CN215107703U - Clean operating room floor mounting structure - Google Patents

Clean operating room floor mounting structure Download PDF

Info

Publication number
CN215107703U
CN215107703U CN202120848595.1U CN202120848595U CN215107703U CN 215107703 U CN215107703 U CN 215107703U CN 202120848595 U CN202120848595 U CN 202120848595U CN 215107703 U CN215107703 U CN 215107703U
Authority
CN
China
Prior art keywords
floor
operating room
clean operating
mounting structure
vertical
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120848595.1U
Other languages
Chinese (zh)
Inventor
还文高
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Shengshi Huawei Decoration Design Engineering Co ltd
Original Assignee
Jiangsu Shengshi Huawei Engineering Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Shengshi Huawei Engineering Technology Co ltd filed Critical Jiangsu Shengshi Huawei Engineering Technology Co ltd
Priority to CN202120848595.1U priority Critical patent/CN215107703U/en
Application granted granted Critical
Publication of CN215107703U publication Critical patent/CN215107703U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

In order to solve because the site environment of building site is more complicated abominable, carry out secondary to the product at the scene with man-hour, whole quality level is difficult to the problem that obtains the assurance, the utility model provides a clean operating room floor mounting structure, the floor structure can all be accomplished at the producer is inside, only need on the scene according to the installation of modularization technology can, the construction environment of scene has been guaranteed, thereby the effectual whole quality level who guarantees the clean operating room, the dust is hidden to the setting of floor turn portion, connection structure makes things convenient for the dismouting, the setting up of silica gel sealing layer makes the operating room sealed effectual, the cleanliness factor is stable, the gypsum board has the effect that keeps warm and strengthen floor intensity with the accordant connection of electrolysis steel sheet structure.

