CN215106345U CN202120750140.6U CN202120750140U CN215106345U CN 215106345 U CN215106345 U CN 215106345U CN 202120750140 U CN202120750140 U CN 202120750140U CN 215106345 U CN215106345 U CN 215106345U
Authority
CN
China
Prior art keywords
sliding
sliding groove
groove rod
rise building
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120750140.6U
Other languages
Chinese (zh)
Inventor
汪世强
孙合
周建
李振兴
徐洪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei Industrial Construction Group Co Ltd HICC
Original Assignee
Hubei Industrial Construction Group Co Ltd HICC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei Industrial Construction Group Co Ltd HICC filed Critical Hubei Industrial Construction Group Co Ltd HICC
Priority to CN202120750140.6U priority Critical patent/CN215106345U/en
Application granted granted Critical
Publication of CN215106345U publication Critical patent/CN215106345U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a high-rise building hangs stone material curtain hooking device futilely, including chute pole one, roof and rolling case, chute pole one side is provided with chute pole two, chute pole one with be provided with the horizontal pole between the chute pole two, chute pole one with chute pole two tops are provided with the roof, the roof top is provided with the motor, the motor drive output is provided with the rolling case, the rolling case below is provided with the lifting rope, the horizontal pole with the welding of chute pole one, the horizontal pole with the welding of chute pole two, the roof with the welding of chute pole one. Has the advantages that: the utility model discloses a set up chute pole one, chute pole two, motor, rolling case and roof, can carry out electronic rotation to the stone material and promote, avoid the stone material to promote hard causing and articulate the difficulty, satisfy the demand that high-rise building hung stone material curtain hooking device futilely and use.

