficiency squeegee - Google Patents

Adjustable pipeline paint high-efficiency squeegee Download PDF

Info

Publication number
CN215197999U
CN215197999U CN202121695284.2U CN202121695284U CN215197999U CN 215197999 U CN215197999 U CN 215197999U CN 202121695284 U CN202121695284 U CN 202121695284U CN 215197999 U CN215197999 U CN 215197999U
Authority
CN
China
Prior art keywords
rod
wire rope
mounting rod
mounting
installation pole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121695284.2U
Other languages
Chinese (zh)
Inventor
凌世俊
张健
严志彬
李秋晨
陈康强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Construction Equipment Installation Co ltd
Original Assignee
Zhejiang Construction Equipment Installation Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Construction Equipment Installation Co ltd filed Critical Zhejiang Construction Equipment Installation Co ltd
Priority to CN202121695284.2U priority Critical patent/CN215197999U/en
Application granted granted Critical
Publication of CN215197999U publication Critical patent/CN215197999U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Coating Apparatus (AREA)

Abstract

The application relates to an adjustable efficient pipeline paint squeegee, which comprises a long rod, a first mounting rod, a second mounting rod, a steel wire rope and a long-strip roller, wherein one end of the first mounting rod is arranged on the end part of the long rod, the other end of the second mounting rod is arranged on the end part of the long rod, the steel wire rope is arranged between the first mounting rod and the second mounting rod, and the long-strip roller is arranged on the steel wire rope; the first mounting rod and the second mounting rod are both arranged at the same end of the Changan, and a certain included angle is formed between the first mounting rod and the second mounting rod; one end of the steel wire rope penetrates through one end, far away from the long rod, of the first mounting rod, and the other end of the steel wire rope penetrates through one end, far away from the long rod, of the second mounting rod; the long strip roller is located between the first installation rod and the second installation rod, the long strip roller is sleeved on the outer portion of the steel wire rope, and the long strip roller is rotatably connected with the steel wire rope. This application has the effect that improves pipeline lateral wall japanning operating efficiency.