Description

Clean operating room floor mounting structure
Technical Field
The utility model relates to a clean operating room technical field, concretely relates to clean operating room floor mounting structure.
Background
The clean operating room adopts different management and control of degree to microbial contamination through the clean technique of air, and the concentration of low bacterial count and low anesthetic gas of strict control for the air cleanliness factor in the space environment is suitable for the requirement of all kinds of operations, thereby the effectual cleanliness that guarantees the operating room improves the operation quality, realizes the minimizing of medical waste simultaneously.
At present, the construction process of purifying the operating room can be generally classified into two types, one type is a field assembling type, and the other type is a field welding type. In both processes, partial processing is carried out on the product in advance inside a manufacturer, and then secondary processing is carried out on the site by a construction team to achieve the purpose of finished products. Because the site environment of a construction site is complex and severe, the overall quality level is difficult to ensure when the product is subjected to secondary processing on site. In order to overcome the defects of the prior art, the prior two types of construction processes can be replaced by an integral modular process.
In order to ensure the smooth realization of the process, the designer actively makes research and innovation based on the practical experience and professional knowledge which are abundant for years in the engineering application of the products and the application of the theory, so as to create a clean operating room floor mounting structure and ensure that the floor mounting structure has higher practicability.
SUMMERY OF THE UTILITY MODEL
In view of this, for the solution because the site environment of building site is more complicated abominable, carry out secondary processing to the product at the scene, whole quality level is difficult to the problem that obtains the assurance, the utility model provides a clean operating room floor mounting structure, the floor structure can all be accomplished at the producer is inside, on-the-spot only need according to the installation of modularization technology can, the construction environment of scene has been guaranteed, thereby the effectual whole quality level who guarantees the clean operating room, the dust is hidden to the setting of floor turn portion not easy, connection structure makes things convenient for the dismouting, the setting up of silica gel sealing layer makes the operating room sealed effectual, the cleanliness factor is stable, the gypsum board has the effect that keeps warm and strengthen floor intensity with the accordant connection of electrolysis steel sheet structure.
A clean operating room floor mounting structure comprising: a planar floor portion 1, a vertical wall panel 2 and a floor turn portion 3; the bottom of vertical wallboard 2 is equipped with connection structure 17, its characterized in that of being connected with reinforced concrete floor: a floor bending part 3 is arranged at the corner joint of the plane floor part 1 and the vertical wall plate 2 and is used for transition of the plane floor part and the vertical wall plate through an arc structure; the arc-shaped part of the floor bending part 3 faces the inside of an operating room, the vertical wall plates 2 are connected through one ends of a plurality of first square through reinforcing ribs 4, the other ends of the plurality of first square through reinforcing ribs 4 are connected with a reinforced concrete floor, the planar floor part 1 and the vertical wall plates 2 respectively comprise an electrolytic steel plate structure 6 and a gypsum board 7, and the electrolytic steel plate structure 6 is wrapped on the inner side wall of the gypsum board 7; the connecting structure 17 is composed of expansion bolts 15 and nuts 16, the expansion bolts 15 are connected with the nuts 16 in a matched mode, the electrolytic steel plate structure 6 of the vertical wall plate 2 is provided with an extending portion 11, the extending portion 11 is a hollow rectangle, a second square tube reinforcing rib 5 is arranged inside the hollow rectangle, the expansion bolts 15 penetrate through the second square tube reinforcing rib 5 to be connected with the reinforced concrete floor, the top of the vertical wall plate 2 is connected with one end of a medical appliance cabinet 18, the bottom of the other end of the medical appliance cabinet 18 is connected with a supporting frame 8, and coiled materials 14 are arranged on the upper portion of the plane floor portion 1, the lower portion of the vertical wall plate 2 and the inner side wall of the floor turning portion 3.
Furthermore, one side of the electrolytic steel plate structure 6, which is close to the operating room, is provided with a rust-proof paint layer, and the upper part of the rust-proof paint layer is provided with an antibacterial paint layer.
Further, the support frame 8 is a frame-shaped tripod and comprises vertical angle steel 9 and oblique angle steel 10, two ends of the vertical angle steel 9 are respectively connected with the bottom of the medical apparatus cabinet 18 and the upper part of the electrolytic steel plate structure 6 through L-shaped angle steel 12, and two ends of the oblique angle steel 10 are respectively connected with the bottom of the medical apparatus cabinet 18 and the upper part of the vertical angle steel 9 through the L-shaped angle steel 12.
Furthermore, the thickness of the gypsum board 7 is 10-15mm, and the thickness of the electrolytic steel plate structure 6 is 1.5 mm.
Further, the first square tube reinforcing ribs 4 are vertical square tube reinforcing ribs, and the cross sections of the first square tube reinforcing ribs 4 are 30mm by 30 mm.
Further, the floor turn portion 3 is made of cement, and the floor turn portion 3 is formed by molding cement.
Further, the inside wall of the top of vertical wallboard 2 and the junction of medical instrument cabinet 18 is equipped with silica gel sealing layer 13, prevents the air admission through silica gel sealing layer 13.
Further, a glue layer is arranged between the coiled material 14 and the electrolytic steel plate structure 6, and the coiled material 14 is bonded with the electrolytic steel plate structure 6 through the glue layer.
Furthermore, the coiled material 14 is made of a PVC material, and the PVC material is good in stain resistance, acid resistance and degradation resistance and free of maintenance; the product is rich in elasticity and good in skid resistance; wear-resisting, antibacterial, will not moth, mildew; the dimensional stability is good, and deformation cannot be influenced by temperature and humidity; safe and environment-friendly and does not contain formaldehyde; sound insulation and noise reduction are realized, and the foot feeling is comfortable; the color and the pattern are rich, and the requirement of individual design is completely met; fire resistance performance grade B1; light weight, reduced building load and less floor joints.
Further, the thickness of the web 14 is 2 to 4mm, preferably 2 mm.