Description

Hanging device for high-rise building dry-hanging stone curtain wall
Technical Field
The utility model relates to a hooking device technical field, concretely relates to stone material curtain hooking device is hung futilely to high-rise building.
Background
A stone dry hanging method, also known as a hollow hanging method, is a novel construction process in the prior wall decoration, the method uses metal hanging pieces to directly hang decorative stone on a wall surface or a hollow hanging on a steel frame without grouting and pasting, and the principle is that main stress points are arranged on a main body structure, and the stone is fixed on a building through the metal hanging pieces to form a stone decorative curtain wall.
At present, the stone material curtain hooking device is hung futilely to current high-rise building mostly adopts manual pulley to promote, because the stone material is heavier, makes the stone material promote hard to cause and articulates the difficulty easily, can not satisfy high-rise building and hang stone material curtain hooking device user demand futilely, secondly, current high-rise building hangs stone material curtain hooking device futilely adopts simple and easy structure mostly, because the stone material piece is big, hangs to articulate because of the high altitude easily and removes inconvenient installation effectiveness that causes and hang low, has reduced the efficiency that high-rise building hung stone material curtain hooking device futilely and has used.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
In order to overcome prior art not enough, present a high-rise building hangs stone material curtain hooking device futilely, solved current high-rise building and hung stone material curtain hooking device futilely, because the stone material is heavier, make the stone material promote hard to cause and articulate the difficulty easily, can not satisfy the problem that high-rise building hangs stone material curtain hooking device user demand futilely.
(II) technical scheme
The utility model discloses a following technical scheme realizes: the utility model provides a high-rise building hangs stone material curtain hooking device futilely, including chute pole one, roof and rolling case, chute pole one side is provided with chute pole two, chute pole one with be provided with the horizontal pole between the chute pole two, chute pole one with chute pole two tops are provided with the roof, the roof top is provided with the motor, the motor drive output is provided with the rolling case, rolling case below is provided with the lifting rope, the horizontal pole with the welding of chute pole one, the horizontal pole with the welding of chute pole two, the roof with the welding of chute pole one, the roof with the welding of chute pole two, the motor with the rolling case passes through the key-type connection, the motor with the roof passes through the screw connection, the lifting rope with the rolling case rotates to be connected.
Furthermore, a first sliding frame is arranged below the lifting rope, and a second sliding frame is arranged below the sliding frame.
By adopting the technical scheme, the lifting rope can drive the first sliding frame to lift.
Furthermore, a telescopic plate is arranged between the first sliding frame and the second sliding frame, locking handles are arranged at two ends of the first sliding frame, an operating switch is arranged on one side of the second sliding groove rod, a cantilever pipe is arranged on one side wall of the first sliding groove rod and one side wall of the second sliding groove rod, a fixing plate is arranged below the cantilever pipe, and a rotating handle is arranged in the middle of the fixing plate.
By adopting the technical scheme, the cantilever pipe can enable the fixing plate to be fixed firmly.
Furthermore, the lifting rope is connected with the first sliding frame in a binding mode, the first sliding frame is connected with the first sliding groove rod in a sliding mode, the first sliding frame is connected with the second sliding groove rod in a sliding mode, the second sliding frame is connected with the first sliding groove rod in a sliding mode, and the second sliding frame is connected with the second sliding groove rod in a sliding mode.
By adopting the technical scheme, the first sliding groove rod and the second sliding groove rod can enable the first sliding frame and the second sliding frame to flexibly slide.
Furthermore, the telescopic plate is connected with the first sliding frame through a screw, the telescopic plate is connected with the second sliding frame through a screw, and the locking handle is connected with the first sliding frame through a screw.
By adopting the technical scheme, the expansion plate can enable the first sliding frame and the second sliding frame to be fixed firmly.
Furthermore, operating switch with the motor passes through the electricity and is connected, choose the pipe with the welding of spout pole one, choose the pipe with the welding of spout pole two.
By adopting the technical scheme, the motor can be turned on and off by the operation switch.
Furthermore, the fixed plate is welded with the cantilever tube, and the rotating handle is connected with the fixed plate through threads.
Through adopting above-mentioned technical scheme, change can make things convenient for the device to fix.
(III) advantageous effects
Compared with the prior art, the utility model, following beneficial effect has:
1. in order to solve the problems that the existing high-rise building dry-hanging stone curtain wall hanging device is mostly lifted by adopting a manual pulley, and the hanging difficulty is easily caused by the difficult lifting of the stone due to the heavier stone, and the use requirement of the high-rise building dry-hanging stone curtain wall hanging device cannot be met, the utility model discloses a slide groove rod I, a slide groove rod II, a motor, a winding box and a top plate are arranged, so that the stone can be electrically rotated and lifted, the hanging difficulty caused by the difficult lifting of the stone is avoided, and the use requirement of the high-rise building dry-hanging stone curtain wall hanging device is met;