Description

Adjustable pipeline paint high-efficiency squeegee
Technical Field
The application relates to the field of pipeline painting equipment, in particular to an adjustable pipeline paint high-efficiency squeegee.
Background
The pipeline refers to a device for conveying gas, liquid or fluid with solid particles, the inner wall and the outer wall of the pipeline need to be subjected to rust prevention treatment, and the rust prevention of the outer wall of the pipeline is usually realized by adopting a painting mode.
At present, the outer wall of the pipeline is painted by manually holding the brush, the coating area of the brush is small, the painting operation efficiency is low, and therefore the pipeline paint high-efficiency squeegee capable of improving the painting work efficiency is needed to be provided.
SUMMERY OF THE UTILITY MODEL
In order to improve the efficiency of pipeline japanning operation, this application provides an adjustable pipeline paint high efficiency brush applicator.
The application provides a high-efficient brush applicator of adjustable pipeline paint adopts following technical scheme:
an adjustable efficient pipeline paint squeegee comprises a long rod, a first mounting rod, a second mounting rod, a steel wire rope and a strip roller, wherein one end of the first mounting rod is arranged at the end part of the long rod; the first mounting rod and the second mounting rod are both arranged at the same end of the Changan, and a certain included angle is formed between the first mounting rod and the second mounting rod; one end of the steel wire rope penetrates through one end, far away from the long rod, of the first mounting rod, and the other end of the steel wire rope penetrates through one end, far away from the long rod, of the second mounting rod; the rectangular cylinder is located between first installation pole and the second installation pole, rectangular cylinder cup joints in wire rope's outside, and rectangular cylinder rotates with wire rope to be connected.
Through adopting above-mentioned technical scheme, the stock is handed to operating personnel to support rectangular cylinder tightly on the pipeline lateral wall, the crooked and laminating pipeline lateral wall of rectangular cylinder, operating personnel drive stock makes rectangular cylinder remove along the pipeline lateral wall, because the area of contact of rectangular cylinder and pipeline lateral wall is great, so improved the efficiency of pipeline lateral wall japanning operation.
Optionally, the end of the steel wire rope penetrating through the first mounting rod and the end of the steel wire rope penetrating through the second mounting rod are both provided with a fixing piece for fixing the steel wire rope, the fixing piece comprises a fixing cylinder sleeved outside the steel wire rope and a fixing bolt vertically penetrating through the outside of the fixing cylinder, and one end of the fixing bolt penetrating through the fixing cylinder abuts against the outside of the steel wire rope.
Through adopting above-mentioned technical scheme for wire rope's both ends dismantlement formula is connected on first installation pole and second installation pole, can change the wire rope of different specifications and the rectangular cylinder of different specifications.
Optionally, a protection cylinder is arranged at one end, away from the long rod, of the first installation rod and one end, away from the long rod, of the second installation rod in a penetrating mode, one end of the steel wire rope penetrates through the protection cylinder on the first installation rod, and the other end of the steel wire rope penetrates through the protection cylinder on the second installation rod.
Through adopting above-mentioned technical scheme, reduce wire rope and cause the condition of damage to first installation pole and second installation pole in the course of the work.
Optionally, a spring is arranged between the protection cylinder and the fixing piece; the mounting is equipped with the mounting panel that is used for installing the spring near the one end of a protection section of thick bamboo, spring one end is fixed in on the mounting panel, the spring other end is fixed in on the protection section of thick bamboo keeps away from the one end terminal surface of rectangular cylinder.
Through adopting above-mentioned technical scheme for wire rope keeps the state of flare-outing, thereby makes rectangular cylinder support tightly on the lateral wall of pipeline all the time, and then has improved the quality of japanning work.
Optionally, the first mounting rod and the second mounting rod can be arranged in a telescopic manner; first installation pole and second installation pole all rotate with the stock and be connected, and be equipped with locking Assembly between first installation pole and the second installation pole.
Through adopting above-mentioned technical scheme, through the length of adjusting first installation pole and second installation pole and the contained angle of adjusting between first installation pole and the second installation pole to adapt to the pipeline of different specifications.
Optionally, the locking assembly includes a first locking rod, a second locking rod inserted into one end of the first locking rod, and a locking bolt penetrating through the outside of the first locking rod, one end of the first locking rod, which is far away from the second locking rod, is rotatably connected to the first mounting rod, one end of the second locking rod, which is far away from the first locking rod, is rotatably connected to the second mounting rod, and one end of the locking bolt, which penetrates through the first locking rod, abuts against the outer wall of the first locking rod.
Through adopting above-mentioned technical scheme, when screwing up the locking bolt, the relative position locking of first locking lever and second locking lever to the contained angle between first installation pole of locking and the second installation pole.
Optionally, the both ends of rectangular cylinder all are equipped with the locating part that is used for spacing rectangular cylinder, the locating part includes spacing section of thick bamboo and wears to locate the outside spacing bolt of spacing section of thick bamboo, wire rope sliding fit is followed to spacing section of thick bamboo, spacing bolt passes the one end of a spacing section of thick bamboo and supports tightly on wire rope's lateral wall.
Through adopting above-mentioned technical scheme, the locating part can be so that rectangular cylinder is located wire rope's centre department, reduces rectangular cylinder tip and touch first installation pole or second installation pole and influence the condition of rectangular cylinder normal rotation mopping.
Optionally, the long rod is arranged in a telescopic manner.