After the technical scheme is adopted, the utility model provides a clean operating room floor mounting structure, the floor structure can all be accomplished at the producer is inside, on-the-spot only need according to the installation of modularization technology can, the construction environment of on-the-spot has been guaranteed, thereby the effectual whole quality level who guarantees the clean operating room, the dust is hidden to setting up of floor turn portion 3, connection structure 17 makes things convenient for the dismouting, silica gel sealing layer 13's setting makes the operating room sealed effectual, the cleanliness factor is stable, gypsum board 7 has the effect that keeps warm and strengthen floor intensity with electrolytic steel plate structure 6's accordant connection.
Drawings
Fig. 1 is a schematic structural view of the installation structure of the clean operating room floor of the present invention.
Fig. 2 is a schematic view of the supporting frame structure of the installation structure of the clean operating room floor of the present invention.
Fig. 3 is a schematic view of a partial structure of the installation structure of the clean operating room floor according to the present invention.
Description of the main elements
Figure BDA0003035918770000031
Figure BDA0003035918770000041
The following detailed description of the invention will be further described in conjunction with the above-identified drawings.
Detailed Description
As shown in fig. 1, it is a schematic structural view of the installation structure of the clean operating room floor of the present invention; as shown in fig. 2, it is a schematic view of the supporting frame structure of the installation structure of the clean operating room floor of the present invention; as shown in fig. 3, it is a schematic view of a partial structure of the installation structure of the clean operating room floor according to the present invention.
A clean operating room floor mounting structure comprising: a planar floor portion 1, a vertical wall panel 2 and a floor turn portion 3; the bottom of vertical wallboard 2 is equipped with connection structure 17, its characterized in that of being connected with reinforced concrete floor: a floor bending part 3 is arranged at the corner joint of the plane floor part 1 and the vertical wall plate 2 and is used for transition of the plane floor part and the vertical wall plate through an arc structure; the arc-shaped part of the floor bending part 3 faces the inside of an operating room, the vertical wall plates 2 are connected through one ends of a plurality of first square through reinforcing ribs 4, the other ends of the plurality of first square through reinforcing ribs 4 are connected with a reinforced concrete floor, the planar floor part 1 and the vertical wall plates 2 respectively comprise an electrolytic steel plate structure 6 and a gypsum board 7, and the electrolytic steel plate structure 6 is wrapped on the inner side wall of the gypsum board 7; the connecting structure 17 is composed of expansion bolts 15 and nuts 16, the expansion bolts 15 are connected with the nuts 16 in a matched mode, the electrolytic steel plate structure 6 of the vertical wall plate 2 is provided with an extending portion 11, the extending portion 11 is a hollow rectangle, a second square tube reinforcing rib 5 is arranged inside the hollow rectangle, the expansion bolts 15 penetrate through the second square tube reinforcing rib 5 to be connected with the reinforced concrete floor, the top of the vertical wall plate 2 is connected with one end of a medical appliance cabinet 18, the bottom of the other end of the medical appliance cabinet 18 is connected with a supporting frame 8, and coiled materials 14 are arranged on the upper portion of the plane floor portion 1, the lower portion of the vertical wall plate 2 and the inner side wall of the floor turning portion 3.
One side of the electrolytic steel plate structure 6, which is close to the operating room, is provided with a rust-proof paint layer, and the upper part of the rust-proof paint layer is provided with an antibacterial paint layer.
The support frame 8 is a frame-shaped tripod and comprises vertical angle steel 9 and oblique angle steel 10, two ends of the vertical angle steel 9 are respectively connected with the bottom of the medical apparatus cabinet 18 and the upper part of the electrolytic steel plate structure 6 through L-shaped angle steel 12, and two ends of the oblique angle steel 10 are respectively connected with the bottom of the medical apparatus cabinet 18 and the upper part of the vertical angle steel 9 through the L-shaped angle steel 12.
The thickness of the gypsum board 7 is 10-15mm, and the thickness of the electrolytic steel plate structure 6 is 1.5 mm.
The first square tube reinforcing ribs 4 are vertical square tube reinforcing ribs, and the cross sections of the first square tube reinforcing ribs 4 are 30mm by 30 mm.
The floor board bending part 3 is made of cement, and the floor board bending part 3 is formed by molding the cement.
The inside wall of the top of vertical wallboard 2 and medical instrument cabinet 18 junction is equipped with silica gel sealing layer 13, prevents the air admission through silica gel sealing layer 13.
And a glue layer is arranged between the coiled material 14 and the electrolytic steel plate structure 6, and the coiled material 14 is bonded with the electrolytic steel plate structure 6 through the glue layer.
The coiled material 14 is made of a PVC material which is good in stain resistance and acid resistance and free of maintenance; the product is rich in elasticity and good in skid resistance; wear-resisting, antibacterial, will not moth, mildew; the dimensional stability is good, and deformation cannot be influenced by temperature and humidity; safe and environment-friendly and does not contain formaldehyde; sound insulation and noise reduction are realized, and the foot feeling is comfortable; the color and the pattern are rich, and the requirement of individual design is completely met; fire resistance performance grade B1; light weight, reduced building load and less floor joints.
The thickness of the web 14 is 2-4mm, preferably 2 mm.
After the technical scheme is adopted, the utility model provides a clean operating room floor mounting structure, the floor structure can all be accomplished at the producer is inside, on-the-spot only need according to the installation of modularization technology can, the construction environment of on-the-spot has been guaranteed, thereby the effectual whole quality level who guarantees the clean operating room, the dust is hidden to setting up of floor turn portion 3, connection structure 17 makes things convenient for the dismouting, silica gel sealing layer 13's setting makes the operating room sealed effectual, the cleanliness factor is stable, gypsum board 7 has the effect that keeps warm and strengthen floor intensity with electrolytic steel plate structure 6's accordant connection.
The above-mentioned embodiments only represent some embodiments of the present invention, and the description thereof is specific and detailed, but not to be construed as limiting the scope of the present invention. It should be noted that, for those skilled in the art, without departing from the spirit of the present invention, several variations and modifications can be made, which are within the scope of the present invention. Therefore, the protection scope of the present invention should be subject to the appended claims.

