CN215166664U - Waterproof construction of construction joint node - Google Patents

Waterproof construction of construction joint node Download PDF

Info

Publication number
CN215166664U
CN215166664U CN202120536675.3U CN202120536675U CN215166664U CN 215166664 U CN215166664 U CN 215166664U CN 202120536675 U CN202120536675 U CN 202120536675U CN 215166664 U CN215166664 U CN 215166664U
Authority
CN
China
Prior art keywords
wall body
construction joint
construction
wall
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202120536675.3U
Other languages
Chinese (zh)
Inventor
赵小朋
陈志通
王海舰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Runya Huanyu Construction Engineering Co ltd
Original Assignee
Beijing Runya Huanyu Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Runya Huanyu Construction Engineering Co ltd filed Critical Beijing Runya Huanyu Construction Engineering Co ltd
Priority to CN202120536675.3U priority Critical patent/CN215166664U/en
Application granted granted Critical
Publication of CN215166664U publication Critical patent/CN215166664U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Building Environments (AREA)

Abstract

The utility model relates to a waterproof construction of construction joint node relates to the field of construction structure, and it is including setting up the water-swelling rubber strip between the first wall body of prior completion pouring and the second wall body of later completion pouring, first wall body has seted up closed annular caulking groove on the contact surface with the second wall body, and water-swelling rubber strip is located the caulking groove, is provided with the mounting plate on the construction joint department wall of first wall body and second wall body jointly. The application has the effect of reducing the possibility of water leakage at the construction joint.