2. for solving current high-rise building and hanging stone material curtain hooking device futilely and all adopt simple and easy structure, because the stone material piece is big, hang to articulate because of the high altitude easily and remove inconvenient installation effectiveness that causes low, reduced high-rise building and hung stone material curtain hooking device availability factor's problem futilely, the utility model discloses a set up sliding frame one, sliding frame two, locking handle and expansion plate, can remove the regulation to the stone material, avoid hanging to articulate because of the high altitude and remove inconvenient installation effectiveness that causes low, improved the efficiency that high-rise building hung stone material curtain hooking device futilely and used.
Drawings
FIG. 1 is a front view of the hanging device for the dry-hanging stone curtain wall of the high-rise building of the present invention;
FIG. 2 is a schematic view showing the connection relationship between the pick-up tube, the fixing plate and the rotating handle in the device for hanging the stone curtain wall on the high-rise building;
fig. 3 is a schematic view of the connection relationship between the first sliding frame, the second sliding groove rod and the first sliding groove rod of the hanging device for the high-rise building dry-hanging stone curtain wall.
The reference numerals are explained below:
1. a first sliding groove rod; 2. a second sliding groove rod; 3. a cross bar; 4. a top plate; 5. a motor; 6. a rolling box; 7. a lifting rope; 8. a first sliding frame; 9. a second sliding frame; 10. a retractable plate; 11. a locking handle; 12. an operating switch; 13. selecting a pipe; 14. a fixing plate; 15. and (4) turning the handle.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
As shown in fig. 1-3, the hanging device for the high-rise building dry-hanging stone curtain wall in the embodiment comprises a first chute rod 1, a top plate 4 and a rolling box 6, wherein one side of the first chute rod 1 is provided with a second chute rod 2, a cross rod 3 is arranged between the first chute rod 1 and the second chute rod 2, the top plate 4 is arranged above the first chute rod 1 and the second chute rod 2, a motor 5 is arranged above the top plate 4, the rolling box 6 is arranged at the transmission output end of the motor 5, a lifting rope 7 is arranged below the rolling box 6, the cross rod 3 is welded with the first chute rod 1, the cross rod 3 is welded with the second chute rod 2, the top plate 4 is welded with the first chute rod 1, the top plate 4 is welded with the second chute rod 2, a first sliding frame 8 is arranged below the lifting rope 7, a second sliding frame 9 is arranged below the first sliding frame 8, a telescopic plate 10 is arranged between the first sliding frame 8 and the second sliding frame 9, two locking handles 1 are arranged at two ends of the first sliding frame 8, two 2 one sides of draw runner pole are provided with operating switch 12, are provided with on one 1 and the two 2 lateral walls of draw runner pole and choose pipe 13, it is provided with fixed plate 14 to choose pipe 13 below, the fixed plate 14 middle part is provided with changes 15, and lifting rope 7 can drive a sliding frame 8 and promote, and operating switch 12 passes through the electricity with motor 5 to be connected, chooses pipe 13 and draw runner pole 1 welding, chooses pipe 13 and draw runner pole two 2 welding, and operating switch 12 can open and close motor 5, and fixed plate 14 with choose pipe 13 welding, changes 15 and fixed plate 14 and pass through threaded connection, changes 15 can make things convenient for the device to fix.
As shown in fig. 1-3, in this embodiment, motor 5 and rolling box 6 pass through the key-type connection, and motor 5 passes through bolted connection with roof 4, and lifting rope 7 rotates with rolling box 6 to be connected, can carry out electronic rotation promotion to the stone material, avoids the hard stone material of causing of promotion to articulate the difficulty, satisfies the demand that high-rise building hangs stone material curtain hooking device futilely and uses.
As shown in fig. 1 and 3, in this embodiment, the lifting rope 7 is tied to the first sliding frame 8, the first sliding frame 8 is slidably connected to the first sliding groove rod 1, the first sliding frame 8 is slidably connected to the second sliding groove rod 2, the second sliding frame 9 is slidably connected to the first sliding groove rod 1, the second sliding frame 9 is slidably connected to the second sliding groove rod 2, the expansion plate 10 is connected to the first sliding frame 8 through a screw, the expansion plate 10 is connected to the second sliding frame 9 through a screw, and the locking handle 11 is connected to the first sliding frame 8 through a screw, so that the stone can be moved and adjusted, the problem that the installation efficiency is low due to inconvenience in high-altitude hanging, hanging and moving is avoided, and the use efficiency of the high-rise building dry-hanging stone curtain wall hanging device is improved.
The specific implementation process of this embodiment is as follows: put the device by the stone material frame, the switch on, pick pipe 13 and block the stone material frame, rotate and change 15, make device and stone material frame chucking, place the stone material in proper order between smooth frame one 8 and smooth frame two 9, and through locking 11 with the stone material chucking lock die, through operating switch 12 starter motor 5, rotate and receive the rolling box 6, drive lifting rope 7 and slide the promotion to the stone material of putting, rise to appointed position when the stone material, open the locking 11, slide the stone material in proper order, move the suitable position with the stone material, conveniently install the stone material and articulate, this high-rise building hangs stone material curtain hooking device futilely simple operation, high durability and convenient use, the efficiency of high-rise building hangs stone material curtain hooking device futilely has been improved.
The above-described embodiments are merely illustrative of the preferred embodiments of the present invention and are not intended to limit the spirit and scope of the present invention. Without departing from the design concept of the present invention, various modifications and improvements made by the technical solution of the present invention by those skilled in the art should fall into the protection scope of the present invention, and the technical contents claimed by the present invention have been fully recorded in the claims.