Claims (10)

1. A clean operating room floor mounting structure comprising: a plane floor part (1), a vertical wall plate (2) and a floor bending part (3); the bottom of vertical wallboard (2) is equipped with connection structure (17) be connected with reinforced concrete floor, its characterized in that: a floor bending part (3) is arranged at the corner joint of the plane floor part (1) and the vertical wall plate (2) and is used for carrying out transition on the plane floor part and the vertical wall plate through an arc structure; the arc-shaped part of the floor bending part (3) faces the inside of an operating room, the vertical wall plates (2) are connected through one ends of a plurality of first square through reinforcing ribs (4), the other ends of the plurality of first square through reinforcing ribs (4) are connected with a reinforced concrete floor, the plane floor part (1) and the vertical wall plates (2) respectively comprise an electrolytic steel plate structure (6) and a gypsum board (7), and the electrolytic steel plate structure (6) is wrapped on the inner side wall of the gypsum board (7); connection structure (17) constitute for expansion bolts (15) and nut (16), expansion bolts (15) and nut (16) accordant connection, electrolysis steel sheet structure (6) of vertical wallboard (2) are equipped with extension (11), extension (11) are the cavity rectangle, the inside second square tube strengthening rib (5) that is equipped with of cavity rectangle, expansion bolts (15) pass second square tube strengthening rib (5) and are connected with the reinforced concrete floor, the top of vertical wallboard (2) is connected with the one end of medical instrument cabinet (18), another end bottom joint support frame (8) of medical instrument cabinet (18), the upper portion of plane floor portion (1), the lower part of vertical wallboard (2) and the inside wall department of floor turn portion (3) all are equipped with coiled material (14).
2. The clean operating room floor mounting structure of claim 1, wherein: and an anti-rust paint layer is arranged on one side of the electrolytic steel plate structure (6) close to the operating room.
3. The clean operating room floor mounting structure of claim 1, wherein: the support frame (8) is a frame-shaped tripod and comprises vertical type angle steel (9) and oblique type angle steel (10), the two ends of the vertical type angle steel (9) are respectively connected with the bottom of the medical appliance cabinet (18) and the upper part of the electrolytic steel plate structure (6) through L type angle steel (12), and the two ends of the oblique type angle steel (10) are respectively connected with the bottom of the medical appliance cabinet (18) and the upper part of the vertical type angle steel (9) through the L type angle steel (12).
4. The clean operating room floor mounting structure of claim 1, wherein: the thickness of the gypsum board (7) is 10-15mm, and the thickness of the electrolytic steel plate structure (6) is 1.5 mm.
5. The clean operating room floor mounting structure of claim 1, wherein: the first square tube reinforcing ribs (4) are vertical square tube reinforcing ribs, and the cross sections of the first square tube reinforcing ribs (4) are 30mm by 30 mm.
6. The clean operating room floor mounting structure of claim 1, wherein: the floor bending part (3) is made of cement, and the floor bending part (3) is formed by molding the cement.
7. The clean operating room floor mounting structure of claim 1, wherein: the top of the vertical wall plate (2) and the inner side wall of the joint of the medical appliance cabinet (18) are provided with silica gel sealing layers (13).
8. The clean operating room floor mounting structure of claim 1, wherein: a glue layer is arranged between the coiled material (14) and the electrolytic steel plate structure (6), and the coiled material (14) is bonded with the electrolytic steel plate structure (6) through the glue layer.
9. The clean operating room floor mounting structure of claim 1, wherein: the material of the coiled material (14) is PVC material.
10. The clean operating room floor mounting structure of claim 1, wherein: the thickness of the coil (14) is 2-4 mm.
CN202120848595.1U 2021-04-23 2021-04-23 Clean operating room floor mounting structure Active CN215107703U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120848595.1U CN215107703U (en) 2021-04-23 2021-04-23 Clean operating room floor mounting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120848595.1U CN215107703U (en) 2021-04-23 2021-04-23 Clean operating room floor mounting structure