Description

Waterproof construction of construction joint node
Technical Field
The application relates to the field of construction structures, especially relate to a waterproof construction of construction joint node.
Background
A construction joint refers to a joint formed between concrete poured in advance and then poured in a concrete pouring process. Specifically, the concrete is poured firstly for a period exceeding the initial setting time, and a joint surface exists between the concrete poured later, and the joint surface is called a construction joint. During construction, a construction joint is an inevitable construction structure. Construction joints cause the building to have the hidden trouble of seeper leakage, and further cause more other bad problems.
SUMMERY OF THE UTILITY MODEL
In order to reduce the possibility that construction joint department leaked, this application provides a waterproof construction of construction joint node.
The application provides a pair of waterproof construction of construction joint node adopts following technical scheme:
the utility model provides a waterproof construction of construction joint node, including setting up the water-swelling rubber strip between the first wall body that prior completion was pour and the second wall body that the back was accomplished and is pour, first wall body has seted up closed annular caulking groove on the contact surface with the second wall body, water-swelling rubber strip is located in the caulking groove, be provided with the mounting plate on the construction joint department wall of first wall body and second wall body jointly.
Through adopting above-mentioned technical scheme, the water-swelling rubber strip that meets between lieing in first wall body and the second wall body meets water inflation, fill the construction joint, closed loop's caulking groove makes and meets water inflation rubber strip also form closed loop, double-deck stagnant water structure has been formed, the sealing action to the construction joint has been strengthened, the caulking groove has left the inflation space of reserving for meeting water inflation rubber strip, avoid meeting water inflation rubber strip to influence the relation of connection between first wall body and the second wall body in the inflation process as far as possible, and simultaneously, the mounting plate has further strengthened the relation of connection of first wall body and second wall body, thereby the compactness of being connected between first wall body and the second wall body when having guaranteed to meet water inflation rubber strip inflation as far as possible, the possibility of first wall body and second wall body construction joint department infiltration has been reduced.
Optionally, the first wall body is provided with a plurality of grooves on a contact surface with the second wall body.
Through adopting above-mentioned technical scheme, because first wall body pours earlier than the second wall body, when the second wall body was pour, the concrete that is used for pouring the second wall body gets into in the recess, after the second wall body initial set, this partial concrete initial set back for form the arch through recess and first wall body gomphosis on the second wall body, strengthened the compactness of being connected between first wall body and the second wall body, reduced the possibility that construction joint department leaked as far as possible.
Optionally, the mounting plate is provided with a plurality ofly, and is a plurality of the mounting plate is arranged along the length direction of the construction joint between first wall body and the second wall equidistant.
Through adopting above-mentioned technical scheme, the compactness of being connected between first wall body and the second wall body has further been strengthened to a plurality of mounting plates.
Optionally, a cement mortar layer is arranged on the wall surface at the construction joint of the first wall body and the second wall body, and the cement mortar layer is located on one side, close to the first wall body, of the fastening plate.
By adopting the technical scheme, after the first wall body and the second wall body are formed, cement mortar is coated at the construction joint, so that the construction joint is shielded from the outside, and the hidden danger of water leakage at the construction joint is further reduced.
Optionally, a composite geomembrane layer is arranged on one side of the cement mortar layer, which is close to the first wall body and the second wall body.
By adopting the technical scheme, before the cement mortar layer is coated, the composite geomembrane is attached to the construction joint of the first wall body and the second wall body to form the composite geomembrane layer, and then the cement mortar layer is coated on one side of the composite geomembrane layer far away from the wall body, so that the composite geomembrane has good water absorption performance, and the possibility of water seepage at the construction joint is reduced as much as possible.
Optionally, the surface of the cement mortar layer far away from the construction joint is coated with an anhydrous copper sulfate layer, and the anhydrous copper sulfate layer is located between two adjacent fastening plates.
By adopting the technical scheme, when the water seepage is caused at the construction joint, the anhydrous copper sulfate layer turns blue, and the warning effect on building users is achieved.
Optionally, all be provided with on the both sides wall body of first wall body and second wall body construction joint department the mounting plate, two that the face is relative wear to be equipped with the double-screw bolt on the mounting plate jointly, be equipped with the nut on the double-screw bolt.
Through adopting above-mentioned technical scheme, press from both sides first wall body and second wall body tightly through double-screw bolt, nut and mounting plate, strengthened the compactness that first wall body and second wall body are connected.
Optionally, the same fastening plate is provided with a plurality of studs, and the studs are arranged on two sides of the construction joint and penetrate through the first wall body or the second wall body.
Through adopting above-mentioned technical scheme, the double-screw bolt of split construction joint both sides plays the taut effect to first wall body and second wall body from the both sides of construction joint when installing the mounting plate on first wall body and second wall body, has further strengthened the compactness of first wall body and second wall body connection.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the closed-loop caulking groove enables the water-swellable rubber strip to form a closed loop, the sealing effect on the construction joint is enhanced, and the fastening plate further enhances the connection relation between the first wall body and the second wall body, so that the connection tightness between the first wall body and the second wall body is ensured as much as possible when the water-swellable rubber strip is swelled, and the possibility of water seepage at the construction joint of the first wall body and the second wall body is reduced;
2. after the second wall body is initially set, the second wall body is provided with the bulge embedded with the first wall body through the groove, so that the connection tightness between the first wall body and the second wall body is enhanced, and the possibility of water leakage at the construction joint is reduced as much as possible;
3. after the first wall body and the second wall body are formed, cement mortar is coated at the construction joint, so that the construction joint is shielded from the outside, and the hidden danger of water leakage at the construction joint is further reduced.
Drawings
FIG. 1 is a schematic diagram of the overall structure of an embodiment of the present application;
FIG. 2 is a schematic illustration of a partial explosion of an embodiment of the present application;
fig. 3 is a partially enlarged schematic view of a portion a in fig. 1.
Reference numerals: 1. a water-swellable rubber strip; 2. caulking grooves; 3. a fastening plate; 4. a groove; 5. a bump; 6. a cement mortar layer; 7. compounding a geomembrane layer; 8. a stud; 9. a nut; 10. a first wall; 11. and a second wall.