Through adopting above-mentioned technical scheme, can carry out the mopping to the pipeline of co-altitude not.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the stock is handed to operating personnel to support rectangular cylinder tightly on the pipeline lateral wall, the crooked pipeline lateral wall of laminating of rectangular cylinder, operating personnel drive stock makes rectangular cylinder remove along the pipeline lateral wall, because the area of contact of rectangular cylinder and pipeline lateral wall is great, so improved the efficiency of pipeline lateral wall japanning operation.
Drawings
FIG. 1 is a schematic diagram of the overall structure of an embodiment of the present application;
fig. 2 is a cross-sectional view of a fastener construction embodying the present application in an embodiment.
Description of reference numerals: 1. a long rod; 2. a first mounting bar; 21. a main rod; 22. a telescopic rod; 3. a second mounting bar; 4. a wire rope; 5. a sliver roller; 6. a fixing member; 61. a fixed cylinder; 611. fixing grooves; 62. fixing the bolt; 63. mounting a plate; 7. a protective cylinder; 8. a locking assembly; 81. a first locking lever; 82. a second locking lever; 83. a locking bolt; 9. a limiting member; 91. a limiting cylinder; 92; a limit bolt; 10. a spring.
Detailed Description
The present application is described in further detail below with reference to figures 1-2.
The embodiment of the application discloses an adjustable pipeline paint high efficiency squeegee. Referring to fig. 1, the adjustable pipe paint high-efficiency squeegee comprises a long rod 1, a first installation rod 2 and a second installation rod 3 which are rotatably connected to one end of the long rod 1, a steel wire rope 4 arranged between the first installation rod 2 and the second installation rod 3, and a strip roller 5 sleeved on the steel wire rope 4. Rectangular cylinder 5 and 4 normal running fit of wire rope, wire rope 4 and rectangular cylinder 5 all have certain flexibility, when applying paint with a brush, support rectangular cylinder 5 tightly on the lateral wall of pipeline, rectangular cylinder 5 and wire rope 4 are all crooked for rectangular cylinder 5 laminates in the lateral wall of pipeline, and rolls along the lateral wall of pipeline through 1 drive rectangular cylinder 5 of stock.
In the embodiment, the long rod 1 is divided into a first rod, a second rod and a third rod, the first rod is inserted into one end of the second rod, and the first rod is in sliding fit with the second rod and is fixed through a bolt; the second rod is inserted into one end of the third rod, and the second rod is in sliding fit with the third rod and is fixed through a bolt. The long rod 1 can be arranged in a telescopic mode, so that the long-strip roller 5 can brush pipelines with different heights.
A locking assembly 8 for locking an included angle between the first installation rod 2 and the second installation rod 3 is arranged between the first installation rod 2 and the second installation rod 3, the locking assembly 8 comprises a first locking rod 81 with one end rotatably connected to the first installation rod 2, a second installation rod 3 with one end rotatably connected to the second installation rod 3 and a locking bolt 83, and one end of the second installation rod 3 close to the first installation rod 2 is inserted into the first installation rod 2, so that the axes of the first installation rod 2 and the second installation rod 3 are on the same straight line. The locking bolt 83 is inserted into a side wall of one end of the first mounting rod 2 close to the second mounting rod 3, and the locking bolt 83 penetrates through one end of the first mounting rod 2 and abuts against a side wall of the second mounting rod 3.
The first mounting rod 2 and the second mounting rod 3 are arranged in a telescopic mode, and the first mounting rod 2 and the second mounting rod 3 are identical in structure. Taking the first installation rod 2 as an example, the first installation rod 2 comprises a main rod 21 with one end rotatably connected to the first rod and an expansion rod 22 inserted into the main rod 21 and far away from one end of the first rod, the expansion rod 22 is in sliding fit with the main rod 21, a bolt is arranged at one end of the main rod 21 close to the expansion rod 22 in a penetrating manner, and one end of the bolt penetrating through the main rod 21 abuts against the side wall of the expansion rod 22.
The length of the first installation rod 2 and the second installation rod 3 and the included angle between the first installation rod 2 and the second installation rod 3 are adjusted, so that the pipeline fixing device is suitable for pipelines with different specifications.
One end of the steel wire rope 4 penetrates through one end, far away from the first rod, of the first installation rod 2, and the other end of the steel wire rope 4 penetrates through one end, far away from the first rod, of the second installation rod 3. The one end that first pole was kept away from to first installation pole 2 and the one end that first pole was kept away from to second installation pole 3 all are equipped with a protection section of thick bamboo 7, and a wire rope 4 passes a protection section of thick bamboo 7 to the one end inner wall fillet setting that the protective sheath is close to rectangular cylinder 5. The protective cylinder 7 can reduce the abrasion of the steel wire rope 4 on the first mounting rod 2 and the second mounting rod 3 in the working process.
Referring to fig. 1 and 2, the two ends of the steel wire rope 4 have the same structure and the same members, for example, the steel wire rope 4 passes through one end of the second installation rod 3, the steel wire rope 4 passes through the protection barrel 7 on the telescopic rod 22 installed in the second installation, the fixing part 6 for fixing the end of the steel wire rope 4 is arranged at one end of the protection barrel 7 far away from the strip roller 5, the fixing part 6 comprises a fixing barrel 61 sleeved outside the steel wire rope 4, a mounting plate 63 arranged at one end of the fixing barrel 61 close to the protection barrel 7 and a fixing bolt 62 penetrating through the side wall of the fixing barrel 61, a fixing groove 611 is formed in the inner wall of the fixing barrel 61 corresponding to the position of the fixing bolt 62, and the fixing bolt 62 penetrates through one end of the fixing barrel 61 and abuts against the steel wire rope 4 at the bottom of the fixing groove 611.
A spring 10 is arranged between the mounting plate 63 and the protection cylinder 7, one end of the spring 10 is fixed on the mounting plate 63, and the other end of the spring 10 is fixed on the end face, close to the mounting plate 63, of the protection cylinder 7. The spring 10 makes the wire rope 4 between first installation pole 2 and the second installation pole 3 keep the state of flare-outing, and on rectangular cylinder 5 brushed the pipeline lateral wall, rectangular cylinder 5 can support tightly in the pipeline lateral wall all the time, has improved the mopping quality.