Publications (1)

Publication Number Publication Date
CN215107703U true CN215107703U (en) 2021-12-10

Family

ID=79271454

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120848595.1U Active CN215107703U (en) 2021-04-23 2021-04-23 Clean operating room floor mounting structure

Country Status (1)

Country Link
CN (1) CN215107703U (en)

Similar Documents

Publication Publication Date Title
CN203924344U (en) Building block and the modular architectural on the middle and senior level with this building block
CN103216115B (en) Modular integrally-movable house
CN105317110A (en) Integrated assembly type steel structure building
CN207739480U (en) A kind of sustainable full module-assembled building system of green
CN108277917A (en) A kind of sustainable full module-assembled building system of green and construction method
CN205314301U (en) Corner connection structure of light gauge steel building
CN106988563A (en) A kind of intelligent integration fast-assembling operating room
CN215107703U (en) Clean operating room floor mounting structure
CN203008410U (en) Modularized overall moving house
CN1632252B (en) Light steel sealed column framework construction system
JPH10121611A (en) Self-standing panel
JPH01215350A (en) Indoor detachable clean room
CN210947512U (en) Outer wall insulation decorative board assembly structure
CN110397158A (en) A kind of boxboard steel construction assembled architecture system
CN204899019U (en) Prefabricated wallboard
CN214740266U (en) Clean operating room furred ceiling mounting structure
CN208898324U (en) A kind of hoistway section connection structure of assembling type steel structure elevator
JP4116021B2 (en) Insulation / airtight / ventilated structure by external heat insulation method and insulation / airtight / ventilated structure improvement method by external heat insulation method for existing building
CN2721779Y (en) Main body structure of assembled purified operation room
CN211200818U (en) Detachable steel keel partition wall module
CN111218980A (en) Polygonal fabricated combined house and construction method thereof
CN215106771U (en) Inorganic beautiful glaze purification assembly plate
CN212715627U (en) Four-side tongue-and-groove sandwich panel assembled integrated wallboard
CN110725468A (en) Prefabricated corrugated steel structure for house and workshop wallboards and construction method thereof
CN201367656Y (en) Wall used for fast-assembling house

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 215011 room 402, building 15, No. 158, Jinfeng Road, high tech Zone, Suzhou, Jiangsu Province

Patentee after: Suzhou Shengshi Huawei Decoration Design Engineering Co.,Ltd.

Address before: 215011 room 402, building 15, No. 158, Jinfeng Road, high tech Zone, Suzhou, Jiangsu Province

Patentee before: Jiangsu Shengshi Huawei Engineering Technology Co.,Ltd.

CP01 Change in the name or title of a patent holder