Detailed Description
The present application is described in further detail below with reference to figures 1-3.
The embodiment of the application discloses waterproof construction of construction joint node. Referring to fig. 1 and 2, the waterproof structure of the construction joint node includes a water-swellable rubber strip 1 disposed between a first wall 10 on which casting is performed first and a second wall 11 on which casting is performed later, and a fastening plate 3 for reinforcing a connection relationship between the first wall 10 and the second wall 11.
After the first wall 10 is poured, a closed ring-shaped caulking groove 2 is formed in the wall surface of the first wall 10, which is required to be in contact with a new wall, namely the second wall 11, and then the water-swelling rubber strips 1 are arranged in the caulking groove 2. And a plurality of grooves 4 are formed on the peripheral sides of the outer ring and the inner ring of the caulking groove 2, and then the second wall body 11 is poured.
In the pouring process, the concrete for pouring the second wall body 11 enters the groove 4, so that the formed second wall body 11 forms the convex block 5 embedded into the groove 4 on the surface abutted to the first wall body 10, and the connection tightness between the first wall body 10 and the second wall body 11 is enhanced.
Meanwhile, after the concrete is contacted with the water-swelling rubber strip 1, the water-swelling rubber strip 1 swells, the second wall body 11 which is not solidified and the caulking groove 2 reserve a space for the swelling of the water-swelling rubber strip 1, and the influence on the connection relation between the first wall body 10 and the second wall body 11 in the swelling process of the water-swelling rubber strip 1 is avoided as much as possible.
Referring to fig. 1 and 3, after the second wall 11 is initially set, the composite geomembrane layer 7 is attached to the first wall 10 and the second wall 11 near the construction joint, and then the cement mortar layer 6 is coated outside the composite geomembrane layer 7.
The composite geomembrane has good water absorption, when water seeps at the construction joint, the composite geomembrane can absorb the seeped water, and meanwhile, the cement mortar layer 6 plays a role in sealing the construction joint, so that the possibility of water seepage of the wall surface is further reduced.
Because meet water inflation when water inflation rubber strip 1 seeps water in construction joint department, in order to avoid meeting water inflation rubber strip 1 when the inflation, influence the compactness of being connected between first wall 10 and the second wall 11, be provided with a plurality of mounting plates 3 on first wall 10 and the second wall 11 jointly. The two sides of the first wall 10 and the second wall 11 in the length direction of the construction joint are both provided with fastening plates 3, and the fastening plates 3 are arranged at equal intervals along the length direction of the construction joint.
Referring to fig. 1, wear to be equipped with many double-screw bolts 8 jointly on two mounting plates 3 that the face is relative, threaded connection has two nuts 9 on the single double-screw bolt 8, many double-screw bolts 8 divide the both sides of arranging construction joint length direction, double-screw bolt 8 pierces through first wall body 10 or second wall body 11, double-screw bolt 8, nut 9 is taut with first wall body 10 and second wall body 11 with mounting plate 3 cooperation, and make the connection of first wall body 10 and second wall body 11 more inseparable, further avoided the water stop rod of water-swelling when the inflation, produce the influence to the connectivity of first wall body 10 and second wall body 11.
After all the constructions are finished, the surface of the cement mortar layer 6 between the fastening plates 3 is coated with anhydrous copper sulfate solution to form an anhydrous copper sulfate layer, and the anhydrous copper sulfate turns blue when meeting water, thereby playing a role of warning when water seeps at the construction joint.
The implementation principle of the waterproof structure of the construction joint node in the embodiment of the application is as follows: be located 1 water inflation of water-swelling rubber strip between first wall body 10 and the second wall body 11, fill the construction joint, closed loop caulking groove 2 makes water-swelling rubber strip 1 also form closed loop, the sealing effect to the construction joint has been strengthened, caulking groove 2 has left the inflation space of reservation for water-swelling rubber strip 1, avoid water-swelling rubber strip 1 to influence the relation of connection between first wall body 10 and the second wall body 11 at the inflation in-process as far as possible, and simultaneously, mounting plate 3 has further strengthened the relation of connection of first wall body 10 and second wall body 11, thereby the compactness of being connected between first wall body 10 and the second wall body 11 when having guaranteed water-swelling rubber strip 1 inflation as far as possible.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. The utility model provides a waterproof construction of construction joint node which characterized in that: including setting up water-swelling rubber strip (1) between first wall body (10) that accomplish earlier and the second wall body (11) that the back was accomplished and was pour, seted up closed annular caulking groove (2) on the contact surface of first wall body (10) and second wall body (11), water-swelling rubber strip (1) is located in caulking groove (2), be provided with mounting plate (3) on the construction joint department wall of first wall body (10) and second wall body (11) jointly.
2. The waterproof structure of a construction joint node of claim 1, wherein: a plurality of grooves (4) are formed in the contact surface of the first wall body (10) and the second wall body (11).
3. The waterproof structure of a construction joint node of claim 2, wherein: the fastening plate (3) is provided with a plurality of, and is a plurality of the fastening plate (3) is arranged along the length direction of the construction joint between the first wall body (10) and the second wall body (11) at equal intervals.
4. A waterproof structure of a construction joint node according to claim 3, wherein: be provided with cement mortar layer (6) jointly on the construction joint department wall of first wall body (10) and second wall body (11), cement mortar layer (6) are located one side that mounting plate (3) are close to first wall body (10).
5. The waterproof structure of a construction joint node of claim 4, wherein: and a composite geomembrane layer (7) is arranged on one side of the cement mortar layer (6) close to the first wall body (10) and the second wall body (11).
6. The waterproof structure of a construction joint node of claim 5, wherein: the surface, far away from the construction joint, of the cement mortar layer (6) is coated with an anhydrous copper sulfate layer, and the anhydrous copper sulfate layer is located between every two adjacent fastening plates (3).
7. The waterproof structure of a construction joint node of claim 6, wherein: all be provided with on the both sides wall body of first wall body (10) and second wall body (11) construction joint department mounting plate (3), the face is relative two wear to be equipped with double-screw bolt (8) jointly on mounting plate (3), be equipped with nut (9) on double-screw bolt (8).
8. The waterproof structure of a construction joint node of claim 7, wherein: and the fastening plate (3) is provided with a plurality of studs (8) and a plurality of studs (8) which are arranged on two sides of the construction joint and penetrate through the first wall body (10) or the second wall body (11).
CN202120536675.3U 2021-03-15 2021-03-15 Waterproof construction of construction joint node Expired - Fee Related CN215166664U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120536675.3U CN215166664U (en) 2021-03-15 2021-03-15 Waterproof construction of construction joint node