In order to limit the strip roller 5 in the middle of the first installation rod 2 and the second installation rod 3, the two ends of the strip roller 5 are both provided with a limiting part 9, the limiting part 9 is sleeved on the steel wire rope 4, and the limiting part 9 is in sliding fit with the steel wire rope 4. The limiting member 9 includes a limiting cylinder 91 and a limiting bolt 92 penetrating the limiting cylinder 91, and one end of the limiting bolt 92 penetrating the limiting cylinder 91 is abutted against the side wall of the steel wire rope 4.
The implementation principle of the embodiment of the application is as follows: according to the pipeline of different specifications, adjust the contained angle between first installation pole 2 and the second installation pole 3 and adjust the length of first installation pole 2 and second installation pole 3 to adapt to the pipeline of different diameters, select the rectangular cylinder 5 of suitable length, cup joint rectangular cylinder 5 in wire rope 4's outside, and spacing rectangular cylinder 5 in wire rope 4's middle part through locating part 9. And sequentially enabling two ends of the steel wire rope 4 to pass through the protective cylinder 7, the spring 10, the mounting plate 63 and the locking cylinder, straightening the steel wire rope 4, and finally screwing the fixing bolt 62 to lock the two ends of the steel wire rope 4.
Stock 1 is handed to operating personnel, with 5 butt of rectangular cylinder on the lateral wall of pipeline to make 5 crooked laminatings of rectangular cylinder in the pipeline lateral wall, make 5 edge pipeline lateral walls of rectangular cylinder to roll through stock 1 at last and apply paint with a brush.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. The utility model provides an adjustable pipeline paint high efficiency brush applicator which characterized in that: the steel wire rope winding machine comprises a long rod (1), a first mounting rod (2) with one end arranged on the end part of the long rod (1), a second mounting rod (3) with one end arranged on the end part of the long rod (1), a steel wire rope (4) arranged between the first mounting rod (2) and the second mounting rod (3), and a strip roller (5) arranged on the steel wire rope (4); the first mounting rod (2) and the second mounting rod (3) are both arranged at the same end of the Changan, and a certain included angle is formed between the first mounting rod (2) and the second mounting rod (3); one end of the steel wire rope (4) penetrates through one end, far away from the long rod (1), of the first mounting rod (2), and the other end of the steel wire rope (4) penetrates through one end, far away from the long rod (1), of the second mounting rod (3); rectangular cylinder (5) are located between first installation pole (2) and second installation pole (3), rectangular cylinder (5) cup joint in the outside of wire rope (4), and rectangular cylinder (5) rotate with wire rope (4) and be connected.
2. The adjustable pipe paint high efficiency squeegee as recited in claim 1 wherein: wire rope (4) pass the one end of first installation pole (2) and the one end that passes second installation pole (3) all is equipped with mounting (6) that are used for fixed wire rope (4), mounting (6) are including cup jointing in the outside solid fixed cylinder (61) of wire rope (4) and wearing to locate solid fixed cylinder (61) outside fixing bolt (62) perpendicularly, fixing bolt (62) pass the one end of solid fixed cylinder (61) and support tightly in the outside of wire rope (4).
3. The adjustable pipe paint high efficiency squeegee as recited in claim 2 wherein: the one end that stock (1) was kept away from in first installation pole (2) and the one end that stock (1) was kept away from in second installation pole (3) all wear to be equipped with a protection section of thick bamboo (7), a protection section of thick bamboo (7) on first installation pole (2) are passed to the one end of wire rope (4), a protection section of thick bamboo (7) on second installation pole (3) are passed to the other end of wire rope (4).
4. The adjustable pipe paint high efficiency squeegee as recited in claim 3 wherein: a spring (10) is arranged between the protection cylinder (7) and the fixing piece (6); the one end that mounting (6) are close to a protection section of thick bamboo (7) is equipped with mounting panel (63) that are used for installing spring (10), spring (10) one end is fixed in on mounting panel (63), spring (10) other end is fixed in a protection section of thick bamboo (7) and keeps away from on the one end terminal surface of rectangular cylinder (5).
5. The adjustable pipe paint high efficiency squeegee as recited in claim 1 wherein: the first mounting rod (2) and the second mounting rod (3) can be arranged in a telescopic manner; first installation pole (2) and second installation pole (3) all rotate with stock (1) and are connected, and are equipped with locking Assembly (8) between first installation pole (2) and second installation pole (3).
6. The adjustable pipe paint high efficiency squeegee as recited in claim 5 wherein: the locking assembly (8) comprises a first locking rod (81), a second locking rod (82) inserted into one end of the first locking rod (81) and a locking bolt (83) penetrating through the outer portion of the first locking rod (81), one end, far away from the second locking rod (82), of the first locking rod (81) is rotatably connected onto the first mounting rod (2), one end, far away from the first locking rod (81), of the second locking rod (82) is rotatably connected onto the second mounting rod (3), and one end, penetrating through the first locking rod (81), of the locking bolt (83) abuts against the outer wall of the first locking rod (81).
7. The adjustable pipe paint high efficiency squeegee as recited in claim 1 wherein: both ends of rectangular cylinder (5) all are equipped with locating part (9) that are used for spacing rectangular cylinder (5), locating part (9) are including spacing section of thick bamboo (91) and wear to locate spacing bolt (92) of spacing section of thick bamboo (91) outside, wire rope (4) sliding fit is followed in spacing section of thick bamboo (91), spacing bolt (92) pass the one end of spacing section of thick bamboo (91) and support tightly on the lateral wall of wire rope (4).
8. The adjustable pipe paint high efficiency squeegee as recited in claim 1 wherein: the long rod (1) is arranged in a telescopic manner.
CN202121695284.2U 2021-07-24 2021-07-24 Adjustable pipeline paint high-efficiency squeegee Active CN215197999U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121695284.2U CN215197999U (en) 2021-07-24 2021-07-24 Adjustable pipeline paint high-efficiency squeegee