Claims (7)

1. The utility model provides a high-rise building hangs stone material curtain hooking device futilely which characterized in that: comprises a first sliding groove rod (1), a top plate (4) and a winding box (6), wherein a second sliding groove rod (2) is arranged on one side of the first sliding groove rod (1), a cross rod (3) is arranged between the first sliding groove rod (1) and the second sliding groove rod (2), the top plate (4) is arranged above the first sliding groove rod (1) and the second sliding groove rod (2), a motor (5) is arranged above the top plate (4), the winding box (6) is arranged at the transmission output end of the motor (5), a lifting rope (7) is arranged below the winding box (6), the cross rod (3) is welded with the first sliding groove rod (1), the cross rod (3) is welded with the second sliding groove rod (2), the top plate (4) is welded with the first sliding groove rod (1), the top plate (4) is welded with the second sliding groove rod (2), and the motor (5) is connected with the winding box (6) through a key, the motor (5) is connected with the top plate (4) through screws, and the lifting rope (7) is rotatably connected with the winding box (6).
2. The high-rise building dry-hanging stone curtain wall hanging device according to claim 1, characterized in that: a first sliding frame (8) is arranged below the lifting rope (7), and a second sliding frame (9) is arranged below the first sliding frame (8).
3. The high-rise building dry-hanging stone curtain wall hanging device according to claim 2, characterized in that: slide frame (8) with be provided with expansion plate (10) between slide frame two (9), slide frame (8) both ends all are provided with locking (11), sliding chute pole two (2) one side is provided with operating switch (12), sliding chute pole (1) with be provided with on sliding chute pole two (2) the lateral wall and choose pipe (13), it is provided with fixed plate (14) to choose pipe (13) below, fixed plate (14) middle part is provided with changes (15).
4. The high-rise building dry-hanging stone curtain wall hanging device according to claim 2, characterized in that: the lifting rope (7) is connected with the first sliding frame (8) in a binding mode, the first sliding frame (8) is connected with the first sliding groove rod (1) in a sliding mode, the first sliding frame (8) is connected with the second sliding groove rod (2) in a sliding mode, the second sliding frame (9) is connected with the first sliding groove rod (1) in a sliding mode, and the second sliding frame (9) is connected with the second sliding groove rod (2) in a sliding mode.
5. The high-rise building dry-hanging stone curtain wall hanging device according to claim 3, characterized in that: the telescopic plate (10) is connected with the first sliding frame (8) through screws, the telescopic plate (10) is connected with the second sliding frame (9) through screws, and the locking handle (11) is connected with the first sliding frame (8) through screws.
6. The high-rise building dry-hanging stone curtain wall hanging device according to claim 3, characterized in that: the operating switch (12) is electrically connected with the motor (5), the cantilever tube (13) is welded with the first sliding groove rod (1), and the cantilever tube (13) is welded with the second sliding groove rod (2).
7. The high-rise building dry-hanging stone curtain wall hanging device according to claim 3, characterized in that: the fixing plate (14) is welded with the cantilever tube (13), and the rotating handle (15) is connected with the fixing plate (14) through threads.
CN202120750140.6U 2021-04-13 2021-04-13 Hanging device for high-rise building dry-hanging stone curtain wall Active CN215106345U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120750140.6U CN215106345U (en) 2021-04-13 2021-04-13 Hanging device for high-rise building dry-hanging stone curtain wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120750140.6U CN215106345U (en) 2021-04-13 2021-04-13 Hanging device for high-rise building dry-hanging stone curtain wall

Publications (1)

Publication Number Publication Date
CN215106345U true CN215106345U (en) 2021-12-10

Family

ID=79265388

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120750140.6U Active CN215106345U (en) 2021-04-13 2021-04-13 Hanging device for high-rise building dry-hanging stone curtain wall

Country Status (1)

Country Link
CN (1) CN215106345U (en)

Similar Documents

Publication Publication Date Title
CN211769417U (en) Cable winding device
CN215106345U (en) Hanging device for high-rise building dry-hanging stone curtain wall
CN212863805U (en) Embedded lifting appliance for carrying pipes
CN211004266U (en) Hoisting equipment for assembly type building construction
CN210064912U (en) Iron ingot hoisting device for iron smelting
CN210102602U (en) Novel high-grade semi-automatic control device for garbage crane
CN214399539U (en) Municipal works construction is mentioned device with well lid
CN212798155U (en) Garbage bin of electronic new forms of energy sanitation car promotes turning device
CN210505484U (en) Supplementary opening device of municipal administration sewer well lid
CN209349825U (en) A kind of anodes used in aluminum electrolysis guide rod anode scrap carbon block pressure-disengaging machine apparatus
CN216072715U (en) Lifting appliance for locomotive cast wheel
CN219770800U (en) Intelligent garbage room with garbage pretreatment function
CN211421886U (en) Wallboard lifting device of integrated building
CN215249123U (en) Reinforcing bar hoisting accessory is used in bridge construction
CN106323669B (en) A kind of mosaic tiles porcelain stone sampling apparatus
CN212927106U (en) Building engineering is with strong protection wall structure of stability
CN211171786U (en) Semi-automatic rubbish spade
CN214618576U (en) Air can three-in-one machine installation strutting arrangement
CN211224961U (en) Self-locking device of rear door-opening type dustbin
CN214942050U (en) Automatic installation equipment convenient to wall subsides installation
CN208733578U (en) A kind of water conservancy water channel garbage cleaning device
CN217337635U (en) Spiral lifting umbrella
CN219794550U (en) Insulation board slurry layer strickling device
CN210824378U (en) Coupling cylinder seat transfer device
CN220300280U (en) Glass curtain wall construction hoist device