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120536675.3U CN215166664U (en) 2021-03-15 2021-03-15 Waterproof construction of construction joint node

Publications (1)

Publication Number Publication Date
CN215166664U true CN215166664U (en) 2021-12-14

Family

ID=79415796

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120536675.3U Expired - Fee Related CN215166664U (en) 2021-03-15 2021-03-15 Waterproof construction of construction joint node

Country Status (1)

Country Link
CN (1) CN215166664U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114319711A (en) * 2021-12-30 2022-04-12 欧安格 Glass fiber net check cloth waterproof gypsum board

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114319711A (en) * 2021-12-30 2022-04-12 欧安格 Glass fiber net check cloth waterproof gypsum board

Similar Documents

Publication Publication Date Title
CN215166664U (en) Waterproof construction of construction joint node
CN108385731A (en) A kind of improved underground-structure deformation joint water proof structure
CN205742504U (en) A kind of intensive construction joint of ultra-large type cistern
CN210049292U (en) Advanced water stop pouring belt structure for building
CN210621627U (en) A structure for reservoir asphalt concrete core cracking treatment
CN109183847B (en) Underground prefabricated pipe gallery
CN214143829U (en) Drainable externally-attached water stop with pasting timeliness
CN206143936U (en) Basement outer wall post -cast strip shutoff waterproof construction
CN210887323U (en) Connect and build engineering underground structure construction joint watertight fittings
CN209568552U (en) A kind of concrete joint water stop structure
CN218148467U (en) Cast-in-place concrete cut-off wall and pore-creating cut-off wall connection structure
CN217078875U (en) Basement post-cast strip seepage prevention structure
CN219887647U (en) Cast-in-situ shear wall with anti-leakage through-wall bolt structure
CN217400097U (en) Three-section post-pouring windowsill coping structure
CN212271252U (en) Interface waterproof construction of new and old concrete
CN217379300U (en) Concrete post-cast strip waterproof construction
CN215906860U (en) Post-pouring belt of foundation slab and beam
CN216766311U (en) Assembled concrete building post-cast strip stagnant water structure
CN215857840U (en) Underground combined mechanism
CN217871055U (en) Novel plugging device for aluminum die bolt hole
CN212867583U (en) Waterproof structure for thin-wall two-lining deformation joint of sewage tunnel
CN212154799U (en) Two lining movement joint structure of shield tunnel
CN220318822U (en) Waterproof concrete outer wall post-pouring strip structure
CN217204705U (en) Easily install rubber waterstop
CN112575743B (en) Geomembrane anchor seal structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211214