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121695284.2U CN215197999U (en) 2021-07-24 2021-07-24 Adjustable pipeline paint high-efficiency squeegee

Publications (1)

Publication Number Publication Date
CN215197999U true CN215197999U (en) 2021-12-17

Family

ID=79428506

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121695284.2U Active CN215197999U (en) 2021-07-24 2021-07-24 Adjustable pipeline paint high-efficiency squeegee

Country Status (1)

Country Link
CN (1) CN215197999U (en)

Similar Documents

Publication Publication Date Title
CN215197999U (en) Adjustable pipeline paint high-efficiency squeegee
CN210697461U (en) Window with automatic cleaning device
CN212284708U (en) Suction coating corrosion prevention device for inner surface of pipe for oil exploitation
CN110375152A (en) A kind of petroleum pipeline corrosion-resistant thermal insulation processing method
CN111871711A (en) Adjustable oil coating machine for connecting piece of conveying pipeline
CN210585527U (en) Horizontal semi-automatic spraying machine
CN109499809B (en) Resin tile color roll coating equipment
CN215314839U (en) Steel support alignment device convenient to rust cleaning
CN209888266U (en) Paperboard gluing device
CN212092920U (en) Spraying device of pipeline anticorrosive paint
CN209244190U (en) A kind of adjustable type spraying rotary broom
CN106622741A (en) Spiral multisurface paint spraying device
CN216587539U (en) Portable painting tool for painting gap between pipeline and wall surface
CN217094204U (en) Straight thread sleeve rust prevention device
CN216131480U (en) Pipeline installation guider
CN217896775U (en) Pre-buried channel with novel high corrosion-resistant protective coating
CN215088548U (en) Metal pipeline rotating and clamping device
CN218029179U (en) Deviation rectifying and reinforcing device for historic building construction
CN212952447U (en) Device of making an uproar falls in roller way baffle
CN218079721U (en) Aluminum plate face correcting unit
CN217190656U (en) Fixing device for automobile hub coating
CN218742658U (en) Rail wheel spraying hook with shaft hole protection
CN212514179U (en) Special pipe anticorrosive paint spraying of oil is with scribbling a detection device
CN216406595U (en) Anti-corrosion protection device
CN218801560U (en) Sand blasting and rust removing device used in pipeline

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant